HomeMy WebLinkAboutRESPONSE - BID - 5826 CITY PARK MOSS ROCK WALL (9)SECTION 00300
BID FORM
PROJECT: CITY PARK MOSS ROCK WALL; Bid No. 5826
Place City of Ft. Collins Purchasing Div.
Date December 4, 2003
1. In compliance with your Invitation to Bid dated November 5, 2003
and subject to all conditions thereof, the undersigned
Delta Construction, Inc. a **(Corporation, Limited Liability Company,
Partnership, Joint Venture, or Sole Proprietor)** authorized to do business
in the State of Colorado hereby proposes to furnish and do everything
required by the Contract Documents to which this refers for the
construction of all items listed on the following Bid Schedule or Bid
Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this proposal
is made in good faith, without collusion or connection with any other
person or persons Bidding for the same Work, and that it is made in
pursuance of and subject to all the terms and conditions of the Invitation
to Bid and Instructions to Bidders, the Agreement, the detailed
Specifications, and the Drawings pertaining to the Work to be done, all of
which have been examined by the undersigned.
3. Accompanying this Bid is a certified or cashier's check or standard Bid
bond in the sum of 5% ($
Instructions to
in accordance with the Invitation To Bid and
Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this Bid.
The name and address of the corporate surety with which the Bidder
proposes to furnish the specified performance and payment bonds is as
follows:United Fire & Casualty Company - Cedar Rapids, Iowa.
5. All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned,
included by implication or appurtenant thereto, are to be performed by the
CONTRACTOR under one of the items listed in the Bid Schedule, irrespective
of whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents.
7. The undersigned Bidder hereby acknowledges receipt of Addenda No.
through N/A
7/96 Section 00300 Page 1
PAUL HOFFMAN
CEO
DELTA CONSTRUCTION, INC.
EXPERIENCE:
1993 — PRESENT DELTA CONSTRUCTION OF NORTHERN COLORAD09 INC., FORT COLLINS,
COLORADO
CEO
Delta is a General Contracting firm with over 25 years of experience in Southeastern
Wyoming and Northern Colorado. Annual sales of $11 million
1988 —1993 THE NEENAN COMPANY, FORT COLLINS9 COLORADO
Project Manager
Responsible for owner coordination, contract administration, subcontractor
negotiation, project buyout, project scheduling and estimating.
MAJOR PROJECTS INCLUDE:
• Northgate Office Building: 10,200 square foot office building in Laramie,
Wyoming.
• First National Bank of Wyoming: Branch bank in Laramie, Wyoming.
• First National Bank: Two banking facilities with drive -ups in Loveland,
Colorado.
• Centennial Medical Office Building: 70,000 square foot MOB in South Denver,
Colorado.
• First National Bank Plaza: Branch bank in Fort Collins, Colorado.
• First National Bank: Drive -up remodel for main bank in Fort Collins, Colorado.
• Custom Homes at Ptarmigan Golf Course in Fort Collins, Colorado.
• Custom Homes in Laramie, Wyoming
• McCarty Honda/KIA: Showroom and detail area in Laramie, Wyoming.
• United States Wildlife: Tenant improvements for Government R&D Lab in Fort
Collins, Colorado.
• Front Range Steel: 14,000 square foot steel fabricating plant with separate office
building in Wellington, Colorado.
• River Bend Park Phase I & II: Self -developed 15,000 square foot
industrial/commercial building in Laramie, Wyoming.
• Bowman Brewpub in Downtown Laramie, Wyoming.
• Fish's Liquor Mart: 10,000 square foot precast concrete building in Fort Collins,
Colorado.
• Orthopedic Center of the Rockies, MRI: 3,526 square foot magnetic imaging
medical office building in Fort Collins, Colorado.
• Oppenheimer Management Corporation: 42,970 square foot two-story office and
production building in Denver, Colorado.
• Gerry Baby Products: 385,000 square foot facility including an office building
(40,000 S.F.), 3 production buildings (71,000 S.F. each), and a warehouse
building (131,000 S.F.) in Thornton, Colorado.
