HomeMy WebLinkAboutCHANGE ORDER - BID - 5717 CONCRETE PROJECT PHASE IChange Order Form. PR _ _ I I . _- 2003 Street Maintenance Program PROJECT NUMBER: 30522131.6 (Concrete Project Phase I - Bid #5717) CONTRACTOR: Vogel Concrete (PO #3302306) CHANGE ORDER NUMBER: 1 n preparing change orders show in order as separate numbered paragraphs the following: 1. Reason for change. 2. Description of change. 3. Change in contract cost. 4. Change in contract time. 1.&2. See attached invoice for details 3. The contract cost will increase by 4. There is no change in contract time. ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL C.O. % OF ORIGINAL CONTRACT ADJUSTED CONTRACT COST $49, 560.00 6 ACCEPTED BY: of 4� / -jton ctor's Repres nl REVIEWED BY( f ���P ✓ l ACCEPTED BY: (P 'ect_Manager - Engineering ACCEPTED BY: r (Project Manager - Light & Powg0 APPROVED BY: Head) APPROVED BY: Agent over $30,000) cc: Accounting Purchasing Contractor Project File 7.73% 7.73% $641, 339.40 $0.00 $0.00 $49,560.00 $690,899.40 DATE: !-�Of I DATE: TE: J ` C'), TE: Q DATE: DATE: /Wc-),3 Light & Power $24,372.52 Pedestrian Access $22,130.92 Street Maintenance $3,155.56 Engineering, Department • 281 North College Avenue • P.O. Sox 380 • Fort Collins, CO 80522.0580 • (303) 221-6605