Loading...
HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 20594SECTION 00950 CHANGE ORDER.' 2 PROJECT TITLE: TROLLEY BARN INTERIOR REHABILITATION PROJECT #: STE M455-061 PO#: 3307571 BID #: 5804 CONTRACTOR: Empire Carpentry DESCRIPTION: Painting 1. Reason for change: Request from City 2. Description of Change: Materials and labor sheet attached — Dan Hedrick Painting • Prep and paint bathroom floor with industrial epoxy paint (2 coats). • Prep and paint vestibule floor with floor coat paint (2 coats). • Paint bench in file room — prime and finish coat • $500.00 credit for not sanding and oiling vestibule floor. Summary: Painting + $1145.00 Floor credit - 500.00 Subtotal $ 645.00 Contractor 5% + $ 32.25 3. Change in Contract Cost: Net adds and deducts $ 677.25 4. Change in Contract Time: 0 day ORIGINAL CONTRACT COST $82,660.00 TOTAL APPROVED CHANGE ORDER $ 92.62 TOTAL PENDING CHANGE ORDER $ 0 TOTAL THIS CHANGE ORDER $ 677.25 TOTAL CHANGE ORDERS TO DATE $ 769.87 TOTAL C.O% OF ORIGNINAL CONTRACT 7,11% ADJUSTED CONTRACT COST (Assuming all change orders approved) $839429.87 ACCEPTED BY: Contractor's DATE: ACCEPTED BY:Lalt--wDATE: Project Manager ACCEPTED BY: �d-,n�� DATE: i¢ — � — 4— Title: DOT Representative APPROVED BY: DATE Purchasing Agent over $30,000 cc: City Clerk Architect urc asm Contractor Project File CDOT Engineer 9/99 Section 00950 Page 1 �� Q��,c ✓ Dan Hedrick Painting Labor and Materials 5/20/2004 727 W. Mountain Ave. Record Fort Collins, CO 80521 Project: Fort Collins Trolley Barn Labor billing / hour: $32.00 Area Item Hours Materials Labor Totals Bathroom floor Pre / clean 2 $64.00 $64.00 1 Epoxy paint kit - 2 gals. $97.00 $97.00 .PaintIcleanup coat 1 3.5 $112.00 $112.00 Paint/cleanup coat 2 2.5 $80.00 $80.00 Total $363.00 Vestibule floor Pre / clean - extensive; old wood 11 $352.00 $352.00 2 gals. floor coatpaint $52.00 $52.00 Paint/cleanu coat 1 5 $160.00 $160.00 Paint/cleanu coat 2 3.5 $112.00 $112.00 Total $676.00 File Room bench Paint in inventory $4.00 $4.00 :::IPrep/prime/cleanup 2 1 $64.00 $64.00 finish coat/cleanup 1.5 1 $48.00 $48.00 Total I$116.00 Total Due $1,145.00 Integral Hardwoods Mick Seiler 2812 Cherry Lane Fort Collins, CO 80521 Phone: 970482-5034 Fax: 970-482-6860 RE: Trolley Barn May 20, 2004 Not having to sand and oil the vestibule floor reduces the scope of this project by $500.00. Miiccck� Seiler