Loading...
HomeMy WebLinkAboutCORRESPONDENCE - GENERAL CORRESPONDENCE - 9932825CHANGE ORDER NO. Addendum #2 PROJECT TITLE: LaPorte Trail Bridge Design CONTRACTOR: AYRES Associates PROJECT NUMBER: PURCHASE ORDER NO.: 9932825 DESCRIPTION: Revisions for elevating trail 1. Reason for change: Environmental sensativity and habitat preservation mandate a revision to the original design 2. Description of Change: The project had already been completed through the preliminary design phase. The original design placed aprox. 250' of trail along an embankment fill along the south bank of the Poudre River. Environmental sensitivity issues then arose, thus requiring this portion of the project to be revisited. The attached document presents the estimated costs for 'redesigning' this portion of the project. This estimate accounts for redesigning this section with a scope to elevate the trail along this section of the river bank. 3. Change in Contract Cost: $45,015.00 4. Change in Contract Time: N/A ORIGINAL CONTRACT COST $69,900.00 TOTAL APPROVED CHANGE ORDER $32,270.00 TOTAL PENDING CHANGE ORDER $0.00 TOTAL THIS CHANGE ORDER $45,015.00 TOTAL % OF ORIGINAL CONTRACT, THIS C.O. 64.40% TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 110,57% ADJUSTED CONTRACT COST $147,185.00 (Assuming all change orders approved) ACCEPTED BY: Contractor's Represent ACCEPTED BY: Project Manager REVIEWED BY: Title: APPROVED BY: Title: APPROVED BY: Purchasing Agent over cc: City Clerk Architect Contractor Engineer Project File Purchasing DATE: O� DATE: ? (, v_4r:9 DATE: DATE:3