HomeMy WebLinkAboutCHANGE ORDER - BID - 5823 19265CHANGE ORDER NO. 01
PROJECT TITLE: CITY OF FORT COLLINS AND CSU TRANSIT CENTER PHASE 1A
CONTRACTOR: G.L. HOFF CO.
PROJECT NUMBER: BID NO.5823
DESCRIPTION:
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: CSU STEAM PIPING REPLACEMENT
2. Description of change: 445 LF STEAM TUNNEL LID
3. Change in contract cost: $12,014.58
4. Change in contract time: CHANGE FROM FEB 11, 2004 TO MARCH 5, 2004
(Attach additional sheets as required)
ORIGINAL CONTRACT COST ............................................... $208,761.00
TOTAL APPROVED CHANGE ORDERS............................................00.00
TOTAL PENDING CHANGE ORDERS .............................................. 00.00
TOTAL THIS CHANGE ORDER ......... .................................. ....... 12,014.58
ADJUSTED CONTRACT COST.....................................$220,775.58
(Assuming all change orders approved)
ACCEPTED
APPROVED
APPROVED BY:
Steve White, Ci" Fort Collins, Project Manager
Cass Beitler,
APPROVED BY:���7
Tom
cc: City Clerk
Contractor
Engineer
Project File
Purchasing
ti
Manager
Manager
- --C'
Date
/&46C h_
Date
1-46 ^0 5- -
Date
I- 2'7-
Date
JAN-09-20N FR- 0°;46 AN U, NOF= �C, H
- - - - - - - - FAX NO, 9706631565
F. 02/04
Q.�sHoFF10M
101111MV811116H [fill
1015 WEST 12TH STREET • P.O. BOX 7448 • LOVELAND, CO W537.0448 • 970-669.3255 • 970-663-15N FAX
Proposal Request Project # 03.171
Number. 1 Revised
Project C.O.F.C. / C.S.U. Transit Center Phase 1A Date: 1/9I04
Owner. City of Fort Collins / Cdorado State University
Description:
Fort Pour and Finish Approximately 445 linear fee; of Tunnel Lid per attached
drawing by S A Miro inc. reoleved 1230.03 (raime:l 12-31-03)
Attachments:
VIA: Prcied Manager / Steve White
Change Proposal Request:
Equipment Rental
$
250.00
Services and Supplies
5
Labor
$
2,520.00
Materials
$
6.144.0n
Subcontracts
$
1,700.00
Subtotal
$
9,614.00
GC General Conditions
$
961,40
GC Markup
$
1,416.33
GC Bond
$
22.85
Total cost of change
$
12,014.68 Unit cost $27.38 per liner ft.
Calendar Days Extension to Contract Completion 23
No Change in Contract Price (Initial 9 no change)
ADD to the Contract Price $12,014-58
DEDUCT iron the Contract Price
CONTRACTOR'S SIGNATURE:
Approved by Architect.
Approved by Owner:
Canceled by Architea/Ovn>er:
Approved Change in want request will be included in a future formal change order.
1 /9m