HomeMy WebLinkAboutCHANGE ORDER - BID - 5834 ZIEGLER ROAD WIDENING PROJECTao 4.3(�
Change Order Form
City of Fort Collins
PROJECT TITLE: Ziegler Road Improvements
PROJECT NUMBER: 30523201.6 (Bid #5834)
CONTRACTOR: Don Kahn Construction, Inc. (PO #4401453)
CHANGE ORDER NUMBER: 3
n preparing change orders Show in order as separate numbered paragraphs the toiiowing
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1 &2. See attached sheet for detail.
3. The contract cost will increase by $29,241.81
4. There will be no change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY: /40t--
ACCEPTED BY:
REVIEWED BY:
APPROVED BY:
4.91%
6.72%
DATE:
DATE: to y
DATE:
DATE:
APPROVED BY: DATE:
(Purchasing Agent over $30,000)
cc: Contractor
Purchasing
Project File
$595,032.54
$10,721.14
$0.00
$29,241.81
$634,995.49
Engineering Department • 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6605
Contractor: Kehn Construction
Project: Zeigler Road
Reconciling Change Order
Date: 07/0812004
Item Quantity
From: 30-May-04
To: 26Jun-04
ADJUSTED VS
to I Amount I Total I Under -run
EXPLINATION FOR RECONCILING CHANGE ORDER
202-01
Remove Pie RCP, CM P, ADS.HDPE
261
LF
$ 8.00
206.00
$ 1.648.00
78.93%
$ 440.00
did not have as much as originally estimated
202-02
Remove Asphalt Pavement 0" -2" Depth)
5.642
SY
$ 1,20
5858.00
$ 7,029.60
103.83%
$ 259.20
extended mill limits
202-03
Remove Asphalt Pavement 5" - 10" Depth)
3,082
SY
$ 2.50
3682.00
$ 9,205.00
119.47%
$ 1,500.00
extended mill limits
202-04
Saw Cut Existing Asphalt
513
LF
$ 1.50
158.00
$ 237.00
30.80%
$ 532.50
did not have as much as originally estimated
202-05
Remove Rip -Rap
60
SY
$ 10.50
30.00
$ 315.00
50.00%
$ 315.00
did not have as much as originally estimated
202-06
Remove Concrete Irrigation Ditch 3.75' wide x 1.76 deep)
1.460
LF
$ 1.35
1460.00
$ 1,971.00
100.00%
$
202-07
Remove Concrete Weir, Flume, Supports and Pipe
1
LS
$ 1.450.00
1.00
$ 1.450.00
100.00%
$
202-08
Remove Fence Barbed Wire Three Strand
254
LF
$ 1A0
254.00
$ 355.60
100.00%
$
202-09
Remove Type III Barricade at the Kechter Intersection
1
EA
$ 100.00
1.00
$ 100.00
100.00%
$
202-10
Remove Storm Sewer Manholes
2
EA
$ 600.00
2.00
$ 1,200.00
100.00%
$
202-11
Abandon 314" Domestic Water Tap FCLWO spec)
1
EA
$ 2,200.00
1.00
$ 2,200.00
100.00%
$
202-12
Removal of debris and Overgrowth
1
LS
$ 2,500.00
1.00
$ 2,500.00
100.00%
$
203-01
Unclassified Excavation
3,355
CY
$ 2.00
8136.00
$ 16,272.00
242.50%
$ 9.562.00
extra work around site for school district
203-02
Embankment - CIP
4,260
CY
$ 0.86
7290.99
$ 6,197.34
171.15%
1 $ 2,576.34
extra work around site for school district
203-03
Borrow Suitable Fill Material CIP
910
CY
$ 5.00
1277.67
$ 6,388.35
140.40%
$ 1,838.35
needed more than extimated
203-04
Had & Dispose
300
CY
$ 3.50
165.00
$ 577.50
55.00%
$ 472.50
less material left site
203-05
jBormw, ABC Class 5 or 6 - CIP
175
TON
1 $ 10.00
71.30
$ 713.00
40.74%
$ 1,037.00
did not need as much as estimated
203-06
Muck Excavation- CIP
626
CV
1 $ 5.50
346.00
$ 1,903.00
55.27%
$ 1,540.00
less than originally estimated
203-07
Topsoil • (Stripping. Stockpiling, Placing) - 6" Depth
1,800
CY
$ 3.55
1800.00
$ 6,390.00
100.00%
$
203-08
To soil - (Stripping, Haul OM -Site
594
CY
$ 4.65
0.00
$
0,00%
$ 2,762.10
did not need as much as estimated
203-09
Median Hardscape Shaping - CIP
950
SF
$ 1.20
768.00
$ 921.60
80.84%
$ 218.40
less than calculated
203-10
Flow Fill Shallow Utilities
250
LF
$ 27.00
65.00
$ 1,755.00
1 26.00%
$ 4,995.00
utilities were deeper in most spots
203-11
Detour Road I la x 26'
1
LS
$ 3.350.00
1.75
$ 5.862.50
175.00%
$ 2,512.50
had to make the road larger than estimated
203-12
Potholing
1
LS
$ 900.00
1.00
$ 900.00
100.00%
$
208-01
Erosion Control
1
LS
$ 1,500.00
1.00
$ 1.500.00
100.00%
$
210-01
Adjust Manhole Ring/Cover
9
EA
$ 2%00
12.00
$ 3.000.00
133.33%
$ 750.00
had more man holes that neeeded adjustment
210-02
Plug Existing 21" Opening
1
EA
$ 200.00
1.00
$ 200.00
100,00%
$
210-03
Adjust Valve Box FCLWD
8
EA
$ 165.00
3.00
$ 495.00
37.50%
$ 825.00
less valve boxes needed to be adjusted
210-04
Relocate Mailboxes Provide Temporary Service
6
EA
$ 75.00
6.00
$ 450.00
100.00%
$
304-01
Aggregate Base Course - Class 5 or 6 - 6" Depth - CIP
3,105
TON
$ 10.70
4090.14
$ 43,764.50
131.73%
$ 10,541.00
Used more ABC in some areas
304-02
Aggregate Base Course Patch Placement - Class 5 or 6 - 6" Depth - CIP
171
TON
$ 12.60
57.89
$ 729.41
33.85%
$ 1,425.19
had less patch need for ABC
306-01
Recondition 8"
6,072
SY
$ 0.80
6702.00
$ 5,361,60
110.38%
$ 504.00
more area than estimated
307-01
FI ash Subgrade Stabilization - 12%
9.239
SY
$ 4.45
6530.00
$ 29,058.50
70.68%
$ 12,055.05
used extra ABC unsted of Fivash in some areas
403-01
Hot Bituminous Pavement - Grading S 3" Depth) - PG 64-28
1,689
TON
$ 35.65
1992.41
$ 71.029.42
117.96%
$ 10,816.57
extended our limits of pavement
403-02
Hot Bituminous Pavement - Grading S 2" Depth) - PG 64-28
754
TON
$ 36.31
754.00
$ 27,377.74
100.00%
$
403-03
Hot Bituminous Pavement - Grading SG 4" Depth) PG 64-22
2,252
TON
$ 29.30
2023.37
$ 59,284.74
89.85%
$ 6,698.86
needed less bottom lift than estimated
403-04
Asphalt Paver Patching - Grading S 3" Depth) - PG 64-28
50
TON
$ 85.00
57.93
$ 4,924.05
115.86%
$ 674.05
had more top patch than estimated celestica drive
403-05
Asphalt Paver Patching -Grading SG 4" De - PG 64.22
99
TON
$ 67.00
86.95
$ 5,825.65
87.83%
$ 807.35
Used less bottom patch
403-06
As haft Patching -Grading SG 4" Depth) - PG 64-22
10
TON
$ 140.00
91.85
$ 12,859.00
918.50%
$ 11.459.00
Had more paver patch than estimated Celestica
403-07
Asphalt Patching - Grading S 3" Depth) - PG 64-28
33
TON
$ 110.00
24.00
$ 2,640.00
72.73%
$ 990.00
did not have as much top patch quantity
506-01
10' x V x 2' T e D-50 Rip -Rap, 6" To oil CIP Per Detail
1
LS
$ 450.00
1.00
$ 450.00
100.00%
$
603-01
24" RCP Class III
176
LF
$ 38.00
166.00
$ 6,308.00
94.32%
$ 380.00
had less do t0 design change in field
603-02
24" RCP Class III FES with Grate
1
EA
$ 675.00
1.00
$ 675.00
100.00%
$
<... 603-04-
14" x 23" HEROP.. -
0'
LF
S, 115.00 :
0.00
$,,
#DtV/dt:'
$: -
603-05
lConcrele Joint Encasements
4
EA
$ 125.00
0.00
$ -
0.00%
$ 500.00
did not have to do to design change in field
603-06
30" PIP Irrigation Pipe
1.346
LF
$ 43.60
1346.00
$ 58,685.60
100.00%
$
603-07
Tie Into Existing 42" Storm Sewer Line for 14x23 HERCP
1
EA
$ 800.00
1.00
$ 800.00
100.00%
$
603-08
4"PVC Schedule 200 Irrigation Sleeving
300
LF
$ 10.50
210.00
$ 2,205.00
70.00%
$ 945.00
less than estimated
603-09
Modify Siphon Structure
1
LS
$ 3.950.00
1.00
$ 3,950.00
100.00%
$
603-10
Airrelease valve2"l riser&tee
3
EA
$ 1,550.00
3.00
$ 4,650.00
100.00%
$
604-01
5'Type R Inlet
1
EA
$ 2,550.00
1.00
$ 2,550.00
100.00%
$
604-02
15'Type R Inlet
1
EA
$ 3,808.00
1.00
$ 3.808.00
100.00%
$
604-03
6' Manhole
1
EA
$ 2,600.00
1.00
$ 2.600.00
100.00%
$
604-04
Tie Into Irrigation Structure
1
EA
$ 800.00
2.00
$ 1,600.00
200.00%
$ 800.00
had an extra
607-02
10range Safety Fence 1,400
LF 1
$ 1.60 1
1400.00
$ 2,240.00
100.00%
$
Contractor: Kohn Construction
Project: Zeigler Road
Reconciling Change Order
Date: 07/0812004
Item
Quantity
From: 30-May-04
To: 26-Jun-04
to I Amount I Total
ADJUSTED WS
Under -run I EXPLINATION FOR RECONCILING CHANGE ORDER
608-01
Concrete Sidewalk 6"
15.444
SF
$ 2.45
18448.00
$ 45,197.60
119.45%
$ 7,359.80
had more than was estimated
608-02
Concrete Access Ramps with colored landings 8"
1,000
SF
$ 5.00
1708.00
$ 8.540.00
170.80%
$ 3.540.00
had extra at celestica
608-03
Concrete Cross an with Aprons 9 112 "
800
SF
$ 5.50
1003.00
$ 5,516.50
126.38%
$ 1,116.50
had extra at celestica
608-05
Hi-Earty Concrete 24 Hour
150
CY
$ 10.00
4.00
$ 40.00
2.67%
$ 1.460.00
did not have to use as much
608-06
Flowable Fill Concrete
342
CY
$ 40.00
183.00
$ 7,320.00
53.51%
$ 6,360.00
used a lot less than estimated
608-07
Exposed Aggregate Median Hardsca i 4"
950
SF
$ 5.35
768.00
$ 4,108.80
80.84%
$ 973.70
less area than estimated
608-08
Pedestrian Refuge Island
too
SF
$ 3.25
100.00
$ 325.00
100.00%
$
609-01
Vertical Curb & Gutter 30"
3.944
LF
$ 8.65
3859.00
$ 33,380.35
97.84%
$ 735,25
not as much as estimated
609-02
Outfall Curb & Gutter 18"
286
LF
$ 8.00
280.00
$ 2,240.00
97.90%
$ 48,00
less than estimated
609-03
Thermal Blankets for Concrete Irrigation Ditch Placement
1,000
LF
$ 0.35
30.00
$ 10.50
3.00%
$ 339.50
did not have to use them as much as estimated
609-05
Driveway Curb Cuts 26 Width)
2
EA
$ 1,350.00
1.00
$ 1.350.00
50.00%
$ 1,350.00
eliminated one of them with field change
609-06
R & R Vertical Curb and Gutter
50
LF
$ 19.50
39.00
$ 760.50
78.00%
$ 214.50
mot as much need do to location thane of mid block
609-07
R & R Concrete Sidewalk
100
SF
$ 3.50
100.00
$ 350.00
100.00%
$
603-03
19" x 30" HERCP
40
LF
$ 25.00
1 0.00
$
0,00%
1$ 1,000.00
eliminated in field
609-04
lConcrete irrigation Ditch Per Detail)
1.400
1 LF
$ 15.001
1420.00
1 $ 21.300.00
1 101.43%
$ 300.00
Imis talc
i JVJ,JJ I.-OI 1'7 Ipmoy.41 I
Contract Bond
1.00
LS
$ 6,100.00
1.00
$ 6,100.00
100.00`Yo
$
625-01
Construction Surveying
1.0o
6,600.00
1.00
$ 6,6D0.00
100.00%
$
626-01
Mobilization
1.00
5,500.00
1.00
$ 5.500.00
100.00%
$
630-01
Two 2 Message Boards
7.00
aR$
350.00
3.00
$ 1,050.00
42.86%
$ 1,400.00
did not use second time
630-02
Flagging
300.00
22.00
934.20
$ 20,552.40
311.40%
$ 13,952.40
extra fia in hours to com lete work
630-03
Traffic Control
1.00
7,950.00
I no
$ 7,950.00
100.00%
$
Subtotal Ziegler Misc. Quantities: $ 47,752.40 $ 12,552.40
ORIGINAL CONTRACT AMOUNT $ 595,032.54 $ 613,304.35
Change Order Number 1 $ 12,221.14 $ 20,041.14
2 $ (1,200.00) $ (1,500.00)
Adjusted Contract Amount:
Total Change Orders:
Change Order % of Total Contract:
$ 606,053.68
$ 11,021.14
1.82%
$ 29,241.81
$ 29,241.81