WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
NORTH FRONT RANGE TRANSPORTATION & AIR QUALITY PLANNING COUNCIL
AND
FELSBURG, HOLT & ULLEVIG
DATED: 1 /31 /00
Work Order Number: No. 3
Purchase Order Numbers: FY03 portion: 3- U�6(-3 FY04 portion:
Project Title: 2030 RTP Assistance
Commencement Date: 7/1/03
Completion Date: 9/30/04
Maximum Fee: (time and reimbursable direct costs):
FY03 portion (7/1/03 thru 9/30/03)
FY04 portion (10/1/03 thru 9/30/04)
Note: the FY04 portions of the scope of work are
contingent on funding being approved and therefore no
FY04 work is to be started until a separate FY04 Notice
to Proceed has been issued.)
Project Description: See Attached
Scope of Services: See Attached
Acceptance:
User
Professional agrees to perform the services
identified above and on the attached forms in
accordance with the terms and conditions
contained herein and in the Professional Services
Agreement between the parties. In the event of a
conflict between or ambiguity in the terms of the
Professional Services Agreement and this work
order (including the attached forms) the
Professional Services Agreement shall control.
Professio I:
By: %
Date: O
The attached forms consisting of _ (—) pages
are hereby accepted and incorporated herein, by
this reference, and Notice to Proceed is hereby
given only on the FY03 pieces indicated herein.
$14,975
$53,935"'
North Front Range Transportation & Air Quality
Planning Council:
By:
Date:
Purchasi — City of Ft. Collins:r
By: V /%
Date: _ 7/1
North Front Range MPO
Scope of Work — RTPAssistance
SCOPE OF WORK — RTP ASSISTANCE
The North Front Range MPO has determined that its staff will be responsible for
preparing the 2030 Regional Transportation Plan (RTP) Update. However, the MPO has
also determined that it will need some technical assistance in several of the work
elements. Felsburg Holt & Ullevig (FHU) has prepared the following scope of services to
identify those elements in which FHU staff will provide assistance to the MPO staff.
1. GENERAL COACHING/MENTORING
Scope:
Because of his experience in having worked on a number of Regional Transportation
Plans over the years, Bob Felsburg will serve as a coach or mentor to MPO staff on any
plan -related subject matter, as requested by the staff. Although the specific scope of this
task cannot be determined at this time, it is expected that Mr. Felsburg could be called
upon to provide advice in a wide range of topics, including:
• Overall structure of the planning process.
• Organization of the public involvement program.
• Interpretation of forthcoming guidelines or directions from CDOT throughout the
planning process.
• Strategy for proper presentation of plan information to the MPO Council or the
Technical Advisory Committee (TAC).
• Review of technical information compiled or prepared by MPO staff, such as
inventory data or travel demand modeling results.
• Project submittal format.
• Regional Transportation Plan outline.
This support could involve attendance of "brainstorming" sessions, telephone calls, or
possibly research and preparation of technical memoranda.
FELSBURG
HOLT &
ULLEVIG
Page 2
North Front Range MPO
Scope o{Worh — RTP Assistance
Level of Effort:
The following estimate assumes 10 hours of Mr. Felsburg's time each month during the
duration of the planning process (July — March).
Principal II 90 Hours @ $150 = $13,500
Support 12 Hours @ $ 60 = $ 720
ODC (5%) = 710
Total Budget $14,930
Fiscal Year 2003: _ $ 4,975
Fiscal Year 2004: = 9,955
Total $14,930
2. CORRIDOR VISIONING
Scope:
A key focus of CDOT's interest in the RTP will be the definition of a "vision" for each
corridor in the study area. Guidance for this effort is still being developed by CDOT, but it
is clear that these corridors are intended to be multi -modal in character. The following
scope is anticipated:
• Ensure that the "regionally significant corridors" being identified by the MPO are
being established in a manner compatible with that expected by CDOT.
• Assist the MPO staff in developing a process to define the Vision of the corridor,
Performance Objectives of how the corridor should work, Strategies to assist in
achieving corridor objectives, and, finally, Projects in the corridor consistent with the
strategies and objectives.
• Work with the MPO staff and Council to complete this visioning process for each
corridor.
Level of Effort:
Principal II
40 Hours @ $150
= $
6,000
Senior Advisor
12 Hours @ $130
= $
1,560
Engineer II
80 Hours @ $ 80
= $
6,400
Graphics
20 Hours @ $ 65
= $
1,300
Support
20 Hours @ $ 60
= $
1,200
ODC (5%)
=
820
Total Budget
$17 280
Fiscal Year 2003: _ $ 5,000
Fiscal Year 2004: = 12 280
Total $17,280
FELSBURG
HOLT &
ULLEV]G
Page 3
North Front Range MPO
Scope of Worh — RTP Assistance
3. REVISIONS TO PROJECT PRIORITIZATION PROCESS
Scope:
Although the CDOT focus in the Statewide Plan will be on the corridor visions, the RTP
will still need to identify and prioritize projects within the corridors. The existing Project
Prioritization Process will be reviewed and modified as appropriate to account for a
number of changing factors:
• Changes in Project Categories as suggested by the MPO.
