HomeMy WebLinkAboutCHANGE ORDER - RFP - P916 GIS RELATED APPLICATION DEVELOPMENTCHANGE ORDER NO. 2
PROJECT TITLE: P916 GIS Related Application Development
CONTRACTOR: Miner & Miner
PROJECT NUMBER: Project 1
PURCHASE ORDER NO.: 3307970
DESCRIPTION: Parcel & Address Updating
1. Reason for Change: Schedule Revision
2. Description of Change:
■ Revised Paragraph 2. Time of Commencement and Completion of Services.
2. Time of Commencement and Completion of Services. The services to be performed
pursuant to this Agreement shall be initiated within two -hundred (200) days following
execution of this Agreement. Services shall be completed no later than February 28,
2005. Time is of the essence. Any extensions of the time limit set forth above must be
agreed upon in writing by the parties hereto.
3. Change in Contract Cost: N/A
4. Change in Contract Time: N/A
ORIGINAL CONTRACT COST
$64,400
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.:
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S:
ADJUSTED CONTRACT COST
$ 64,400
ACCEPTED BY:
U.`
DATE:
Y er & Miner Inc.
ACCEPTED BY:
` "
DATE: 1-3-0S
_ roject Ma
REVIEWED BY:
DATE:
Title:
APPROVED BY:
DATE:
Title:
APPROVED BY:
DATE:
Purchasing Agent over $30,000
Cc: Purchasing
David Carey -Fwd: P-916 Change Order #2 Page 1
From: David Carey
To: ron.yoshimura@miner.com
Date: 12/30/04 2:47PM
Subject: Fwd: P-916 Change Order #2
Ron,
Please print two (2) copies, sign both and return to me. We will return one of the copies after the City
representative signs
Thanks and have a happy new year!
David Carey, C.P.M.
Buyer -City of Fort Collins
Phone: (970) 416-2191
Fax: (970) 221-6707
E-mail: dcarey@fcgov.com
CC: Marcus Bodig
David Carey - P-916 Change Order #2 Page 1
From: Jan Elliott
To: ron.yoshimura@miner.com
Date: 12/30/04 2:20PM
Subject: P-916 Change Order #2
Change Order #2 is attached. Please contact David Carey at 970-416-2191 if you have questions.
CC: David Carey