HomeMy WebLinkAboutRESPONSE - BID - 5823 CITY OF FORT COLLINS AND CSU TRANSIT CENTER (4)SECTION 00300
BID FORM
PROJECT: CITY OF FORT COLLINS AND COLORADO STATE UNIVERSITY TRANSIT CENTER
PHASE 1A; Bid No. 5823
Place Loveland, Colorado
Date 11/5/03
1. In compliance with your Invitation to Bid dated October 13, 2003 ,
and subject to all conditions thereof, signed ECI Site Construction
Management a * (Corporatio , Limited Liability
Company, Partnership, Joint Venture, or ietor)** authorized to do
business in the State of Colorado hereby proposes to furnish and do
everything required by the Contract Documents to which this refers for the
construction of all items listed on the following Bid Schedule or Bid
Schedules.
2. The undersigned Bidder does hereby declare and stipulate that this proposal
is made in good faith, without collusion or connection with any other
person or persons Bidding for the same Work, and that it is made in
pursuance of and subject to all the terms and conditions of the Invitation
to Bid and Instructions to Bidders, the Agreement, the detailed
Specifications, and the Drawings pertaining to the Work to be done, all of
which have been examined by the undersigned.
3. Accompanying this Bid is a certified or cashier's check or standard Bid bond
in the sum of 5% of total bid ($
5% of total bid ) in accordance with the Invitation To Bid and
Instructions to Bidders.
4. The undersigned Bidder agrees to execute the Agreement and a Performance
Bond and a Payment Bond for the amount of the total of this Bid within
fifteen (15) calendar days from the date when the written notice of the
award of the contract is delivered to him at the address given on this Bid.
The name and address of the corporate surety with which the Bidder
proposes to furnish the specified performance and payment bonds is as
follows: Employers Mutual Casualty Company, P.O. Box 712 Des Moines, IA 50303
5. All the various phases of Work enumerated in the Contract Documents with
their individual jobs and overhead, whether specifically mentioned,
included by implication or appurtenant thereto, are to be performed by the
CONTRACTOR under one of the items listed in the Bid Schedule, irrespective
of whether it is named in said list.
6. Payment for Work performed will be in accordance with the Bid Schedule or
Bid Schedules subject to changes as provided in the Contract Documents.
7. The undersigned Bidder hereby acknowledges receipt of Addenda No.
7/96 Section 00300 Page 1
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
CSU Transit Center
City of Fort Collins
Coover-Clark & Associates, P.C.
$
1,892,216.45
12/02
Fort Collins, CO
970-221-6273
303-783-0040
Diamond Valley Sports Complex
Town of Windsor
Jim Sell Design, Inc.
$
490,535.00
10/02
Windsor, CO
970-674-2444
970-484-1921
Douglas County Entry Signage
Douglas County Government
Design Concepts
$
93,463.00
10/02
Douglas County
303-470-0140
303-664-5301
Springer Park & Perry Pines Park
Douglas County Government
Design Concepts
$
63,809.00
10/02
Douglas County
303-470-0140
303-664-5301
Bluffs Regional Park
Douglas County Government
The Architerra Group
$
637,424
6/02
Douglas County
303-663-6226
303-948-0766
EastlWest Regional Trail
Douglas County Government
The Architerra Group
$
165,666
8t02
Douglas County
303-663-6226
303-948-0766
Jim Hamm Pond & Nature Area
City of Longmont
The Norris Dullea Company
$
630,855
6/02
City of Longmont
303-651-8448
303-892-1166
Fossil Creek Park Ph. IA
City of Fort Collins
BHA Design
$
956.545
5/02
City of Fort Collins
970-221-6618
970-223-7577
Dad Clark Park - Maintenance
Highlands Ranch Metro District
Shalkey & Team, Inc.
$
7,412
5/02
Highlands Ranch Metro. District
303-791-2710
303-820-3340
Highland Heritage Regional Park Entry Sign
Douglas County Government
Design Concepts
$
61,329
5/02
Douglas County Government
303470-0140
303-664-5301
Aurora Wheel Park
City of Aurora
ICON Engineering, Inc.
$
1,968,600
5/02
City of Aurora
303-739-7179
303-221-0802
Athletic Fields at the Ridge at West Meadows
Foothills Park & Recreation Dist.
Design One
$
1,426,495
5/02
Foothills Park & Recreation Distdct
303409-2304
303-832-2020
Valmont City Park Ph. I
City of Boulder
McLaughlin Water Engineers, Inc.
$
2,237,584
5102
City of Boulder
303413-7225
303-458-5550
Rock Creek South Recreation Center
Superior Metro District No. 2
The Norris Dulles Company
$
2,007,216
5t02
Superior Metro District
303-987-0835
303-892-1166
Fairgrounds Regional Park Playground
Douglas County Government
Design Concepts
$
87,182
4/02
Douglas County Government
303470-0140
303-664-5301
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Dad Clark Park
Highlands Ranch Metro District
Shalkey & Team, Inc.
$
700,217
9/01
Highlands Ranch Metro. District
303-791-2710
303-820-3340
Castle Rock Community Park
Town of Castle Rock
Carder -Burgess
$
3,350,502
8/01
Town of Castle Rock
303-814-7446
303-820-5240
Bingham Lake
Douglas County Government
The Architerra Group
$
218,650
8/01
Douglas County Government
303-470-0140
303-948-0766
Eaton Park
City of Boulder
City of Boulder
$
152,770
8101
City of Boulder
303-413-7228
303-413-7228
Bayou Gulch Regional Park Ph. I
Douglas County Government
Design Concepts
$
291,347
5101
Douglas County Government
303-470-0140
303-664-5301
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Boulder Skate Park
City of Boulder
Shapins Associates
$
695,190
12/00
Boulder, CO
303-413-7227
303-442-4588
Big Dry Creek
Highlands Ranch Metro. District
Mundus Bishop Design, Inc.
$
633,963
10/00
Highlands Ranch Metro. District
303-791-2710
303-830-2585
Highland Heritage Regional Park
Douglas County Government
Design Concepts
$
531,184
9100
Douglas County Government
303-470-0140
303-664-5301
Challenger Park Phase Vill
Douglas County Government
Design Concepts
$
171,124
7100
Parker, CO
303-660-7490
303-664-5301
Foothills Community Park
City of Boulder
Design Concepts
$
1,642,803
7/00
City of Boulder
303413-7223
303-664-5301
Challenger Park Phase VII
Douglas County Government
Design Concepts
$
1,181,530
6/00
Parker, CO
303-660-7490
303-665-5313
Cottonwood Glen Park
City of Fort Collins
City of Fort Collins
$
1,137,277
6/o0
Fort Collins, CO
970-221-6618
970-221-6618
Willow Farm Park
City of Longmont
Design Concepts
$
1.111,036
6/00
Longmont, CO
303-651-8448
303-664-5301
Pinery Park
Douglas County Government
Design Concepts
$
87,813
2100
Douglas County
303-660-7490
303-664-5301
Bradfield Paris
City of Boulder
Play Environments
$
389,654
4/00
Boulder, CO
303-441-3061
303-682-0854
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Challenger Park Phase VI
Douglas County Government
Design Concepts
$
545,975
3199
Parker, CO
303-660-7490
303-664-5301
Redstone Park
Highlands Ranch Metro. District
Design Concepts
$
3,123,338
9/99
Highlands Ranch Metro. District
303-791-2710
303-664-5301
Community Park in North Boulder
City of Boulder
Design Concepts
$
1,270,635
10/99
Boulder, CO
303-413-7227
303-664-5301
West Woods Park
City of Arvada
City of Arvada
$
308,231
9199
Arvada, CO
303-660-1036
303-660.1036
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Challenger Park Phase V
Douglas County Government
Design Concepts
$
423,725
3/98
Parker, CO
303-660-7490
303-6645301
Columbine Meadows Park
City of Broomfield
The Norris Dulles Company
$
423,757
5/98
Broomfield, CO
303438-6388
303-892-1166
Grant Frontier Park
City and County of Denver
Wank and Associates
$
1,044,065
6/98
Denver, CO
303-640-5491
303-628-0053
Cobblestone Park
City of Westminster
Civitas, Inc.
$
590,410
7/98
Westminster, CO
303430-2400 ext. 2214
303-571-0053
Mitchell Gulch Neighborhood Park
Town of Castle Rock
The Norris Dulles Company
$
558,218
10/98
Castle Rock, CO
303-660-1036
303-892-1166
Westfield Park
City of Fort Collins
BHA Design, Inc.
$
1,021,493
10198
Fort Collins, CO
970-227-6366
970-223-7577
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Alexander Dawson School
Alexander Dawson Foundation
Fletemeyer & Lee Associates, Inc.
$
470,561
5/98
Lafayette, CO
702-733-7880
303-443.3750
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Stazio Balifields Phase II
City of Boulder
Bucher, Willis, & Ratliff
$
1,464,415
6/97
Boulder, CO
303-441-3400
303-292-5056
Daniel L. Schaefer
Foothills Park & Rec. District
Donald H. God! & Associated, Inc.
$
490,061
6/97
Lakewood, CO
303-987-2673
303-989-2853
Xeric Demonstration Garden
City of Greeley
MDG, Inc.
$
107,662
8/97
Greeley, CO
970-351-2131
303-571-5787
Grandview Cemetery
City of Fort Collins
City of Fort Collins
$
48,359
8/97
Fort Collins, CO
970-221-6660
97D-221-6660
Leffhand Creek Park
City of Longmont
Rocky Mountain Consultants, Inc.
$
570,374
10/97
Longmont, CO
303-651-8448
303-7725282
Brighton Ballfields
City of Brighton
Design Concepts
$
1,030,397
11/97
Brighton, CO
303-659-4050
303-644-5301
Lafayette Library
City of Lafayette
Civitas, Inc.
$
148,090
10/97
Lafayette, CO
303-6655588
303-571-0053
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Potts P.U.D.
Russ Campion
Architecture One
$
64,455
05/97
Fort Collins, CO
970-490-1447
970-669-9060
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Loveland Sculpture Park
City of Loveland
Landmark Engineering
$
413,022
10/96
Loveland, CO
97D-962-9800
970-667-6286
Challenger Park Phase IV B
Douglas County Government
Design Concepts
$
309,311
10/96
Parker, CO
303-660-7490
303-447-8144
Ridgeview Park
City of Fort Collins
City of Fort Collins - Chuck Ainsworth
$
96,923
10/96
Fort Collins, CO
970-22M360
970-221-6360
Rogers Grove Phase II
City of Longmont
Wank Associates
$
204,337
08/96
Longmont, CO
303-651.8446
303-628-0003
Sloan Lake Trail Improvements
City of Denver
EDAW, Inc.
$
465,040
07/96
Denver, CO
303-964-2552
303534-0747
Challenger Park Phase IV
Douglas County Government
Design Concepts
$
212,916
07/96
Parker, CO
303-660.7480
303-447-8144
Northglenn Park Construction
City of Northglenn
City of Northglenn
$
212,692
07/96
Northglenn, CO
303450-8839
303-450-8839
Superior Elementary
Boulder Valley School District
Environmental Concems, Inc.
$
148,909
09/96
Boulder, CO
303-447-5081
970-669-6291
Highlands Ranch Phase II
Highlands Ranch Metro District
The Norris Dullea Company
$
40,546
07/96
Highlands Ranch, CO
303-791-0430
303-860-1166
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Courtyard by the Marriott
White Lodging Services
Lantz-Boggio Architects, P.C.
$
128,078
11/96
Louisville, CO
219-769-2367
303-773-0436
Emerald Glen
Bray Enterprises
BHA Designs
$
258,212
07/96
Loveland, CO
970-663-1897
970-223-7577
North Park Office Building
Virga Corporation
Bruce Pizzimenti - Play Environments
$
31.403
04/96
Loveland, CO
970-667-2627
303-682-0854
RESIDENTIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Deifik Residence
Bruce and Nancy Deifik
EDAW, Inc.
$
150,037
06/96
Greeley, CO
303-3534222
3035954522
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Challenger Park, Phase III
Douglas County Parks
Design Concepts
$
201,722
10/95
Parker, CO
303-660-7490
303- 47-8144
North Shore Park
City of Longmont
Kent Scott Nelson
$
315,851
1 O/95
Longmont, CO
303-651-8446
719-630-7322
Brighton Park
City of Brighton
$
109,946
4/95
Brighton, CO
303-773-3800
Roger's Grove Park
City of Longmont
Paula Fitzgerald
$
95,590
4195
Longmont, CO
303-651-8446
303-651-8446
Bein Park
Town of Berthoud
Play Environments
$
131,911
3/95
Berthoud, CO
970-532-2643
303-682-0854
Centennial Park Pump Station
City of Loveland
Aqua Engineering
$
101,806
4195
Loveland, CO
970-962-2451
970-229-9668
New Fort Collins High School
Poudre R-1 School District
Architectural Horizons
$
1,465,000
08/95
Fort Collins, CO
970-482-7722
970-225-2704
Highlands Ranch 100 Park
Highlands Ranch Metro District
The Norris Dultea Company
$
400,584
10195
Highlands Ranch, CO
303-791-0430
303-860-1166
Boulder High School Pump Station
Boulder Valley School District
Aqua Engineering
$
108,252
4195
Boulder, CO
303-447-5044
970-229-9668
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Mariana Glen Phases I & II
Bray Enterprises
BHA Design
$
222,201
9/95
Loveland, CO
970-663-1897
970-223-7577
Mckee Medical Center
Mckee Medical Center
Aqua Engineering
$
187,882
10195
Loveland, CO
970-635-4170
970-229-9668
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Challenger Regional Park Phase II
Douglas County
Design Concepts
$
125,692
9/94
Parker, CO
303-660-7490
303-447-8144
Drake Wastewater Treatment Plant
City of Fort Collins
EDAW, Inc.
$
194,779
5/94
Fort Collins, CO
970-221-6660
970-484-6073
Sheridan Lighted Ballfields
South Suburban Parks 8 Rec District
Design Concepts
$
282,096
5194
Sheridan, CO
303-795-6531
303-447-8144
Skyview High School
Adams County School District
Fletemeyer & Lee
$
189,380
8/94
Thomton, CO
303-443-3750
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
KMart Distribution Center
KMart Corporation
Randy Randall Assoc.
$
201,203
7/94
Brighton, CO
303-654-0054
303-465-4746
Rocky Mountain Factory Outlet Mall
JMJ Properties
Environmental Concerns, Inc.
$
135,590
7/94
Loveland, CO
616-798-4670
970-669.6291
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Stephens Park, Phase It
Town of Vail
EDAW, Inc.
$
237,133
7/93
Vail, CO
303-479.2161
970484-6073
Longmont Service Center
City of Longmont
Paula Fitzgerald
$
72,830
10/93
Longmont, CO
303-651-8446
303-651-8446
Challenger Regional Park - Phase 1
Douglas County
Design Concepts
$
284,052
9193
Parker, CO
303-660-7490
303-447-8144
Brighton Recreation Center
City of Brighton
Winston Associates
$
120,058
6/93
Brighton, CO
303-773-3800
303-440-9200
Foothills Athletic Complex
Foothills Parks 8 Rec District
Lary Rogers Design
$
142,656
5193
Lakewood, CO
303-987-3602
303-989-6996
Laurel Elementary School
Poudre School Distnct
Dulaney Architects
$
76,183
7/93
Fort Collins, CO
970-490-3507
303-770-0987
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Longmont Shopko Stores
Shopko, Inc.
Reams 8 Patterson, Inc.
$
67,290
10/93
Longmont, CO
Loveland Shopko Stores
Shopko, Inc.
Tupa Associates
$
88,898
10193
Loveland, CO
303-755-6315
through I
ECI Site Construction Management
CONTRACTOR
BY: 6Ak__�w
Rick Coulter, Vice-Pres ennt ---
ADDRESS: P.O. Box 2135
Loveland, CO 80539
8. BID SCHEDULE (Base Bid)
Please use the attached Bid Schedule when submitting your bid.
9. PRICES
The foregoing prices shall include all labor, materials, transportation,
shoring, removal, dewatering, overhead, profit, insurance, etc., to cover
the complete Work in place of the several kinds called for.
Bidder acknowledges that the OWNER has the right to delete items in the Bid
or change quantities at his sole discretion without affecting the Agreement
or prices of any item so long as the deletion or change does not exceed
twenty-five percent (250) of the total Agreement Price.
PECTFUMY SUBMITTED:
w
Title
Date
License Number (If Applicable)
(Seal - if Bid is by corporation)IV)
Attest: >�
Barbara J. erson
Address P.O. Box 2135
Telephone (970) 669-6291
7/96 Section 00300 Page 2
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Squires Park Soccer Fields
City of Westminster
Norris Dullea Co.
$
119,150
8/92
Westminster, CO
303430-2400
303-860-1166
SouthShore Scenic Parkway
City of Loveland
Jerry Adamson
$
146,930
5/92
Loveland, CO
970-962-2451
970-962-2451
Westview Middle School
St. Vrain School District
Paula Fitzgerald
$
146,377
6/92
Longmont, CO
303-776-6200
303-776-0960
Southwest Elementary School
Poudre School District
Dulaney Architecture
$
105,320
9/92
Fort Collins, CO
970-490-3507
303-770-0987
Southshore Park, Phase II
City of Loveland
Aqua Engineering
$
40,801
6192
Loveland, CO
970-962-2451
970-229-9668
Northlake Park Pump Station
City of Loveland
Aqua Engineering
$
67,045
6/92
Loveland, CO
970-962-2451
970-229-9668
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
High Plains Youth Center
ReBoundl Colorado
Rockne Associates
$
136,812
6/92
Brush, CO
303-730-1418
303-730-6125
Benson Park Children's Sculpture
High Plains Arts Council
Ripley & Assoc.
$
47.044
11/92
Garden, Loveland, CO
970-663-2940
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Longmont Price Park Xeriscape
City of Longmont
EDAW, Inc.
$
27,000
10191
Longmont, CO
303-651-8376
970484-6073
Northlake Parks Sidewalks
City of Loveland
City of Loveland
$
33,886
9/91
Loveland, CO
970-962-2451
970-962-2451
Northlake Park Athletic Fields
City of Loveland
City of Loveland
$
83,761
7191
Loveland, CO
970-962-2451
970-962-2451
Greenway Neighborhood Park
City of Broomfield
Fleetmeyer & Lee
$
221,818
6/91
Broomfield, CO
303469.3301
303-443-3750
South Shields Street Improvements
City of Fort Collins
City of Fort Collins
$
45,627
8191
Fort Collins, CO
970-221-6660
970-221-6660
Canal Importation Channel
City of Fort Collins
City of Fort Collins
$
32,000
10191
Fort Collins, CO
970-221-6660
970-221-6660
Utility Service Center
City of Fort Collins
CityScape
$
11,100
4/91
Fort Collins, CO
970-221-6660
970-2264074
COMMERCIAL
PROJECT NAME
OWNER
ARCHITECT
CONTRACT
COMPLETION
Harbor Walk Improvements
The Group, Inc.
The Group, Inc.
$
17,000
7/91
Fort Collins, CO
970-221-0700
970-221-0700
Spirit of Joy Church
Spirit of Joy Church
Linda Ripley
$
32,550
10191
Fort Collins, CO
Dan Ostenniller Office & Water Feature
Dan Ostermiller
Environmental Concerns, Inc.
$
26,000
8/91
Loveland, CO
Sculptor
970-669-6291
Loveland Sculpture Works
High Plains Arts Council
Environmental Concerns, Inc.
$
47,350
8/91
Loveland, CO
Benson Park Plaza
High Plains Arts Council
Stacy Swearingen
$
56,000
8/91
Loveland, CO
Chatfield Arboretum
Denver Botanical Gardens
EDAW, Inc.
$
33,000
5/91
Denver, CO
ENVIRONMENTAL CONCERNS, INC.
EQUIPMENT LIST
AS OF 7129/03
VEHICLES
YEAR
MAKE
MODEL
VIN
1990
Chevy
Suburban
1GBEV16K4LF146493
1990
GMC
2-Ton Dump
1GDG6H1P1LJ603217
1991
GMC
2-Ton Topkick
1GDG6HIP7MJ058789
1994
Chevy
C1500
1GCDC14Z7RZ231364
1995
Dodge
Ram Pickup
1B7KF26C6SS204149
1995
Dodge
Ram Pickup
1B7KF26C1SS198146
1997
Chevy
K1500 Extended Cab
2GCEK19RXV1274373
1999
Dodge
Ram 1500 CC
3B7HF13Z2XM539227
2001
Ford
FSeries
3FTSW31F81MA13654
2001
Dodge
Ram 2500
3B7KF2361G752033
2002
Dodge
Ram 2500
3B7KF23622M248270
2003
Dodge
Ram
1D7HU18ZX3S138045
EQUIPMENT
John Deere 4x4 Tractor
790
LV079OG475301
1992
Case Unil-oader
1845c
JAF0101800
1993
Case Backhoe
580JK
JJG0176878
1994
Case Backhoe
580SK
JJG0173372
1998
Case Skid Steer
1845c
JAF0274586
1998
Case Pallet Forks
LAF1137
SN# 41087
Case Pallet Forks
1998
Vermeer
V5750
Lease / Purchase
Vermeer Tree Spade
TS-30
1VRC101L9T1001780
1993
Fabricated Wheel Compactor
1999
Case Trencher
560
JAF0254012
2001
Case Skid Steer
1845c
JAF0334249
2003
Case 75XT Skid Steer Loader
JAF0352005
TRAILERS
1973
Porte space Office Trailer
CMP
1094
1985
GE Captial Office/Construction Trailer
GSV-832
582640
1985
830 Satellite Mobile Storage Office
SE# 17320
1983
Red Equipment Trailer
ID612191COLO
1992
Homemade 4-Wheeler Trailer
1 D0601907CO
1992
Eager Beaver
10HDB
112HAN302NLO39349
1993
Sport Trailer
6X10 CARGO
STI0BPC12S9935143
1997
Big Tex Trailer
12P1-20
16VPX2027V1388907
2002
Big Tex Trailer
4K8PX182721 H92485
MISCELLANEOUS
Fimco Lawn & Garden Sprayer
LG25B 25 Gal 12-volt
(2) Honda Water Pumps
WH2OX
1995
Lowe 12" Auger
Model DFB - 12
Pentax Transit AL6
Sanborn Air Compressor
Model B07FL350-20
SE# L0880931
Skil Circular Saw
1994
Stihl Weed Eater
Model FS76
SE# 626919490
Toro Lawnmower
Bench Grinder
Model 59500
Husqvama Chain Saw
50 Rancher
Hotsey
Model 550B
1995
Coleman Powermate Generator
1994
Gen Set Generator Pro 4000
6EGHB28018A
1994
Walker Mower
MTSD
SE# 2414601637
Box Scraper
1998
John Deere Box Bushhog
BX720
1995
Spectra Physics Laser Transit
David White Auto Lazer
2110
SN#AG144759
Laser 2110 - Level
SN# AG193815
Maxey Snow Plow
SN# A4061
John Deere Snow Blower
TRS22
M0TR22A180264
Snapper Lawn Mower
ECLP21601RV
95101584
1999
CTI Forks
60 S
56271
Stihl Trimmer
241080629
ec,
site Construction Management
PRINCIPALS:
MANAGEMENT
QUALIFICATIONS
Brian Peterson, President
Brian graduated from the University of Nebraska Curtis with a degree in
commercial horticulture. He has over 25 years experience in the site
construction industry and founded ECI in 1980. Brian manages company
operations including marketing.
RICK COULTER, Vice President and General Superintendent
Rick has over 20 years experience in the site construction industry and
specializes in project team management, value engineering and
Owner/Contractor relations. Rick oversees field operations by conducting routine
site visits and attending weekly site meetings. Rick also maintains close one- on -
one relationships with all superintendents and project managers.
OFFICE STAFF:
Ted Johnson, Project Manager and Lead Estimator
Ted is a 1999 graduate of Colorado State University with a B.S. in Construction
Management. Ted has worked with ECI since 1997 and is the lead estimator,
responsible for project procurement and owner negotiations. Ted also works as
a project manager and is familiar with design/build and CM/GC project formats.
Ted has a strong background in civil, park, and site construction management
and project budgeting.
Tina Connect, Project Manager and ECI Administrator
Tina is a 1995 graduate of Colorado State University and joined ECI that same
year. As a project manager, Tina coordinates all project documentation and
works closely with the ECI estimating and field staff. Tina also coordinates all
project administration for ECI, which includes all aspects of budgeting, cost
control and analysis, and contract documentation. Tina is also involved in
marketing and has given numerous presentations on delivery methods for site
construction.
Selina Coulter, Administrative Assistant
Selina is an integral part of the ECI office team. She performs certified and
standard payroll, human resources, MSDS documentation, insurance certificate
administration, accounts payable and receivable and many other standard office
duties.
Sean Reynolds, Junior Estimator / Bid Administrator
Sean joined the ECI office staff full time in February of 2002. Sean graduated
from Colorado State University with a bachelor degree in natural science. Sean
assists ECI project managers and estimators with bid take -offs, project
scheduling using SureTrak, bid document procurement, submittals, and
subcontractor bid solicitations.
FIELD STAFF
Mike Paetzel, Superintendent
Mike started with ECI in 1989. He is experienced in all phases of site
construction and manages substantial and diverse projects. These projects
include skate parks, roller hockey rinks, multi -use buildings, and other complex
site elements. Mike is also involved in ECI's safety program and conducts
company accident investigations and coordinates field safety management.
Wes Statkus, Superintendent
Wes has been with ECI for over 7 years. He has experience with drainage
projects including box culvert construction and is key in the supervision of
landscaping and irrigation subcontractors. Wes is also instrumental in
performing and supervising ECI's warranty work and assists in project punch list
and close out.
Chad Oleson, Superintendent
Chad has over 19 years experience in the utility, earthwork and site construction
industry. Chad has worked with ECI since 1994 and has successfully completed
large park and public improvement projects. Chad specializes in site demolition,
concrete, grading, and drainage installation.
John Oatsvall, Superintendent
John has more than 7 years of experience with ECI. He has managed the
construction of many diverse projects including neighborhood parks, trails, and
synthetic turf field drainage and base installation.
Ray Gonzales, Superintendent
Ray started with ECI in 1989. He has managed the construction of larger park
projects and has experience with site drainage and grading, concrete flatwork
and post tension courts, landscaping, irrigation, and site amenity installation.
Bob Coulter, Superintendent
Bob has over 30 years experience in site and building construction. He has
worked for ECI since 1998. Bob manages site construction projects that
encompass restroom/concession buildings and shelter structures.
0117/
ACORD,a CERTIFICATE OF LIABILITY INSURANCE M/DILYYYYJ
10N 7/03
PRODUCER THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
Flood & Peterson Insurance Inc ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
4821 Wheaton Drive HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
P O Box 270370 ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
Fort Collins, CO 80527 INSURERS AFFORDING COVERAGE NAIC #
INSURED INSURERA: Travelers Insurance
Environmental Concerns, Inc. INsuRER6: Pinnacol Assurance
ECI Site Construction Management INSURER C:
PO Box 2135 INSURER D:
Loveland, CO 80539 INSURER E:
cuvtKAUtb
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
LTR
ADDIL
NSR
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE
DATE (MMIDD/YYI
POLICY EXPIRATION
DATE MMIDD/Y1'
LIMITS
A
GENERAL LIABILITY
X COMMERCIAL GENERAL LIABILITY
CLAIMS MADE F OCCUR
DTC08099A7531ND
10/01/03
10/01/04
EACH OCCURRENCE
$1,000,000
DAMAGE TO RENTEDPREMISES Me occurrence)
a300 000
MED EXP (Any one person)
$5 000
PERSONAL IL ADV INJURY
$1,000,000
GENERAL AGGREGATE
$2 000 000
GENT AGGREGATE LIMIT APPLIES PER:
POLICY F1Eo- F LOC
PRODUCTS - COMP/OP AGG
s2,000,000
A
AUTOMOBILE
LIABILITY
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
HIREDAUTOS
NON-OWNEDAUTOS
DT8108099A7531ND
10/01/03
10101/04
COMBINED SINGLE LIMIT
(Ea accident)
$1,000,000
X
BODILY INJURY
(Per person)
S
X
BODILY INJURY
(Per accident)
$
X
PROPERTY DAMAGE
(Per accident)
$
GARAGE LIABILITY
ANY AUTO
AUTO ONLY - EA ACCIDENT
E
OTHER THAN EA ACC
AUTO ONLY: AGG
$
$
A
EXCESS/UMBRELLA LIABILITY
X OCCUR CLAIMS MADE
DEDUCTIBLE
RX RETENTION $ 10000
DTSMCUP8099A753
10/01/03
10101/04
EACH OCCURRENCE
s2,000,000
AGGREGATE
s2,000,000
S
E
$
B
WORKERS COMPENSATION AND
EMPLOYERS'LIABILITY
ANY PROPRIETOR/PARTNER/EXECUTIVE
OFFICER/MEMBER EXCLUDED?
H yes, a under
PR
SPECIALAL PROVISIONS below
1221742
07/01/03
07/01/04
X I TWOSLTATUjI
IMIT
E.L. EACH ACCIDENT
$1,000,000
E.L. DISEASE - EA EMPLOYEE
$1,000,000
E.L. DISEASE - POLICY LIMIT
E1,000 000
OTHER
DESCRIPTION OF OPERATIONS I LOCATIONS / VEHICLES / EXCLUSIONS ADDED BY ENDORSEMENT / SPECIAL PROVISIONS
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
For Information Only DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 4 n DAYS WRITTEN
NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
IMPOSE NO OBLIGATION" LIABILITY O�,ANY KIND ) THE INSURER, ITS AGENTS OR
AUTHORIZED REPRESENkfMV(//i . "
--•�_ —� �—�� ••��, iFJCOL44UlM[OY43`J MJP W AGURO CORPORATION 1988
SECTION 00410
BID BOND
ECI Site Construction
KNOW ALL MEN BY 'THESE PRESENTS; that we, the undersignedManagement, a division
of Environmental
Cnnrnrng, Inc as Principal, and Employers Mutual CasuallX_LomRany as�
Surety, are hereby held and firmly bound unto the Cit o£ Fort Collins, Colorado,
as OWNER, in the sum of $ 5% of total bid for the payment of which, well and
truly to be made, we hereby jointly and severally bind ourselves, successors, and
assigns.
THE CONDITION of this obligation is such that whereas the Principal has
submitted to the City of Fart Collins, Colorado the accompanying Bid and hereby
made a part hereof to enter into a Construction Agreement for the construction
Of Fort Collins Project, CITY OF FORT COLLINS AND COLORADO STATE UNIVERSITY
TRANSIT CENTER PHASE lA; Bid No. 5823.
NOW THEREFORE,
(0) If said Bid shall be rejected, or
(b) If said Bid shall be accepted and the principal shall execute and deliver
a Contract in the form of Contract ar.tached hereto (properly completed in
accordance with said Bid) and shall furnish a BOND for his faithful
performance of said Contract, and for payment of all persons performing
labor or furnishing materials in connection therewith, and shall in all
other respects perform the Agreement created by the acceptance of said Bid,
then this obligation shall be void; otherwise the same shall remain in
force and effect, it being expressly understood and agreed that the
liability of the Surety for any and all claims hereunder shall, in no
event, exceed the penal amount of this obligation as herein staked.
The Surety, for value received, hereby stipulates and agrees that the obligations
of said Surety and its BOND shall be in no way impaired or affected by any
extension of the time within which the OWNER may accept such Bid; and said Surety
does hereby waive notice of any such extension.
Surety Companies executing bonds must be authorized to transact business in the
State of Colorado and be accepted by the OWNER.
7/96 Section 00420 Page 2
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands
and seals this 5th ` day of November , 2003, and such of them as are
corporations have caused their corporate seals to be hereto affixed and these
presents to be signed by their proper officers, the day and year first set forth
above.
PRINCIPAL
ECI Site Construction Management, a
Name:division of Environmental Concerns,
' nc .
Address: P.O. Box 2135
Loveland, 80539
(SEAL)
7/96
SURETY
Emaployers Mutual Casualty Company
P.O. Box 370010
Denver, CO 80237
Tittle; Attorney -in -Fact
(SEAL)
Section 00410 Page, 3
No Text
City of Fort Collins & Colorado State University
Transit Center -Phase IA
BID SCHEDULE
Each following Items shall include the costs of all labor, materials, tools, equipment,
services, incidentals, overhead, profit, and bonds.
ITEM
1. LANDSCAPE / IRRIGATION IMPROVEMENTS (INSIDE FENCE)
Provide and install landscaping / irrigate improvements inside fence
Also, include hydrant and drain sump as shown
SUBTOTAL $
2. PHONE SERVICE INCLUDING CONDUIT / BORING
Two (2) 1" conduits including boring, trenching, backfill with flowfill,
installation of emergency phone provided by others. 0O
SUBTOTAL $ (o � --
3. All required work less above Items 1 and 2. o®
SUBTOTAL $ 2O 6? 3Z
oG
TOTAL LUMP SUM $ .2 23 18 Q �
Section 00300 Page 3
SECTION 00430
SCHEDULE OF SUBCONTRACTORS
List all subcontractors for the work items listed below and all subcontractors
performing over 150 of the contract.
ITEM
CONG 7� ?,4✓W4
7/96
SUBCONTRACTOR
Section 00430 Page 1
r.
SECTION 00420
STATEMENT OF BIDDER'S QUALIFICATIONS
All questions must be answered and the data given must be clear and
comprehensive. This statement must be notarized. If necessary, questions may
be answered on separate attached sheets. The Bidder may submit any additional
information he desires.
1. Name of Bidder: E . ; on ;on Manav,n nr a d; .;�; �f F ,,{ ^^^ental Concerns
2. Permanent main office address: 2526 R. H3gy 402, Loveland, CO 80937 Inc.
3. When organized:
4. If a corporation, where incorporated: gr,re of Calorndo
5. How many years have you been engaged in the contracting business under your
present firm or trade name? 22 gears
6. Contracts on hand: (Schedule these, showing the amount of each contract and
the appropriate anticipated dates of completion.)
SEE ATTACHED
7. General character of Work performed by your company:
Park construction and management installation of pump stations sleeving,misc.
grading and subgrades erosion control site ameneties ur her fines trail pavers,
and small storm drain systems.
8. Have you ever failed to complete any Work awarded to you? No
If so, where and why?
9. Have your ever defaulted on a contract? Nn
If so, where and why?
10. Are you debarred by any government agency? NO
If yes list agency name.
7/96
Section 00420 Page 1
11. List the more important projects recently completed by your company, stating
the approximate cost of each, and the month and year completed, location
and type of construction.
SEE ATTACHED
12. List your major equipment available for this contract.
SEE ATTACHED
13. Experience in construction Work similar in importance to this
project:
90% of our projects are municipal park projects
SEE ATTACHED project references
14. Background and experience of the principal members of your organization,
including officers:
SEE ATTACHED
15. Credit available: $ NIA
16. Bank reference: Homo ergo Bank Cont—art—, Gar_thshnmas 935 N rla, land A.
Loveland, CO 80537
17. Will you, upon request, fill out a detailed financial statement and furnish
any other information that may be required by the OWNER?
YES —
18. Are you licensed as a General CONTRACTOR? YES
If yes, in what city, county and state?Loveland, Larimer, Colorado What
class, license and numbers?
19. Do you anticipate subcontracting Work under this Contract? YES
If yes, what percent of total �F�Ion ract? 70%
and to whom? Zp p (j-6 YA O( ' .1 j� I Vki
20. Are any lawsuits pending against you or your firm at this time? NO
If
DETAIL yes,
7/96 Section 00420 Page 2
21. What are the limits of your public liability?" DETAIL
See Attached insurance certificate
What company? Flood & Pet rs n • Agent Contact: Dan Mills
22. What are your company's bonding limitations?
23. The undersigned hereby authorizes and requests any person, firm or
corporation to furnish any information requested by the OWNER in
verification of the recital comprising this Statement of Bidder's
Qualifications.
Dated at I&IIAMCL this Z day of _ 1t� Q, 20-03.
e Construction
Name
By:
Tit1eN.J President
State of Colorado
)
County of Larimer
Jay Brian Paterson being duly sworn deposes and says that he is
President of F.CI Site Construction Mana ent and that
(name of organization)
the answers to the foregoing questions and all statements therein contained are
true and correct.
Subscribed and sworn to before me this day of
2003 .
n
`f�f ira a c�
My commission expires
=y
pU&LIc
7/96 Section 00420 Page 3
ECI SITE CONSTRUCTION MANAGEMENT
CURRENT WORK IN PROGRESS
PROJECT/LOCATION
DESCRIPTION
CONTRACT
GENERAL
EST.
OWNER
OF WORK
AMOUNT
CONTRACTOR
COMP.
COMPLETE
DATE
Section 30 Park & Ballfields
Park Construction w/
$9,545,532
ECI
11/03
City and County of Broomfield
93%
Broomfield
Sythetic Turf Field
CM/GC
303-464-5801
Douglas County Fairgrounds Regional Park
Park Construction
$1,441,523
ECI
4/04
Douglas County Government
25%
Douglas County
303-663-6226
Kittredge Tennis Court Replacement
Tennis Court Complex
$1,041,706
ECI
10/03
University of Colorado at Boulder
98%
Boulder, CO
Construction
303-735-3136
ECI SITE CONSTRUCTION MANAGEMENT
MAJOR PROJECTS COMPLETED
MUNICIPAL
PROJECT NAME
OWNER ARCHITECT
CONTRACT
COMPLETION
APS Stadium
Aurora Public Schools Davis Partnership
$
807,100.16
8/03
Aurora, CO
303-367-3DD0 303-861-8555
Greenland Open Space
Douglas County Government Architerra
$
651,930.24
6/03
Douglas County
303-660-7495 303-948-0766
Valmont Sod
City of Boulder N/A
$
153,165.18
6/03
Boulder, CO
303-413-7225
Louisville In -Line Rink
City of Louisville Design Concepts
$
351,607.82
5/03
Louisville, CO
303-335-4909 303-664-5301
East West Greenway
Mortenson -G.C. EDAW
$
1,244,402.00
8/03
Stapleton Redevelopment
303-321-4122 303-595-4522