Pan[ Iloifinan, President. Delta C onstrtictioll. Inc.
Page I
• Donnelly Applied Films: 38,700 square foot office building in Boulder,
Colorado.
• First Interstate Bank Drive -up Facility: 1,400 square foot drive -through banking
facility in Fort Collins, Colorado.
• First Interstate Bank Branch Office Facility: 3,800 square foot office banking
facility in Fort Collins, Colorado.
• Western Forge: 56,000 square foot production and warehouse facility in
Colorado Springs, Colorado.
• Data Ray: 65,000 square foot production facility for computers in Westminster,
Colorado.
• D.I.S.C.: 40,200 square foot high -end office building in Boulder, Colorado.
• Builder's Square: 90,000 square foot retail/warehouse building in Fort Collins,
Colorado.
• Valli Hi Plaza: Project included a Walgreen's retail space and a complete
renovation of a retail strip center in Colorado Springs, Colorado.
• Broomfield Family Practice: 16,000 square foot medical office building in
Broomfield, Colorado.
• ESAB Automation: 108,000 square foot office and manufacturing facility in Fort
Collins, Colorado.
• Avista Medical Office Building: 40,000 square foot three-story medical office
building in Louisville, Colorado.
• Orthopedic Center of the Rockies: 43,000 square foot two-story orthopedic
facility in Fort Collins, Colorado.
1987 — 1988 WESTERN STATES CONSTRUCTION COMPANY, INC., LOVELAND, COLORADO.
Cost and Scheduling Engineer: Developed and maintained project schedules and
overall project cost control.
Estimator: Responsible for lump sum and unit price bids ranging in contract price
from $200,000 to $20 million.
Contract Quality Control Representative: Responsible for quality control, field
inspection, submittal review and report documentation.
Project Engineer: Responsible for project control, submittal administration,
estimating and buyout.
1985 -1987 COLORADO STATE UNIVERSITY, DEPARTMENT OF INDUSTRIAL SCIENCES, FORT
COLLINS, COLORADO.
Instructor: Taught an evening graduate class in Microcomputer Applications in
Construction. Software taught includes Lotus 1-2-3, Primavera, as well as database
and word processing applications.
Graduate Teaching and Research Assistant: Taught a graduate -level course in
Computer Applications. Assisted in teaching a senior -level Scheduling and Cost -
Control course, and taught six drafting fundamentals courses.
SUMMER 1986 DELTA CONSTRUCTION COMPANY, INC., LARAMIE, WYOMING
Estimator
Managed entire bidding process for lump sum projects. Developed a computerized
estimating system.
JANUARY 1985 - M.A. MORTENSON CONSTRUCTION COMPANY, LAKEWOOD, COLORADO
JULY 1985 Carpenter
Worked in all aspects of carpentry for the construction of a $20 million Marriott
Hotel.
1'aul ll<>thnan, ['resident, Delta Col75tfucti()1a, Inc,
Page
1983- 1986 INDEPENDENT CONTRACTOR
Designed, estimated and constructed residential construction projects.
1980 - 1985 DELTA CONSTRUCTION COMPANY, INC., LARAMIE. WYOMING
Labor Foreman
Supervised laborers and general construction fieldwork.
EDUCATION:
MAY 1987 COLORADO STATE UNIVERSITY, FORT COLLINS, COLORADO
Master of Science in Construction Management
MAY 1984 UNIVERSITY OF WYOMING, LARAMIE, WYOMING
Bachelor of Science in Manufacturing Technology
Paul lloftrnan, President. Delta C onstructjon� lnci
Page 3
EXPERIENCE:
2000
1992 — 2000
1991-1992
1988 —1989
1986 —1987
GREG ORR
DIRECTOR OF OPERATIONS
DELTA CONSTRUCTION, INC.
DELTA CONSTRUCTION COMPANY9 INC.9 FORT COLLINS, COLORADO
Director of Operations
NEENAN COMPANY
Senior Project Manager
ADOLFSON & PETERSON
Field Engineer
WALTERS CONSTRUCTION MANAGEMENT
Labor Foreman
F.R. ORR CONSTRUCTION COMPANY
Laborer
MAJOR PROJECTS INCLUDE:
• Kids Harbor Daycare: 11,200 square foot day care facility constructed of
wood frame with EFIS and timber architecture, Loveland, Colorado.
