HomeMy WebLinkAboutWORK ORDER - RFP - P897 CUSTODIAL SERVICESApr-06-04 11:38A PORTER INDUSTRIES Inc 9706352566 P_02 CHANGE ORDER PROJECT TITLE Custodial Services PROJECT NUMBER: P 897- Porter Industries CHANGE ORDER NUMBER-2-PClean - 2004 DESCRIPTION: In preparing change orders show in order as separate numbered paragraphs the following. 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1. Building Addition 2. Add Lincoln Center - 17,261 SF 3. Cost per month $ 2,455 - Apr. 1-Dec 31,2004 - $22,095 4. No change in contract time. ORIGINAL CONTRACT COST $150,696.00 APPROVED CHANGE ORDERS 7,680.50 TOTAL PENDING CHANGE ORDERS -00- TOTAL THIS CHANGE ORDER 22,095.00 ADJUSTED CONTRACT COSTS r $180,471.50 ACCEPTED BY: SUBMITTED BY: REVIEWED BY: Representative) TE -6'U ,TE 'S`- 6 -O of J6Z� DATE y -GH Superintendent) APPROVED BY�' / - DATE perations Services Deputy Director) cc: Contractor, Contract Administrator, Dept File, Purcp (c/o Jim Hume)