HomeMy WebLinkAboutRESPONSE - BID - 5881 POUDRE TRAIL REHABILITATION (2)SECTION 00300
BID FORM
PROJECT: POUDRE TRAIL REHABILITATION; BID NO. 5881
Place 1 � CD CT
Date
1. In compliance with your Invitation to Bid dated-- O cT 'cD9
and subject to all conditions thereof, the undersigned
COLfflAQO C0NSTRUCTdR39 INC. a *CorporationLimit
—T ** authorized to do business
in the State of Colorado hereby proposes to furnish and do everything
required by the Contract Documents to which this refers for the
construction of all items listed on the following Bid Schedule or Bid
Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this proposal
is made in good faith, without collusion or connection with any other
person or persons Bidding for the same Work, and that it is made in
pursuance of and subject to all the terms and conditions of the Invitation
to Bid and Instructions to Bidders, the Agreement, the detailed
Specifications, and the Drawings pertaining to the Work to be done, all of
which have been examined by the undersigned.
3. Accompanying this Bid is a certi igd or ---cashier's check or standard Bid
bond in the sum of $
in accordance with the Invitation To Bid and
Instructions to Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this Bid.
The name and address of the corporate surety with which the Bidder
proposes to furnish the specified performance
^and payment bonds is as
follows Con re-tM�rs
5. All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned,
included by implication or appurtenant thereto, are to be performed by the
CONTRACTOR under one of the items listed in the Bid Schedule, irrespective
of whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents.
7. The undersigned Bidder hereby acknowledges receipt of Addenda No.
through
7/96 Section 00300 Page 1
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 150 of the contract.
ITEM
�AarG$Crr#. �
Dr nGiTie,... � cs ,r{p,( R�ics7natTia,.
7/96
SUBCONTRACTOR
M«s«tw Rl„aae :rj'c fP..
Section 00430 Page 1
/t COwRADO
�i CONSTRUCTORS
INC.
UNIT # EQUIPMENT
TRUCKS
203
'95 Dodge 2500 4x4 sH diesel
205
'93 Dodge 2500 4x4 diesel
206
'97 Dodge 35M 4x4 diesel flatbed
207
'97 Dodge 3500 04 diesel flatbed
208
197 Dodge 2500 04 diesel
209
'99 Dodge 3500 4x4 diesel
210
01 Chev. SiNrerado 1500 ExL
211
01 Dodge 3500 4x4 diesel
212
02 Chevy 1500 LS SiNerado
213
04 Dodge 2500 4x4 diesel
TRAILERS
300
'94 P.J. 83x16 14,0000 w/racks
301
'94 Stadite 5x9 TC
302
'94 Stadde 4x8
303
'95 Stadite 82x16 7,0000 wrecks
304
'95 Stactte 82x16 duv- tail 10,0009
305
'96 P.J. 83x1614,000#
306
'96 Job office / Storage
307
'96 P.J. 83x48 14,000#
308
'97 P.J. 83x4814,000#
309
197 P.J. 83x48 14,000#
310
'98 Job office / Storage
311
-99 Box / Storage
312
68 Class 2 Field Office Trailer
313
2000 Wells Cargo Trailer
314
2001 P.J. 83x18 Trailer
315
2001 P.J. 83x18 Trailer
EQUIPMENT
400
'88 Gomaco Comm. III Slip Form
401
Gomaco Slip Form Molds
402
'94 Bob Cat 853
403
9 Ton Crane
404
Gomaoo Bridge Deck Finisher
405
'97 Bob Cat 873
406
'88 Gomaco Comm. III Slip Form
407
Morrison Vibrating Screed
408
48" Sidewalk Mold
SMALL TOOLS
500
Curb & Gutter Form Rails
501
Bridge Stripping Buggy
502
Hydro Breaker for Bob Cat
503
Rock Cut Form Liners
504
Bob Cat Dozer Blade
505
E-Z Drill
506
Welder
507
Concrete Saw
Tt
Jumping Jack Tamper,Macasa
T2
Plate Tamper, Vibramax
T3
Plate Tamper, Mikasa
T4
Whacker, Jumping Jack
T5
Whadker, Plate Compactor
ROBERT C. CLINE
702 Dearborn Street
Fort Collins, Colorado 80525
(303) 427-0868 (Office)
EXPERIENCE
1994 - Present VICE PRESIDENT
Colorado Constructors, Inc.