• Obermann Dental Office: 12,000 square foot dental office with the latest in
technology and innovations, Fort Collins, Colorado.
• Vision Graphics: 22,000 square foot tilt -up structural addition to existing
production floor, Loveland, Colorado.
• Cytomation Phase I and II: Two buildings totaling 80,000 square feet of
storage/lab/R&D/office space, Fort Collins, Colorado.
• Dovatron: 72,000 square foot office and production facility, Longmont,
Colorado
• Union Medical Campus Phases I and II: 6.5 million dollar, 145,000 square
foot, medical office buildings, Colorado Springs, Colorado.
• Boston Chicken Corporate Headquarters: 92,000 square feet ($9,600,000)
Phase II of Boston Chicken/ Einstein Bagels Headquarters, Golden, Colorado.
• Triad West: 105,000 square foot spec warehouse/office/production facility,
Golden, Colorado.
• Balzers Thin Films: $1,200,000 tenant finish with classroom and clean rooms,
Golden, Colorado.
• Quantum SSPG: 460,000 square foot office, warehouse, and production
facility including a 700-person full service cafeteria, Colorado Springs,
Colorado.
• 1899 Wynkoop: 270,000 square foot, $17,600,000 office, retail and
underground parking, Denver, Colorado.
G"i'_; OU, PAIJOCI. VLina-goo- I)ttt;.a C_onsi "coon;. Inc, Page 1
EDUCATION:
1992 COLORADO STATE UNIVERSITY, FORT COLLINS, COLORADO
Bachelors of Science, Construction Management
1996 Primavera training courses including P3 scheduling and expedition
Cleanroom Design Build workshop, Arizona State University.
1997 Alliance for Construction Excellence Clean room Taskforce hosted by Arizona
State University's Del E. Webb School of Construction.
Greg Orr. [`rolie t Manat >r, 1Mia C.orlctruc,ion, inc. Page 2
JOHN BAKER
CONSTRUCTION MANAGER
DELTA CONSTRUCTION, INC.
EXPERIENCE:
1999 - PRESENT DELTA CONSTRUCTION, INC., FORT COLLINS, COLORADO
Preconstruction Manager
1992 -1999 THE NEENAN COMPANY, FORT COLLINS, COLORADO
Preconstruction Manager/Project Manager
1986 -1992 HENSEL PHELPS CONSTRUCTION COMPANY, GREELEY, COLORADO
Project Engineer
MAJOR PROJECTS INCLUDE:
• The Ranch at Larimer County Fair Grounds: five pre-engineered metal buildings
totaling 230,000 square feet. These buildings include the Maintenance Building,
Exhibition Building, Indoor Arena along with the East and West Livestock
Pavilions, Loveland, Colorado.
• Obermann Dental Office: 12,000 square foot dental office with the latest in
technology and innovations, Fort Collins, Colorado.
• Vision Graphics: Preconstruction services for a 22,000 square foot site -cast high
bay warehouse addition to existing facility located near Loveland Airport,
Colorado.
• Cytomation I, II, III: Preconstruction services for three one-story brick buildings
totaling 80,000 square feet. Consists of storage, lab, and office areas in Fort
Collins, Colorado.
• Hercules Industries: Preconstruction services for a 12,000 square foot masonry
addition with matching facade to an existing building; including an additional
12,000 square foot spec office/warehouse.
• Veeco/Ion Tech: 24,000 square foot pre -cast core and shell building.
• Vi-Per Investments: Preconstruction services for a 12,000 square foot, two-
story, core and shell finish.
• Ball Aerospace & Technologies Corp: 117,700 square foot, $13 million R&D
facility for the development of high tech communication devices. The facility
includes a 30,000-gallon immersion tank, 90,000 square feet of high bay testing
and integration space with 15-ton overhead cranes, and 27,000 square foot office
space. This project is located adjacent to Jefferson County Airport and required
extensive coordination with FFA and Airport Authority, Broomfield, Colorado.
• Quantum Peripherals -Phase 2: An additional 67,000 square feet of research
facility and approximately 20,000 square feet of two-story office space,
Louisville, Colorado.
• Quantum Peripherals -Phase 1: 190,000 square foot facility with 60,000 square
feet of two-story office and cafeteria space and 130,000 square feet of high bay
research and utility support spaces at a total project cost of $49 million,
Louisville, Colorado.
.tohn I3 her. Cmigrc€cNcit3 khmaLer Delta C'orasiruc�ti�>�q, istc. Pace I
• Longmont United Hospital: Five story patient bed tower located on the existing
LUH campus. Facility includes two floors of patient recovery rooms, NICU,
cafeteria, meeting rooms, conference rooms, lobby and administrative space,
Longmont, Colorado.
• Rocky Mountain Cancer Center: This three story 39,000 square foot facility
required extensive negotiations with Denver's Uptown Hospital District to meet
their design and construction covenants, Denver, Colorado.
• Midtown Surgery Center: 18,000 square foot outpatient surgery center consisting
of pre and post operation, four operating rooms, twenty-three hour recovery
rooms and administrative space, Denver, Colorado.
• Plum Creek Medical Center: 12,000 square foot gatekeeper facility consisting of
medical office, imaging and emergency care, Castle Rock, Colorado.
• Poudre Valley Hospital -A, B and C Wing Remodel and Additions: $18 million
addition of fourth and fifth floors to existing wing and new construction of B
Wing and C Wing, Fort Collins, Colorado.
• Colorado Convention Center: $95 million convention center for the City and
County of Denver constructed in a fast track, design build format in eighteen
months, Denver, Colorado.
OTHER PROJECTS:
Assignments with HPCC prior to being promoted to Project Engineer include
Stapleton B Concourse for United Airlines in Denver, Colorado, the Atlas Centaur
facility for General Dynamics in San Diego, California, the Device Assembly
Buildings for the Department of Energy near Las Vegas, Nevada and the Blade
Repair facility for the U.S. Air Force at Tinker Air Force Base, Oklahoma — among
others.
EDUCATION:
DECEMBER 1985 COLORADO STATE UNIVERSITY, FORT COLLINS, COLORADO
Bachelor of Science in Industrial Construction Management
John Bakm C'on�t:rucnk.gj 1hi a_uien Delta ConsLruct on. lac. I'<:<y u
Amended Bid Schedule
Project: City Park Moss Rock Wall
Date: 12/11/2003
Bid Description
Delta
Delta
Item Contract
Construction
I
Construction
I
Quantit
Unit
Unit Price
TOTAL
1
Mobilization
1
LS
$ 5,518.59
$ 5,518.59
2
Tree Protection
1
LS
$ 1,055.44
$ 1,055.44
3
Traffic Control
1
LS
$ 926.62
$ 926.62
4
Moss Rock Wall - One side veneer
222
LF
$ 223.81
$ 49,685.82
5
Moss Rock Wall - Two side veneer
25
LF
$ 223.12
$ 5,578.00
6
Moss Rock Column - 4'6" ht
2
EA
$ 460.06
$ 920.12
7
Imoss Rock Column - 5'6" ht
2
EA
$ 709.04
$ 1,418.08
8
French Drain
235
LF
$ 8.80
$ 2,068.00
CONSTRUCTION TOTAL
67,170.67
gnature
Corporate Seal
Attest
Date
SECTION 00410
BID BOND
KNOW ALL,
MEN BY THESE PRESENTS:
that
we,
the undersigned
DELTA *
as Principal, and UNITED FIRE & CASUALTY COMPANY
as
Surety, are
hereby held and firmly bound unto the
City
of Fort
Collins, Colorado,
as OWNER, in the sum of **$ for
the
payment
of which, well and
truly to be
made, we hereby jointly and severally
bind
ourselves, successors, and
assigns.
THE CONDITION of this obligation is such that whereas the Principal has
submitted to the City of Fort Collins, Colorado the accompanying Bid and hereby
made a part hereof to enter into a Construction Agreement for the construction of
Fort Collins Project, CITY PARK MOSS ROCK WALL; BID NO. 5826.
NOW THEREFORE,
(a) If said Bid shall be rejected, or
(b) If said Bid shall be accepted and the Principal shnil execute and deliver a
Contract in the form of Contract attached hereto (properly complcted in
accordance with said Bid) and shall furnish a BOND for his faithful
performance of said Contract, and for payment of all persons performing
labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said Bid,
then this obligation shall be void; otherwise the same shall remain in
force and effect, it being expressly understood and agreed that the
liability -of the Surety for any and all claims hereunder shall, in no
event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the obligations
of said Surety and its BOND shall be in no way impaired or affected by any
extension of the time within which the OWNER may accept such Bid; and said Surety
does hereby waive notice of any such extension.
Surety Companies executing bonds must be authorized to transact- business in the
State of Colorado and be accepted by the OWNER.
* CONSTRUCTION OF NORTHERN COLORADO, INC., 208 Racquette Drive, Fort Collins, CO 80524
** Five Percent (5%) of the Total Amount of the Bid
7/96 Section 00410 Paqe 2
w
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands
and seals this 4th day of December 20 031 and such of them as are
corporations have caused their corporate' -seals to be hereto affixed and these
presents to be signed by their proper officers, the day and year first set forth
above.
PRINCIPAL
DELTA CONSTRUCTION OF NORTHERN
Name: COLORADO, INC.
Address: 208 Racquette Drive
Fort Collins, Colorado A0524
By: 1-j✓
Tyrf �t WMEW
�. ✓ I.r�
(SEAL)
7/96
SURETY
UNITED FIRE & CASUALTY COMPANY
1660 S. Albion Street, Suite 907
Title: Atl
(SEAL)
Section 00410 Page 3
DElta Construction of Northern Colorado, Inc.
CONTRACTOR
BY: P ul Hof
ADDRESS: 208 Racquette Drive
Ft.Collins, CO 80524
8. BID SCHEDULE (Base Bid)
Please use the attached Bid Schedule when submitting your bid.
9. PRICES
The foregoing prices shall include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc., to cover
the complete Work in place of the several kinds called for.
Bidder acknowledges that the OWNER has the right to delete items in the Bid
or change quantities at his sole discretion without affecting the Agreement
or prices of any item so long as the deletion or change does not exceed
twenty-five percent (25%) of the total Agreement Price.
RESPEC UL SUBM T D:
10
Signa ure D!Y-I-
PrPRident
A-99
License Number (If Applicable)
(Seal - if Bid is by cor ration)
Attest Pill- I
Address 208 Racquette Drive
Collins. CO 80524
Telephone 970-498-8766
7/96 Section 00300 Page 2
No Text
CITY PARK MOSS ROCK WALL
BID SCHEDULE
Bid items are described in Section 01800
BID
ESTIMATED
ITEM #
DESCRIPTION
QUANTITY
UNIT
1
Mobilization
LS
2
Tree Protection
1
LS
3
Traffic Control
1
LS
4
Moss Rock Wall - One side veneer
222
LF
5
Moss Rock Wall - Two side veneer
25
LF
6
Moss Rock Column - 4' 6" height
2
EA
7
Moss Rock Column - 5' 6" height
2
EA
8
French Drain
235
LF
TOTAL BID
(written)
UNIT
PRICE
$ A, S/8.
of-
$ / O�'
$
Section 00300 Page 3
ITEM
TOTAL
Figure
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 150 of the contract.
ITEM
*, �S,OVA y
7/96
SUBCONTRACTOR
Section 00430 Page 1
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and
comprehensive. This statement must be notarized. If necessary, questions may be
answered on separate attached sheets. The Bidder may submit any additional
information he desires.
1. Name of Bidder: Delta Construction of Northern Colorado, Inc.
2. Permanent main office address
3. When organized: 1975
208 Racquette Dr. Fort Collins, CO
4. If a corporation, where incorporated: Colorado
5. How many years have you been engaged in the contracting business under your
present firm or trade name? 5
6. Contracts on hand: (Schedule these, showing the amount of each contract and
the appropriate anticipated dates of completion.)
Please see attached "Work Under Contract"
7.
General character of Work performed by your
General Contracting, Supervision, and
compan :
Car- Kry
8.
Have you ever failed to
If so, where and why?
complete any Work awarded to you? No
9.
Have your ever defaulted
If so, where and why?
on a contract? No
10.
Are you debarred by any
If yes list agency name.
government agency?
No
7/96 Section 00420 Page 1
11. List the more important projects recently completed by your company,
stating the approximate cost of each, and the month and year completed,
location and type of construction.
Please see attached "Delta's Major Project List"
12. List your major equipment available for this contract.
Skidster, one -ton truck theodilite, laser level
13. Experience in construction Work similar in importance to this
project:
CSU Ropes Course, I-80 Landscape for the City of Laramie, Timnath
Town Hall Restoration and numerous landscaping and retaining wa s
tied to various construction projects
14. Background and experience of the principal members of your organization,
including officers:
See attached resumes for Greg Orr, Paul Hoffman, and John Baker
4
15. Credit available: $ 500,000
16. Bank reference: First National Bank, Todd Campbell, 970-482-4861
17. Will you, upon request, fill out a detailed financial statement and furnish
any other information that may be required by the OWNER?
.,...
18. Are you licensed as a General CONTRACTOR? yes
If yes, in what city, county and state -Loveland, Ft. Collins & CFhytnne
class, license and numbers?Glass A-99 and Class A # 04 12108
19. Do you anticipate subcontracting Work under this Contract?yes
If yes, what percent of total contract? 80sk
and to whom? _q,, Suhrnntrartors List
20. Are any lawsuits pending against you or your firm at this time?No
If
DETAIL yes,
7/96 Section 00420 Page 2
21. What are the limits of your public liability? DETAIL
$2,000,000 for General Aggregate, $3,000,000 for Excess Liability
What company? Travelers Insurance
22. What are your company's bonding limitations? Single Project= $5,000,000
Aggregate Program = $8,000,000
23. The undersigned hereby authorizes and requests any person, firm or
corporation to furnish any information requested by the OWNER in
verification of the recital comprising this Statement of Bidder's
Qualifications.
Dated at 3:00 p.m. this 4th day of December 2003,
iia�iuc.�rc�n or ivortnern Colorado, Inc.
Name of Bidder
By: Paul Hoffman
t
Title: CEO
State of Colorado
County of Larimer
Paul Hoffman being duly sworn deposes and says that he is
CEO of Delta Construction of N.C. and that
(name of organization)
the answers to the foregoing questions and all statements therein contained are
true and correct.
scribed and sworn to before me this 4 - day of
^L 200=1
lic
My commission expires
,SPRY. Pv
20: hod
'JEANNA W.
WHIPPLE
_ ......;Q
My CagYMiron Exp res Aug. 31. 2001
7/96 Section 00420 Page 3
CONSTRUCTION, INC.