• Potential changes in Project Categories to reflect Transportation Commission
Investment Categories:
- System Quality
- Safety
- Mobility
• Possible changes in the Evaluation Criteria and the Scoring Guidelines to account for
current philosophies of the Council.
Another objective of this task will be to recommend a process whereby it will not be
necessary to carry all projects through the extensive project prioritization process. A
screening methodology will be developed in concert with MPO staff and the TAC.
A final element of this task would be to develop a methodology for prioritizing projects
across Project Categories, a specific request of CDOT for this RTP. This has not been
done in the past, although we have previously identified a number of alternative
approaches to achieve this goal. Those alternatives will be revisited, additional
approaches may be developed, all alternatives will be discussed with the TAC, and a
recommendation will be made.
The end product of this task would be a revised Project Prioritization Process guidebook.
Level of Effort:
Principal II
20 Hours @ $150
= $
3,000
Senior Advisor
12 Hours @ $130
= $
1,560
Engineer II
24 Hours @ $ 80
= $
1,920
Support
12 Hours @ $ 60
= $
720
ODC (5%u)
=
360
Total Budget
$
7,560
Fiscal Year 2003:
= $
5,000
Fiscal Year 2004:
= 2,560
Total
$
7,560
FELSBURG
HOLT &
ULLEVIG
Page 4
North Front Range MPO
Scope of Wor% — RTP Assistance
4. RESOURCE ALLOCATION
Scope:
CDOT is presently in the process of establishing estimates of the revenues which may be
available to each MPO/TPR in the future. CDOT is also developing investment strategies
which will provide guidance to the MPOs/TPRs in how those funds can be allocated to
projects within the Regional Transportation Plans. FHU will assist the MPO in
coordinating with CDOT regarding this information and this process. We will then work
with the Council to understand the implications of the CDOT estimates and guidelines
and to refine the methodology through which the information will be applied to determine
resource allocation in the RTP. With this methodology established, FHU will then assist
the Council in applying it in order to develop the Financially Constrained Plan for the
North Front Range.
Level of Effort:
Principal II 20 Hours @ $150
Engineer II 20 Hours @ $ 80
Support 10 Hours @ $ 60
CDC (5%)
Total Budget
5. CONGESTION MANAGEMENT PLAN
Scope:
_ $
3,000
_ $
1,600
_ $
600
=
260
$
5,460 (Fiscal Year 2004)
FHU will assist the MPO staff in the development of a Congestion Management Plan as
part of the RTP. This effort will begin with a literature search and a review of other
Congestion Management Plans in Colorado in order to summarize the "best practices"
currently being used in such plans. After a review of these findings with the MPO staff
and the TAC, a proposed outline of the Congestion Management Plan will be drafted.
Upon concurrence with the outline, FHU will work with MPO staff to compile the
information necessary to "flesh out' and complete the plan. This will then be presented to
the Council for acceptance.
Level of Effort:
Principal II
Senior Advisor
Engineer II
Support
ODC (5%)
Total Budget
FELSBURG
HOLT &
ULLEVIG
20 Hours @ $150
10 Hours @ $130
40 Hours @ $ 80
12 Hours @ $ 60
_ $
3,000
_ $
1,300
_ $
3,200
_ $
720
=1
410
$
8,630 (Fiscal Year 2004)
Page 5
North Front Range MPO
Scope of wor% - RTP Assistance
6. REVIEW DRAFT PLAN/REPORT
Scope:
FHU will review and comment on the Draft Regional Transportation Plan/Report as
prepared by the MPO staff.
Level of Effort:
Principal II
Engineer II
Support
ODC (5%)
Total Budget
7. ATTEND MEETINGS
Scope:
12Hours @$150
12 Hours @ $ 80
4 Hours @ $ 60
_ $
1,800
_ $
960
_ $
240
= 150
$
3,150 (Fiscal Year 2004)
FHU will attend TAC and Council meetings, as requested by MPO staff, to assist with
presentations and discussions of specific elements of the Regional Transportation Plan
process. Preparation for and attendance at up to 6 TAC meetings and 4 Council
meetings has been budgeted.
Level of Effort
Principal II
Engineer II
Support
ODC (Travel)
Total Budget
SUMMARY
60 Hours @ $150
24 Hours @ $ 80
8 Hours @ $ 60
_ $ 9,000
_$ 1,920
_ $ 480
= 500
$11,900 (Fiscal Year 2004)
The following is a summary of the budget estimate for all of the above noted tasks:
1.
General Coaching/Mentoring
= $14,930
2.
Corridor Visioning
= $17,280
3.
Revisions to Project Prioritization Process
= $ 7,560
4.
Resource Allocation
= $ 5,460
5.
Congestion Management Plan
= $ 8,630
6.
Review Draft Plan/Report
= $ 3,150
7.
Attend Meetings
= $11,900
Total
Estimated Budget
$68,910
Fiscal Year 2003:
= $14,975
Fiscal Year 2004:
= $53,935
Total
$68,910
EELSBURG
HOLT &
ULLEVIG
Page 6