HomeMy WebLinkAboutCHANGE ORDER - REQUISITION - 20094SECTION 00950
CHANGE ORDER NO.* 3
PROJECT TITLE: TROLLEY BARN INTERIOR REHABILITATION
PO#: 3307571
PROJECT #: STE M455-061
BID #: 5804
CONTRACTOR: Empire Carpentry
DESCRIPTION: Excavation — Excavate and backfill street cut and asphalt patch for new water tap
1. Reason for change: Request from City
2. Description of Change: Obtain street cut permit. Cut and excavate Cherry Street on NW corner of 330 North
Howes Street, as directed. Backfill hole after tap is placed.
3. Change in Contract Cost: Net adds and deducts $ 5,119.45
4. Change in Contract Time: 0 day
ORIGINAL CONTRACT COST
$
82,660.00
TOTAL APPROVED CHANGE ORDER
$
92.62
TOTAL PENDING CHANGE ORDER
$
677.25
TOTAL THIS CHANGE ORDER
$
5,119.45
TOTAL C.O.% OF ORIGNINAL CONTRACT
7.1 %
ADJUSTED CONTRACT COST (Assuming all change orders approved)
$88,549.32
ACCEPTED BY:
DATE:
ACCEPTED BY: X Y DATE: S a y D y
Steve S field Project Manager
APPROVED BY: DATE: S of y/0 Ll
Title:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: Ci Clerk Architect
rc as1 Contractor
Project File
Engineer
9/99 Section 00950 Page I