HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 20702 CHANGE ORDER 406/19/2004 07:52 9702216534 FACILITIES PAGE 04 CHANGE ORDER NO. 04 PROJECT TITLE: GITY OF FORT COLLINS AND CSU TRANSIT CENTER PHASE 1A CONTRACTOR: G.L. HOFF CO. PROJECT NUMBER: BID N0.5823 DESCRIPTION: In preparing change orders show in order as separate numbered paragraphs the following: 1. Reason for change: CSU request for change_ 2. Description of change: See attachments. 3. Change in contract cost: $1,329.30 4. Change in contract time: CHANGE. FROM FEB 11, 2004 TO April 30, 2004 (Attach .additional sheets as required) ORIGINAL CONTRACT COST................................................$208,761.00 TOTALAPPROVED CHANGE ORDERS... ................................... 20,189.44 TOTAL PENDING CHANGE ORDERS_ ...... I ................... 00,00 TOTAL THIS CHANGE ORDER ............ ... .............................. .......1,329.30 ADJUSTED CONTRACT COST ........................... 230 279 74 (Assuming all chap a orders approved) ACCEPTED BY ACCEPTED BY: APPROVED BY: efzel �l Steve White, City of Fort Collins, Project Manager APPROVED BY: CasS eitler, qNroject Manager APPROVED BY- ' Tom Frazier, Tra ort, G eral Manager cc: City Cierk Project File Contractor Purchasing Engineer ne4 Da et ylzblw DATE ' Z/ )251. e, Date 47-26 >� Date �A- SQ-e q Date