HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 16679Change Order Form
PROJECT TITLE: Lemay Ave. Widening Project
PROJECT NUMBER: 30523250.6 (Bid #5767)
CONTRACTOR: Gerrard Excavation (PO #3301894)
CHANGE ORDER NUMBER: 2
n preparing change orders s ow in order as separate numbered paragrap s the tollowing:
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1 &2. See attached sheet for detail.
3. The contract cost will increase by $ 46,196.23
4. There will be no change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
$2,566,613,79
$1,823.60
$0.00
$46,196.23
1.80%
1.67%
$2,614,633.62
ACCEPTED BY: _ `^�� • DATE: tl tc. t�-1 st ZpO�
( Contractor's Representative) �—
REVIEWED BY:
ACCEPTED
(Project M�a{eger- Engineering)
ACCEPTED BY: _ < T/
(Project Manager - Sto mwater)
nA
ACCEPTED BY:
(DepartmendHead - Engineering)
APPROVED BY:
Agent over $30,000)
cc: Contractor
Purchasing
Project File
DATE:
DATE: 4/24k T>
DATE:
DATE: 5 Z b o
DATE:-4� 03
�,,s„,eca,i1g ueyaiuuen[ • lai ivortn Cotlege Avenue • P.O. Box 380 • Fort Collins, CO 80522.0580 • (303) 221-6605
LEMAY AVENUE WIDENING PROJECT
Gerrard Excavating
Flowfill for culverts
- See attached submittal -
Item
Unit $ / Un—li-7
Total
lGerrard Excavating Flowfill for Culverts
600 CY
1 $ 47.55
$ 28,530.00
I v I r,L- 5 28,53U.00
The extra flowfill is used to backfill the pedestrian underpass
and the Stone Creek Channel box culverts.
Posted to Pay Estimate # 2
MAY.22.2003 6:38AM GERRARD EXCAVATING N0.405 P.5/6
Gm
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
DATE: May 14, 2003
TO: City of Ft. Collins, Street Oversizing
Attn: Eileen Bayens
FROM: Bill Nicholl
RE: Lemay Avenue Widening
Request for Change Order:
Flowfill for culverts:
600 CY @ 47,55/CY S 28,530.00
TOTAL CHANGE ORDER S 28,530.00
ChgO rd FlowfillCu Iverts
Gerrard Excavating
Conduit Crossings
LEMAY AVENUE WIDENING PROJECT
- See attached submittal -
Item
Unit
$ / Unit
ITotal
Gerrard Excavating
Excavate Trench and Haul of Spoils
600 LF
$
4.50
$
2,700.00
Gerrard Excavating4"
Schedule 40 PVC
2000 LF
2.10
$
4,200.00
Gerrard Excavatln
2 Laborers for 5.5 Hours
11 Hrs
f$35.00
$
385.00
oncrete onng
ut rent in ox or ectnc an as ines
1 LS
5.86
$
685.86
g v i � $ 7,970 66
The Stone Creek Channel had utilities that could not be relocated therefre
we had to trench across the newbox culvert. There were extra utilities
that needed to cross the roadway and pedestrian underpass in conduit.
Posted to Pay Estimate # 2
MAY.22.?oo3 a:3eAM GERRARD EXCAVATING N0.405 P.4/6
Ge"41jet
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
DATE: May 14, 2003
TCI: City of Ft. Collins, Street Oversizing
Attn: Eileen Bayens
FROM: Bill Nicholl
RE: Lemay Avenue Widening
)� Request for Change Order:
Excavate 600 LF of trenches for City of Ft Collins Electric:
600 LF @ 4.50/LF S 2,700.00
4" Schedule 40
2,000 LF @ 2.10/LF S 4,200.00
TOTAL REQUEST FOR CHANCE ORDER
ChgOrderRequest51303Trenches
$ 6,900.00
LEMAY AVENUE WIDENING PROJECT
Gerrard Excavating
Remove Trees at South Ridge Greens Golf Course
- See attached submittal -
Item
Unit
$ / Unit
Total
Gerrard Excavating Loader
2 Hrs
$
75.00
$
150.00
Gerrard Excavating 322 Excavator
5 Hrs
$
125.00
$
625.00
Gerrard Excavating Rock Trailer
4.5 Hrs
$
75.00
$
337.50
Gerrard ExcavaDump Fees
1 LS
$
115.00
$
115.00
errar xcavatmting 15 o Overhead and Profit
1 LS
$
184.12
$
184.12
5 1,411.62
Prior to bidding, the South Ridge Greens Golf Course staff had
planned on relocating the existing trees along Lemay Avenue to a different
location on the Golf Course. The City of Fort Collins Forestry Department
inspected the trees and determined that they were not salvagable.
