HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 20259CHANGE ORDER NO. A
PROJECT TITLE: Poudre Trail Fence - W. of Taft Hill Road
CONTRACTOR: Waterford Corporation
PROJECT NUMBER: 5841
PURCHASE ORDER NO.:
DESCRIPTION: Minor changes to scope of work
1. Reason for change: Quantity adjustments and additional work required
2. Description of Change: See Payment Application #1 attached for details
ADD - Additional grounding rods for PRPA spec requirements
$455.00
ADD - Tie into adjacent landowner's fence
$260.00
ADD - 6 Ft. Chain Link Fence Bracing Section
$3,674.70
DELETE - Brown Extruded Vinyl Clad Fence
($99,870.38)
DELETE - Brown Extruded Vinyl Clad Fence Gates
($853.34)
ADD - 6 Ft. Chain Link Fence (along north trail boundary)
$56,535.03
ADD - 6 Ft. Chain Link Fence (along Triber property)
$28,870.83
ADD - 6 Ft. Chain Link Fence (over ped tunnel)
$3,924.00
ADD - 6 Ft. Chain Link Fence Gate Section-8Ft.
$1 238.44
ADD - Fence Demolition
$1,270 34
ADD - Fence Demolition -Additional concrete post base removal
$1,270.34
ADD - Install 24" ADS culvert
$800 00
DELETE - Tree Removal
($825 00)
3. Change in Contract Cost:
($3,250.04)
4. Change in Contract Time: 30 calendar days
TOTAL APPROVED CHANGE ORDER $0.00
TOTAL PENDING CHANGE ORDER $0.00
TOTAL THIS CHANGE ORDER $ (3,250.04)
TOTAL % OF ORIGINAL CONTRACT, THIS C.O. -2.79%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S -2.79%
ADJUSTED CONTRACT COST $113� 3
(Assutnina all chanae.Drders aonroved)
ACCEPTED BY:
DATE: to
Contractor's Representativ
ACCEPTED BY:
DATE: 2
Project Manager
REVIEWED BY:
DATE:
Title:
APPROVED BY:
DATE:
Title:
APPROVED BY:
DATE:
Purchasing Agent over $30,000
cc: City Clerk Architect
Contractor Engineer
Project File Purchasing