HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 3301445CHANGE ORDER NO. 1
PROJECT TITLE: Halligan Reservoir Enlargement PROJ. NUM.: 50265100
CONTRACTOR: Ayres Associates P.O. NUMBER: 3301445
DESCRIPTION:
1. The Phase IIA scope provided for the two months of field work to trap for the
Preble's Meadow Jumping Mouse (PMJM), after starting the work it was
recognized that it would take an additional month to complete the trapping. The
Utility also recognized it would be better to have final reports prepared for both
PMJM and the wetlands delineation. These were to have been prepared under the
Phase IIB scope.
2. Increase the field work to trap the PMJM by one month.
3. Increase the contract amount $28,807.
4. No increase in contract time.
ORIGINAL CONTRACT COST
$279,411.00
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
$28,807.00
ADJUSTED CONTRACT COST
$308,218.00
% OF ORIGINAL CONTRACT, THIS CO
10.3%
% OF ORIGINAL CONTRACT, ALL CO'S
10.3%
ACCEPTED BY:
DATE: iO ?7 U•3
REVIEWED BY:
APPROVED BY:
APPROVED BY: (/%�6 �;"
Utilities General Manager
M WWtZe]ky/:1P7:3`�
Director Purchasing/Risk Management
Over $30,000
cc: Purchasing, Finance, Engineer, Contractor, File
DATE: /Q•ZU•o3
DATE: /t�• ,z U
DATE: /O-L7-03
DATE:
CHANGE ORDER NO. 1
PROJECT TITLE: Halligan Reservoir Enlargement PROJ. NUM.: 50265100
CONTRACTOR: Ayres Associates P.O. NUMBER: 3301445
DESCRIPTION:
1. The Phase IIA scope provided for the two months of field work to trap for the
Preble's Meadow Jumping Mouse (PMJM), after starting the work it was
recognized that it would take an additional month to complete the trapping. The
Utility also recognized it would be better to have final reports prepared for both
PMJM and the wetlands delineation. These were to have been prepared under the
Phase I113 scope.
2. Increase the field work to trap the PMJM by one month.
3. Increase the contract amount $28,807.
4. No increase in contract time.
ORIGINAL CONTRACT COST $279,411.00
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER $28,807.00
ADJUSTED CONTRACT COST $308,218.00
% OF ORIGINAL CONTRACT, THIS CO 10.3%
% OF ORIGINAL CONTRACT, ALL CO'S „ n 10.3%a
ACCEPTED BY: _ �1�, n , �� DATE: (o I aqI U 3
REVIEWED BY:
APPROVED BY:
APPROVED BY:
APPROVED BY:
Director Purchasing/Risk Management
Over $30,000
cc: Purchasing, Finance, Engineer, Contractor, File
DATE: /0•2q•o3
DATE: /�• ;Z [)
DATE: /a-L7-0 3
DATE: