Loading...
HomeMy WebLinkAboutCORRESPONDENCE - GENERAL CORRESPONDENCE - 3307007 (2)CHANGE ORD NO. #30 PROJECT TITLE: FOSSIL CREEK COMMUNITY PARK PHASE 1 B CONTRACTOR: Clark Construction Company, Inc, PROJECT NUMBER: 5681 PURCHASE ORDER NO.: 2202M DESCRIPTION: A Change times for substantial c mpletion & fnal acceptance 1. Reason for change: A Change times for substantial c mpls&an & final acceptance 2. Description of Change: A Chage Was for substantial C=Odon & final acceptance 3. Change in Contract Cost $0.00 4. Change In Contract Time: 41 days TOTAL APPROVED CHANGE ORDER TOTAL PENDING CHANGE ORDER TOTAL THIS CHANGE ORDER TOTAL % OF ORIGINAL CONTRACT, THIS C.O. TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S ADJUSTED CONTRACT COST 9.94% 6,698A69.81 (Assuming all change orders approved) / ACCEPTED BY: ' DATE: Contractor's Representative ACCEPTED BY: DATE: /0.3/• 3 Project Manager REVIEWED BY. DATE: Title: APPROVED BY: DATE: Title: APPROVED BY: DATE: Purchasing Agent over $30,000 o City Clink Ard*ect CaNacW Ergk e Project File Purchaalnp CHANGE OR R NO. #31 TV PARK 1B PROJECT TITLE: FOSSIL CREEK COMMUNI CONTRACTOR Clark Construction Company, Inc. PROJECT NUMBER 6681 PURCHASE ORDER NO.: 2202M DESCRIPTION: AChargetimefor final acc�ance 1. Reason for change: A nge Chatime for tirral aca 2. Description of Change: A. Change Owfor finalacceptance 3. Change in Contract Cost $0.00 4. Change in Contract Tkne: 61 TOTAL APPROVED CHANGE ORDER j578,970 TOTAL PENDING CHANGE ORDER $26,559 TOTAL THIS CHANGE ORDER $0 TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 0.00% TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 9.94% ADJUSTED CONTRACT COST (Assuming all change orders approved) ACCEPTED BY: Contractor's Representative ACCEPTED BY: Project Manager REVIEWED BY: Title: APPROVED BY: Tide: APPROVED BY: Purchasing Agent over $30,000 oCay Clerk Argdeq Contractor Engineer Pr*d Fie pwdw*m DATE: /% DATE:./% *1'•!7'3 DATE: L�4 DATE: