HomeMy WebLinkAboutWORK ORDER - RFP - CURED IN PLACE PIPEEXHIBIT "A"
WORK ORDER FORM
PURSUANT TO AN AGREEMENT BETWEEN
THE CITY OF FORT COLLINS
AND
INSITUFORM TECHNOLOGIES, INC.
DATED: July 21, 2000
Work Order Number:
Purchase Order Number:
Project Title: 2002 Insituform Projects
;CM�Jommencement Date: �p
Completion Date: /9 N 01
Maximum Fee: °(arse and reimbursable direct costs):
Project Description: City of Fort Collins Wastewater Utilities 2002 Cured In Place Pipe
Scope of Services:
Address: 3400 Blk. McConnell Dr., 3700 Blk. Post Rd., 3600 Blk. Anvil Ln., 2924 Lambert Ln., 2900 Blk.
Welch Dr., 3300 Blk. Orchard Dr., 1500 & 1600 Blk. Redwood St., 1200 Blk. Riverside, 2100 Blk.
Springfield Dr., 2600 Blk. Kildeer, 1700 Blk. Lakeshore Dr., 3200 Blk. Camelot Dr.
Pipe Diameter: 8", 10" & 12" Vetrified Clay Pipe
Length: 12" — 213 lineal feet 10" — 994 lineal feet 8" — 4,889 lineal feet
Service Connections: 75
Protruding Taps: 0
Insitutube: 0.20 nominal wall thickness, based on 400,000 PSI Modulus
➢ Certificate of Insurance as indicated in Contract
➢ Mobilization and demobilization
➢ Pipeline cleaning prior to and after installation
➢ Preliminary Video and Service Connection Identification
➢ Mainline Bypass pumping during installation
➢ Insitutube pipe installed complete including curing and finishing
➢ As -built Video inspection logs and Video tape
➢ Proper Traffic Control for the work site as approved by City of Fort Collins Traffic Operations
Superintendent.
➢ Coordination and notification with project manager, residents, homeowners association, water
districts, including letters and flyers prior to installation
➢ Coordination with appropriate water district to operate fire hydrants during installation
➢ Daily fax notification to Utility Supervisor of project work being completed on that day
➢ Project pre -construct meeting with Utility Supervisor
➢ Two Year Contractor's Warranty