HomeMy WebLinkAboutCORRESPONDENCE - GENERAL CORRESPONDENCE - 2207850CHANGE ORDER NO.1 PROJECT TITLE: COFC WTF- Backwash Recycle Project - U.V. Equipment Procurement i CONTRACTOR: Hydro Construction CO, Inc P.O. NUMBER: 2207850 VENDOR NUMBER: 109420 CHARGE NUMBER: 5026433.529290.6 DESCRIPTION In preparing change orders show inorder as separate numbered paragraphs the following: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time 1. Final quantity adjustments for Contract 2. Change in line item quantities/cost 3. ($17,545.51) 4. None (Attach additional sheets as required) ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF ORIGINAL CONTRACT, THIS CO: TOTAL % OF ORIGINAL CONTRACT, ALL CO'S: ADJUSTED CONTRACT COST (Assuming all change orders approved) ACCEPTED (Contractor's Representative) REVIEWED BY: APPROVED BY: (Water R/Asources and Treatment Manager) APPROVED BY: A „- (Utilities General Manager) APPROVED BY: (Purchasing Agent Over $30,000) UU: Uity Clerk Purchasing Contractor Project File Stormwater Finance Manager -10.10% $173,882.00 $0.00 $0.00 ($17,545.51) $156,336.49 DATE: tI f2o ` DATE: I /117,A9 DATE: /' / �3-6;2 DATE: 1 (1- 1 7-0 3 DATE: NOTE: Signature of Contractor indicates agreement herewithin, including any adjustment in contract sum or contract time. CHANGFRM.XLS