Loading...
HomeMy WebLinkAboutCORRESPONDENCE - BID - 5800 POUDRE TRAIL REHABILITATION (3)TABLE OF CONTENTS TECHNICAL SPECIFICATIONS DIVISION 1 GENERAL REQUIREMENTS Schedule of Drawings Section 01000 Project Summary Section 01100 Summary of Work Section 01160 Site Conditions Section 01200 Measurement and Payment Section 01300 Coordination and Project Meetings Section 01310 Construction Schedules Section 01330 Shop Drawings, Product Data and Samples Section 01340 Survey Data Section 01400 Quality Control and Testing Section 01500 Temporary Controls Section 01510 Temporary Utilities Section 01570 Traffic Control Section 01600 Material and Equipment Section 01700 Contract Close -Out Section 01800 Definition of Bid Items DIVISION 2 SITEWORK Section 02050 Demolition Section 02100 Mobilization Section 02200 Earthwork and Grading Section 02221 Trenching, Backfilling and Compaction Section 02250 Topsoil Section 02520 Portland Cement Concrete Paving Section 02900 Site Revegetation City of Fort Collins Table of Contents Park Planning and Development Page 1 of 1 DIVISION 1 SECTION 01200 - MEASUREMENT AND PAYMENT PART 1 -GENERAL 1.01 Description A. This section covers the methods employed in determining the payment due for work completed under this contract. B. The bid price should cover all work required by this contract based upon the quantities outlined in the bid form. C. Where actual quantities differ from those outlined in the bid form; unit prices as stipulated in the bid form shall be utilized to compute payment. D. Where unit prices are not set forth on specific work, that work shall be considered a subsidiary obligation of the Contractor. E. Quantities given in the bid form are estimates for the purpose of evaluating bids consequently some difference may arise in actual and bid quantities. 1.02 Lump Sum Prices A. Where lump sum (LS) prices are given for an item in the bid schedule or for items added during construction by change order, the price will include all materials, labor, overhead and any other cost incurred to complete the construction of the item in accordance with the plans and specifications. B. All unit prices for each item shall include its pro rata share of profits, taxes, and overhead, and are for the items installed in place, maintained and guaranteed. Including these factors, unit prices must accurately reflect actual costs. Unit prices are to be valid for the life of the contract. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION City of Fort Collins SECTION 01200 — MEASUREMENT AND PAYMENT Park Planning & Development Division Page 1 of 1 VIBION-T SECTION 01300 — COORDINATION AND PROJECT MEETINGS PART 1-GENERAL 1.01 General A. In order to provide for an orderly progression of work, all parties involved in the construction will meet at various times during the project to discuss pertinent items regarding the work. B. Coordinate operations under contract in a manner that will facilitate progress of the Work. C. Conform to the requirements of public utilities and concerned public agencies in respect to the timing and manner of performance of operations that affect the service of such utilities, agencies, or public safety. 1.02 Conferences A. The pre -construction conference will be held at a time to be determined by the Owner, after the award of the contract and prior to the issuance of the Notice to Proceed. The meeting will involve the Owner, the Engineer, the Contractor and representatives of the owners of utilities and other properties that will be directly affected by the work. Among the Contractor's representative on the site. The Contractor will have a complete construction schedule ready for review at the time of the pre -construction conference. B. Hold conferences for coordination of the Work when necessary. C. The City may hold coordination conferences to be attended by all involved when Contractor's operations affects, or is affected by, the work of others. 1.03 Progress Meetings A. Contractor and the City shall schedule and hold regular progress meetings at least weekly and at other times as requested by the City or required by the progress of the Work. B. Attendance shall include: 1. Contractor and Superintendent 2. Owners Representative 3. Landscape Architect 4. Others as may be requested by contractor, Landscape Architect or Owner C. Minimum Agenda shall include: 1. Review of work progress since last meeting 2. Identifrcation and discussion of problems affecting progress 3. Review of any pending change orders 4. Revisions of Construction Schedule as appropriate 1.04 Job Site Administration A. Contract administration and construction observation services will be provided by the Owner. The Owner will make decisions regarding changes in the work and adjustments in contract quantities and/or unit prices. END OF SECTION City of Fort Collins SECTION 01300 —COORDINATION AND PROJECT MEETINGS Park Planning & Development Division Page 1 of 1 DIVISION 1' SECTION 01310 - CONSTRUCTION SCHEDULES PART 1-GENERAL 1.01 General A. Prepare detailed schedule of all construction operations and procurements after review of tentative schedule by parties attending the pre -construction conference. No work is to begin at the site until City's acceptance of the Construction Schedule. B. For special restrictions on float and time extensions reference is made to the Agreement. 1.02 Format and Submissions A. Prepare Construction and Procurement schedules in a graphic format suitable for displaying schedule and actual progress. B. Submit two copies of each schedule to owner for review. Owner will return one copy to contractor with revisions suggested or necessary for coordination of the Work with the needs of Owner or others. 1.03 Progress Revisions A. Submit revised schedules and reports when changes are foreseen, when requested by City, and with each application for progress payment. B. Show changes occurring since previous submission. l . Actual progress of each item to date. 2. Revised projections of progress and completion. C. Provide a narrative report as needed to define: 1. Anticipated problems, recommended actions, and their effects on the schedule. 2. The effect of changes on schedules of other work. 1.04 City's Responsibility A. City's review is only for the purpose of checking conformity with the Contract Documents and assisting Contractor in coordinating the Work with the needs of the Project. B. It is not to be construed as relieving Contractor from any responsibility to determine the means, methods, techniques, sequences, and procedures of construction as provided in the General Conditions. PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01310 — CONSTRUCTION SCHEDULES Park Planning & Development Division Page 1 of 1 ONIMON 1 i SECTION 01330 — SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1-GENERAL 1.01 Shop Drawings A. Submit newly prepared information drawn accurately to scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Standard information prepared without specific reference to the Project is not a Shop Drawing. B. Shop Drawings include fabrication and installation Drawings, setting diagrams, schedules, patterns, templates, and similar Drawings. Include the following information: 1. Dimensions. 2. Identification of products and materials included by sheet and detail number. 3. Compliance with specified standards. 4. Notation of coordination requirements. 5. Notation of dimensions established by field measurement. 6. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 24 by 36 inches. 7. Submittal: Submit 3 blue- or black -line prints and 2 additional prints where required for maintenance manuals, plus the number of prints needed by the Contractor for distribution. The Owner's Representative will retain 2 prints and return the remainder. a. One of the prints returned shall be marked up and maintained as a "Record Document." 8. Do not use Shop Drawings without an appropriate final stamp indicating action taken. 1.02 Product Data A. Collect Product Data into a single submittal for each element of construction or system. Product Data includes printed information, such as manufacturer's installation instructions, catalog cuts, standard color charts, roughing -in diagrams and templates, standard wiring diagrams, and performance curves. 1. Mark each copy to show applicable choices and options. Where printed Product Data includes information on several products that are not required, mark copies to indicate the applicable information. Include the following information: a. Manufacturer's printed recommendations. b. Compliance with trade association standards. c. Compliance with recognized testing agency standards. d. Application of testing agency labels and seals. e. Notation of dimensions verified by field measurement. f. • Notation coordination requirements. 2. Do not submit Product Data until compliance with requirements of the Contract Documents has been confirmed. City of Fort Collins SECTION 01330 — SHOP DRAWINGS, PRODUCT DATA AND SAMPLES Park Planning & Development Division Page 1 of 3 3. Preliminary Submittal: Submit a preliminary single copy of Product Data where selection of options is required. 4. Submittals: Submit 2 copies of each required submittal; submit 4 copies where required for maintenance manuals plus additional conies as needed by the Contractor for distribution. The Owner will retain one and will return the other marked with action taken and corrections or modifications required. 5. Distribution: Furnish copies of final submittal to installers, subcontractors, suppliers, manufacturers, fabricators, and others required for performance of construction activities. Show distribution on transmittal forms. a. Do not proceed with installation until a copy of Product Data is in the Installer's possession. b. Do not permit use of unmarked copies of Product Data in connection with construction. 1.03 Samples A. Submit full-size, full -fabricated Samples cured and finished as specified and physically identical with the material or product proposed. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture, and pattern. 1. Mount or display Samples in the manner to facilitate review of qualities indicated. Include the following: a. Specification Section number and reference. b. Generic description of the Sample. c. Sample source. d. Product name or name of the manufacturer. e. Compliance with recognized standards. f. Availability and delivery time. 2. Submit Samples for review of size, kind, color, pattern, and texture. Submit Samples for a final check of these characteristics with other elements and a comparison of these characteristics between the final submittal and the actual component as delivered and installed. a. Where variation in color, pattern, or other characteristic is inherent in the material or product represented, submit at least 3 multiple units that show approximate limits of the variations. b. Refer to other Specification Sections for requirements for Samples that illustrate workmanship, fabrication techniques, details of assembly, connections, operation, and similar construction characteristics. c. Refer to other Sections for Samples to be returned to the Contractor for incorporation in the Work. Such Samples must be undamaged at time of use. On the transmittal, indicated special requests regarding disposition of Sample submittals. d. Samples not incorporated into the Work, or otherwise designated as the Owner's property, are the property of the Contractor and shall be removed from the site prior to Substantial Completion, 3. Preliminary Submittals: Submit a full set of choices where Samples are submitted for selection of color, pattern, texture, or similar characteristics from a range of standard choices. The Owner will review and return preliminary submittals with the Owner's notation, indicating selection and other action. City of Fort Collins SECTION 01330 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES Park Planning & Development Division Page 2 of 3 4. Submittals: Except for Samples illustrating assembly details, workmanship, fabrication techniques, connections, operation, and similar characteristics, submit 3 sets. The Owner will return one set marked with the action taken. 5. Maintain sets of Samples, as returned, at the Project Site, for quality comparisons throughout the course of construction. a. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal. b. Sample sets may be used to obtain final acceptance of the construction associated with each set. B. Distribution of Samples: Prepare and distribute additional sets to subcontractors, manufacturers, fabricators, suppliers, installers, and others as required for performance of the Work. Show distribution on transmittal forms. 1.04 Quality Assurance Submittals A. Submit quality -control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality -control submittals as required under other Sections of the Specifications. B. Certifications: Where other Sections of the Specifications require certification that a product, material, or installation complies with specified requirements, submit a notarized certification from the manufacturer certifying compliance with specified requirements. 1. Signature: an officer of the manufacturer or other authorized individual shall sign Certification documents. C. Inspection and Test Reports: Requirements for submittal of inspection and test reports from independent testing agencies are specified in Division 1 Section "Quality Control and Testing," and in the applicable technical specifications. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION 01330 City of Fort Collins SECTION 01330 — SHOP DRAWINGS, PRODUCT DATA AND SAMPLES Park Planning & Development Division Page 3 of 3 DIVISION 1 SECTION 01340 - SURVEY DATA PART 1 - GENERAL 1.01 Survey Requirements A. Contractor is responsible for the layout of the Work. The City will not provide surveying. B. Base all measurements, both horizontal and vertical, on established control points. Verify all established control points at site prior to laying out the work. C. Perform layout of the Work with qualified personnel. 1. At minimum stake concrete sidewalks at grade changes, changes in horizontal alignment, and at 25-foot stations along the sidewalk centerline. D. All field books, notes, and other data developed by Contractor in performing surveys required by the Work will be available to City for examination throughout the construction period. 1.02 Submittals A. Submit to City all survey data with other documentation required for final acceptance. PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01340 - SURVEY DATA Park Planning & Development Division Page 1 of 1 DIVISION 1 SECTION 01400 - QUALITY CONTROL AND TESTING PART 1 -GENERAL 1.01 General A. Provide such equipment and facilities as the City may require for conducting field tests and for collecting and forwarding samples. Do not use any materials or equipment represented by samples until tests, if required, have been made and the materials or equipment are found to be acceptable. Any product that becomes unfit for use after approval hereof shall not be incorporated into the work. B. All materials or equipment proposed to be used may be tested at any time during their preparation or use. Furnish the required samples without charge and give sufficient notice of the placing of orders to permit the testing. Products may be sampled either prior to shipment or after being received at the site of the work. C. Tests shall be made by an accredited testing laboratory selected by the Owner. Except as otherwise provided, sampling and testing of all materials and the laboratory methods and testing equipment shall be in accordance with the latest standards and tentative methods of the American Society for Testing Materials (ASTM). D. Where additional or specified information concerning testing methods, sample sizes, etc., is required, such information is included under the applicable sections of the Specifications. Any modification of, or elaboration on, these test procedures which may be included for specific materials under their respective sections in the Specifications shall take precedence over these procedures. 