HomeMy WebLinkAboutCHANGE ORDER - RFP - P897 CUSTODIAL SERVICES (6)CHANGE ORDER PROJECT TITLE Custodial Services PROJECT NUMBER: P 897- Porter Industries CHANGE ORDER NUMBER-1-PClean - 2005 DESCRIPTION: In preparing change orders show in order as separate numbered paragraphs the following. 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1. A. Remainder of year cost B. Increase in service 2. A. Lincoln Center — Jan — Mar service B. YAC addition of Gym 3. A. Lincoln Center - $7,365 B. YAC gym-ydy - 4,416 Total change $11,781 4. No change in contract time. ORIGINAL CONTRACT COST $150,696.00 APPROVED CHANGE ORDERS 29,775.50 TOTAL PENDING CHANGE ORDERS -00- TOTAL THIS CHANGE ORDER 11,781.00 ADJUSTED CONTRACT COSTS $192,252.50 ACCEPTED BY:// .r ,& In DATE (Contractors Representa ' ) SUBMITTED BY: Administrator) TE TE 42 o -01 APPROVED BY: DATE rations Services Deputy Director) cc: Contractor, Contract Administrator, Dept File, Purchasing (Go Jim Hume)