HomeMy WebLinkAboutCHANGE ORDER - BID - 2207049 CHANGE ORDER 5 5727 UTILITIY SERVICES CENTERCHANGE ORDER NO. 5 PROJECT TITLE: Utility Services Center Warehouse Storage Improvements — BID #5727 CONTRACTOR: Mark Young Construction Inc PROJECT NUMBER: 5727 DESCRIPTION: In preparing change orders show in order as separate numbered paragraphs the following: Reason for change: Added landscaping north side of site, added discharge pipe to wet lands pond, added outlet pipe to water quality pond, added pipe to stilling basin, demo existing fence and retaining wall, changed height of fence along trail, changed box culvert trash rack, and deleted HERCP Pipe and slotted storm drain. Description of change: See attached summary sheets. Change in contract cost: Credit — Fifteen Thousand Four Hundred Twenty-four Dollars ($15,424.00) 3. Change in contract time: No change in contract time. (Attach additional sheets as required) ORIGINAL CONTRACT COST $2,273,200 TOTAL APPROVED CHANGE ORDERS $206,411 TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER ($15.424) ADJUSTED CONTRACT COST $2,464,187 (Assuming all change orders approved) ACCEPTED BY: <J�2d 1 7 Mark Young Construction, Inc. Date ACCEPTED BY: Projects Manager REVIEWED BY: Architects APPROVED BY cc: City Clerk Project File Contractor Purchasing Engineer Date 1 27 D Date 1 Dat