1.02 Test Reports A. Submit 2 copies of the reports of all tests made by testing laboratories, plus copies to be returned to the contractor. 1.03 City's Responsibilities A. City of Fort Collins shall be responsible for and shall pay all costs in connection with the following testing: Soils compaction tests. 2. Tests not called for by the Specifications of materials delivered to the site. 3. Concrete test 1.04 Contractor's Responsibilities A. In addition to those inspections and tests called for in the General Conditions, Contractor shall also be responsible for and shall pay all costs in connection with testing required for the following: 1. All performance and field testing specifically called for by the specifications. 2. All re -testing for Work or materials found defective or unsatisfactory, including tests covered under 1.03 above. 3. Testing of pipe. 4. Vacuum testing of manholes. 5. Concrete materials and mix designs. 6. Gradation tests for embedment, fill and backfill materials. 7. Material Substitution - any test for basic material or fabrication of equipment offered as a substitution for a specified item on which a test may be required in order to prove it compliant with the specifications. City of Fort Collins SECTION 01400 - QUALITY CONTROL AND TESTING Park Planning & Development Division Page 1 of 2 Nothing contained herein is intended to imply that the Contractor does not have the right to have tests performed on any material at any time for his/her own information and job control so long as the Owner does not assume responsibility for the cost or for giving them consideration when appraising quality materials. 1.05 Transmittal of Test Reports A. Submit 2 copies of each report of tests and engineering data furnished by the Contractor for City Representative's review. The Owner's Representative will retain one and will return the other marked with action taken and corrections or modifications required. B. The testing laboratory retained by the Owner will furnish three (3) copies of a written report of each test performed by laboratory personnel in the field or laboratory. Two (2) copies of each test report will be transmitted to the City Representative and one (1) copy to the Contractor within seven (7) days after each test is completed. 1.06 Contractor's Quality Control System A. General: The Contractor shall establish a quality control system to perform sufficient inspection and tests of all items of work, including that of his subcontractors, to ensure conformance to the functional performance of this project. This control shall be established for all construction except where the Contract Documents provide for specific compliance tests by testing laboratories or engineers employed by the City. Contractor's control system shall specifically include all testing required by the various sections of the Specifications. B. Contractor's quality control system is the means by which he assures himself that his construction complies with the requirements of the Contract Documents. Controls shall be adequate to cover all construction operations and should be keyed to the proposed construction schedule. C. Records: maintain correct records on an appropriate form for all inspections and tests performed, instructions received from the City and actions taken as a result of those instructions. These records shall include evidence that the required inspections or tests have been performed (including type and number of inspections or test, nature of defects, causes for rejection, etc.) proposed or directed remedial action, and corrective action taken. Document inspections and tests as required by each section of the Specifications. Provide copies to City in a reasonable time. D. Pipe alignment and grade is to be maintained through the use of suitable surveying instruments or laser equipment operated continuously during construction. Horizontal tolerances of + 0.3 feet and vertical tolerances of + 0.1 feet maximum deviation from plan and construction staking are to be maintained, except that visible "snaking" of the horizontal alignment and changes in directions of slope will not be permitted. PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01400 — QUALITY CONTROL AND TESTING Park Planning & Development Division Page 2 of 2 DIMSION I SECTION 01500 - TEMPORARY CONTROLS 1.01 Noise Control A. Take reasonable measures to avoid unnecessary noise when construction activities are being performed in populated areas. B. Construction machinery and vehicles shall be equipped with practical sound muffling devices, and operated in a manner to cause the least noise consistent with efficient performance of the work. C. Cease operation of all machinery and vehicles between the hours of 6:00 p.m. and 7:00 a.m. 1.02 Dust Control A. Dusty materials in piles or in transit shall be covered to prevent blowing. B. Earth and road surfaces subject to dusting due to construction activities and detouring of traffic shall be kept moist with water or by application of a chemical dust suppressant. 1. Chemical dust suppressant shall not be injurious to existing or future vegetation. 1.03 Pollution Control A. Prevent the pollution of drains and watercourses by sanitary wastes, concrete, sediment, debris and other substances resulting from construction activities. 1. Retain all spent oils, hydraulic fluids and other petroleum fluids in containers for disposal off the site. 2. Prevent sediment, debris or other substances from entering sanitary sewers, storm drains and culverts. 1.04 Erosion Control A. Take such measures as are necessary to prevent erosion of soil that might result from construction activities. 1. Measures in general will include: a. Control of runoff. b. Trapping of sediment. c. Minimizing area and duration of soil exposure. d. Temporary materials such as hay bales, sandbags, plastic sheets, riprap or culverts to prevent the erosion of banks and beds of watercourses or drainage swales where runoff will be increased due to construction activities. B. Preserve natural vegetation to the greatest extent possible. C. Locate temporary storage and route construction traffic so as to preserve vegetation and minimize erosion. D. Comply with the City of Fort Collins' Storm Drainage Erosion Control Manual. END OF SECTION City of Fort Collins SECTION 01500 - TEMPORARY CONTROLS Park Planning & Development Division Page 1 of 1 DIVISION.I SECTION 01000 — PROJECT SUMMARY PART 1-GENERAL 1.01 Scope A. This section contains general requirements that are applicable to this project. 1.02 Description of Work A. The Contractor shall provide all labor, materials and equipment necessary to perform the work items called for on the bid schedule. 1.03 City Furnished Materials A. None. 1.04 Conditions of Work A. Area of Work: The Contractor shall confine his operations to the immediate work area. Material storage shall be confined to areas shown on the Drawings or designated by the City. B. Regulations: The Contractor shall comply with all applicable Federal, State, and local regulations pertaining to safety, traffic control, fire prevention, erosion control and environmental protection. C. Working Hours: The Contractor's working hours shall be between 7:00 a.m. and 5:00 p.m., with no work on weekends or Federal holidays, unless otherwise approved by the City. D. Material Storage: The Contractor's material and equipment storage site shall be limited to the area of the project site. The area shall be kept orderly and free of litter. 1.05 Project Cleanup A. The Contractor is responsible to maintain the construction site in a clean and orderly condition from the start of the project to completion. Daily cleanups are required. 1. The City may require Contractor to perform cleanup within 100 feet of the progress of the work and perform cleanup of the site daily prior to work stoppage. B. Store volatile wastes in covered containers and dispose off -site. 1. Provide on -site covered containers for the collection of waste materials, debris and rubbish. 2. Neatly store construction materials, such as concrete forms, when not in use. C. Wastes shall not be buried or burned on the site or disposed of into storm drains, sanitary sewers, streams or waterways. D. At project completion the Contractor shall remove all equipment, materials, and debris from the site including toilets and dumpsters. Areas around work sites shall be cleaned with dirt and grass surfaces raked clean of any slag from the Contractor's operations. Broom clean exterior paved surfaces. Remaining dirt and fill material shall be removed, or may be scattered, with the approval of the City. 1.06 Trash Removal A. All non -salvageable items and trash shall be hauled off the site and disposed of in accordance with applicable state and local regulations. Items shall be transported in tarp -covered or closed vehicles. Any materials dropped or blown off vehicles shall be picked up immediately by Contractor. City of Fort Collins SECTION 01000 -PROJECT SUMMARY Park Planning & Development Division Page 1 of 3 DIVISION 1 SECTION 01510 - TEMPORARY UTILITIES PART 1-GENERAL 1.01 Utilities A. Furnish all utilities necessary for construction including, but not limited to temporary electric power and pay all cost associated with utilities during and used for the contract period. All temporary utilities installation shall meet the construction safety requirements of OSHA, State and local governing agencies. 1.02 Water A. Contractor is responsible for obtaining water for construction and shall pay all costs associated with establishing a temporary meter used during construction. 1.03 Sanitary Facilities A. Furnish temporary sanitary facilities at the site in the vicinity of the construction for the needs of construction workers and others performing work or furnishing services on the Project. B. Properly maintain sanitary facilities of reasonable capacity throughout construction periods. C. Enforce the use of such sanitary facilities by all personnel at the site. D. Obscure sanitary facilities from public view to the greatest extent practical. PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01510 - TEMPORARY UTILITIES Park' Planning & Development Division Page 1 of 1 DM SION 1 SECTION 01570 -TRAFFIC CONTROL PART 1 -GENERAL 1.01 General A. Traffic Control necessary to complete the project as depicted in the plans and specifications will be provided by the Contractor and will not be paid for separately. B. The Contractor must submit traffic control plans and coordinate all traffic control with the City's Traffic Control Coordinator. The traffic control plans must he submitted and approved 72 hours prior to starting construction and before making each modification. C. Conformance: City of Fort Collins Work Area Traffic Control Handbook, Manual of Uniform Traffic Control Devices (U.S. Dept. of Transportation), or applicable statutory requirements of authority having jurisdiction. D. Limited closures may be permitted for short periods up to three days to allow installation of concrete pavement. Closures must be requested and approved 72 hours prior to anticipated closure. E. Limited alternating one-way traffic operation may be permitted during the hours from 9:00 A.M. to 3:30 P.M. One-way traffic operation must be requested and approved 72 hours prior to anticipated operation. F. At all times, Contractor must maintain two-way traffic with a minimum of one lane of traffic in each direction. Limited closures may be allowed. G. The Contractor must coordinate with adjacent residents to provide and maintain them sufficient access during the duration of the project. It will be the Contractor's responsibility to coordinate and communicate with the residents during construction. H. Keep traffic areas free of excavated material, construction equipment, pipe, and other materials and equipment. I. Keep fire hydrants and utility control devices free from obstruction and available for use at all times. J. Conduct operations in a manner to avoid unnecessary interference with public and private roads and drives. K. Provide and maintain temporary approaches or crossings at streets, businesses, and residences. L. Keep roads open and in acceptable condition, unless closure or detour has been approved by City's Traffic Control Coordinator 72 hours prior to closure or detour. M. Define a temporary pedestrian access route for children coming from the surrounding neighborhoods. This pedestrian access route shall be located outside of the project limits. The pedestrian access route shall be kept free of excavated material, construction equipment, pipe, and other materials. 1.02 Traffic Control Plan A. Submit a detailed traffic control plan to Traffic Control Coordinator for review and acceptance. Plan must be accepted 72 hours prior to work commencing at the site. Maintain the accepted plan throughout all phases of construction. Provide copy to Owner prior to submittal. 1. Notify parks dept, police, sheriff, ambulance services, and fire authorities of traffic control plan and the schedule of it. Distribute copies if requested. City of Fort Collins SECTION 01570 - TRAFFIC CONTROL Park Planning & Development Division Page 1 of 2 1.03 Flagmen A. Required where necessary to provide for public safety, or the regulation of traffic, or by jurisdictional authorities. B. Shall be properly equipped and licensed. 1.04 Warning Signs and Lights A. Provide suitable barricades and warning signs for: 1. Open trenches and other excavations. 2. Obstructions, such as material piles, equipment, piled embankment. B. Illuminate by means of warning lights all barricades and obstructions from sunset to sunrise. C. Protect roads and driveways by effective barricades on which are placed acceptable warning signs. 1.05 Parking A. Provide suitable parking areas for the use of all construction workers and others performing work or furnishing services in connection with the Project so as to avoid interference with private property, public traffic, City's operations, or construction activities. Such parking shall occur on the project site or another suitable location, approved by the City. 1.06 Roadway Usage between Operations A. At all times when Work is not actually in progress, Contractor shall make passable and shall open to traffic such portions of the Project and temporary roadways or portions thereof as may be agreed upon between Contractor and City and all authorities having jurisdiction over any properties involved. PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01570 - TRAFFIC CONTROL Park Planning & Development Division Page 2 of 2 , SION 11 SECTION 01600 — MATERIALS AND EQUIPMENT PART 1 -GENERAL 1.01 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. 1.02 Summary A. This Section includes administrative and procedural requirements governing the Contractor's selection of products for use in the Project. 1.03 Definitions A. Definitions used in this Article are not intended to change the meaning of other terms used in the Contract Documents, such as "specialties," "systems," "structure," "finishes," "accessories," and similar terms. Such terms are self-explanatory and have well -recognized meanings in the construction industry. 1. "Products" are items purchased for incorporation in the Work, whether purchased for the Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "systems," and terms of similar intent. 2. "Materials" are products substantially shaped, cut, worked, mixed, finished, refined, or otherwise fabricated, processed, or installed to form a part of the Work. 3. "Equipment" is a product with operational parts, whether motorized or manually operated, that requires service connections, such as wiring or piping. 1.04 Submittals A. Product List: Prepare a list showing products specified in tabular form acceptable to the Owner. Include generic names of products required. Include the manufacturer's name and proprietary product names for each item listed. 1. Coordinate product list with the Contractor's Construction Schedule and the Schedule of Submittals. 2. Form: Prepare product list with information on each item tabulated under the following column headings: a. Related Specifications Section number. b. Generic name used in Contract Documents. C. Proprietary name, model number, and similar designations. d. Manufacturer's name and address. e. Supplier's name and address. f. Installer's name and address. g. Projected delivery date or time span of delivery period. 3. Initial Submittal: Within 30 days of date commencement of the Work, submit 3 copies of an initial product list. Provide a written explanation of omissions of data and for known variations from Contract requirements. City of Fort Collins SECTION 01600 - MATERIALS AND EQUIPMENT Park Planning & Development Division Page 1 of 3 4. Complete List: Within 60 days after date of commencement of the Work, submit 3 copies of the completed product list. Provide a written explanation for omissions of data and for known variations from Contract requirements. 5. Owner's Action: The Owner will respond in writing to Contractor within 2 weeks of receipt of the completed product list. No response within this period constitutes no objection to listed manufacturers or products, but does not constitute a waiver of the requirement that products comply with Contract Documents. The Owner's response will include a list of unacceptable product selections, containing a brief explanation of reasons for this action. 1.05 Quality Assurance A. Source Limitations: To the fullest extent possible, provide products of the same kind from a single source. B. Compatibility of Options: When the Contractor is given the option of seeking between 2 or more products for use on the Project, the product selected shall be compatible with products previously selected, even if previously selected products were also options. C. Foreign Product Limitations: Except under one or more of the following conditions provide domestic products, not foreign products, for inclusion in the Work: 1. Not available domestic product complies with the Contract Documents. 2. Domestic products that comply with the Contract Documents are available only at prices or terms substantially higher than foreign products that comply with the Contract Documents. 1.06 Product Delivery, Storage and Handling A. Delivery, store, and handle products according to the manufacturer's recommendations, using means and methods that will prevent damage, deterioration, and loss, including theft. 1. Schedule delivery to minimize long -tern storage at the site and to prevent overcrowding of construction spaces. 2. Coordinate delivery with installation time to assure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses. 3. Delivery products to the site in an undamaged condition in the manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing. 4. Inspect products upon delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected. 5. Store products at the site in a manner that will facilitate inspection and measurement of quantity or counting of units. 6. Store heavy materials away from the Project structure in a manner that will not endanger the supporting construction. 7. Store products subject to damage by the elements above ground, under cover in a weather -tight enclosure, with ventilation adequate to prevent condensation. PART 2 -PRODUCTS 2.01 Product Selection A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, new at the time of installation. B. Product Selection procedures: The Contract Documents and governing regulations govern product selection. Procedures governing product selection include the following: City of Fort Collins SECTION 01600 — MATERIALS AND EQUIPMENT Park Planning & Development Division Page 2 of 3 1. Proprietary Specification Requirements: Where Specifications name only a single product or manufacturer, provide the product indicated. No substitutions will be permitted. 2. Semiproprietary Specification Requirements: Where Specifications name 2 or more products or manufacturers or where Specifications specify products or manufacturers by name, accompanied by the term "or equal" or "or approved equal," provide one of the products listed or comply with the Contract Document provisions concerning "substitutions" or obtain approval for use of an unnamed product. 3. Nonproprietary Specification Requirements: When Specifications list products or manufacturers that are available and may be incorporated in the Work, but do not restrict the Contractor to use these products only, the Contractor may propose any available product that complies with Contract requirements. Comply with Contract Document provisions concerning "substitutions" to obtain approval for use of an unnamed product. 4. Descriptive Specification Requirements: Where Specifications describe a product or name, provide a product or assembly that provides the characteristics and otherwise complies with Contract requirements. 5. Compliance with Standards, Codes, and Regulations: Where Specifications only require compliance with an imposed code, standard, or regulation, select a product that complies with the standards, codes, or regulations specified. 6. Visual Matching: Where Specifications require matching an established Sample, the Owner's decision will be final on whether a proposed product matches satisfactorily. 7. Visual Selection: Where specified product requirements include the phrase "... as selected from manufacturer's standard colors, patterns, textures..." or a similar phrase, select a product and manufacturer that complies with other specified requirements. The Owner will select the color, pattern, and texture from the product line selected. PART 3 - EXECUTION 3.01 Installation of Products A. Comply with manufacturer's instructions and recommendations for installation of products in the applications indicated. Anchor each product securely in place, accurately located and aligned with other Work. END OF SECTION City of Fort Collins SECTION 01600 — MATERIALS AND EQUIPMENT Park Planning & Development Division Page 3 of 3 DIVISION 1 SECTION 01700 - CONTRACT CLOSEOUT PART 1 -GENERAL 1.01 Related Documents A. Drawings and general provisions of the Contract, including general and supplementary conditions and other Division 1 specification sections, apply to this section. 1.02 Summary A. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: I . Inspection procedures. 2. Project record document submittal. 3. Operation and maintenance manual submittal. 4. Submittal of warranties. 5. Final cleaning. B. Closeout requirements for specific construction activities are included in the appropriate Sections in Divisions 2 through 16. 1.03 Substantial Completion A. Preliminary Procedures: Before requesting inspection for certification of Substantial Completion, complete the following. List exceptions in the request. 1. In the Application for Payment that coincides with, or first follows, the date Substantial Completion is claimed, show 100 percent completion for the portion of the Work claimed as substantially complete. 2. Advise the Owner of pending insurance changeover requirements. 3. Submit specific warranties, workmanship bonds, maintenance agreements, final certifications, and similar documents. 4. Obtain and submit releases enabling the Owner unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases. 5. Submit record drawings, maintenance manuals, final project photographs, damage or settlement surveys, property surveys, and similar final record information. 6. Deliver tools, spare parts, extra stock, and similar items. 7. Make final changeover of permanent locks and transmit keys to the Owner. Advise the Owner's personnel of changeover in security provisions. 8. Complete startup testing of systems and instruction of the Owner's operation and maintenance personnel. Discontinue and remove temporary facilities from the site, along with mockups, construction tools, and similar elements. 9. Complete final cleanup requirements, including touchup painting. 10. Touch up and otherwise repair and restore marred, exposed finishes. B. Inspection Procedures: On receipt of a request for inspection, the Owner will either proceed with City of Fort Collins SECTION 01700 - CONTRACT CLOSEOUT Park Planning & Development Division Page 1 of 6 inspection or advise the Contractor of unfilled requirements. The Owner will prepare the Certificate of Substantial Completion following inspection or advise the Contractor of construction that must be completed or corrected before the certificate will be issued. 1. If the Owner's Representative determines that the work is not substantially complete at the time of review or that deficiencies remain at time of compliance review, the Contractor shall pay for the additional review(s) by Owner's Representative. 2. Results of the completed inspection will form the basis of requirements for final acceptance. 1.04 Status after Substantial Completion A. The date of substantial completion marks the beginning of the maintenance period defined in Section 02970 — Planting Maintenance. B. During maintenance period, the following conditions hold: 1. Insurance: Same as during construction. 2. Electricity and Irrigation Water: Supplied by Owner, as installed by Contractor under this contract. 3. Bonds: Remain in effect. 4. Retainage: Same as during construction. 1.05 Final Acceptance A. Preliminary Procedures: Before requesting final inspection for certification of final acceptance and final payment, complete the following. List exceptions in the request. 1. Submit the final payment request with releases and supporting documentation not previously submitted and accepted. Include insurance certificates for products and completed operations where required. 2. Submit an updated final statement, accounting for final additional changes to the Contract Sum. 3. Submit a certified copy of the Owner's final inspection list of items to be completed or corrected, endorsed and dated by the Owner. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance and shall be endorsed and dated by the Owner. 4. Submit final meter readings for utilities, a measured record of stored fuel, and similar data as of the date of Substantial Completion or when the Owner took possession of and assumed responsibility for corresponding elements of the Work. 5. Submit consent of surety to final payment. 6. Submit a final liquidated damages settlement statement. 7. Submit evidence of final, continuing insurance coverage complying with insurance requirements. B. Reinspection Procedure: The Owner will reinspect the Work upon receipt of notice that the Work, including inspection list items from earlier inspections, has been completed, except for items whose completion is delayed under circumstances acceptable to the Owner. Upon completion of reinspection, the Owner will prepare a certificate of final acceptance, If the Work is incomplete, the Owner will advise the Contractor of Work that is incomplete or of obligations that have not been fulfilled but are required for final acceptance. 2. If necessary, reinspection will be repeated. City of Fort Collins SECTION 01700 — CONTRACT CLOSEOUT Park Planning & Development Division Page 2 of 6 1.06 Record Document Submittals A. General: Do not use record documents for construction purposes. Protect record documents from deterioration and loss in a secure, fire-resistant location. Provide access to record documents for the Owner's reference during normal working hours. B. Record Drawings: Maintain a clean, undamaged set of blue or black line white -prints of Contract Drawings and Shop Drawings. Mark the set to show the actual installation where the installation varies substantially from the Work as originally shown. Mark which drawing is most capable of showing conditions fully and accurately. Where Shop Drawings are used, record a cross-reference at the corresponding location on the Contract Drawings. Give particular attention to concealed elements that would be difficult to measure and record at a later date. 1. Mark record sets with red erasable pencil. Use other colors to distinguish between variations in separate categories of the Work. 2. Mark new information that is important to the Owner but was not shown on Contract Drawings or Shop Drawings. 3. Note related change -order numbers where applicable. 4. Organize record drawing sheets into manageable sets. Bind sets with durable -paper cover sheets; print suitable titles, dates, and other identification on the cover of each set. 5. Prior to Contract Closeout, obtain from the Owner a reproducible mylar copy of the Drawings. Using technical drafting pen, duplicate information contained on the Record Drawings maintained on site. Label each sheet "Record Drawing." On the first sheet, the Contractor or resident Superintendent shall execute the following statement: Having reviewed this document and all attachments, I affirm that, to the best of my knowledge, the information presented here is true and accurate. Signed: Position: Date: C. Record Specifications: Maintain one complete copy of the Project Manual, including addenda. Include with the Project Manual one copy of other written construction documents, such as Change Orders and modifications issued in printed form during construction. 1. Mark these documents to show substantial variations in actual Work performed in comparison with the text of the Specifications and modifications. 2. Give particular attention to substitutions and selection of options and information on concealed construction that cannot otherwise be readily discerned later by direct observation. 3. Note related record drawing information and Product Data. 4. Upon completion of the Work, submit record Specifications to the Owner. D. Record Product Data: Maintain one copy of each Product Data submittal. Note related Change Orders and markup of record drawings and Specifications. 1. Mark these documents to show significant variations in actual Work performed in comparison with City of Fort Collins SECTION 01700 — CONTRACT CLOSEOUT Park Planning & Development Division Page 3 of 6 information submitted. Include variations in products delivered to the site and from the manufacturer's installation instructions and recommendations. 2. Give particular attention to concealed products and portions of the Work that cannot otherwise be readily discerned later by direct observation. 3. Upon completion of markup, submit complete set of record Product Data to the Owner. Miscellaneous Record Submittals: Refer to other Specification Sections for requirements of miscellaneous record keeping and submittals in connection with actual performance of Work. Immediately prior to the date or dates of Substantial Completion, complete miscellaneous records and place in good order. Identify miscellaneous records properly and bind or file, ready for continued use and reference. Submit to the Owner. F. Maintenance Manuals: Organize operation and maintenance data into suitable sets of manageable size. Bind properly indexed data in individual, heavy-duty, 2-inch (51-mm), 3-ring, vinyl -covered binders, with pocket folders for folded sheet information. Mark appropriate identification on front and spine of each binder. Include the following types of information: 1. Emergency instructions. 2. Spare parts list. 3. Copies of warranties. 4. Wiring diagrams. 5. Recommended "tum-around" cycles. 6. Inspection procedures. 7. Shop Drawings and Product Data. 8. Fixture lamping schedule. 1.07 Warranties and Bonds A. Provide duplicate notarized copies. Maintain copies of all Contractor's submittals and assemble documents executed by subcontractors, suppliers, and manufacturers. Provide table of contents and assemble in binder with durable plastic cover. B. Submit material prior to final application for payment. For items of Work delayed materially beyond date of substantial completion, provide updated submittal within ten days after acceptance, listing date of acceptance as start of warranty period. 1.08 Final Payment A. At the end of maintenance period, submit written certification that Contract Documents Work has been reviewed and that Work is complete in accordance with Contract Documents and ready for Owner Representative's review. B. In addition to submittals required by the conditions of the Contract provide submittals required by governing authorities, and submit a final statement of accounting giving total adjusted Contract Sum, previous payments and sum remaining due. C. Owner's Representative will issue a final Change Order reflecting approved adjustments to Contract Sum not previously made by Change Order. D. Retainage will be held until advertisement for liens and encumbrances is completed. PART 2 — PRODUCTS (Not Applicable) City of Fort Collins SECTION 01700 — CONTRACT CLOSEOUT Park Planning & Development Division Page 4 of 6 1.07 Verification of Dimensions A. The Contractor shall he responsible for the coordination and proper relation of the work. He shall field verify all dimensions and advise the City of any discrepancies prior to proceeding with that phase of the work. 1.08 Fire Hydrants A. Fire Hydrant Connections: City's permission is required for connection to fire hydrants. Only compatible adapters shall be utilized for hydrant connections. A gate valve shall be provided and installed by the Contractor between the hydrant and supply hoses to control flow. Connection shall include backflow protection. Temporary connections to fire hydrants shall he disconnected at the end of each working day. No quick closing valves such as plug or butterfly valves will he used. 1.09 Outages A. Utility outages necessitated by the work shall be requested in writing at least fifteen (15) working days prior to the proposed outage. The request shall be directed to the City and shall stipulate the specific utility system(s) and circuits to be affected, the location of the work, the time at which the shutdown will occur, and the duration of the outage for each system. Outages shall be kept to a minimum both in number and in duration. Where multiple outages are required, as many outages as can be accurately scheduled shall he submitted as a group. 1.10 Fill Material A. Excess fill material, including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be hauled off the site and disposed of in accordance with applicable State and local regulations. B. Additional fill material, if required, shall be hauled to the site from off the site as a necessary part of the work. Material composition shall be subject to the requirements of the specifications. 1.11 Parking A. Parking of the Contractor's vehicles shall be restricted to an area designated by the City. 1.12 Telephone A. Business Telephone: At the beginning of construction, the Contractor shall provide the City with a telephone number at which the Contractor or his representative may be contacted at any time during regular working hours. The Contractor shall also provide a phone number for after -duty hours contact. 1.13 Sanitary Provisions A. The Contractor shall provide temporary toilets for the use of construction personnel. Location, type, proposed maintenance, etc., shall be approved by the City prior to placing toilets. Temporary toilets shall be removed at the completion of construction and the adjacent area restored to the condition existing prior to the start of construction or as indicated on the plans. 1.14 Pollution Abatement A. Transporting materials to or from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be covered, wetted or otherwise protected. Gravel, sand and concrete shall be contained within vehicles to prevent spillage. B. Prevent the deposit of dirt, mud or debris on improved streets and roads, and remove all should such deposition occur. C. Burning of any material on site is prohibited. City of Fort Collins SECTION 01000 — PROJECT SUMMARY Park Planning & Development Division Page 2 of 3 PART 3 — EXECUTION 3.01 Closeout Procedures A. Operation and Maintenance Instructions: Arrange for each Installer of equipment that requires regular maintenance to meet with the Owner's personnel to provide instruction in proper operation and maintenance. Provide instruction by manufacturer's representatives if installers are not experienced in operation and maintenance procedures. Include a detailed review of the following items: 1. Maintenance manuals. 2. Record documents. 3. Spare parts and materials. 4. Tools. 5. Lubricants. 6. Fuels. 7. Identification systems. 8. Control sequences. 9. Hazards. 10. Cleaning. 11. Warranties and bonds. 12. Maintenance agreements and similar continuing commitments B. As part of instruction for operating equipment, demonstrate the following procedures: 1. Startup, 2. Shutdown. 3. Emergency operations. 4. Noise and vibration adjustments. 5. Safety procedures. 6. Economy and efficiency adjustments. 7. Effective energy utilization. 3.02 Final Cleaning A. General: The General Conditions require general cleaning during construction. Regular site cleaning is included in Division 1. B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to the condition expected in a normal, commercial building cleaning and maintenance program. Comply with manufacturer's instructions. 1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion. C. Removal of Protection: Remove temporary protection and facilities installed for protection of the Work during construction. 1. Remove labels that are not permanent labels. 2. Clean transparent materials, including mirrors and glass in doors and windows. 3. Clean exposed exterior and interior hard -surfaced finishes to a dust -free condition, free of stains, films, and similar foreign substances. Restore reflective surfaces to their original condition. Leave concrete floors broom clean. 4. Wipe surfaces of mechanical and electrical equipment. Remove excess lubrication and other substances. Clean plumbing fixtures to a sanitary condition. Clean light fixtures and lamps. 5. Clean the site, including landscape development areas, of rubbish, litter, and other foreign substances. Sweep paved areas broom clean; remove stains, spills, and other foreign deposits. Rake grounds that are neither paved nor planted to a smooth, even -textured surface. City of Fort Collins SECTION 01700 - CONTRACT CLOSEOUT Park Planning & Development Division Page 5 of 6 D. Compliance: Comply with regulations of authorities having jurisdiction and safety standards for cleaning. Do not bum waste materials. Do not bury debris or excess materials on the Owner's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from the site and dispose of lawfully. 1. Where extra materials of value remain after completion of associated Work, they become the Owner's property. Dispose of these materials as directed by the Owner. END OF SECTION 01700 City of Fort Collins SECTION 01700 -CONTRACT CLOSEOUT Park Planning & Development Division Page 6 of 6 DIVISION 1 SECTION 01800 — DEFINITION OF BID ITEMS The following items describe the scope of work for this contract and are further clarified through limit -of -work boundary notes on the drawings and specifications. The work described in each Bid Item may contain work from one or several technical specification sections. Contractor shall refer to the technical specifications that apply to the individual components. Bid Item 1 — Mobilization Contractor shall furnish all labor, materials and equipment for mobilization of personnel, equipment and supplies at the project site in preparation for work on this project. Bid Item 2 — Traffic Control Contractor shall furnish all labor, materials and equipment for approved traffic control plan by a City of Fort Collins approved Traffic Control Company. This includes furnishing, installing, and maintaining traffic control for the duration of the trail project. Bid Item 3 — Demolition Contractor shall provide all labor and equipment for demolition and removal of 8'— 9' wide asphalt trail (Existing Poudre Trail). Work includes all hauling and fees. The removed asphalt to be hauled to 300 Hoffman Mill Road (behind Coloradoan on Riverside), coordinate with owner's representative. Bid Item 4 — Subarade Preparation Contractor shall furnish all labor, materials and equipment to recondition and level subgrade. Top 6"of Subgrade to be reconditioned to 95% compaction. Item includes water and minor earthwork associated with the expansion from 8' trail to 10'trail. This item includes stripping and saving 4" of topsoil for landscape restoration operations. Bid Item 5 — Concrete Trail Contractor shall furnish all labor, materials and equipment to install 10' wide concrete sidewalk. Bid amount includes installation of 5" thick standard concrete (3,500 psi) with fiber mesh reinforcement. A. Yosemite Brown Concrete: 2 lbs. per sack of Yosemite Brown Color. B. Standard Gray Concrete: no color additives Bid Item 6 — Landscape Restoration Contractor shall provide all labor and equipment to backfill concrete trail, redistribute topsoil, and fine grade disturbed areas for preparation of seeding operations. Bid Item 7 —Seeding Contractor shall provide all materials, labor and equipment to seed areas disturbed by construction. This work includes hydra mulching disturbed areas. END OF SECTION END OF DIVISION 1 City of Fort Collins Section 01800 - Definition of Bid Items Park Planning & Development Division Page 1 of 1 No Text DIVISION 2 SECTION 02050 - DEMOLITION PART 1-GENERAL 1.01 Description of Work A. Demolition or salvage and removal of boulders (if found) for re -use in landscape; and remove fencing, other plant material, and debris or other items on the site necessary for the construction of the project. 1.02 Quality Assurance A. Standards listed hereunder and referenced elsewhere in these specifications shall become a part of this specification and are incorporated herein by reference. The latest edition, amendment or supplements thereto in effect thirty (30) days before date of invitation shall apply. 1. City of Fort Collins, Street Cut and Excavation Repair Standards 2. City of Fort Collins, Stormwater Drainage Design and Construction Standards PART 2 - MATERIALS - Not Used PART 3 - EXECUTION 3.01 Inspection and Reviews A. Schedule site meeting with Owner's Representative to verify and mark limits of demolition. 3.02 Protection A. Refer to the General Requirements for site protection and temporary controls. B. Erect barriers and warning signs as necessary to prevent injury to the public and construction personnel. C. Protect features and areas not marked for demolition. Limit use of site to the delineated areas. D. Use of explosives is prohibited. 3.03 Demolition and Removal A. Items listed for salvage remain the property of the City. Items listed for demolition become the property of the Contractor. B. Remove from site items shown on demolition plan. C. Arrange for and pay costs associated with off -site disposal. 3.04 Hidden Conditions A. A hidden condition is any feature that could not be discovered or reasonably inferred from a careful inspection of the site prior to demolition. B. Promptly report hidden conditions to the Owner's Representative. C. Hidden conditions may cause damage to features that are to remain in a finished work if demolition operations continue. Stop demolition operations affected by hidden conditions until a determination is made by the Engineer. D. Hidden conditions may cause a change in contract time or price; refer to the General Conditions. END OF SECTION City of Fort Collins Seclion 02050 - Demolition Park Planning & Development Division Page 1 of 1 DIVISION 2 SECTION 02100 - MOBILIZATION PART 1-GENERAL 1.01 Work Included A. Prepare the site for construction. B. Move in and move out personnel and equipment. C. Set up and remove temporary offices, buildings, facilities and utilities. 1.02 Site Conditions A. The City has provided the right-of-way, easement or project site for all permanent access or permanent construction for the project. Any additional access, access right-of-way, construction areas, or additional needed land which may be involved in the construction of this project shall be the responsibility of the Contractor. B. The land owned by the City may be used as site headquarters, storage yard, or base of operations provided that the use of said land meets with all of the requirements and restrictions imposed by the City at the time of usage. 1.03 Site Preparation for Contractor Occupancy A. The Contractor shall provide all temporary facilities as required for performing the work. The Contractor shall secure and maintain proper storage areas for equipment and materials in locations she/he may deem necessary for the proper execution of the job as approved by the City Representative. No storage yard or project headquarters site may be utilized in conflict with objections from the adjacent property owners unless the Contractor obtains from the City specific written permission for such objectionable use. No objectionable material will be allowed to blow from, wash off or drain off of any storage yard on to adjacent property. B. The Contractor shall maintain all storage yards in as neat and orderly a manner as possible, allowing no accumulation of waste materials or disposal piles. The Contractor may construct a temporary security fence for the protection of materials, tools, and equipment. The fence shall be maintained during the construction period. Upon completion of work, the security fence shall be removed from the site. The Contractor shall provide adequate parking facilities within the designated area for personnel working on the project. C. The Contractor shall obtain the necessary permits for connection to necessary services provided by utility companies serving the project area. D. Materials, equipment, and work required for temporary storm water management during the construction period shall be provided by the Contractor as required to ensure public safety and to protect the work in progress and materials stored on site. 1.04 Damage or Use -Fee Claims A. Any damage or use -fee claims filed against the Contractor may become a part of the final settlement of this project and may be cause for delay of final acceptance or delay of final payment. City of Fort Collins Section 02100 —Mobilization Park Planning and Development Division Page 1 of 2 PART 2 - NOT USED PART 3 - EXECUTION 3.01 Obstructions A. The location of some utilities and obstructions may not be shown. Bidders are advised to carefully inspect the existing facilities before preparing their proposals. The removal and replacement of minor obstructions such as electrical conduits, air, water, and waste piping and similar items shall be anticipated and accomplished, even though not shown or specifically mentioned. Major obstructions encountered that are not shown on the Contract Drawings or could not have been foreseen by visual inspection of the site prior to bidding should immediately be brought to the attention of the City Representative. The City Representative will make a determination for proceeding with the work. If the City Representative finds that the obstruction adversely affects the Contractor's costs or schedule for completion, a proper adjustment to the Contract will be made in accordance with the General Conditions. 3.02 Demolition A. Any pipes or existing structures encountered during construction shall be preserved until accepted for removal by the City Representative. The Contractor shall be required to repair pipes or structures in use that are damaged during construction at no cost to the City. The removal of abandoned pipes shall be reviewed by the City Representative. 3.03 Removal and Salvage of Materials A. The Contractor shall carefully remove materials specified to be reused or salvaged so as not to damage the material. Reuse by the Contractor of salvaged material will not be permitted, except as specifically shown or specified herein. Existing materials to be removed or replaced and not specifically designated for salvage shall become the property of the Contractor. Provide and maintain dust tight temporary partitions, bulkheads, or other protective devices during the construction to permit normal operation of the existing facilities. Construct partitions of plywood, insulating board, plastic sheets, or similar material. END OF SECTION City of Fort Collins Section 02100 — Mobilization Park Planning and Development Division Page 2 of 2 DIVISION 2 SECTION 02200 - EARTHWORK AND GRADING PART 1 —GENERAL 1.01 Description of Work A. The Contractor shall provide all labor, materials and equipment necessary to perform the work items called for on the bid schedule. B. The Contractor shall perform all excavation regardless of the type, nature, or condition of material encountered, as specified or required in order to accomplish the construction. 1.02 City Furnished Materials A. None, unless otherwise noted on the Bid Schedule. 1.03 Site Conditions A. A geotechnical investigation may have been performed for the City in order to obtain relative data concerning the character of material in and upon which the project is to be built. If an investigation has been performed, the information will be available to the Contractor for information purposes only, and is not to be considered a part of the Contract Documents. The Contractor shall satisfy himself as to the kind and type of soil to be encountered and any water conditions that might affect the construction of the project. B. The locations of existing utilities are shown in an approximate way only and not all utilities may be shown. The Contractor shall determine the exact location of all existing utilities prior to commencing work. The Contractor shall be fully responsible for any and all damages that might be occasioned by his failure to exactly locate and preserve any and all utilities. If utilities are to remain in place, the Contractor shall provide adequate means of support and protection during construction. C. Should drawn, or incorrectly drawn, piping or other utilities be encountered during excavation, the Contractor shall advise the City within thirty (30) minutes of encountering the utility. The Contractor shall cooperate with the City and utility companies in keeping respective services and facilities in operation to the satisfaction of the respective owners. The City reserves the right to perform any and all work required should the Contractor fail to cooperate with the respective companies, and back charge the Contractor for any and all expenses. D. The Contractor shall provide barricades and signs in accordance with the Uniform Manual of Traffic Control Devices where applicable. The Contractor shall maintain all devices in a working marmer. 1.04 Fill Material A. Excess fill material, including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be hauled off the site and disposed of in accordance with applicable State and local regulations. City of Fort Collins Section 02200 — Earthwork and Grading Park Planning & Development Division Page 1 of 5 B. Additional fill material, if required, shall be hauled to the site from off the site as a necessary part of the work. Material composition shall be subject to the requirements of the specifications. 1.05 Testing and Inspections Coordinate and schedule testing with City Representative. PART 2 - MATERIALS 2.01 Soil Materials A. Coarse -grained soils free from debris, roots, organic material, and non -mineral matter containing no particles larger than 4-inch size and classified as either: Sands with fines (SM, SC) and less than 25 percent of the soil particles passing the No. 200 sieve, or 2. Clean sands (SW, SP) 3. Native soils as determined acceptable by the Engineer. 2.02 Filter Fabric A. Filter Fabric shall be Typar 3451 W, Mirafr 700X or approved equal. PART 3 - EXECUTION 3.01 Preparation A. Field measurements: Before commencing work, locate all baselines and coordinates required for control of the work, establish required grade staking for control of excavation, fill and embankment construction. Filed verify by excavation the location all utility crossings, service connections, and connections to existing lines before proceeding with earthwork. B. Layout Lines and Levels: I. The drawings indicate existing elevations and proposed elevations. The existing elevations and proposed are given for the convenience of the Contractor to assist him in arriving at the quantities of excavation, grading, backfilling etc. 2. Before earthwork operations are started, all construction items shall be completely staked out for the Owner's approval. For any area with a two- percent slope or flatter, the Contractor shall lay out a 50-foot on -center grid and calculate the exact elevation at every intersection of the grid lines. These calculations will be approved by the Owner's Representative. C. Removal of TopSoil: Strip existing earthen material (topsoil) to a depth of 4 inches over the entire site. Stockpile on site in area approved by Owner's Representative. Keep topsoil segregated. Place, grade, and shape stockpile for proper drainage. 3.02 Excavation A. Prior to beginning excavation operations, accomplish all site preparation in accordance with these specifications. Perform excavation of every description to the lines and grades indicated on the drawings. City of Fort Collins Section 02200 — Earthwork and Grading Park Planning & Development Division Page 2 of 5 B. Complete excavation work to the grade elevations shown on the drawings for all areas to be paved. 3.03 Clearing the Site A. All areas underlying new structures, paved areas, site fills and embankments shall be cleared of stumps, shrubs, brush, and other vegetative growth. B. Any material containing roots, grasses and other deleterious or organic matter generally found in the top six inches of undisturbed natural terrain shall be stripped from all areas requiring excavation, grading, trenching, subgrade preparation for foundations and embankment work. The City will require stripped top soil deemed suitable for spreading over the finished grades to be stockpiled and preserved until the finished grading operation, at which time it shall be spread uniformly over areas to be seeded or sodded. C. Upon completion of the project, completion of a particular phase of the project, or termination of the use of any particular area, site, storage yard right-of-way or easement, the Contractor shall promptly and neatly clean up the area and re-establish the ground to the contours required by the project or conditions prior to project commencement. 3.04 Earth Fill Construction A. The Contractor shall perform all grading to the lines and grades specified and/or established by the Engineer, with an appropriate allowance for topsoil. All slopes shall be free of all exposed roots and stones exceeding 3-inch diameter, which are loose and liable to fall. Tops of banks shall be rounded to circular curves not less than 6-feet in radius. B. Rounded surfaces shall be neatly and smoothly trimmed. Topsoil shall be replaced to a depth of 4-inches in areas to be revegetated. C. The Contractor shall protect the fill against freezing when atmospheric temperature is less than 35 degrees F (1 degree Q. 3.05 Compaction A. The Contractor shall meet minimum percentage density specified for each area classification as follows. Percentage of Maximum Density Requirements: Compact soil to not less than the indicated percentages of maximum density relationship determined in accordance with ASTM D 698. Sidewalks - 95 percent 2. Unpaved Areas - 90 percent B. Control moisture content within 2% of optimum moisture content as determined by ASTM D 698. Where subgrade or layer of soil material is too dry to permit compaction to the specified density, uniformly apply water to surface of cut area, subgrade, or loosely placed layer of soil material. Mix soil and applied water by blading, disking, or other methods to achieve uniform moisture content throughout the soil mass to be compacted. C. Remove and replace, or scarify and air dry, soil material that is too wet to permit compaction to specified density. Soil material that has been removed because it is too wet to permit compaction City of Fort Collins Section 02200 — Earthwork and Grading Park Planning & Development Division Page 3 of 5 D. Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids, or other harmful materials. Surface drainage from the construction site, which contains harmful amounts of sediment, shall not be allowed to drain onto adjacent areas. All grading shall be accomplished to allow sedimentation to settle out prior to flowing onto adjacent areas. E. Flushing of concrete trucks is allowed only at the project site or the designated contractor storage area, with the responsibility of control and cleanup resting with the Contractor. F. Toxic, corrosive and flammable materials for construction other than specified shall not be used without prior approval of the City of Fort Collins. When approved, disposal of these materials or their containers will be off site and conform to state and federal regulations. 15 Protection of Property A. Initiate, maintain and supervise necessary protection to prevent damage, injury or loss to: 1. The Work and materials and equipment to be incorporated in the project, whether in storage on or off the site: and 2. Property at the site or adjacent thereto, including fences, patios, driveways, sidewalks, pavement, trees, shrubs, lawns, walks, structures, utilities and underground facilities not designated for removal, relocation or replacement in the course of construction. B. Maintain, protect, and support existing utilities and other appurtenances against damage by shoring, bracing, or other means. C. Do not stockpile excavated material against existing appurtenances. 1.16 Survey Requirements A. Contractor shall perform all surveying necessary to complete the work. 1.17 Construction Superintendent A. The construction superintendent shall beat the job site anytime work is being accomplished by any of the trades. PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01000 — PROJECT SUMMARY Park Planning & Development Division Page 3 of 3 may be stockpiled or spread and allowed to dry. Assist drying by disking, harrowing or pulverizing until moisture content is reduced to a satisfactory value. D. Puddling is not an acceptable method of compaction. 3.06 Grading A. Paved Areas: Immediately prior to placing structural pavements, shape area to the required lines, grades, and limits to provide the finished elevations indicated and roll with an approved heavy vibratory roller until compacted to the specified density. Maintain moisture content within 2% of optimum during final rolling and until subgrade is covered by subsequent construction. Remove loose material and protect subgrade until covered. The subgrade under all paved areas and the play area shall conform to the elevations shown on the drawings. B. Landscape Area and Remainder of Site: Rough grade areas as indicated on grading plan to 4 inches below finish grade. After rough grading is finished, compacted and approved, scarify area to a depth of at least 6 inches. 2. Place previously stockpiled topsoil in all areas within the limits of the project not indicated to receive subsequent foundations, slabs on grade, walks, safety surfacing or other similar materials. 3. Uniformly distribute topsoil on the disturbed area and evenly spread to a thickness of 4 inches deep after light compaction. Perform spreading so that planting can proceed with little additional soil preparation or tillage. Do not place topsoil when subgrade is frozen, excessively wet, extremely dry or in a condition otherwise detrimental to specified grading, seeding and planting specifications. C. Finish Grading: 1. Grade all excavated sections, filled sections, construction disturbed areas and adjacent transition areas to finish elevation. Make finished surfaces smooth, compacted and free from irregular surface changes. 2. Unless indicated otherwise on drawings, finish grade area adjacent to sidewalks and pavements to % inch below finish elevation of sidewalk and pavement. 3. Remove all construction debris. Grades not otherwise indicated shall be uniform levels or slopes between such points and existing finish grade. Abrupt change in slopes shall be rounded. 3.07 Settlement A. Where completed compacted areas are disturbed by subsequent construction operations or adverse weather, the Contractor shall scarify the ground surface, re -shape, and compact to required density prior to further construction. B. Any settlement in backfill, fill, or in structures built over the backfrll or fill, which may occur within the guarantee period in the General Conditions will be considered to be caused by improper compaction methods and shall be corrected at no cost to the City. Any structure damaged by settlement shall be restored to their original condition by the Contractor at no cost to the City. City of Fort Collins Section 02200 — Earthwork and Grading Park Planning & Development Division Page 4 of 5 3.08 Disposal of Excess Excavation and Waste Materials and Special Requirements A. The Contractor shall dispose of all excess excavated material not required for fill on -site, as directed by the Engineer. B. The Contractor shall remove and be responsible for legally disposing of excess fill material not placed on -site, waste materials, trash and debris. C. The Contractor shall conduct all site grading operations and other construction activities to minimize erosion of site soil materials. He/she shall be responsible to maintain streets/public ROW daily by removing any spillage of dirt, rocks or debris from equipment entering or leaving the site. END OF SECTION City of Fort Collins Section 02200 — Earthwork and Grading Park Planning & Development Division Page 5 of 5 DIVISION 2 SECTION 02221— TRENCHING, BACKFILLING, AND COMPACTION PART 1-GENERAL 1.01 Scope Furnish all labor, materials, and equipment, and perform all operations to complete trenching, including excavation, subgrade preparation, drainage, filter fabric installation, bedding, backfrlling, compacting, and finish grading for underground pipelines, service lines, sleeving, and appurtenances as shown on the drawings and as specified herein. 1.02 Related Work A. Section 02200 — Earthwork and Grading. B. Section 02520 — Portland Cement Concrete Paving. C. Section 02600 — Domestic Water Supply. D. Section 02700 — Sanitary Sewerage Systems. E. Section 02810 —Irrigation. F. Section 16000 — General Electrical. 1.03 Protection A. Obtain utility locations before commencing work. Protect all existing underground utilities, above ground structures or plantings, or repair to original condition. PART 2 MATERIALS: 2.01 Trench Backfill Material A. Trench excavation or imported material free from frozen material, stumps, roots, brush, other organic matter, cinders or other corrosive material, debris, and rocks or stones greater than 2 inches in any dimension. 2.02 Other A. Bedding, piping, filter fabric, and other materials specified on the drawings and in related sections. PART 3 EXECUTION 3.01 Preparation A. Remove and stockpile topsoil from areas to be disturbed by construction. Keep topsoil segregated from non -organic trench excavation materials and debris. 