Posted to Pay Estimate # 2
APR.23.2003 1:36PM GERRARD EXCAVATING
G�
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
DATE: April 23, 2003
TO: City of Ft. Collins, Street Oversizing
Attn: Eileen Bayens
FROM: Bill Nicholl
RE.: Lemay Avenue Widening
Request for change order:
Time involved removing additional trees;
Loader: 2 hrs @ 75.00/hr
322 excavator: 5 hrs @ 125.00/hr
Rock trailer: 4.5 hrs @ 75,00/hr
Dump fees
Subtotal
15% overhead and supervision
TOTAL REQUEST
Pleasecontact
lme if you have any additional questions.
TmeRemovalChgOrder
$ 150.00
$ 625.00
$ 337.50
$ 115.00
S 1,227.50
$ 184.12
$ 15411.62
NO.853 P.2/2
LEMAY AVENUE WIDENING PROJECT
Gerrard Excavating
Remove and Replace Sprinkler Irrigation Main
- See attached submittal -
Item
Unit $ / Unit
I Total
VBellmire Landscapin Installnewsprinkler main
1 LS
$ 3,223.00
$ 3,223.00rrard
Excavating Excavate and Backfill
1, 1..
1 LS
$ 2,520.00
$ 2,520.00
5,743.00
Due to the construction of the new box culvert at Stone Creek
Channel, the sprinkler main on the Paragon Point Subdivision
property needs to be relocated. This work includes: excavating and
backfilling for the existing main, new main and for the latterals; and
installing the new sprinkler main, two valve assemblies, thrust blocks
control wires and repairing lateral lines.
Posted to Pay Estimate # 2
aewrapa
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
BID PROPOSAL
DATE: April 7, 2003
PROPOSAL #: 030404
SUBMITTED TO: City of Ft Collins
Attn: Eileen Bayens
JOB NAME: Lemay Avenue Widening
Remove & Replace Sprinkler Irrigation Main
• Excavate and backfill existing main
• Excavate and backfill for new main
• Excavate and backfill for laterals as required
• Install new sprinkler main, two(2) valve assemblies, thrust blocks, repair lateral lines, one
control wire bundle
Lump Sum Price $ 59743.00
Breakdown:
Labor/Equipment $ 2,520.00
Subcontractor $ 3,223.00
See additional provisions, included as part of this proposal and to be made a part of the
contract.
Authorized Signature - ,
SprinlderMainBid
LEMAY AVENUE WIDENING PROJECT
Gerrard Excavating
Bedding for Underpass and Stone Creek Channel
- See attached submittal -
Item
Unit $ / Unit
I Total
Gerrard Excavating Place 1 1/2" rock under box culverts
Gerrard Excavating Credit for Base Course under box culverts
307 TONS
1 LS
$ 16.25
$ 2,672.00
$ 4,988.75
$ (2,672.00)
5 2,316.75
The plans asked for 6" of road base under the pedestrian underpass and
the Stone Creek Channel box culverts. We made the decision to change
this section to 1 1/2" washed rock one foot deep.
Posted to Pay Estimate # 2
MAY.22.2003 8:37AM GERRARD EXCAVATING N0.405 P.2i6
G�
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970)669-1463
FAX: (970) 669-1964
DATE: May 14, 2003
TO: City of Ft. Collins, Street Oversizing
Attn: Eileen Baycns
FROM: Bill Nicholl
RE: Lemay Avenue Widening
46- Request for Change Order:
Use 11/z" rock under pedestrian box culvert in lieu of road base:
307 tons @ 16.25/ton $ 45988.75
Less base course in quote ($ 2,672.00)
TOTAL CHANGE ORDER $ 2,316.75
ChgOrderRequest51303
Gerrard Excaveting
Cap Irrigation Lines
LEMAY AVENUE WIDENING PROJECT
WANNIMMINIMMMI
See attached submittal -
Item
Unit $ / Unit
Total
errar xca%a mg Gap Irrigation Lines
14 EA I $ 16.00
1 $ 224.00
^� a tza UU
The as -built drawings for the irrigation along the Paragon Point and
Huntington Hills Subdi%sions were incorrect and did not showall
of the stubs for the irrigation.
Posted to Pay Estimate # 2
MAY.22.2003 8.38AM GERRARD EXCAVATING
G04&141
EXCAVATING INC.
1739 South County Road 13C
Loveland, CO 80537
Phone: (970) 669-1463
FAX: (970) 669-1964
DATE: May 22, 2003
TO: City of Ft. Collins, Street Oversizing
Atha: Eileen Bayens
FROM: Bill Nicholl
RE: Lemay Avenue Widening
Request for Change Order:
Cap irrigation lines —14 additional:
14 each @ 16.00/each
TOTAL CHANCE ORDER
�i
ChgOrdCap IrrigationUnes
$ 224.00
$ 224.00
NO.405 P.6/6