Denver, Colorado
Responsible for all engineering functions of the corporation, including
estimating, project management and supervision of field operations.
1990 - 1994 VICE PRESIDENT CONTRACT ADMINISTRATION
Lawson Construction Company
Longmont, Colorado
Responsible for supervision of estimating and project management
personnel. Projects range in scope from small bridges and structures to
multimillion dollar concrete paving projects. Owners include the City
and County of Denver, Denver International Airport and Colorado
Department of Transportation.
1986 - 1990 PROJECT MANAGER, A. S. Homer Construction co., Inc.,
Englewood, Colorado
Responsible for estimating and managing assigned projects varying in
size from two to twenty million dollars. Projects include steel box
girder, cast in place post tensioned concrete box and tee girder,
prestressed concrete box and I girder bridges.
1982 - 1986 PROJECT MANAGER, Flatiron Structures Company,
Longmont, Colorado
Responsible for management of assigned projects including estimating,
cost control, subcontract and material procurement. Projects include cast
in place post tensioned box girder and tee girder bridges, varying in size
from two to four million dollars. Assisted in the development of
computer estimating and project management systems.
1983 - 1984 CASTING ENGINEER, Flatiron Structures Company,
Eagle, Colorado.
Responsible for the geometric and quality control for five precast
segmental box girder bridges. The bridges have a total of 18 spans with
span lengths from 106' to 132' totaling 2,116' for all five bridges. The
segments were manufactured by "short line" match casting, and erected
by the span -by -span method.
PROFESSIONAL Current member of the Colorado Contractors Association/
ACTIVITIES Colorado Department of Transportation Bridge Committee.
Chaired Committee in 1999.
MANAGED PROJECTS FOR PREVIOUS COMPANIES
PROJECT: INTERSTATE 25 FROM 58TH AVENUE TO INTERSTATE 70 INTERCHANGE.
OWNER COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $4,555,000.00
DESCRIPTION: 147,0W SQUARE YARDS OF CONCRETE PAVING ON MAIN
LINE 1-25 FROM 58TH AVENUE TO 1-70 INTERCHANGE IN DENVER,
COLORADO.
PROJECT: SOUTH CAMPUS SITE WORK, FOR CONTINENTAL AIRLINES JOINT USE
CARGO, IN FLIGHT KITCHEN AND GROUND SUPPORT EQUIPMENT
FACILITIES.
OWNER: DENVER INTERNATIONAL AIRPORT
AMOUNT: $5,805,000.00
DESCRIPTION: 63,000 SQUARE YARDS OF CONCRETE PAVING, 162,000
CUBIC YARDS OF UNCLASSIFIED EXCAVATION, DRAINAGE, LIGHTING AND
LANDSCAPING.
PROJECT: NORTH/SOUTH CONSTRUCTION ROADS, SECURITY GATES AND PARKING
LOTS
OWNER: DENVER INTERNATIONAL AIRPORT
AMOUNT: $2,596,000.00
DESCRIPTION: 90,000 SQUARE YARDS OF CONCRETE PAVING, 300,000 CUBIC YARDS OF
UNCLASSIFIED EXCAVATION, 140 OF CUBIC YARDS OF CONCRETE BOX
CULVERT, LIGHTING AND DRAINAGE.
PROJECT: INTERSTATE 70 AND AIRPORT BOULEVARD INTERCHANGE
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $3,669,000.00
DESCRIPTION: 138,000 SQUARE YARDS OF CONCRETE PAVING ON MAIN LINE 1-70 AND
MAIN LINE AIRPORT BOULEVARD.
PROJECT: INTERSTATE 25 FROM 58TH AVENUE THRU INTERSTATE 76
INTERCHANGE
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $2,245,000.00
DESCRIPTION: 86,000 SQUARE YARDS OF CONCRETE PAVING ON MAIN LINE 1-25 FROM
58TH AVENUE TO 1-76 INTERCHANGE IN DENVER, COLORADO.
PROJECT: RECONSTRUCTION OF 15TH STREET FROM BLAKE STREET TO COLFAX
AVENUE
OWNER: CITY AND COUNTY OF DENVER
AMOUNT: $1,774,000.00
DESCRIPTION: 22,000 SQUARE YARDS OF CONCRETE PAVING ON 15TH STREET THRU
DOWNTOWN DENVER, COLORADO. THE PROJECT WAS CONSTRUCTED IN
ELEVEN PHASES UNDER TRAFFIC.
PROJECT: BRIDGE REPLACEMENT, INTERSTATE 225 OVER SAND CREEK
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $4,036,000.00
DESCRIPTION: THREE PHASE TRAPEZOIDAL STEEL BOX GIRDER BRIDGE ON 1-225 OVER
SAND CREEK IN AURORA, COLORADO. THE PROJECT INCLUDED 1,324
CUBIC YARDS OF SUBSTRUCTURE CONCRETE, 1,793 CUBIC YARDS OF
SUPERSTRUCTURE CONCRETE AND 1,793,400 POUNDS OF STRUCTURAL
STEEL.
PROJECT: BRIDGE REPLACEMENT, TEJON BOULEVARD OVER FOUNTAIN CREEK
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $1,598,000.00
DESCRIPTION: PRESTRESS CONCRETE I GIRDER ON TEJON BLVD. OVER FOUNTAIN CREEK
IN COLORADO SPRINGS, COLORADO. THE PROJECT INCLUDED 690 CUBIC
YARDS OF SUBSTRUCTURE CONCRETE AND 1032 CUBIC YARDS OF
SUPERSTRUCTURE CONCRETE.
PROJECT: BRIDGE REPLACEMENT, INTERSTATE 25 NORTH & SOUTH BOUND BRIDGES
OVER INTERSTATE 70
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $4,884,000.00
DESCRIPTION: THREE PHASE STEEL BOX ARCH GIRDER BRIDGE ON I-25 OVER 1-70 IN
DENVER, COLORADO. THE PROJECT INCLUDED 1277 CUBIC YARDS OF
SUBSTRUCTURE CONCRETE, 1430 CUBIC YARDS OF SUPERSTRUCTURE
CONCRETE AND 2,042,440 POUNDS OF STRUCTURAL STEEL. THE PROJECT
WAS CONSTRUCTED UNDER TRAFFIC IN AN INTERSECTION THAT CARRIES
285,000 VEHICLES PER DAY.
PROJECT: NEW BRIDGE CONSTRUCTION ON INTERSTATE 76 OVER SHERIDAN BLVD.
IN ARVADA COLORADO.
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $3,067,000.00
DESCRIPTION: TWIN, CAST IN PLACE POST TENSIONED TEE GIRDER BRIDGES ON
INTERSTATE 76 OVER SHERIDAN BOULEVARD. THE PROJECT INCLUDED
325 CUBIC YARDS OF SUBSTRUCTURE CONCRETE, 870 CUBIC YARDS OF
SUPERSTRUCTURE CONCRETE AND 435,000 CUBIC YARDS OF
EMBANKMENT MATERIAL.
PROJECT: BRIDGE REPLACEMENT ON 64TH AVENUE OVER US 85 IN COMMERCE
CITY, COLORADO.
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $2,247,000.00
DESCRIPTION: CAST IN PLACE POST TENSIONED BOX GIRDER BRIDGE ON 64TH AVENUE
OVER US 85. THE PROJECT INCLUDED 320 CUBIC YARDS OF
SUBSTRUCTURE CONCRETE AND 938 CUBIC YARDS OF SUPERSTRUCTURE
CONCRETE. THE BRIDGE DECK IS VARIABLE WIDTH AND CURVED, WITH
VARYING SUPERELEVATION.
Craig Gabel Long
5111 Beech Street
Arvada, CO 80002
(303) 420-1268 (Home)
(303) 427-0868 (Office)
EXPERIENCE
1994 to Present; PRESIDENT, Colorado Constructors, Inc. Responsible for business and office
administration for this concrete construction company.
1993 to 1994; ESTIMATOR and GENERAL MANAGER, Concrete Works of Colorado, Inc.
Responsible for estimating, bidding and project management for this concrete and pipe
construction company.
1989 to 1993; Various positions at Yenter Companies;
1992 to June 1993; VICE PRESIDENT, ROC EX, Inc.. a division of Yenter Companies,
Morrison, CO. Responsible for marketing, estimating and project management for this
excavation and pipe contractor.
1991 to 1992; VICE PRESIDENT, Yenter & Sons Blasting, Golden, CO. Responsible
for estimating, marketing and project management for this drilling and blasting company.
We grew from a company doing one million dollars a year to five companies doing four
million and organized a support staff that wasn't there when we were smaller. I hired an
estimator/project manager to assist in the growth of the company who grew to the
position of VP of the quarry and highway company.
1989 to 1991; ESTIMATOR and PROJECT MANAGER, Yenter & Sons Blasting,
Golden, CO. Responsible for estimating, bidding and negotiating work. Helped in
installing new management systems and controls for this small family business.
1988 to 1989; ESTIMATOR and PROJECT MANAGER, D.C.C.I., Castle Rock, CO.
Responsible for estimating, bidding, negotiating work, subcontract and material
procurement for this water and waste water treatment plant company.
1987 to 1988; ESTIMATOR and PROJECT MANAGER, I.F. Jenson Company, Castle Rock,
CO. Responsible for estimating, bidding, negotiating work, purchasing materials and
writing subcontracts for this concrete paving company.
1986 to 1987; CHIEF ESTIMATOR, Mountain States Paving, Inc., Arvada, CO. Responsible
for estimating, bidding, negotiating work, training and organizing of estimators. Helped
in installing new management systems and controls for this re -organized concrete paving
company.
1985 to 1986; GENERAL MANAGER and PRESIDENT, Kela Concrete Corp. and VICE
PRESIDENT, Women Constructors, Inc., Henderson, CO. Hired to estimate, bid and
manage work, set up office procedures for this concrete paving and flatwork company in
the Colorado market. Responsible for managing all office procedures, establishing
computerized estimating system, bidding and negotiating work, establishing cost controls
and getting the company prequalified with various agencies (Colorado Department of
Highways and others). At the time WCI was established I prepared and submitted all the
information to get prequalified with the Colorado Department of highways and helped
organize the business.
1983 to 1985; VICE PRESIDENT, DIVISION MANAGER, Palisade Construction Company /
KNC Inc., Denver, CO. Hired to start and manage a heavy and highway construction
division in the Colorado market. Responsible for determining the market, establishing an
estimating system (which I Computerized), bidding and negotiating work, hiring and
managing necessary supervision, establishing cost controls and full profit/loss
responsibility for this division of the Terra Construction Companies.
1976 to 1983; Various positions at Flatiron Structures Company
1982 to 1983; VICE PRESIDENT, Flatiron Structures Company, Longmont, CO.
Responsible for managing a division of the company including estimate preparation (I
computerized part of the estimating system), bidding jobs, assigning jobs, assigning
crews, material and subcontract procurement for this heavy and highway construction
company. During my tenure from 1975 to 1983, the gross profit on my jobs built each
year was the largest of the project managers.
1976 to 1982; ESTIMATOR / PROJECT MANAGER, Flatiron Structures Company,
Longmont, CO. Responsible for estimating jobs, monitoring costs, subcontract and
material procurement. Jobs bid include Colorado Highway Department, local cities,
counties and private developers. To my knowledge my crews were the first in Colorado
to slip -form over one mile of curb and gutter in a day.
1973 to 1976; Supervisory positions for D&M Construction Co., Denver, CO, Garland
Construction Co., Denver, CO, Fortune Construction Co., Denver, CO, and I ran my own
framing company building houses for Golden Key Building Corp.
EDUCATION
B.S. Industrial Construction Management, Colorado State University, June, 1973. Important
courses; Construction Estimates and Costs, Construction Planning and Scheduling,
Structural Theory and Design, Human Relations in Business, Calculus, Differential
Equations. Other concentration: Electrical Engineering.
PROFESSIONAL ORGANIZATIONS
Member of the American Association of Cost Engineers International
Member of various committees of the Colorado Contractors Association
CURTIS W. WHEELER
1754 S. Leyden Street
Denver, Colorado 80224
(303) 427-0868 (Office)
EXPERIENCE
1995 - Present GENERAL SUPERINTENDENT
Colorado Constructors, Inc.
Denver, Colorado
Responsible for developing field side of the bridge construction
Division. General Superintendent for all structures work.
1989 - 1995 SUPERINTENDENT
Flatiron Structures Company
Longmont, Colorado
Management of new construction and renovation projects for
Leading concrete construction firm. Supervise construction of
273 Mw co -generation plan with 5 combustion turbines and 2
steam turbine foundations — a project of more than $100 million
in conjunction with Frontier Kemper. Administration of $15
million viaduct replacement project at 150' Street underpass.
Reconstruction of I -mile section of I-25 at 39& Avenue for RTD and
HOV lanes; this was a 3-phase, $10 million project which included
widening of the interstate and two bridges and miscellaneous ramp
and street renovation. Manage and coordinate as many as 25
subcontractors per project.
1986 - 1989 CARPENTER SUPERINTENDENT
A & R Construction, Inc.
Commerce City, Colorado
Coordinate and supervise crew of 60 on new construction of
Budweiser plant. Prepare bids and order materials.
1983 - 1986 CARPENTER
G.E. Johnson Construction Company, Denver
G.H. Phipps Construction Company, Denver
Remodeling and new construction projects including Martin
Marietta, St. Joseph Hospital and Presbyterian St. Luke's Hospital.
1965 - 1983 ASSISTANT SUPERINTENDENT CARPENTER GENERAL FORMAN
A. S. Horner Construction Company
Denver, Colorado
Coordinate construction projects for major highway/bridge construction
Contractor. Supervisor as many as 100 personnel per project. Managed
expansion construction of Ideal Cement Plant in Portland, Colorado, and
new construction of Henderson West Mill Site in Henderson, Colorado —
a project requiring 80,000 cubic yard of concrete. Also served as carpenter
and laborer.
PROJECTS CONSTRUCTED BY COLORADO CONSTRUCTORS, INC.
WITHIN THE PAST FIVE YEARS
PROJECT: BRIDGE REPLACEMENT ON SH 36 OVER WOLF CREEK.
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $785,000.00
DESCRIPTION: 2-SPAN (104'-0", 104'-0") PRESTRESSED CONCRETE BOX GIRDER
BRIDGE
PROJECT: SUPERSTRUCTURE REPLACEMENT ON HOVER STREET OVER THE
ST. VRAIN RIVER
OWNER: CITY OF LONGMONT, COLORADO
AMOUNT: $1,100,000.00
DESCRIPTION: REPLACEMENT OF EXISTING DOUBLE TEE SUPERSTRUCTURE
WITH PRESTRESSED CONCRETE BOX GIRDERS. CONSTRUCTED
IN THREE PHASES UNDER TRAFFIC.
PROJECT: BRIDGE REPLACEMENT ON SOUTH BOUND INTERSTATE 25 OVER
WALSEN ARROYA
OWNER: COLORADO DEPARTMENT OF TRANSPORTATION
AMOUNT: $1,239,000.00
DESCRIPTION: 2-SPAN (101'-0", 101'-0") PRESTRESSED CONCRETE BT 54 GIRDER
BRIDGE
PROJECT: BRIDGE REPLACEMENTS ON 120T" AVENUE OVER BOX ELDER
CREEK, AND 88TH AVENUE OVER COMMANCHE CREEK
OWNER: ADAMS COUNTY, COLORADO
AMOUNT: $1,202,000.00
DESCRIPTION: 3-SPAN (75'-0", 100'-0", 75'-0") PRESTRESSED CONCRETE BT 54
GIRDER BRIDGE; 2-SPAN (75'-0", 75'-0") PRESTRESSED CONCRETE
BT 54 GIRDER BRIDGE
PROJECT: BRIDGE REPLACEMENT ON RUSSELVILLE ROAD OVER EAST
CHERRY CREEK
OWNER: DOUGLAS COUNTY, COLORADO
AMOUNT: $345,686.00
DESCRIPTION: 2-SPAN (50'-0", 50'-0") PRESTRESSED CONCRETE BOX GIRDER
BRIDGE
PROJECT: WALTON CREEK BRIDGES
OWNER: STORM MOUNTAIN RANCH, STEAMBOAT SPRINGS, COLORADO
AMOUNT: $939,000.00
DESCRIPTION: DESIGN BUILD 4 TIMBER BRIDGES, HIGHWAY RATED.
4-SPAN (50'-0", 50'-0", 50'-0", 50'-0")
2-SPAN (35'-0", 35'-0")
1-SPAN (67'-0"), 1-SPAN (35'-0"), 1-SPAN (70'-0") EQUESTRIAN BRIDGE
DANNY L. HOEY
801 43rd Street
Evans, Colorado 80620
RESUME
WORK EXPERIENCE
1994 to Present: COLORADO CONSTRUCTORS, INC, Arvada, CO; General
Superintendent. Supervising flatwork construction crews. In charge of all production, quality
control and customer relations. Working all aspects of concrete paving, curb and gutter from
sub -grade to final product.
1989 to 1994: LAWSON CONSTRUCTION COMPANY, Longmont CO; Paving
Superintendent. Supervising crews of up to 12 employees. In charge of production, quality
control and customer relations. Working all aspects of concrete paving, curb and gutter from
sub -grade to final product.
1978 to 1989: FLATIRON CONCRETE CONSTRUCTION COMPANY, Ft Collins,
CO; Various jobs over the years. 1987 to 1989 Field Superintendent. Supervision of crews of 8
to 20 employees on various curb and gutter jobs. In charge of production, quality control and
customer relations. In charge of ordering concrete. Held position as Safety Officer.
1984 to 1987 Foreman. In charge of running individual projects. Supervised training of
new operators on concrete pavers, motor graders, loaders and backhoes. Responsible for
production and quality control.
1980 to 1984 Leadman/Operator. Operated motor grader, backhoe, loader and concrete
paver for curb gutter jobs. Drove transport truck moving equipment from job to job.
1978 to 1980 Manual laborer for concrete construction.
EDUCATION
1991 - Present, Certified supervisor with City of Aurora.
1990 - 1992 Gomaco University, Ida Grove, Iowa. Attended one week training class on concrete
placers, spreaders and two track pavers.
1984 - 1986 Gomaco University, Ida Grove, Iowa. Attended one week training class on
Commander III curb and gutter machines. 1988 American Concrete Institute, Denver, CO.
Completed written and testing performance examinations for Certified Testing Technician.
1976 Montrose High School, High School, Montrose, CO. Graduated high school and received
diploma.
CNARADO C(WSnWCTQBs MC,
CONTRAC OR
C O
BY:
ADDRESS: O C) 1V (oc1d Wcn 5�.'le
C6 ca(D 1
8. BID SCHEDULE (Base Bid)
Bid items are described in Section 01800
BID
ESTIMATED
UNIT
ITEM
ITEM #
DESCRIPTION
QUANTITY
UNIT
PRICE
TOTAL
1
Mobilization
1.00
LS
'
2
Traffic Control
1.00
LS
S
oe
2, Seu, —
eo
Z' Sen •-
3
Demolition
72 944.00
SF
5" Colored Concrete
3`,y7Zet
4
Paving
91,180.00
SF
Z es
d�c
Parking Lot
p 00
5
Improvements
1.00
LS
6
Landscape Restoration
91,180.00
SF
7
Hydro Seeding
91,180.00
SF
9
(y tom_
TOTAL OF BASE BID
40
72'teg H6-G690;4 %Ji�R7� s,v �io(JtA..O �y/�/E f�uvOR60 S ..0a..ir ede_ DN//Aa& $3'�G 97/
(written) Ax& ,• rrr ojF a Ts
9. PRICES
The foregoing prices shall include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc., to cover
the complete Work in place of the several kinds called for.
Bidder acknowledges that the OWNER has the right to delete items in the Bid
or change quantities at his sole discretion without affecting the Agreement
or prices of any item so long as the deletion or change does not exceed
twenty-five percent (25%) of the total Agreement Price.
7/96 Section 00300 Page 2
MW
ZCOLORADO
ONSTRUCTORSS
INC.
"Transforming two dimensional drawings
into three dimensional reality"
CURRENT CITY, COUNTY AND STATE LICENSES
MUNICIPALITY
TYPE OF LICENSE
NUMBER
EXP.
City of Arvada
Contractors License
LO1-076
July 30, 2005
City of Aurora
ROW Concrete
2005 133912 00 CL
August 1, 2005
2003 10878500 SL
Supervisor 7/06
City of Boulder
(as needed)
City of Broomfield
General Contr. Class C
C2003-712
December 31, 2004
Colorado Department
Heavy Highway Contt.
Vendor ID
March 31, 2005
of Transportation
Concrete Contractor
0968A
City & County of Denver
RW - Sidewalk
231420
December 31, 2004
Structures/PreQual.
May 31, 2005
City of Ft. Collins
ROW Concrete
Bond — 3/7/05
City of Grand Junction
State of Kansas
Dept. of Transportation
City of Lakewood
City of Longmont
City of Louisville
State of Nebraska
Dept. of Transportation
City of Thornton
General Contractor
General Contractor
Contractors License
(as needed)
(as needed)
General Contractor
Contractors License
9682
964.174,
City of Westminster General License 64956
City of Wheat Ridge (as needed)
State of Wyoming General Contractor
Dept. of Transportation Prequalification
6810 N Broadway, Suite B, Denver, Colorado 80221
email: ColoradoConshvctors@compuserve.com
February 1, 2005
November 12, 2004
April 6, 2006
February 28, 2005
October 12, 2005
March 31, 2005
February 28, 2005
(303) 427-0868
f (303) 427-0882
RESPFULLY
SUB
�1
Signatu
C EC)
Title
License Number (If Applicable
(Seal - if Bid is by corporation)
Attest:��
6
Address ( , u ( O
7/96
Z-7 do j o
Date
T�r<,c-tj vcSv�te-t�
yej- C6 P3O'ZZ1
Telephone 3 H 1-7 0
Section 00300 Page 3
SECTION 00400
SUPPLEMENTS TO BID FORMS
00410Bid Bond
00420Statement of Bidder's Qualifications
00430Schedule of Subcontractors
7/96 Section 00410 Page 1
SECTION 00410
BID BOND
KNOW ALL MEN BY THESE PRESENTS: that we, the undersigned
as Principal, and as
Surety, are hereby held and firmly bound unto the City of Fort Collins, Colorado,
as OWNER, in the sum of $ for the payment of which, well and
truly to be made, we hereby jointly and severally bind ourselves, successors, and
assigns.
THE CONDITION of this obligation is such that whereas the Principal has
submitted to the City of Fort Collins, Colorado the accompanying Bid and hereby
made a part hereof to enter into a Construction Agreement for the construction of
Fort Collins Project, POUDRE TRAIL REHABILITATION; BID NO. 5881.
NOW THEREFORE,
(a) If said Bid shall be rejected, or
(b) If said Bid shall be accepted and the Principal shall execute and deliver a
Contract in the form of Contract attached hereto (properly completed in
accordance with said Bid) and shall furnish a BOND for his faithful
performance of said Contract, and for payment of all persons performing
labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said Bid,
then this obligation shall be void; otherwise the same shall remain in
force and effect, it being expressly understood and agreed that the
liability of the Surety for any and all claims hereunder shall, in no
event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the obligations
of said Surety and its BOND shall be in no way impaired or affected by any
extension of the time within which the OWNER may accept such Bid; and said Surety
does hereby waive notice of any such extension.
Surety Companies executing bonds must be authorized to transact business in the
State of Colorado and be accepted by the OWNER.
7/96 Section 00410 Page 2
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands
and seals this day of , 20 , and such of them as are
corporations have caused their corporate seals to be hereto affixed and these
presents to be signed by their proper officers, the day and year first set forth
above.
PRINCIPAL
Name:
Address:
By:
Title:
ATTEST:
By:
(SEAL)
By:
Title:
SURETY
(SEAL)
7/96 Section 00410 Page 3
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and
comprehensive. This statement must be notarized. If necessary, questions may be
answered on separate attached sheets. The Bidder may submit any additional
information he desires.
1. Name of Bidder: COLOR"O CONSTRUCTORS, IN,
2. Permanent main office address: `p/O Al, /�/OBcieuaa� L7CSU(e-r-, (�D V042�
3. When organized:
4. If a corporation, where incorporated: C6100.0-oto
5. How many years have you been engaged in the contracting business under your
present firm or trade name? V-tw.rS
6. Contracts on hand: (Schedule these, showing the amount of each contract and
the appropriate anticipated dates of completion.) 1
• *4, a l S. Go Vogl 2 S i� St . T•� /D ds.Ks. t13 -
/d rf �/2,000,00 o oS
.raA- 47t. -
Fi oflt._. 0/76,6-o0•oo 09as 0 CSr-f. 723 l/ s
7. General character of Work erfrmed by your company:
g
8. Have you ever failed to complete any Work awarded to you? Alt
If so, where and why?
9. Have your ever defaulted on a contract? A/o
If so, where and why?
10. Are you debarred by any government agency? A)j)
If yes list agency name.
7/96 Section 00420 Page 1
11. List the more important projects recently completed by your company,
stating the approximate cost of each, and the month and year completed,
location and type of construction.
v0 oovva t. _ev
n.w r Vv awe - - � • ✓ h`I i, va - V G! 1Vy'0r'1 LOO V JVO&4i 5LUIDACWjOAA— ,
V.0 ! 7 / n rL. na is X-CIPa4/s - r/ 91, 3 2 V . Oa
12. List your major equipment available for this contract.
Ale4tSc Sec goy � Jl7
13. Experience in construction Work similar in importance to this
project:
xu</o of Gt. C4'W-it..S. f .a7 S S96 00
07F Ga! c� 1,09 t�4 Z.ov
%/lfa tFc C/asl�%ra: l - Ci &I o f- ff7i/o!.` i 2/1, /744OD
14. Background and experience of the principal members of your organization,
includin officers:
/ xs-r' Ste= �'T?u%sci /c5 Gtul sS
15. Credit available: $ SOO, DOO. 00
16.
Bank reference: �(-cc��iy��L--� 533 5 Arrsnl Pkvy 1,oL. jctj
17.
Will you, upon request, fill out a detailed
financial statement and
furnish
any other information that may be
required by the
OWNER?
�s5
18.
Are you licensed as a General CONTRACTOR?
�GS
If yes, in what city, county and state?
'.st
What
class, license and numbers?
19.
Do you anticipate subcontracting Work under
this Contract? J�
If yes, what percent o total contract?
/ S
and to whom? ram �TT.-, „ i _ A
20. Are any lawsuits pending against you or your firm at this time? /yp
If
DETAIL yes,
7/96 Section 00420 Page 2
21. What are the limits of your public liability? DETAIL
E Beeu✓aµul / Boo BOD - „ram / �& 02 e00 Boy
What company? %r`,r�l o/s /r�p�jL� Csyu, l
22. What are your company's bonding limitations? 014,doof00 O
23. The undersigned hereby authorizes and requests any person, firm or
corporation to furnish any information requested by the OWNER in
verification of the recital comprising this Statement of Bidder's
Qualifications.
1
Dated at (iGns CounD thisZ-%fiL day of
COLOMDO CONSTBUCTOM9 Me
Name of Bidder
By: —
Title: Blecs
State of Ca La,
County of A DA,,, S
OCT , 2GD4.
��-=./E being duly sworn deposes and says that he is
o�OLOMO CONSTRUCTORS, IAFC.
and that name of organization)
the answers to the foregoing questions and all statements therein contained are
true and correct.
Subscribed and sworn to before me this 2� n day of
Oc: 2004
0
No ary Pu ic'
My commission expires Z 6— M ay Jc:;,IJ
7/96 -Section 00420 Page 3