HomeMy WebLinkAboutCHANGE ORDER - BID - 5767 LEMAY AVENUE WIDENING PROJECTChange Order Form
g
City of Fort Collins
PROJECT TITLE: Lemay Ave. Widening Project
PROJECT NUMBER: 30523250.6 (Bid #5767)
CONTRACTOR: Gerrard Excavation (PO #3301894)
CHANGE ORDER NUMBER: 3
n preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1 &2. See attached sheet for detail.
3. The contract cost will increase by $ 33,611.45
4. The contract time will be increased by 3 days.
ORIGINAL CONTRACT COST $2,566,613.79
TOTAL APPROVED CHANGE ORDERS $48,019.83
TOTAL PENDING CHANGE ORDERS $0.00
TOTAL THIS CHANGE ORDER $33,611.45
TOTAL % OF THIS CHANGE ORDER 1.31 %
TOTAL C.O. % OF ORIGINAL CONTRACT 3.18%
ADJUSTED CONTRACT COST $2,648,245.07
(Assuming all change orders approved)
F
ACCEPTED BY: l e C \ DATE:Z�l emu _ ZOU
( Contractor's Representative)
REVIEWED BY:
ACCEPTED BY/
(Project Mang r-Engineering)
ACCEPTED BY: /
(Project Manager - St (Project Manager ormwr)orrmwr)
ACCEPTED BY: cul)5��r
(Dap ant Head - En ig nearing
APPROVED BY: Y `
(Pu hasi Agent over $30,000)
cc: Contractor
Purchasing
Project File
DATE: 6! 2� 03�
DATE: CG 03
DATE:
DATE:
—BATE: V
nngtneenng uepartment • 1.61 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522.0580 • (303) 221-6605
06/17/2003 16:39 9706350426 BELMIRE PAGE 02
FIELD WORK ORDER
Belmire Sprinkler & Landscaping P.O. Box 7932 Loveland, CO 80537
PROJECT Lv
OWNER/ GC �� ('rrc1 n1
DATE 14 4 G— n Z
The Owner's Representative authorizes and directs Belmire Sprinkler & Landscaping to accomplish
the following additional work on the above named project. The Owner agrees that the costs
submitted for this additional work will be paid as a Change Order to the Contract
DESCRIPTION of WORK
Z� h CO"
Approved
MATERIALS $
0rS LABOR Man Hours Q $45/ Hour ��$ Jc(c,Q
EQUIPMENT Hours @ $65/ Hour 6 L $ / ZA, _
Date�0
Superintendent Date
Belmire Sprinkler & Landscaping
06/17/2003 16:39 9706350426 BELMIRE PAGE 03
FIELD WORK ORDER
Belmire Sprinkler & Landscaping P.O. Box 7932 Loveland, CO 80537
PROJECT Lc mn ul > K; i K] cl
OWNER/ GC ���bit� l rtrc in
DATE OA - (I - Q j
The Owner's Representative authorizes and directs Belmire Sprinkler & Landscaping to accomplish
the following additional work on the above named project. The Owner agrees that the costs
submitted for this additional work will be paid as a Change Order to the Contract
DESCRIPTION of WORK
MATERIALS
i -I: •
Man Hours @ $451 Hour
Hggrs (5 $651 Hour
Approved=G�y
Superintendent Snn �Or i t (C C i r
Belmire Sprinkler & Landscaping
S >; / _
$ 1An -
Date
Date
06/17/2003 16:39 9706350426 BELMIRE PAGE 04
FIELD WORK ORDER
Belmire Sprinkler & Landscaping P.O. Box 7932 Loveland, CO 80537
PROJECT I..at, Y V l\ ae�.� ► i c�
OWNER/ GC <�n�A n 1� n
DATE 06-1f—B
The Owner's Representative authorizes and directs Belmire Sprinkler & Landscaping to accomplish
the following additional work on the above named project. The Owner agrees that the costs
submitted for this additional work will be Daid as a Change Order to the Contract.
DESCRIPTION of WORK
MATERIALS $
LABOR Man Hours @ $45/ Hour ►- S $
EQUIPMENT Hours (a $65/ 14nur C.
Approved
Superintendent &ZC
Belmire Sprinkler & Landscaping
W
Date
Date —a —0-
BE/17/2003 16:39 9706350426 BELMIRE PAGE 05
FIELD WORK ORDER 7
Belmire Sprinkler & Landscaping P.O. Box 7932 Loveland, CO 80537
PROJECT L eiv ey W -i AC m i ma
DATE C36 — V� 03
The Owner's Representative authorizes and directs Belmire Sprinkler & Landscaping to accomplish
the following additional work on the above named project. The Owner agrees that the costs
submitted for this additional work will be paid as a Change Order to the Contract
DESCRIPTION of WORK
Y , •, ems,
Approved
MATERIALS $ 9'm _ Q0
Man Hours @ $45/ Hour yq 5 $
Hours (2 $65/ Hour $
v
Date
Superintendent -- n�. � • Date I , L L A�
Belmire Sprinkler & Landscaping
06/17/2003 16:39 9106350426 BELMIRE PAGE 06
FIELD WORK ORDER
Belmire Sprinkler & Landscaping P.O. Box 7932 Loveland, CO 80537
PROJECT �'.ChW/ [L)i �C�l►Jq
OWNER/GC & n a C�;�,
DATE 6 ` 11- n
The Owner's Representative authorizes and directs Belmire Sprinkler & Landscaping to accomplish
the following additional worm on the above named project. The Owner agrees that the costs
submitted for this additional work will be paid as a Change Order to the Contract.
DESCRIPTION of WORK
MATERIALS $ 9 -A_
3 a nc- LABOR Man Hours @ $45/ Hour $ /,3 65 QQ
EQUIPMENT Hours $65/ Hour $ 95 _
Approved Date ��
Superintendent Date G Z 6� (y3
Belmire Sprinkler & Landscaping
Mks , ikr44n ' d5i �<k 2 etGt r', r i<'<
t „,.
Gerrard Excavating
Landscaping Items
LEMAY AVENUE WIDENING PROJECT
- See attached submittal -
rgriF e> .i[r<t :�
Item
Unit $ / Unit
Total
Gerrard Remove and Haul Existing Sod
3888 SF
$ 0.80
$ 3,110.40
Belmire Install BlsSod
12960 SF
$ 0.37
$ 4,795.20
mire
ta wit u c ing Netting
11400 SF
$ 0.98
$ 11,172.00e
W 41 79 077 60
The original scope of work included seeding the parkways along the
existing subdivisions and the newly constructed landscaped medians.
We changed the scope to include placing sod in the parkways along the
existing subdivisions since this area will be maintained by the adjacent
property owners. The parks department decided it would be too
costly to mow the medians, therefore we are placing mulch and a weed
barrier in the medians until we hire a landscaper to place the plantings.
Posted to Pay Estimate # 3
MAY.21.2003 12:04PM GERRARD EXCAVATING
Gem
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
DATE: May 21, 2003
TO: City of Ft. Collins, Street Oversizing
Attu: Eileen Bayens
FROM: Bill Nicholl
RE: Lemay Avenue Widening
Pricing request for landscaping items;
1. Remove and haul existing sod
Approximately 3,888 SF @ 0.80/SF
2. Install bluegrass sod
Approximately 12,960 SF @ 0.37/SF
NO.385 P.2/2
S 3,110.40
S 4,795.20
3. Install 4" mulch (choice Cedar Mulch from Hageman's) with mulch netting
Approximately 11,400 SF @ 0.98/SF S 115172.00
Sod installation will take approximately 4 days; mulch installation will take approximately 3
days.
Please contact me if you have any questions.
master
�.t¢�`,,, ( Kohl ,�� �, �? E><r;�'� �4{ e� ✓''i4. i c ,# t`�ti�<� �4', a��;'�r i ..���� '� �,}'` �.:
Gerrard Excavating
Additional Surveying
LEMAY AVENUE WIDENING PROJECT
- See attached subrrittal -
Item
Unit / Unit
Total
Northern En ineerin Surve Fossil Creekfor Li ht and Power
1 Hr
$ 110.00
$ 110.00
ortern ngmeenng urvey an to or a ectnc vau t
1. 1..
2 Hrs
1 $ 110.001
$ 220.00
a asu.uo
Additional surveyng for our Light and Power Departnent outside of the
original scope of work
Posted to Pay Estirrete # 3
7 ,
LEMAY"ENUE WIDENING PROJECT
Gerrard Excavating
Reform Pedestrian Bridge
- See attached submittal -
Item
Unit / Unit
Total
Concrete Structures Reform Underpass
52 Hrs
$ 37.00
$ 1,924.00
Concrete Structures Su ervisor
2 Hrs
$ 37.00
$ 74.00
on tructures orms,Steel, Concrete
1 LS
$ 133.00
$ 133.00
"' ^� i 2,131.00
arcsrd F-Xcavaffng Additional Contractays 3 DAY 1 104 DER DAYS
There was an error found in the elevations after the paraphet w ails
were formed.
�. Tory._.®
Posted to Pay Estimate # 3
OEM"
f( i✓ > F t. >
LEMAY AVENUE WIDENING PROJECT
L
Gerrard Excawting
Additional Work at Stone Creek Channel
- See attached submittal -
Item
Unit $ / Unit
I Total
Gerrard Exca%e 30" ADS FES
1 EA
$ 450.00
$ 450. 00
errar xcawting rout Rip Rap
240 SF
$ 7.50
$ 1,800.00
'" 5 225000
`•K. e w a N �q;�w
The existing 30" ADS pipe did not have a flared end section, and the
slope on the vvest side is steep so vve grouted the rip rap.
Posted to Pay Estimate # 3
LEMAY AVENUE WIDENING PROJECT
Gerrard Excavating
Install irrigation cover
- See attached submittal -
Item
Unit $1 Unit
1 Total
juerrard Lxcavating Install irrigation cover
1 EA
$ 260.00
$ 260.00
IVIAL $ 26000
There is an irrigation box that could not be relocated so we
had a special cover made.
Posted to Pay Estimate # 3
,.. � ;t f� ��5� r a€ n:;>? PA
i�2��a�c� � t� t f�,��,���G�, �� E, ry "4a.��T''cy .��3 ✓.
Gerrard Excavating
Repair Sprinkler Lines
LEMAY AVENUE WIDENING PROJECT
- See attached submittal -
Item
Unit
1 $!Unit
I Total
Belmire Repair Irrigation Lines
1 LS
1 $ 8,693.50
1 $ 8,693.50
juerrard Excawing o Overhead and SupeNsion
1 LS
1 $ 869.35
$ 869.35
The existing sprinkler systems on both the Paragon Point Subdi%ion
and the Huntington Hills SubdiNsion needed to be repaired due to the
incorrect as-builts that were supplied for locations
Posted to Pay Estimate # 3
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
DATE: June 19, 2003
TO: City of Ft. Collins, Street Oversizing
Attn: Eileen Bayens
FROM: Bill Nicholl
RE: Lemay Avenue Widening
Request for change order for additional work:
1. Survey at Lemay and Fossil Creek for electric department
1 hr @ 110.00/hr $ 110.00
2. Survey and stake TBC for electric vault placement:
2 hrs @ 110.00/hr $ 220.00
3.
Lemay Avenue — reform pedestrian bridge due to elevation discrepancy:
Concrete Structures
52 hours @ 37.00/hr
$ 1,924.00
'
Supervisor
2 hrs @ 37.00/hr
$ 74.00
Forms, steel, concrete
$ 133.00
Total $ 29131.00
4.
Add 30" ADS FES at Stone Creek:
FES
$ 450.00
5.
Grout rip rap at Stone Creek
240 SF @ 7.50/SF
$ 1,800.00
6.
Install ring and cover marked "irrigation"
in sidewalk at Lemay and Pheasant Run
1 each @ 260.00/each
$ 260.00
7.
Additional work completed by Belmire Sprinkler & Landscape per the attached
breakdown:
Lump Sum
$ 8,693.50
10% overhead and supervision
S 869.35
Total $ 9,562.85
TOTAL CHANGE ORDER REQUEST
$14 533.85
ChgReg61303