HomeMy WebLinkAboutCHANGE ORDER - BID - 5804 TROLLEY BARN INTERIOR REHABILITIATIONSECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: TROLLEY BARN INTERIOR REHABILITATION
PO#: 3307571
PROJECT #: STE M455-061
BID #: 5804
CONTRACTOR: Empire Carpentry
DESCRIPTION: New furnace for South Addition & Minor Electrical Changes
1. Reason for change: Request from City
2. Description of Change:
Install new 75,000 BTU Heater in South Addition (vent, gas
pipe, & thermostat included).
• Electrical changes per customer request.
• Deduct $4,000.00 allowance for security system.
3. Change in Contract Cost: Net adds and deducts $ 92.62
4. Change in Contract Time: 0 day
ORIGINAL CONTRACT COST
$82,660.00
TOTAL APPROVED CHANGE ORDER
$ 92.62
TOTAL PENDING CHANGE ORDER
$ 00.00
TOTAL THIS CHANGE ORDER
$ 92.62
TOTAL C.O.%OF ORIGNINAL CONTRACT
00.1%
ADJUSTED CONTRACT COST (Assuming all change orders approved)
$82,752.62
ACCEPTED BY
DATE:
ACCEPTEDBY:'DATE: y
Pro t Manager
APPROVED BY: DATE:
Title:
APPROVED BY: -47L- DATE:
Purchasing Agent over $30,000
cc: Ci Clerk Architect
urchasin Contractor
Project File
Engineer
9/99 Section 00950 Page I