HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 2201622 P812 SECOND SHEET ICESECTION 00950
CHANGE ORDER NO. 11
PROJECT TITLE: Second Sheet of Ice at EPIC
CONTRACTOR: The Neenan Company
BID NUMBER: P-812
DESCRIPTION: The design and construction of an addition to the Edora Pool Ice Center (EPIC) to house a
full size ice arena and associated facilities and equipment.
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: To incorporate miscellaneous changes into the contract.
2. Description of change: Provide all materials, labor and equipment necessary to: delete asphalt
patching, wall in room 118, keying of locksets, bathroom accessories and lockers in coaches room; prep nine
(9) hollow metal doors and frames for dead bolt locks; provide equipment shelf in storage room; enlarge two
overhead doors to 12'X12'; install three (3) etched glass units; move wall between rooms 136 & 137 and add a
closet; add drop ceiling in corridor 127; add subfloor to conditioning room; ventilate the Zamboni room; relocate
RTU-3 and duct work to conditioning room; run CO & CO2 sensors to DDC panels; change light fixtures in
locker rooms; add reflectors in conditioning room.
3. Change in Contract Cost: $22,810.00
4. Change in Contract Time: 2 Days
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $3,360,896.00
TOTAL APPROVED CHANGE ORDERS 268.226.62
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER 22,810.00
ADJUSTED CONTRACT COST $3,651,932.62
(Assuming all change orders approved)
ACCEPTED BY-
l�
Contractors Representative
REVIEWED BY: �� CA -I,-,_
Facilities Project Mai
cc: City Clerk Project File
D/B Contractor Purchasing
7 O�
Date
Z 7 03
Date