WE HEREBY ENTER OUR BID FOR THE CITY OF FORT COLLINS
REQUIREMENTS FOR TENNIS COURT LIGHTING AT MARTINEZ PARK
PER THE BID INVITATION AND ANY REFERENCED SPECIFICATIONS AND DRAWINGS:
The City of Fort Collins Parks Department is requesting bids for the tennis court lighting at
Martinez Park. The work will consist of installing new poles, lights, conduit, wires and electrical
connections for a complete job. Old poles and lights will be removed by the Parks Department.
Contract must be completed 90 days after notice to proceed is issued. Substantial completions
must be completed by March 14, 2003 with final completion by March 21. The successful bidder
must enter into the attached services agreement (sample) and supply proof of insurance
"Exhibit B" as requested. Substantial completion means all poles, lights, wiring, and other
components must be installed. Final completion means everything must be energized and
working and the site is cleaned of any debris.
Any technical questions should be directed to Eileen Scholl, Project Manager at (970) 416-2062.
Any purchasing questions should be directed to John Stephen, CPPB, Senior Buyer at (970)
221-6775.
A prebid meeting will be held at Martinez Park, 600 N. Sherwood, Ft. Collins at 10:00 a.m. on
November 18, 2002.
BID SCHEDULE TENNIS COURT LIGHTING AT MARTINEZ PARK
The contractor shall furnish all labor and material for tennis court lighting at Martinez Park per
specification, including installing new poles, lights, wires and electrical connections for a
complete job.
LUMP SUM $ 3 36o , o o
Firm Name L ! .L>
(Are you a corporation, D A, Partnership, LLC, PC)
Signature _PRINTED NAME �i4v/17 /UHF
Title GcOVe&s4-C_. AlNylugej2
Address A"✓
Phone/Fax 1193--6)9s6 �.�,� .4•� �_/��S
I
To: City of Ft. Collins Purching
From: The Electric Shop, Ltd.
Re: Bid #5750 Martinez Park Tennis Courts Lighting
References for Tennis Court Lighting
1. Edora Park Tennis Courts, City of Fort Collins. November 1990 start and
February 1991 completion. That project was very similar to this one, we removed
and replaced the existing fight poles, fixtures and wiring. A new service was also
installed with all controls to operate the lights.
2. Lake Loveland Tennis Courts, City of Loveland. Summer of 1991. This was a
new tennis court and involved the installation of light poles, fixtures and controls.
3. Fort Collins Country Club Tennis Courts. March of 2000. Removal and
replacement of old light poles and fixtures.
If you have need of further information just let us know.
Thank you,
David Noe