Restoration of Franz -Smith Cabin
Empire Carpentry
PO # 3307983 BID # 5787
1. Reason for change: Extensive wood rot in log that was not detected in the original assessment.
2. Description of Change: (1) Replace two additional logs measuring approx. 50 ft.
(2) Add south side roof guttering
3. Change in Contract Cost: $ 2,725.40 (see attached itemization)
4. Change in Contract Time: Add 68 days. New substantial completion date is October 19, 2004
ORIGINAL CONTRACT COST
$
117,000.00
TOTAL APPROVED CHANGE ORDER
$
0.00
TOTAL PENDING CHANGE ORDER
$
0.00
TOTAL THIS CHANGE ORDER
$
2,725.40
TOTAL %OF THIS CHANGE ORDER
2.3%
TOTAL C.O.% OF ORIGNINAL CONTRACT
2.3%
ADJUSTED CONTRACT COST
$
119,725.40
(Assuming all change orders approved)
ACCEPTED BY
ACCEPTED BY
Steve White, Project Manager
ACCEPTED BY: 1.
" WWII",
!A
Collins Museum
DATE:
DATE:
DATE: ? t
TE:—h jwt-
APPROVED BY: DATE:
Purchasing Agent over $30,000 • 1 • -
cc: City Clerk Architect MCI iF>0 #
Purchasing Contractor Oki # _ -
Project File Batch r
Engin P'V #
9/99 Section 00950 Page 1
PROJECT TITLE: Restoration of Franz -Smith Cabin
CONTRACTOR: Empire Carpentry
PROJECT #: PO # 3307983 BID # 5787
CHANGE ORDER NO.1
COST ITEMIZATION
Remove 2 old logs from cabin
$ 320.00
Search for and acquire 2 new logs (Hainey) 3 hrs
$ 150.00
Cost of logs (50 total ft. @ $3.00 per linear foot)
$ 150.00
Log delivery to jobsite (1 trip)
$ 100.00
Moving of 2 logs from truck to cabin (6 people; 1 hr)
$ 240.00
Dovetail 2 logs (10 firs, $300 each log)
$ 600.00
Drill & peg 2 logs
$ 400.00
Install new logs
$ 200.00
Materials
20.00
Subtotal
$ 2,180.00
Profit 15%
327.00
Replace 2 additional logs subtotal
$ 29507.00
Southside roof gutter installation (Apex Gutter) $ 208.00
Profit 5% 10.40
Southside gutter subtotal $ 218.40
Change order total $ 2,725.40