HomeMy WebLinkAboutCHANGE ORDER - BID - 5681 FOSSIL CREEK COMMUNITY PARKPROJECT NUMBER:
PURCHASE ORDER NO.:
DESCRIPTION:
1. Reason for change
2. Description of Change:
CHANGE ORDER NO. #11
FOSSIL CREEK COMMUNITY PARK PHASE 1 B
Clark Construction Company, Inc.
5681
2202988
Add Boulder Retaining Wall at Playground (Clark #26)
Add other general contractor (Artscapes LLC) to project as new subcontractor for
playground rock retaining walls in project.
Add Boulder Retaining Wall at Playground = $54811
3. Change in Contract Cost: $54,811.00
4. Change in Contract Time:
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
ADJUSTED CONTRACT COST
ACCEPTED BY:
Contractor's Representative
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
$54,811.00
0.90%
3.70%
$6,318,461.56
(Assuming all change orders approved)
APPROVED BY:
Title:
APPROVED BY:
Purchasing Agent over $30,0
ccCity Clerk Architect
Contractor Engineer
Project File Purchasing
DATE: Z O?i
DATE: IZ • O 77 .02
DATE: /Z - -,+ 4 _ y ut�,�-
DATE:
DATE: I It t t 4 U .� .
CHANGE ORDER NO. #10
PROJECT TITLE: FOSSIL CREEK COMMUNITY PARK PHASE I
CONTRACTOR: Clark Construction Company, Inc.
PROJECT NUMBER: 5681
PURCHASE ORDER NO.: 2202988
DESCRIPTION: A. Change Catch Basin at Skate Park (Clark #14)
B. Change Concrete at Skate Park (Clark #10)
C. Change Tennis Court Top Layer (Clark #20)
1. Reason for change: A. Change catch basin at skate park - installed in incorrect location in earlier phase
B. Change concrete details at skate park - at request of skate park designer
C. Change tennis court top layer - per clarification with subcontractor
2. Description of Change: A. Change catch basin = no change in price
B. Change concrete details = $2,685
C. Change tennis court top layer = no change in price
3. Change in Contract Cost: $2,685.00
4. Change in Contract Time:
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
ADJUSTED CONTRACT COST
$168,025.00
$0.00
$2,685.00
0.04%
2.80%
$6,263,650.56
(Assuming all change orders approved)
ACCEPTED BY:DATE: y O Z
Contractor's Representative
ACCEPTED BY:
Project Manager
REVIEWED BY: T=
Title:
APPROVED BY
Title:
APPROVED BY:
Purchasing Agent over $30,000
ccCity Clerk Architect
Contractor Engineer
Project File Purchasing
DATE: /Z • 0, j • O Z-
DATE:1Z—
DATE:
DATE: