HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 19466 CHANGE ORDERCHANGE ORDER
PROJECT TITLE Custodial Services
PROJECT NUMBER: P 897- Varsity Contractors
CHANGE ORDER NUMBER-3-Varsity -2004
DESCRIPTION: in preparing change orders show in order as separate numbered
paragraphs the following:
1. Reason for change. 2. Description of change. 3. Change in contract cost. 4.
Change in contract time.
1. Increase in service
2. Add service to exercise room at Water Reclamation once a week.
3. Once a week $18.00 For service from Mar —Dec 2004 - $792.00
4. No change in contract time.
ORIGINAL CONTRACT COST $337,068.90
APPROVED CHANGE ORDERS 9,382.93
TOTAL PENDING CHANGE ORDERS -00-
TOTAL THIS CHANGE ORDER 792.00
ADJUSTED CONTRACT COSTS $347,243.83
N
SUBMITTED BY:
REVIEWED BY:
APPROVED
Representative)
Contract Administrator)
,TE a--7n--off
TE Z- a3 - nq
TE O9 "o?S'" 0 `I
DATE
cc: Contractor, Contract Administrator, Dept File, Purchasing (c/o Jim Hume)