HomeMy WebLinkAboutCHANGE ORDER - RFP - MASON TRANSPORTATION COORIDOR BIKE PEDESTRIAN TRAITransportation Services
Transportation Planning
CHANGE ORDER FORM
City of Fort Collins
PROJECT TITLE: Mason Transportation Corridor, Bike/Pedestrian Trail
PROJECT NUMBER: 30521900
CONTRACTOR: Felsburg Holt & Ullevig (PO #2206648)
CHANGE ORDER NUMBER: 1
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1. & 2. See attached letter for reason and description of change.
3. The contract cost will increase by $96,120.00
4. The contract time will be increased thru March 31, 2005.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED BY:
SUBMITTED BY:
REVIEWED BY:
APPROVED BY:
APPROVED BY:
APPROVED BY:
Agent)
5.85%
5.85%
cc: City Clerk) A
Contractor G �. ?�' " " � ✓ %/�
Purchasing '�j7/` City Clerk
Project File
$1,642, 542.00
$0.00
$0.00
$96,120.00
$1,738,662.00
DATE:
-E: k 3L
TE:
TE: 313� M4
TE:
DATE: I Z
215 North Mason • First Floor • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 224-6058 • FAX (970) 221-6239
MAR 31 '04 13:48 FR FHU
303 721 0832 TO 919702216239 P.02/05
19FELSBURG
HOLT &
ULLEVIG
engineering paths to transportation solutions
March 18, 2004
Ms. Kathleen Reavis, AICP
Senior Transportation Planner
City of Fort Collins
215 N. Mason Street
P.O. Box 580
Fort Collins, CO 80522-0580
Re: Mason Transportation Corridor
FHU Reference No. 02-181
Dear Ms. Reavis:
This letter is provided to update you on our current budget status and to provide you with a fee
estimate for additional services as you have requested. We would like the opportunity to
discuss the contents of this letter with you once you have had a chance to review it.
Budget Status
As you are aware, our contract currently includes three principal work activities:
• Alternatives Analysis Report preparation
■ Trail design to the south of Harmony Road
■ Trail design to the north of Harmony Road
The total budget negotiated for these tasks is $656,920. A breakdown of individual budgets by
consultant and per work task was summarized In our letter proposal dated June 27, 2003. As of
the end of February, 2004, work assignments have resulted in expenditures of $598,303,
leaving a remaining budget of $58,617 to complete all of the FOR comments for both design
segments and to complete the Alternatives Analysis Report
Budget Supplement Request
We have performed an accounting of the remaining work assignments to complete the
construction plans and we respectfully request an increase in our budget of $39,600. The
following is a summary of our reasoning for this request: aj- wn,5'
1L&. ,��
• The trail design to the south of Harmony Road has been revised several tlrnas,.mast
recently with the addition of an Ad -Alternate component
- There was an additional plan review meeting for the South of Harmony segment which
required additional plan preparation, reproduction and meeting time. - ay� FL
f,&A,1Al ✓ 4r,�
6300 South. Syracuse Way, Suite 600 Centennial, CO 80111 tel .30.3.721.1440 fax 303.721.0832
www.fhueng.com info@fhuen.a.com
MAR 31 '04 13:49 FR FHU
303 721 0832 TO 919702216239 P.03i05
Ms. Kathleen Reavis, AICP
March 18, 2004
Page 2
• Underlying right-of-way ownership complicated the right-of-way clearance process and
required more substantial right-of-way plan development. — �s'w ,ru
■ It was necessary for us to design the trallheaA d paging lot twice, once as a paved lot and
once as a gravel lot.
■ The number of cost estimate lterations for the entire project (BRT included) became
more significant than anticipated.
Coordination with the New Mercer Ditch to establish design parameters and
expectations has been troublesome. Specific to crossings, guidance has changed no r
less than three times resulting in redesign and layout. — �+w ,w , � ',t e"�'
■ We spent significant effort In verifying and checking the Vexel mapping.
■ It will be necessary to redesign part of the trail system adjacent to the large detention
pond between Troutman and Horsetooth to address comments at the FOR. This work
also requires additional wetland mitigation and permitting work by Carter & Burgess.
Additional Requested Services
Per your request on March 12, we will complete the design of the MTC Trail adjacent to the
Redtail Pond and will include these plan sheets In the final plan package. Also per your
direction, there will not be an Ad -alternate plan format. We estimate the following fees to
complete that work:
Felsburg Holt & Ullevig = $8,000.00
Carter & Burgess = 500.00
Total = $8,500.00
Construction Assistance
We have not had an opportunity to discuss this issue with Mike Herzig since he is out of the
office this week. We understand, however, that the following services would be provided:
■ Review shop drawings.
• Provide as -built drawings summarizing information provided by the Contractor.
■ Respond to City requests of design clarifications, etc.
There is some uncertainty as to the staff needs for this work but we estimate that approximately
8 hours per week would be required. The current understanding of approximate construction
time is 90 days for the South of Harmony Road segment, and 180 days for the North of
Harmony Road segment However, both projects will likely be under construction at the same
time. Therefore, the maximum anticipated construction time is 180 days. Dividing 180 days by
five working days per week equates to 36 weeks. Thirty-six weeks at 8 hours per weeks
equates to a total of 288 hours of construction assistance. Therefore, we estimate the following
fee to complete this level of effort:
MAR 31 '04 13:49 FR FHU
303 721 0832 TO 919702216239 P.04i05
Ms. Kathleen Reavis, AICP
March 18, 2004
Page 3
■ Construction Engineer = 288 hours C $80/hour = $23,040.00
■ CADD = 40 hours ® $70.00/hour = $ 2,800.00
■ Administration = 20 hours @ $60.00/hour = $ 1,200.00
■ Carter & Burgess = $ 5,000,00
■ EDAW = $ 5,000.00
■ Mileage (18 trips to Fort Collins) _ $ 1,080.00
• Other Direct Costs (printing, etc.) = 1 0
Total = $39,120.00
Continued BNSF Coordination Services
FHU can continue to assist you In coordination efforts with the BNSF. We cannot provide you
with a definitive estimate of the number of work hours necessary to fully complete this task;
however, we have included an estimate of 80 hours as part of this budget request. The
associated fee for that level of work efforts follows:
Senior Engineer (FHU) = 80 Hours @ $110.00/hour = $8,800.00
ODC's =200-00
Total = $9,000.00
Summary
In summary, we are requesting that our current budget be increased by the following amounts to
cover remaining design services, completion of the Alternative Analysis Report, construction
assistance and for BNSF coordination activities:
Finish Current Design = $39,500.00
Additional Design = $ 8,500.00
Construction Assistance = $39,120.00
BNSF Coordination = 9,000.00
TOTAL = $96,120.00
As such, we respectfully request an Increase in our budget of $96,120, from $656,920 to %
$753,040 for these tasks, with a total MTC budget Increased from $1,642,542 to $1,738,662.
Schedule
We anticipate that the design of both trail projects can be completed by the end of April, 2004.
The completion of the Alternatives Analysis Report could occur within approximately two weeks
after receiving your final comments, dependent upon the magnitude of those comments.
Coordination efforts with the BNSF are anticipated to last through June, 2004.
MAR 31 '04 13:49 FR FHU 303 721 Oe32 TO 919702216239 P.05i05
Ms. Kathleen Reavis, AiCP
March 18, 2004
Page 4
Please call us with any questions you may have.
Sincerely,
FELSBURO HOLT & ULLEVIG
Dean P. Bradley, PE
Principal
Richard R. Folimer, PE, PTOE
Senior Transportation Engineer
** TOTAL PAGE.05 **