WORK UNDER CONTRACT
Start
Schedule
Project Name
Owner/Client
Contract Amount
Date
Completion
TriHydro
TriHydro
$
1,935,000
Oct-03
May-04
Value Plastics
Mike Rainsberger
Value Plastics
970-223-9769
$
300,000
Aug-03
Oct-03
Nortrak
Nortrak
Robert Krenser
$
302,048
Jul-03
Nov-03
Rio Grande Hospital
Valley Citizens Foundations
$
525,000
Dec-03
Jan-04
City of Fort Collins
Larimer County
Babs Cornel
Community Corrections
970-498-5907
$
4,000,000
Mar-03
Apr-04
Colorado State University
CSU Dairy Barn
Bill Conn
$
80,862
Hold
n/a
Paul Hoffman
Design
DCI Windsor II
970-498-0827
$
280,500
Phase
N/A
Total Work Under Contract $ 5,488,410
Work Under Contract Page 1
CONSTRUCTION, INC. Deltas Major Project List
Consaactio
Contract
Name
Description
Project Address
Facility Type
n Type
Amount
Fiaish Date
327 S. Link Lane
Carriage Shoppe
Industrial
Fort Collins, CO
Addition
Commercial
$433,480
May-03
5225 Yellowstone Blvd.
New Metal
Cool River Wine _&_Spirits
`
Retail Building_ _
Cheyenne, WY
Building
Commercial
S483,487
Jun-03
625 Sherry Drive
New
Marrou Concrete
Commercial Office Bldg. Fort Collins, CO
Construction
Commercial
$500,000
Jan-99
7320 Greendale Road
New Metal
Legacy Counters
Office/Manufacturing
Windsor, CO
Building
Commercial
$525,814
Jun-03
4715 Innovation Dr.
AMCC
Office Tenant Finish
Fort Collins, CO
Commercial TF
Commercial
$593,000
Jan-01_
148 E. Foothills Pkway
Retail
Gear Tire Center
Retail Rennovation
Fort Collins, CO
rennovation
Commercial
$60_0,000
Oct-00
7250 Greenridge Rd
New Metal
Schmidt Earthbuilders
Office/Industiral
Windsor, CO _
Building
Commercial
$624,660
Mar-03
311 W. Licolnway
New Metal
Cheyenne Tech Center
New Office Building
Cheyenne, WY —
Building
Commercial
$630,000
Jul-99
3325 Timberline
New Metal
Value Plastics _
Airplane Hanger —
Fort Collins, CO
Building
Commercial_
$750,000
Dec-98
2330 East Prospect
__
New
Veeco/Ion Tech
High Tech R&D
Fort Collins, CO
Construction
Commercial
$806,000
Apr-00
4700 Innovation Drive
New
Merit Electric —_
Commercial Office Bldg. Fort Collins, CO
Construction
Commercial
S900,000
Aug-98
4700 Innovation Drive
New
Cyotmation Bldg lI
Office/Biomedical/R&D
Fort Collins, CO _
Construction
Commercial _
$1,029,887
Sep-01
1220 Oakpark Drive
New
ToothZone
Dental Office
Fort Collins, CO
Construction
Commercial
$1,051,297
Mar-02
Patton Avenue in
New Metal
Advanced Manufacturing
Office/Manufacturing _Loveland
Building
Commercial
$1,098,845
Oct-03
1801 Piney River Drive
New
Kids' Harbor Daycare _!_
Daycare facility _
Loveland, CO _
Construction
Commercial
$1,100,000
Aug-02
New
Cathedral Home for Children Educational Facility
Laramie, WY
Construction
Commercial
$1,100,000
Dec-02
4715 Innovation Dr.
Hercules Industries
office/ Warehouse
Fort Collins, CO
New Addition
Commercial
$1,162,760
Sep-00
4700 Innovation Drive
New
_
C�mation Bldg I
Office/Biomedical/R&D
Fort Collins, CO
Construction
Commercial
$1,200,000
Feb-01_
3693 County Rd. 30
New
Scion Industries _
Office / Industrial
Fort Collins, CO
Construction
Commercial
$1,505,000
Mar-02
201 W. 67th Court
New
Vi-Per Vet Clinic
2 veterinary bldgs.
Loveland, CO
Construction
Commercial
$2,100,000
Aug-00
4 Pre-engineered Metal
Crossroads Blvd.
New
_
Larimer County Fairgrounds
Buildings
Loveland, CO
Construction
Commercial
$3,232,895
Jun-03
1267 N. 15th Street
New
_
Reynolds Crossing
Office/Campus
Laramie, WY
Construction
Commercial
$4,200,000
On going
4373 N. Street
New
WyoTech Hotrod Shop
Educational/industrial
Laramie, WY
Construction
Commercial
$5,299,650
Dec-02
4007 Automation Dr.
New
Healing Arts Institute
Educational/Office Bldgs Fort Collins, CO
Construction
Commercial
$8,000,000
Mar-99