SECTION 00950
CHANGE ORDER NO. FIVE (5)
GARDENS ON SPRING CREEK; BID NO. 5748
7F082.20
Golden Triangle Construction, Inc.
700 Weaver Park Road
Longmont, CO 80501
DESCRIPTION:
1. Reason for change:
2. Description of Change
3.
Change
in Contract
Cost:
4.
Change
in Contract
Time:
ORIGINAL CONTRACT COST:
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL o OF THIS CHANGE ORDER
TOTAL C.O. a OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders annrn
ACCEPTED BY:
See attached Gardens on Spring Creek
Change Order No. 5 Summary dated
June 13, 2003.
0 days
$1,540,968.00
$ 147,924.00
$ 0.00
$ 8,648.00
0.56°s
10.160
$1,697,540.00
DATE: 6/13/03
aff Dingwal / Vice President yy ACCEPTED BY: DATE:
Steve Seefeld/Project Manager
REVIEWED BY:
Title:
APPROVED BY:
Title:
DATE:
DATE:
APPROVED BY:
DATE:
Purchasing Agent over $30,000
CC: City Clerk
Project File
Engineer
dak/548/Fonns/OwnChgOrd5
Contractor
Architect
a s 'in-9
—�
Section 00950 Page 1
RFI
PCR# ASI Description
1 • Demo trees
2• Stabilization utilities
3 • Tank removal ?
a
Gardens on Spring Creek
Change Order No. 5 Summary
Cost
Add: $ 1,332
Add: $ 5,808
Add: $ 1,508
Total Add: $ 8,648
June 13, 2003
Hold
PWC App'd
DNP for CO
Remarks
dak /Job 548 - ChgSum05 PCR# = Proposed Change Request PWC = Proceed With change DNP = Do Not Proceed CO = Change Order