HomeMy WebLinkAboutPrebid - BID - 5799 NORTHEAST AREA OVERLAY PROJECT (2)NORTHEAST AREA OVERLAY PROJECT PRE -BID CONFERENCE July 1, 2003 City of Fort Collins Engineering Dept. Street Oversizing Program NORTHEAST AREA OVERLAY RAFFIC CONTROL AND WORK ■ TRAFFIC CONTROL: o Traffic Control Plans must be submitted and approved 72 hours prior to the start of construction and before making each modification. o Full road closures must be submitted 3 weeks prior to any work being done. o Local Residential Access: ■ Local access must be maintained at all times for all residents on Douglas Road and County Road 11. o City of Fort Collins will coordinate with the homeowners so driveways can be closed for short oerlods of time TRAFFIC CONTROL AND WORK ■ WORK AREA SAFETY: o The Contractor shall provide, at the Contractor's expense, all work area safety control devices, such as barricades and safety fence around all excavations, trenches and drop offs. NORTHEAST AREA OVERLAY IGHLIGHTS FROM PECIFICATIONS: REMOVALS .-. o 202-02RotwWAsWMP&v 1(0'-4.S)-(SV) r HIGHLIGHTS FROM SPECIFICATIONS: ■ REMOVALS o 202-03 Remove Tree Stumps (Avg. Width= 12' Dia.) 3 � NORTHEAST AREA OVERLAY IGHLIGHTS FROM PECIFICATIONS: • REMOVALS 0 202-04 Remove Concrete DAVewaya (4• Thick)_ (SF) lwwV awM�� FROM ■ REMOVALS 0 202-05 Remove Pipe (RCP, CMP. PVC) - (LF) HIGHLIGHTS FROM ■ REMOVALS o 202-06 Remove Fence (Various Types) - (LF). NORTHEAST AREA OVERLAY FROM • REMOVALS o 202-07 DemollOon of Farm House (Counay Club Rd. and NORTHEAST AREA OVERLAY IGHLIGHTS FROM ■ REMOVALS o 202-10 Clearing and Grubbing—(LS) FROM REMOVALS HIGHLIGHTS FROM • EECAVATION AND EMBANKMENT 203-01 UM dlsd E• wcwn—(Ch NORTHEAST AREA OVERLAY FROM EXCAVATION AND EMBANKMENT . M 41 UnalaaMaaC ExenMlen-(CY) . 20342 Embankment (OP)-(CY) . 20343 Tops" -(shippino at)aMPiNnN, placing) 6'DePte-(CY) . 203,114 Barrow Onalte Material (AaphM RotwnlEnya)-(CY) . 203458o StuNabI. PIN Material -(CYi . 20346 Mack Eaea.attan-(CW) -(CY) a 20347 Bartow ABC (Class titer 6)-(GIP)-(TON) . 2U46Pa"m"-(L3) HIGHLIGHTS FROM HIGHLIGHTS FROM APErelfireATIONSm • EROSION CONTROL o 2DS-01 Erosion Control - (LS) - Precautions must betaken to Stabilize the work area during =11bYCNOn t0 minimize ermin. r� NORTHEAST AREA OVERLAY FROM ■ RESET STRUCTURES 0 210-01 Adjust valve Box(ELCO Water Distnct)-(EA) a 210-02 Adjust Manhole Mng/Cowr-(EA) a 210-03 Relocate Maillmos;-(EA) Alnuebwsboleu Rd. and fWWof LisaRRd.tt between Country cafeClub Rd. ■rf et was Lase Rd.wab oth n■paw g relocated 1. b reel than of the maavnY, as otlwe U. get nt O , sp a.teN the n.n To ranl.houWer Y per U. S. Pa[ Oulu ap.e■c.lom. FROM AGGREGATE EASE COURSE a 304-01 Aggregate Base Course- (Class 5 w 6)- (TON) o 304-02 Shouidenng ABC (Class 5 w6)(4'Deplh)-(CIP) RECONDITIONING o 306-01Reconcsdwing(8')-(SY) LIGHTS FROM ■ HOT BITUMINOUS PAVEMENT o 403-01 Hot Bituminous Pavement- Grading 3.3v Depth - (PG 64-28) -(TON) o 403-02 Hot Bituminous Pavement- Grading SG -4.5" Dairth - (PG 64.22) - (TON) NORTHEAST AREA OVERLAY FROM • NOT MTUYINOU! PAVlYlNT o 40343 Avph*K Pawr P•mhng- GrtlYp 8. r Opth ®OrKwm" (PO 64-32)- (TON) FROM NOT BITUMINOUS PAVSMBNT • 403-0/AphMP. L*vOWVC..rr.-Gn"8(PO64") HIGHLIGHTS FROM IS HOT BITUMINOUS PAVEMENT a 403-05 Asphalt Patching — Grading SG — 4.5" Depth — (PG 64-22) — (TON) NORTHEAST AREA OVERLAY FROM ■ RIPRAP o 506-01 15 X 2a Type H Rip Rap w/6' Topsoil - (TON) FROM CULvurs AND aatteRa a v it CM-ILF) a ttsatr Caw-Fta-ttM a tlJO]tr epCW N-ILF) e YSN IY tGCW N-qI-ILt) o ssustr cNr-NI s WC -Fes iw e M IWNCFCWN-NI e Ysas N'xpCWl!-Flt-ItN n tp eCFCWN-IU) e ttl.t1 ]r eCFeW N-FA MFW IM-ItN FROM In MANHOLES, INLETS AND METER VAULTS a 604-01 Area Inlet — (EA) o W4-02 Reset and Pow Type R ln* 0t —(EA) NORTHEAST AREA OVERLAY IGHLIGHTS FROM . FENCES 607-01 Replace Fwo, with new (W owtn Win! w/T•Poat-(LF) HIGHLIGHTS FROM ■ FENCES 607-02 Relocate 3 PAR Dowel Fence wlNo CYmb Fabtk - (LF) FROM ■ FENCES o 607-03�Tempmw7Onnpe SeM7 Fm (Jwewt Pfopwly)—(MF) NORTHEAST AREA OVERLAY INTRODUCTIONS: ■ Street Oversizing Program: o Matt Baker — Program Manager (224-6108) o Craig Farver — Construction Manager (222-0854 cell #) o Eileen Bayens — Project Engineer (222-0351 cell #) o Quentin Egan — Construction Manager (222-0860 cell #) o Scott Woodruff — Project Engineer (221-6605) o Mark Laken — Construction Manager (222-3546 cell #) INTRODUCTIONS: ■ COFC DEPARTMENTS: ==:--j o John Stephen — Purchasing Agent (221-6777) o Cam McNair — City Engineer (221-6605) o Syl Mireles — Traffic Control Coordinator (221-6815) o Bob Zakely — Watershed Env. Shed (224-6063) o Ralph Zentz — Assistant City Forester (221-6302) NORTHEAST AREA OVERLAY GHTS FROM ■ FENCES o 607-04 Install 6' PMY&q Fence (Hotchkiss Property) _ (LF) HIGHLIGHTS FROM ■ SIDEWALKS AND DECORATIVE CROSSWALKS o 60"1 Conte Driveways (e') —(SF) • TIWw• k N1••nM bWMLwlp Ya rt Y•Iw••n Wwwy GYYaNO YIIY abNrW l�N Awl Mr/ NYb•n•• INI M NlYllry NNrN• bNN•T •ti wr• NI Ytl, w11 N YrMN Wtl N eain nw Nr •NIrY rn•1 b tlb OIY •sbwe OrMw•y. GHTS FROM CURB AND GUTTER o 609-01 Vertical Curb and Gutter (30•) — (LF) NORTHEAST AREA OVERLAY FROM ■ WATERLINES 0 61"1 W X r Tapping Saddle - (EA) a 819-02 F Tapping Gate Valve w/Valve Box - (EA) 0 819413 8' PVC Pipe C900 wrapped Plug and Bkwm(!- (LF) 0 81901Fln"rmnt Assembly -(EA) IGHLIGHTS FROM LANDSCAPING QUANTITIES o Ro$tM Landscape Rock Ar Icr Private Owners- (LS) o ReplaceRaNroad Ties-(LS) 0 W Blue Spruce Pine Trap - (EA) o Rebcoo Exis*V Sprinkler Meace-(LS) NO THEAST AREA OVERLAY THANKS FOR COMING. ARE THERE ANY QUESTIONS? DRIVEWAYS 1949 DOUGLAS RD. OIL CO. ACCESS RD. JUANITA RD. No Text 1421 DOUGLAS RD. #2 1401 DOUGLAS RD. 1401 DOUGLAS RD. #2 NORTHEAST AREA OVERLAY INTRODUCTIONS: ■ LARIMER COUNTY: o Marc Lyons — Access & Utility Coordinator (498-5709) o Bill Gleiforst — Traffic Services Supervisor (498-5707) ■ ELCO WATER DISTRICT: o Mike Schied — District Engineer (493-2044) o Jack Warner— Field Operations Manager (566-2286) INTRODUCTIONS: ■ CITY OF FORT COLLINE ENGINEERING: ^� 0 Scott Woodruff - SOS Civil Engineer (970-221-6605) ■ INTER -MOUNTAIN ENGINEERING: 0 Mike Moore, PE - Project Manager (970-9495072) �+ NORTHSTAR ENGINEERINGt 0 Patricia.Kroetch,PE- Project Manager - (970-666.6939) ■ TST ENGINEERING: -► 0 Keith G. Sheaffer, , PE - Project Manager (970-226-0557) ,.