HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 21249PROJECT TITLE: CONTRACTOR: PROJECT NUMBER: DESCRIPTION: SECTION 00950 CHANGE ORDER NO. 1 Restoration of Franz -Smith Cabin Empire Carpentry PO # 3307983 BID # 5787 1. Reason for change: Extensive wood rot in log that was not detected in the original assessment. 2. Description of Change: (1) Replace two additional logs measuring approx. 50 ft. (2) Add south side roof guttering 3. Change in Contract Cost: $ 2,725.40 (see attached itemization) 4. Change in Contract Time: Add 68 days. New substantial completion date is October 19, 2004 ORIGINAL CONTRACT COST $ 117,000.00 TOTAL APPROVED CHANGE ORDER $ 0.00 TOTAL PENDING CHANGE ORDER $ 0.00 TOTAL THIS CHANGE ORDER $ 2,725.40 TOTAL %OF THIS CHANGE ORDER 2.3% TOTAL C.O.% OF ORIGNINAL CONTRACT 2.3% ADJUSTED CONTRACT COST $ 119,725.40 (Assuming all change orders approved) ACCEPTED BY ACCEPTED BY Steve White, Project Manager ACCEPTED BY: 1. " WWII", !A Collins Museum DATE: DATE: DATE: ? t TE:—h jwt- APPROVED BY: DATE: Purchasing Agent over $30,000 • 1 • - cc: City Clerk Architect MCI iF>0 # Purchasing Contractor Oki # _ - Project File Batch r Engin P'V # 9/99 Section 00950 Page 1 PROJECT TITLE: Restoration of Franz -Smith Cabin CONTRACTOR: Empire Carpentry PROJECT #: PO # 3307983 BID # 5787 CHANGE ORDER NO.1 COST ITEMIZATION Remove 2 old logs from cabin $ 320.00 Search for and acquire 2 new logs (Hainey) 3 hrs $ 150.00 Cost of logs (50 total ft. @ $3.00 per linear foot) $ 150.00 Log delivery to jobsite (1 trip) $ 100.00 Moving of 2 logs from truck to cabin (6 people; 1 hr) $ 240.00 Dovetail 2 logs (10 firs, $300 each log) $ 600.00 Drill & peg 2 logs $ 400.00 Install new logs $ 200.00 Materials 20.00 Subtotal $ 2,180.00 Profit 15% 327.00 Replace 2 additional logs subtotal $ 29507.00 Southside roof gutter installation (Apex Gutter) $ 208.00 Profit 5% 10.40 Southside gutter subtotal $ 218.40 Change order total $ 2,725.40