3.02 Trenching A. Excavate trenches by open cut methods. Segregate suitable backfill. Rough trench excavation will leave trench with uniform width and vertical sidewalls from an elevation one foot above the top of installed pipe to the bottom of pipe. City of Fort Collins Section 02221 — Trenching, Backfilling and Compacting Park Planning & Development Division Page 1 of 2 B. Minimum trench width will provide 6 inch space between pipe wall and side of trench. Maximum trench width will be shown on the drawings or in the appropriate pipeline section. If not specified elsewhere the maximum trench width is the pipe O.D. plus 20 inches. C. Grade trench bottom to provide uniform clearance for bedding material. De -water trench. Remove loose material and foreign objects. When required, install filter fabric per manufacturer's specifications. D. Unstable subgrade is not expected. If unstable subgrade material is encountered, report the condition to the Owner. Remedy and payment for subgrade stabilization will be based on the actual conditions encountered. 3.03 Bedding A. Pipe will be bedded in accordance with the detailed drawings or the appropriate pipeline specification. 3.04 Backfilling and Compaction A. Backfill trench promptly after completion of pipe bedding. B. Deposit material in uniform layers with thickness commensurate with the soil encountered and the compaction equipment used. C. Compaction requirements will be made at the moisture content and will meet the densities, by zone, specified in Section 02200 — Earthwork and Grading. D. Coordinate and schedule compaction tests with City Representative. 3.05 Surface Restoration A. Restore pavements according to City of Fort Collins Standards. B. Restore landscaped areas according to Section 02900 — Site Revegetation END OF SECTION City of Fort Collins Section 02221 — Trenching, Backfilling and Compacting Park Planning & Development Division Page 2 of 2 DIVISION 2 SECTION 02250 — TOPSOIL PART 1 — GENERAL 1.01 Scope A. This work shall consist of excavating, stockpiling, and placing topsoil on the project site( and/or furnishing, hauling, and stockpiling) and placing topsoil from approved sources. This work shall also include preservation of vegetation and objects designated to remain from injury or defacement. PART 2 — MATERIALS 2.01 Topsoil A. Topsoil shall consist of the organic growing layer of soil which is reasonable free of admixtures of subsoil, refuse, stumps, roots, rocks, brush, weeds, heavy clay, hard clods, toxic substances or other material which would be detrimental to proper development of vegetative growth. PART 3 — EXECUTION 3.01 Protection of Existing Improvements A. Provide protection necessary to prevent damage to existing improvements indicated to remain in place. B. Protect improvements on adjoining properties and on City's property C. Restore damaged improvements to their original condition, acceptable to parities having jurisdiction. D. Protect existing trees and other vegetation indicated to remain in place, against unnecessary cutting, breaking, or skinning of roots, skinning and bruising of bark, smothering of trees by stockpiling construction materials or excavated material within drip line, excess foot or vehicular traffic, or parking of vehicles within drip line. Provide temporary guards to protect trees and vegetation to be left standing. E. Water trees and other vegetation to remain within limits of contract work as required to maintain their health during the course of construction operations. F. Provide protection for roots over 1-1/2" diameter cut during construction operations. Coat cut faces with an emulsified asphalt, or other acceptable coating, formulated for use on damaged plant tissues. Temporarily cover exposed roots with wet burlap to prevent roots from drying out; cover with earth as soon as possible. G. Repair or replace trees and vegetation indicated to remain which are damaged by construction operations, in a manner acceptable to parties having jurisdiction. Employ qualified tree surgeon to repair damages to trees and shrubs. Replace trees which cannot by repaired and restored to full growth status, as determined by the City. 3.02 Construction Requirements A. Materials selected for topsoil shall be excavated and stockpiled (and/or furnished, hauled, and stockpiled) and placed at the site and graded. Topsoil shall be placed directly upon constructed cut and fill slopes without the use of stockpiles whenever conditions and the progress or work will permit. City of Fort Collins Section 02250 — Topsoil Park Planning & Development Division Page 1 of 2 B. Strip topsoil to whatever depths encountered in a manner to prevent intermingling with underlying subsoil or other objectionable material. C. Limit stripping to limits of construction shown on the drawings; or to as small an area as practical within the right-of-way or limits of construction. D. Remove heavy growths of grass from areas before stripping. E. Where trees or bushes are indicated to be left standing, stop topsoil stripping a sufficient distance form the trees or bushes to prevent damage to main root system. F. Stockpile topsoil in storage areas designated or agreed to prior to starting work. Construct storage piles to freely drain surface water. Cover storage piles if required to prevent wind-blown dust. Maintain topsoil free from contamination. G. The area where topsoil shall be removed are: 1. Where final contours on the drawings indicate excavation or filling. 2. Under all asphalt parking and drive areas. 3. Under all walkways. 4. Under all graveled driveways and storage areas. 5. Under all new building sites. H. Topsoil shall be placed and graded in landscaped areas. Placement shall not impede drainage patterns. Topsoil shall not be placed until the areas to be covered have been properly prepared and grading operations in the area have been completed. END OF SECTION City of Fort Collins Section 02250 — Topsoil Park Planning & Development Division Page 2 of 2 DIVISION 2 SECTION 02520 — PORTLAND CEMENT CONCRETE PAVING PART 1-GENERAL Scope A. Furnish all labor, materials, supplies, equipment, transportation, and perform all operations in connection with and reasonably incidental to complete installation of concrete paving as shown on the drawings and as specified herein. Items of work specifically included are: B. Subgrade preparation for trail C. Form work. D. Reinforcement. E. Surface finish. F. Construction, expansion and control joints. G. Curing. H. Concrete trail I. Interior slabs -on -grade in restroorn, etc. Work Not Included A. Items of work specifically excluded or covered under other sections: B. Excavation and backfill. C. Earthwork and grading. D. Cast -in -place structural concrete or precast concrete, such as foundations, drainage appurtenances, and pad and building. E. Joint sealers. Related Work A. Division 2 — Site Work: a. Section 02050 — Demolition. b. Section 02200 — Earthwork/Grading. c. Section 02221 — Trenching, Backfilling, and Compaction. B. Not Used C. Division 7 — Thermal and Moisture Protection: 1. Section 07900 — Joint Sealers. References A. ACI 301 —Specifications for Structural Concrete for Buildings. B. ASTM C33 — Concrete Aggregate. C. ASTM C 150 —Portland Cement. City of Fort Collins SECTION 02520 - Portland Cement Concrete Paving Park Planning & Development Division Page 1 of 10 D. ASTM C260 — Air Entraining Admixtures for Concrete. E. ASTM C309 — Liquid Membrane — Forming Compounds for Curing Concrete. F. ACI 304 — Recommended Practice for Measuring, Mixing, Transporting, and Placing Concrete. G. ACT 305R—Hot Weather Concreting. H. ACI 306R — Cold Weather Concreting. I. ACI 308 — Standard Practice for Curing Concrete. J. ACI 309 — Recommended Practice for Consolidation of Concrete. K. ACI 318-89 — Building Code Requirements for Reinforced Concrete. Regulatory Requirements: A. Conform to applicable code of governing authority for paving work within public right-of-way. Tests: A. Submit proposed mix design to testing laboratory for review prior to commencement of work. For standard premix concrete mixes, the supplier's quality control records may be substituted for job mix testing. B. Concrete Testing Service: Contractor will engage a testing laboratory to perform materials evaluation, testing and design of concrete mixes as approved by Owner. All testing costs will be borne by the Contractor. Should any test(s) fail to meet the specifications, the cost of the failed test and all subsequent testing shall be borne by the Contractor. C. Coordinate and schedule sampling testing during concrete placement with City Representative. Submittals: A. Submit product data under provisions of Section 01300 —Submittals. B. Submit data on admixtures and curing compounds. C. Submit a ten pound sample of aggregate for exposed aggregate finish. D. Submit manufacturer's data on leave -in -place construction joint form Test Panels: A. Provide a 3' x 3' test panel for finish and tooling of joints for Owner approval. Provide one panel for each pavement type specified. In casting the panels, use personnel and methods to be employed on the work. B. If sample disapproved, cast additional samples until approval is obtained. Maintain test panel on site until finished work is accepted. Test panel will represent minimum workmanship standard. C. Work completed prior to text panel approval shall be subject to removal and replacement at Owner's request. PART 2 MATERIALS 2.01 Concrete Materials: A. General: Provide materials of same brand and source throughout the project unless otherwise noted. B. Portland Cement: ASTM C150, Type I or Type 1/II, gray color. City of Fort Collins SECTION 02520 - Portland Cement Concrete Paving Park Planning & Development Division Page 2 of 110 C. Aggregates: ASTM C33, normal weight. In addition, the combined aggregate shall comply with the following gradation, shown in percent passing. Sieve Size '/4-Inch Nominal Maximum Size '/4 Inch 90 — 100 3/8 Inch 60 — 80 No. 4 40 — 60 No. 8 30 — 45 No. 16 20 — 35 No. 30 13 — 23 No. 50 5 — 15 No. 100 0-5 D. Coarse Aggregate for Exposed Aggregate Finish: 5/8-inch maximum size; rounded shape, ratio of maximum to minimum dimensions not to exceed 2.5:1; color to be tan to brown, no more than 2% white or black combined, no pink, no red, no green. E. Water: Clean and not detrimental to concrete. 2.02 Form Materials: A. Slab Edges: Two by lumber permitted for surfaces not exposed to view in the final work. Use concrete -form grade hardboard, "plyform" grade plywood, or metal for forming surfaces exposed to view. Forms shall be straight and sufficiently stiff and well braced to meet line tolerances specified in Part 3. B. Keyed Joint Form: Wooden key or leave -in -place metal construction joint form. C. Form Coatings: Commercial form -coating compounds that will not bond with, stain, or adversely affect concrete surfaces, and will not impair subsequent treatments of concrete surfaces. 2.03 Reinforcement: A. Reinforcing Steel: ASTM A615; 60 ksi yield grade; deformed billet -steel bars, uncoated finish. B. Welded Steel Wire Fabric: Smooth wire, ASTM A185, uncoated finish, flat sheets. C. Fibermesh: Bundled, fibrillated, virgin polypropylene fibers manufactured for use in premix concrete and having the following characteristics: 1. Special Gravity: 0.91. 2. Tensile Strength: 70 to 100 ksi. 3. Fiber Lengths: % inch, '/4 inch. 4. Accepted Materials: "Fibermesh" by Fibermesh Company of Chattanooga, TN; or "Forta CR" by Forta Corporation of Groove City, PA. D. Dowels: ASTM A615; 40 or 60 ksi yield grade, plain steel, uncoated finish; matched sleeve and cap one end. Provide dowel basket to hold dowels in parallel alignment. 2.04 Admixtures: A. General: Unless specified in the mix or directed in Part 3, no admixtures shall be used without approval of the Owner's Representative. Do not use admixtures that would result in mixing water with a concentration of more than 150 ppm of chloride ion. City of Fort Collins SECTION 02520 — Portland Cement Concrete Paving Park Planning & Development Division Page 3 of 10 B. Air Entraining: ASTM C260. C. Water Reducing: ASTM C494, Type A. D. Accelerator: Nonchloride, ASTM C494, Type C or E. E. Retarder: ASTM C494, Type B or D. F. Color Agent: Davis Colors of Los Angeles, California. 2.05 Related Materials: A. Expansion Joint Filler: ASTM D 1752, closed cell polyethylene, 'h inch thickness. B. Joint Sealant: See Section 07000. C. Surface Retardant: Surface retarding agent intended for exposed aggregate. Retardx-SR0" by Prokrete of Denver, Colorado, or approved equal. D. Curing Compound for Standard Non -Colored Walks, Curbs, Gutters, Etc: White pigmented, wax - resin based compound, ASTM C309, Type I, Class A. Recommended by manufacturer for use on exterior sidewalks and driveways. E. Curing Compound for Concrete with Coloring Agent: Davis Seal Color to match colored concrete. F. Curing Compound and Sealer for Exposed Aggregate Concrete: Acryseal by Prokete Industries of Denver, Colorado. G. Curing Compound for Interior Slabs: Protex Promulsion 100 or equal. H. Interior Floor Sealer: Protex Triple Seal or equal. 2.06 Concrete Mix: A. Mix concrete in accordance with ASTM C94. 1. Provide concrete for non -colored sidewalk of the following characteristics: Unit Measurement a. Compressive Strength 3,500 psi at 28 days b. Minimum Cement 564 lb./cy c. Maximum Aggregate Size I '/z inches d. Fibrous Reinforcement '/4 lb./cy e. Air Entrainment 4% to 6% f. Maximum Water/Cement Ratio 0.46 g. Maximum Slump 4 inches 2. Provide concrete for colored sidewalk (Poudre Trail) of the following characteristics: Unit a. Compressive Strength at 28 days b. Minimum Cement c. Maximum Aggregate Size d. Fibrous Reinforcement e. Air Entrainment f. Maximum Water/Cement Ratio g. Coloring Agent h. Maximum Slump City of Fort Collins Park Planning & Development Division Measurement 3.500 psi 564 lb./cy 1 '/z inches 3/41b./cy 4% to 6% 0.46 per manufacturer's recommendations 4 inches SECTION 02520 — Portland Cement Concrete Paving Page 4 of 10 DIVISION 1 SECTION 01010 - SUMMARY OF WORK PART 1 -GENERAL 1.01 Description of Work A. The City of Fort Collins Poudre Trail rehabilitation includes demolition of existing trail, minor earthwork, sub -grade prep, new 10' wide concrete trail, fine grading, hydro -seeding and landscape restoration for any areas disturbed by construction. B. Protection and Restoration. 1. Replace to equal or better conditions all items removed and replaced or damaged during construction. Restore all areas disturbed to match surrounding surface conditions. 1.02 Notices to Private Owners and Authorities A. Notify private owners of adjacent property, utilities, affected governmental agencies, and school district when execution of the work may affect them. B. Give notification 48 hours in advance to enable affected persons to provide for their needs when it is necessary to temporarily deny access or services. C. Contact utilities at least 48 hours prior to excavating near underground utilities. D. Contact all agencies at least 72 hours prior to start of construction. Notify all agencies of the proposed scope of work schedule and any items that would affect their daily operation. E. Names and telephone numbers of affected agencies and utilities in the area are listed below for Contractor's convenience. Water - City of Fort Collins, Colorado 221-6681 Storm Sewer - City of Fort Collins, Colorado 221-6605 Sanitary Sewer - City of Fort Collins, Colorado 221-6681 Electrical - City of Fort Collins, Colorado 482-5922, 221-8553 Gas - Public Service Company of Colorado 482-5922, 221-8553 Telephone - U.S. West Communications 484-0300, 226-6310 Roads - City of Ft. Collins, Colorado 221-6815 Cable Television — AT&T Cable Services 493-7400 Utility Locates - One -call System 1-800-922-1987 Safety - Occupational Safety and Health Administration (OSHA) 844-3061 Fire - Poudre Fire Authority Non -Emergency 221-6581/ Emergency 911 Police - City of Fort Collins Police Department Non -Emergency 221-6550 / Emergency 911 Larimer County Sheriffs Department - Non -Emergency 221-7177 Postmaster - United States Postal Service 482-2837 Ambulance - Poudre Valley Hospital Non -Emergency 484-1227 / Emergency 911 Public Transportation - TransFort 221-6620 Traffic Control - Traffic Engineering 221-6815 City of Fort Collins SECTION 01100 — SUMMARY OF WORK Park Planning & Development Division Page 1 of 2 B. Pozzolanic mineral admixture is not permitted. C. Use accelerating admixtures in cold weather as directed in Part 3. D. Use set -retarding admixture during hot weather as directed in Part 3. E. Water reducing agent is permitted. 2.07 Selection of Proportions: A. Mix Design: Cost of concrete mix design is responsibility of Contractor. B. Selection of Proportions: Use method of ACI 3013.9. Proportioning base on method of ACI 301 3.10 not allowed. 1. Field test records used for documentation of the average strength produced by a propos mix in accordance with ACI 301 3.9.3.2 shall, in addition to the requirements listed, comply with the following: a. The test record shall represent production concrete from a single design mix produced during the past year. b. The test record shall represent concrete proportioned to produce the maximum slur allowed by these specifications, and for air -entrained concrete, within a +0.5% of t maximum air content allowed. 2. Mixes proportioned on the basis of trial mixtures shall meet the provisions of ACI 301 3.9.3.3. PART 3 EXECUTION 3.01 Subgrade Preparation: A. Shape and compact subgrade to match appropriate detail. Compact to 95% density as measured by ASTM D698. Coordinate with Section 02200 — Earthwork, Article 3.05, Compaction. B. Where subgrade cannot be compacted, remove subgrade. Replace with bed course. Compact to 95% density as measured by ASTM D698. C. Moisten subgrade to minimize absorption of water from fresh concrete. Subgrade shall not be muddy, soft, frozen, or covered with standing water when concrete is placed. 3.02 Form Work: A. General: Design, construct, and brace forms in accordance with ACI 301 and ACI 347. In addition to those requirements, forms shall be placed and braced so the finished edges and joints meet the tolerances listed later in this section. B. Preparation of Form Surfaces: 1. Clean reused forms of concrete matrix residue; repair and patch as required to return forms to acceptable surface condition. 2. Coat contact surfaces of forms with specified form -coating compound before reinforcement is placed. Apply form -coating compound according to manufacturer's instructions. Do not allow excess form -coating material to accumulate in forms or to come in contact with concrete surfaces against which fresh concrete will be placed. C. Slipforming: Slipforming of vertical curb and gutter sidewalks is permitted. D. For Surfaces Exposed To View: Form faces shall be free from raised grain, tears, worn edges, patches, dents, or other defects which would impair texture of the concrete surfaces. Minimize number of seams in form material, and arrange seams in an orderly manner. City of Fort Collins SECTION 02520 — Portland Cement Concrete Paving Park Planning & Development Division Page 5 of 10 3.03 Reinforcement and Embedments: A. General: 1. Fabricate, position, and secure reinforcement and embedded items according to ACI 301 and ACI 315. Coordinate with other sections for locations, instructions, or equipment for embedded items. 2. Shop drawings are not required. 3. Welding reinforcement is not permitted. 4. In the event of discrepancy, immediately notify the Owner's Representative. Do not proceed with installation in areas of discrepancy until all such discrepancies have been fully resolved. B. Field -Bending of Reinforcement: Reinforcement partially embedded in concrete shall not be field -bent, except as noted on the drawings or specifically permitted by the Owner's Representative. C. Inspection of Reinforcement: Completed installation of concrete reinforcement must be reviewed by the Owner's Representative before depositing concrete. D. Unless otherwise indicated, place reinforcement where required at top of slabs on grade. Provide i/2-inch minimum cover over reinforcement. E. Dowels: Grease sleeves, insert dowels and through form, secure dowel basket against movement. F. Notches for Sleeving: Notch both vertical sides of walk or slab where sleeving occurs. G. Welded wire fabric shall be overlapped one full mesh and tied. H. Fibrous Reinforcement: 1. Add fibrous concrete reinforcement to concrete materials at the time concrete is batched in amounts in accordance with approved submittals for each type of concrete required. 2. Mix batched concrete in accordance with manufacturer's recommendations for uniform and complete dispersion. 3.04 Joints: A. General: Place joints in accordance with ACI 301. Conform to the tolerances listed later in Part 3. B. Isolation/Expansion Joints: Isolation joint and expansion joint are synonymous for concrete paving. 1. Place isolation joints where work abuts existing walls, curbs and structures, and where shown on the drawings. 2. Interrupt reinforcement at isolation joint. Install dowels only where indicated on drawings. 3. Joint filler shall extend full depth of the slab. Hold back filler from top of slab as required for sealant. Attach joint filler to first placement. 4. Seal all expansion joints per Section 07900. C. Keyed/Construction Joints: Keyed joint and construction joint are synonymous for concrete paving. 1. Reinforcement, if required, shall continue through the joint. 2. Install where indicated on drawings, or where required by concrete delivery or finishing rate. 3. Key first placement. Key shall be 1 %2 inches wide and '/. inches deep. City of Fort Collins SECTION 02520 - Portland Cement Concrete Paving Park Planning & Development Division Page 6 of 10 4. After first placement has hardened, clean and roughen face. Install control joint form at top of slab. 5. Subject to Owner's Representative approval; manufactured leave -in -place cold joint form may be used. D. Control/Score Joint: Control joint and score joint are synonymous for concrete paving. 1. Control joints shall penetrate 1/3 of slab thickness. 2. Sawn Joints: Control joints on play area curb shall be sawn. Kerf shall be 3/16-inch wide. Start cutting as soon as concrete is able to be sawn without dislodging aggregate. Complete cutting before shrinkage cracks occur. Joints perpendicular to walls may be less than required depth within 6 inches of the wall, and may stop 2 inches from the wall. Wash slurry from concrete to avoid staining of slab. 3. Tooled Joints: Control joints maybe cut into the plastic concrete during finishing operations. Tooled joints shall have '/< radius, and shall not incorporate a troweled edge unless specifically noted on the drawings. 4. Formed control joints are permitted only in conjunction with keyed joints. 5. Unless otherwise indicated, provide control joints at the following intervals: Use Tyke Maximum Spacing Colored and non -colored sidewalk Sawn Joints 10' c-c & Continuous along centerline 3.05 Concrete: A. Preplacement Inspection: Form work installation, reinforcing steel placement, and installation of all items to be embedded or cast in, to be verified by the Owner's Representative prior to placement. B. General: Comply with ACI 301, ACI 304, and as herein specified. C. Added Water: Concrete mix has been designed to a specific water cement ratio in order to enhance durability of the final product. Do not add water at the job site or concrete will not be accepted. D. Cold Weather Placement: When depositing concrete after the first frost or when the mean daily temperatures area below 40 degrees, follow recommendations of ACI 306 as modified herein. Use specified accelerator. Maintain concrete temperature at a minimum of 55 degrees for not less than 72 hours after depositing. Do not place concrete without approval of the Owner's Representative on days when temperature at 9:00 a.m. is below 30 degrees. Job -cured cylinders for verification of strength and/or the adequacy of the Contractor's protective methods will be required. E. Hot Weather Placement: When depositing concrete in hot weather, follow recommendations of ACI 305 as modified herein. When the air temperature is expected to exceed 90 degrees, the Contractor shall obtain acceptance from the Civil Engineer or Owner's Representative of the procedures to be used in protecting, depositing, finishing, and curing the concrete. The temperature of concrete at the time of placement shall not exceed 90 degrees. Protect to prevent rapid drying. Start finishing and curing as soon as possible. Specified water reducing retarding admixture may be used. The use of continuous wetting or fog sprays may be required by the Owner's Representative for 24 hours after depositing. F. Placing: Deposit and consolidate concrete slabs in a continuous operation, within the limits of construction joints, until the placing of a panel or section is completed. Deposit concrete as nearly as practicable in its final location to avoid segregation. City of Fort Collins SECTION 02520 — Portland Cement Concrete Paving Park Planning & Development Division Page 7 of 10 G. Consolidation: Consolidate concrete with internal vibrators with a minimum frequency of 7,000 rpm. Maintain one standby vibrator for every three vibrators used. Consolidate according to ACI 309. Do not transport concrete with vibrators. Work concrete into corners and around embedments and reinforcement. H. Surface Leveling: Strike off and level surface with screed of sufficient length to span the slab. On slabs greater than 15 feet wide, use intermediate screed strips. 3.06 Finishes: A. Float Finish: After surface stiffens enough to support the operation, float with hand floats or powered disc floater. Use magnesium float; do not use wood float on air entrained concrete. Check surface planeness with a 10-foot straight edge, applied at not less than two different angles. Cut down high spots and fill low spots to produce a surface with Class B tolerance. Refloat the slab to a uniform sandy texture. B. Broom Finish: Concrete flatwork shall receive a heavy broom finish applied at a right angle to the direction of travel. The plaza area shall have smooth troweled joints, 1'/2 inches from the centerline of the joint, to result in a total trowel width of 3 inches. All other flatwork shall have broom finish over joints. C. Exposed Aggregate Finish: Immediately after floating, apply surface retardant. Apply retardant uniformly. Cover with polyethylene sheet to retain moisture. When mortar is hard enough to retain aggregate but soft enough to be removed by brushing, wash the surface with water and remove mortar from surface aggregate by brushing. Do not dislodge aggregate. D. Coordinate rate of concrete placement with pace of washing crew. E. Formed Finishes: Surfaces Not Exposed to View: Patch tie holes and defects. Chip off fins greater than '/. inch in height. 2. Surfaces Exposed to View: Patch tie holes and defects. Completely remove fins. Schedule of Finishes: Sidewalk — heavy broom finish. F. Notch both vertical sides of concrete flatwork to indicate location of irrigation sleeves. 3.07 Curing/Sealing: A. Apply curing compound within 30 minutes of completing finish. Follow manufacturer's recommendations for applying compound. Reapply in areas exposed to rain within 3 hours of initial application. Maintain continuity of coating and repair damage during 7-day curing period. Follow manufacturer's instructions for sealing interior slabs. 3.08 Tolerances: A. Surface Planeness: Unless otherwise specified, produce slabs with a Class B tolerance. 1. Finishes with Class B tolerances shall be true planes within %, inch in 10 feet, as determined by a 10-foot straight edge placed anywhere on the slab in any direction. 2. Slope interior slabs to drains as indicated. B. Formed Surfaces, Joints, and Embedments: Unless otherwise specified, the finished work shall meet the following tolerances: 1. Variations of formed, or cut or tooled linear element: a. In 20 feet: '/2 inch. City of Fort Collins SECTION 02520 - Portland Cement Concrete Paving Park Planning R Development Division Page 8 of 10 b. For entire length: I inch. 3.09 Field Quality Control: A. Field inspection and testing will be performed under provisions of Paragraph 1.06, Tests, and as specified below. B. Concrete Tests: Shall be provided by the Contractor and shall be accordance with requirements of ACI 301, Chapter 16 — Testing, except as noted or modified in this section. a. Strength test. i. Mold and cure four cylinders from each sample. ii. Test one at 7 days and one at 14 days for information and one at 28 days for acceptance. Keep the remaining one as a spare to be tested as directed by the Owner. b. Minimum samples. Collect the following minimum samples for each 28-day strength concrete used in the work for each day's placing: uanti 50 cubic yards or less 50 to 100 cubic yards 100 cubic yards or more Number of Samples one two two plus one sample for each additional 100 cubic yards c. Sample marking. i. Mark or tag each sample of compression test cylinders with date and time of day cylinders were made. ii. Identify location in work where concrete represented by cylinders was placed. iii. Identify delivery truck or batch number, air content, and slump. d. Slump test. Conduct test for each strength test sample and whenever consistency of concrete appears to vary. e. Air content. Conduct test from one of first three batches mixed each day and for each strength test sample. C. Acceptance of Concrete: 1. If the average of three consecutive 7-day tests falls below the specified 7-day strength, the Owner shall have the right to require conditions of temperature and moisture necessary to secure the required strength and may require core tests in accordance with ASTM C-42. 2. Strength level of concrete will be considered satisfactory so long as average of all sets of three consecutive strength test results equals or exceeds specified 28-day strength and no individual strength test result falls below specified strength by more than 500 psi. D. Failure of Test Cylinder Results: 1. Upon failure of the 28-day test cylinder results, Owner may require Contractor, at his expense, to obtain and test at least three cored samples from area in question. 2. Concrete will be considered adequate if average of three core tests is at least 85 percent of, and if no single core is less than 75 percent of the specified 28-day strength. 3. Upon failure of core test results, Owner may require Contractor, at his expense, to perform load tests as specified in ACI 318, Chapter 2. City of Fort Collins SECTION 02520 - Portland Cement Concrete Paving Park Planning & Development Division Page 9 of 10 4. In the event an area is found to be structurally unsound, the Owner may order removal and replacement of concrete as required. The costs of the core tests, the load test and the structural evaluation shall be borne by the Contractor. 5. Fill all core holes with a non -shrink grout as Master Builders Masterflo 713 or approved equal. E. Maintain records of placed concrete items. Record date, location of pour, quantity, air temperature, and test samples taken. END OF SECTION City of Fort Collins SECTION 02520 - Portland Cement Concrete Paving Park Planning & Development Division Page 10 of 10 DIVISION 2 SECTION 02900 - SITE REVEGETATION PART 1-GENERAL 1.01 Description of Work A. The work covered by this specification includes the furnishing of all materials and application of fertilizer, seed and mulch to areas defined in the plans or required by field condition. The work shall be completed in accordance with these specifications, accepted horticultural practice, and with the plans. 1.02 Related Work A. See appropriate sections for site work needed prior to work required in this section. Obtain approval from the Engineer prior to starting work required in this section. 1.03 Submittals A. Submit manufacturer's specifications and literature on all products. B. Submit materials list including quantities and description of materials. 1.04 Quality Assurance A. Source Quality Control: Manufacturer's test for purity and germination of seed, dated within six months of seeding. B. Certificates: Manufacturer's certification that fertilizer meets specification requirements. PART 2 - MATERIALS 2.01 Grass Seed A. Grass seed shall be of the latest crop available. Seed shall meet Colorado Department of Agriculture Seed Laws, Chapter 35, Article 27. B. The seeding mixture shall be applied at a pure live seed (PLS) rate per acre AS SHOWN ON SHEET 4 OF 4. C. Do not use seed which has become wet, moldy, or otherwise damaged in transit or in storage. D. The Contractor shall compensate for percentage of purity and germination by furnishing sufficient additional seed to equal the specified pure live seed product. The formula for determining the quantity of pure live seed (PLS) shall be: Pounds of Seed (Bulk) x Purity x Germination = E. Pounds of Pure Live Seed (PLS) The Contractor shall present to the Engineer a certificate of the PLS test of the grass seed which he intends to use. All grass furnished shall be delivered in sealed bags showing the weight, analysis and vendor's name. 2.02 Fertilizer A. Commercial fertilizer type and application rate shall be AS SHOWN ON SHEET 4 OF 4. City of Fort Collins Section 02900 - Site Revegetation Park Planning & Development Division Page t of 4 2.03 Mulch A. Hydraulically spray or approved equal. 2.04 Topsoil A. Topsoil shall be select earth material of loose friable loam reasonably free of admixtures of subsoil, refuse stumps, roots, rocks, brush, weeds or other material which can be detrimental to the proper development of ground cover. PART 3 - EXECUTION 3.01 General A. The pattern of seeding and mulching, and fertilization if required, shall be as detailed or as required by field conditions to provide a uniform stand of grass acceptable to the City. In no case shall revegetation occur within 30 days of the application of a chemical weed control substance. B. Warranty excludes replacement of plants after final acceptance because of injury by storm, drought, drowning, hail, freeze, insects or diseases. 3.02 Preparation A. Verify that soil preparation has been completed prior to seeding. B. Seed areas damaged by construction activities as directed by the Engineer. C. Apply by broadcasting or drillings at the rate specified herein. D. Selection of the time of seeding shall be Contractor's responsibility, consistent with erosion control. E. Rework previously prepared areas that have become compacted or damaged by rains or traffic. F. Do not drill or sow during windy weather or when ground is frozen or unfrllable. G. Cover seed to depth between'/4 to'/2 inch by raking or harrowing. H. Firm seed areas with roller weighing maximum of 100 tbs. per foot to width. 3.03 Hydraulic Seeding and Mulching A. Seed and fertilize in the amounts per acre designated. Wood cellulose fiber mulch at 2,000 lbs/ acre. B. Combine with water to provide a slung. Perform hydraulic application in such a manner that the liquid carrier will uniformly distribute the material over the entire area to be seeded at rates not less than indicated herein. Do not compact. Double the amount of seed per acre if seed and mulch are applied in a single application. 3.04 Drill Seeding A. Seed shall be applied in a minimum of two passes at 90 degrees two each other. 3.05 Reseeding and Repair A. Reseed and mulch areas where there is not a satisfactory stand of grass at the end of 60 days after seeding. B. Minimum satisfactory stand: 4 plants per square foot. City of Fort Collins Section 02900 — Site Revegetation Park Planning & Development Division Page 2 of 4 3.06 Areas to be Seeded A. All areas that have been damaged or disturbed by the Contractor's operation shall be reseeded according to these specifications and as indicated on the plans. 3.07 Maintenance A. No maintenance is required, UNLESS NOTED ON THE BID SCHEDULE. City of Fort Collins Section 02900 — Site Revegetation Park Planning & Development Division Page 3 of 4 From Union Pacific Trail Specification Fertilizer and Seed Mix Commercial Fertilizer (18-46-0) Nitrogen Phosphorus Potassium Application rate of 250 lbs per acre Percent available by weight 18 46 0 Seed Mix Pure Live Seed Lbs./Acre Seed Buffalo Grass 40% 13 Blue Gramma 30% 14 Sheep's Fescue 30% 13 100 40 END OF SECTION City of Fort Collins Section 02900 — Site Revegetation Park Planning & Development Division Page 4 of 4 PART 2 - MATERIALS (Not Used) PART 3 - EXECUTION (Not Used) PART 4 - MEASUREMENT & PAYMENT (Not Used) END OF SECTION City of Fort Collins SECTION 01100 —SUMMARY OF WORK Park Planning & Development Division Page 2 of 2 POUDRE TRAIL REHABILITATION SCHEDULE OF DRAWINGS Cover Sheet Layout Plan Traffic Control Plan Trail Details Trail Details No Text 10111DIA=09:ri\IMA=1:F�\:IINor,%91@ ol,"K'i0:4II049[•l►`■Die jAn jr ir v •�. �'.�, 1 �* i r TRAIL � l � i 4 t L [W,1VIARl'INEZ� W -� y a _ r t -v, a.- .4 - �,_ >r -, f" �.J a .. ,�' s e;�•. � •ri4. .= _ IIi a - , c 0 L L a 0 •O N any 8681103 SPI014S I B ` F k � / . Ic a§§ k B dqm K § \/§ ( � in b Zz 5?; K c ; ■ 8d§ § ! \ E k�� � | o ° z w m ¥ Ld . }� ;CD , @ mm= /■{ ( §§m &§§PQ § /_) � E� � \e�§ / §/2g § §P§ ] §2 ] I � Q Q- w m w F-- w � U Z O U Bz � � LU � � D 0 CL SHEET D—] § U) F- F— w 0 5 <-4 n�m� I m S z Z O Q 8e. e--,w x z Q M bg Y J iV 8 O�J S� J < �5 LJ 0 N F— Z (n N LLI ;Z II ' Z t3 � Q 0 M J F- 0 SHEET D-2 5 W DIVISION I SECTION 01160 — SITE CONDITIONS PART 1 - SITE INVESTIGATIONS AND REPRESENTATION 1.01 General Investigations A. The Contractor acknowledges that he has satisfied himself as to the nature and location of the work, the general and local conditions, particularly those bearing upon access to the site; handling, storage, and disposal of materials; availability of water, electricity and roads; uncertainties of weather, or similar physical conditions at the site; the conformation and conditions of the ground; the equipment and facilities needed preliminary to and during the execution of the work; and all other matters which can in any way affect the work or the cost thereof under this Contract. 1.02 Soil Conditions A. The Contractor further acknowledges that he has satisfied himself as to the character, quality and quantity of surface and subsurface materials to be encountered from his inspection of the site and from reviewing any available records of exploratory work furnished by the Owner or included in these Documents. Failure by the Contractor to acquaint himself with the physical conditions of the site and all the available information will not relieve him from responsibility for properly estimating the difficulty or cost of successfully performing the work. 1.03 Contractor Representation A. The Contractor warrants that as a result of his examination and investigation of all the aforesaid data that he can perform the work in a good and workmanlike manner and to the satisfaction of the Owner. The Owner assumes no responsibility for any representations made by any of its officers or agents during or prior to the execution of this Contract, unless (1) such representations are expressly stated in the Contract, and (2) the Contract expressly provides that the responsibility therefore is assumed by the Owner. PART 2 - INFORMATION ON SITE CONDITIONS 2.01 General Any information obtained by the Engineer regarding site conditions, subsurface information, groundwater elevations, existing construction of site facilities, and similar data will be available for inspection, as applicable, at the office of the Engineer upon request. Such information is offered as supplementary information only. Neither the Engineer nor the Owner assumes any responsibility for the completeness or interpretation of such supplementary information. A. Differing Subsurface Conditions: In the event that the subsurface or latent physical conditions are found materially different from those indicated in these Documents, and differing materially from those ordinarily encountered and generally recognized as inherent in the character of work covered in these Contract Documents, the Contractor shall promptly, and before such conditions are disturbed, notify the Owner in writing of such changed conditions. 2. The Engineer will investigate such conditions promptly and following this investigation, the Contractor shall proceed with the work, unless otherwise instructed by the Engineer. If the Engineer finds that such conditions do so materially differ and cause an increase or decrease in the cost of or in the time required for performing the work, the Engineer will recommend to the Owner the amount of adjustment in cost and time he considers reasonable. The Owner will make the final City of Fort Collins SECTION 01160 — SITE CONDITIONS Park Planning & Development Division Page 1 of 3 decision on all Change Orders to the Contract regarding any adjustment in cost or time for completion. B. Underground Utilities: Known utilities and structures adjacent to or encountered in the work are shown on the Drawings. The locations shown are taken from existing records and the best information available from existing utility plans, however, it is expected that there may be some discrepancies and omissions in the locations and quantities of utilities and structures shown. Those shown are for the convenience of the Contractor only, and no responsibility is assumed by either the Owner or the Engineer for their accuracy or completeness. PART 3 - CONTRACTOR'S RESPONSIBILITY FOR UTILITY PROPERTIES AND SERVICE 3.01 General A. Where the Contractor's operations could cause damage or inconvenience to railway, telegraph, telephone, television, oil, gas, electricity, water, sewer, or irrigation systems, the operations shall be suspended until all arrangements necessary for the protection of these utilities and services have been made by the Contractor. B. Notify all utility offices which are affected by the construction operation at least 48 hours in advance. Under no circumstances expose any utility without first obtaining permission from the appropriate agency. Once permission has been granted, locate, expose, and provide temporary support for all existing underground utilities. C. The Contractor shall protect all utility poles from damage. If interference of power poles, telephone poles, guy wires, or anchors are encountered, notify the Owner's Representative and the appropriate utility company at least 48 hours in advance of construction operations to permit the necessary arrangements for protection or relocation of the interfering structure. D. The Contractor shall be solely and directly responsible to the Owner and operators of such properties for any damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of any injuries or damage which may result from the construction operations under this Contract. E. Neither the Owner nor its officers or agents shall be responsible to the Contractor for damages as a result of the Contractor's failure to protect utilities encountered in the work. F. If the Contractor while performing the Contract discovers utility facilities not identified in the Drawings or Specifications, he shall immediately notify the Owners and the utility in writing. G. In the event of interruption to domestic water, sewer, storm drain, or other utility services as a result of accidental breakage due to construction operations, promptly notify the proper authority. Cooperate with said authority in the restoration of service as promptly as possible and bear all costs of repair. In no case shall interruption of any water or utility service be allowed to exist outside working hours unless prior approval is granted. H. The Contractor shall replace, at his own expense, any and all other existing utilities or structures removed or damaged during construction, unless otherwise provided for in these Contract Documents or ordered by the Engineer. 3.02 Interfering Structures A. Take necessary precautions to prevent damage to existing structures whether on the surface, aboveground, or underground. An attempt has been made to show major structures on the Drawings. The completeness and accuracy cannot be guaranteed, and it is presented simply as a guide to avoid known possible difficulties. City of Fort Collins SECTION 01160 - SITE CONDITIONS Park Planning & Development Division Page 2 of 3 3.03 Field Relocation A. During the progress of construction, it is expected that minor relocations of the work will be necessary. Such relocations shall be made only by direction of the Owner's Representative. If existing structures are encountered that prevent the construction, and that are not properly shown on the Drawings, notify the Owner's Representative before continuing with the construction in order that the Owner's Representative may make such field revision as necessary to avoid conflict with the existing structures. If the Contractor shall fail to so notify the Owner's Representative when an existing structure is encountered, and shall proceed with the construction despite the interference, he shall do so at his own risk. 3.04 Easements A. Easements and permits will be obtained by the Owner where portions of the work are located on public or private property Easements will provide for the use of the property for construction purposes to the extent indicated on the easements. Copies of these easements and permits are available upon request to the Owner. It shall be the Contractor's responsibility to determine the adequacy of the easement obtained in every case and to abide by all requirements and provisions of the easement. The Contractor shall confine his construction operations to within the easement limits or make special arrangements with the property owners or appropriate public agency for the additional area required. Any damage to property, either inside or outside the limits of the easements provided by the Owner, shall be the responsibility of the Contractor as specified herein. The Contractor shall remove, protect, and replace all fences or other items encountered on public or private property. Before final payment will be authorized by the Owner's Representative, the Contractor will be required to furnish the Owner with written releases from property owners or public agencies where side agreements or special easements have been made by the Contractor or where the Contractor's operations, for any reason, have not been kept within the construction right-of-way obtained by the Owner. B. It is anticipated that the required easements and permits will be obtained before construction is started. However, should the procurement of any easement or permit be delayed, the Contractor shall schedule and perform the work around these areas until such a time as the easement or permit has been secured. 3.05 Land Monuments A. The Contractor shall notify the Owner's Representative of any existing Federal, State, Town, County, and private land monuments encountered. Private monuments shall be preserved, or replaced by a licensed surveyor at the Contractor's expense. When Government monuments are encountered, the Contractor shall notify the Owner's Representative at least two (2) weeks in advance of the proposed construction in order that the Owner's Representative will have ample opportunity to notify the proper authority and reference these monuments for later replacement. END OF SECTION City of Fort Collins SECTION 01160 — SITE CONDITIONS Park Planning & Development Division Page 3 of 3