� 1340 DOUGLAS RD. TROUBLE TRAIL DRIVEWAY 1500 DOUGLAS RD. 1520 DOUGLAS RD. e _ 1640 DOUGLAS TRAILER PARK 1640 DOUGLAS ENTRANCE #2 All »ti 9F t on AS, k t �� � � aJ��yg➢.��ya4 � �� pmµ 2� � n6 �'P . e :. l7 s � y a F c+ �3 MAV tic us 1 v Y d ��s`$�. ���� �S F� h2 £ ^3✓ ��> i� �$ ��'•i�`�".��'�yr i��4' � Y F l # 5 I d� f 1950 DOUGLAS RD. NORTHEAST AREA OVERLAY ATTENDANCE: Please be sure to register 1 BID OPENING, I ■ When: o July 15, 2003 (3:00 PM) ■ Where: o 215 North Mason Street (2"d Floor) No Text 2024 COUNTRY CLUB RD. ss. �. «�' �p +� ,� 2209 COUNTY RD. 11 2301 COUNTY RD. 11 No Text 2305 COUNTY RD. 11 23U9 COUNTY RD. 11 2401 COUNTY RD. 11 2405 COUNTY RD. 11 NORTHEAST AREA OVERLAY 0 IMPORTANT MILESTONES: ■ AWARD CONTRACT 0 Approximately the last week in July ■ PRE -CONSTRUCTION MEETING 0 Mandatory Meeting Prior to Start of Construction 0 Date to be determined after contract is awarded ■ CONSTRUCTION START DATE 0 August4, 2003 ■ SUBSTANTIAL COMPLETION 0 55 working days ■ FINAL COMPLETION 0 Maximum allotted time = 10 working days following substantial completion SUMMARY OF WORK: ■ NORTHEAST AREA OVERLAY o The improvements for widening County Road 11 from just north of the Storybook Subdivision north to Douglas Road then west on Douglas Road 650 feet past the Hearthfire Subdivision Entrance (approx. 3 miles in length) includes: rotomilling the existing roadway 6 feet on each side, overlaying the entire roadway with 3 inches of asphalt, earthwork, waterline installation for the ELCO Water District, stormwater improvements, house demolition, driveway culverts, shouldering, landscaping, fencing and re -grading. 2409 COUNTY RD. 11 2413 COUNTY RD. 11 2501 COUNTY RD.11 #1 2501 COUNTY RD. 11 #2 2505 COUNTY RD. 11 2509 COUNTY RD. 11 3 Y $ q % a s♦ k Ao 6bU5 CUUNTY RD. 11 zouj UUUNTY RD. 11 nt,cv eumr S'1'A'1'1UN DRIVEWAY NORTHEAST AREA OVERLAY [CONSTRUCTION DOCS: ■ NORTHEAST AREA OVERLAY: o Designed by City of Fort Collins ■ Sheet#'sO—lg o Designed by Northstar Engineering ■ Sheet #'s 1 — 5, 10 —16 o Designed by Inter -Mountain Engineering ■ Sheet #'s CO — C6, C21 — C22, C26 — C28, C31 o Designed by TST Engineering ■ Sheet #'s 26 - 32 HIGHLIGHTS FROM GENERAL ■ SUPERINTENDENTS: o The General Contractor SHALL employ a full time Superintendent whose sole responsibility is to monitor and coordinate all facets of the work. ■ LIQUIDATED DAMAGES: o SUBSTANTIAL COMPLETION: ■ The Contractor will be given 55 working days to substantially complete the project. Substantial Completion shall be defined as the completion of all earthwork, pavement, concrete work, striping, signage, landscaping and any other pertinent items as required for this project. The roadways must be opened to traffic. If the Contractor goes past the 55 working days, damages in the amount of $1,150.00 for each working day will be assessed. 3223 COUNTY RD. 11 � ■ «� e No Text 3405 COUNTY RD. 11 MISCELLANEOUS PICTURES FARMHOUSE TO BE DEMOLISHED ,. lot_ 4 e t 5 $ a6 U1 k 3 e Jw Y t I f q � � ♦ 5 � � � t Y � �� to t SF' F _ _. A �J{_t i'.i3�}t-Y'.Y.#Y _ a^ .., rr« .!' �E+Y R>�.''eY.� is �SF� jf ~iL ; • 'a �i 6.. . S`B. v'a f z' r sa, ��:. INLET DECK TO BE REMOVED No Text NORTHEAST AREA OVERLAY HIGHLIGHTS FROM GENERAL h .rR ..y 1 1 HIGHLIGHTS FROM GENERAL QQNDITIONS AND GENERAL RWO ■ CONSTRUCTION SURVEYING: o Provided by the City of Fort Collins ■ TRAFFIC CONTROL: o Provided by the Contractor. GEOTECHNICAL AND MATERIALS TESTING: o Provided by the Owner. it will be the Contractor's responsibility to schedule the testing. 11 SOUTH FROM RICHARDS LAKE RICHARDS LAKE WEST FROM 11 No Text :.� , � _ - �, k ^ r No Text AREA WHERE (2) 36" RCP'S CROSS P • 9 > iS , r is e a� S"1 }} 4, i ty r 11 „ g � T HEARTHFIRE ENTRANCE HEARTHFIRE ENTRANCE NORTHEAST AREA OVERLAY HIGHLIGHTS FROM GENERAL ■ PROJECT MEETING: o Once a week at the construction trailer located on -site, time to be determined. The TCS will be required to attend all weekly meetings. ■ PROGRESS AND SCHEDULE REVISIONS: o Schedules shall be updated weekly. The Contractor may be required to submit additional schedules depending on the progress of the project. ■ HAUL ROUTES: o Arterial and Collector streets only. Contractor will not be allowed to use residential streets to access the site with trucks hauling materials. HIGHLIGHTS FROM GENERAL ■ SITE CLEAN-UP: o The Construction work and processes shall be kept and accomplished in a neat, clean and orderly fashion. NORTHEAST AREA OVERLAY ITE COORDINATION WITH ■ COMCAST CABLE: o Will need to relocate overhead cable lines and cable boxes on the east side of County Rd 11 and the north side of Douglas Road once the grade has been brought to proposed elevations. ■ XCEL ENERGIES (ELECTRIC): o Once the earthwork has been completed on the east side of County Road 11 at Country Club Road, the overhead power crews will relocate the existing power poles to the east outside of the new Right -of -Way. This work will be completed after the earthwork is complete and prior to the final lift of asphalt being placed. ■ ELCO WATER DISTRICT: o Prior to August 4t', ELCO Water District will be on site upgrading several water services along County Rd. 11. It may become necessary to coordinate some of this work if they run past our start date. TRAFFIC CONTROL AND WORK ■ TRAFFIC CONTROL: o The traffic control for this project will be paid for by the Lump Sum to the Contractor and will include all costs for .� the traffic control associated with this project.