HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 15281SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: City Park Pool Renovation
CONTRACTOR: Dohn Construction, Inc.
BID NUMBER: 5731
DESCRIPTION: The renovation of the pool with new concrete, pool, features, piping and equipment and
mechanical building, complete with related sdewort( and landscaping.
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Incorporation of various Proposal Requests.
2. Description of change: PR#: 1) demolish And remove 20' of existing unforeseen concrete wall -
$1,073.00; 2) Miscellaneous pool changes - $22,827.00; 3) Credit to Owner for use of on site facilities for field
office — ($269.00); 4) Miscellaneous site changes - $11,848.00; 5) Add removal of unknown foundation — credit
for partial demolition - $2,609.00; 6) Add ground wire, removal of tree ring & rigid bond breaker - $1016.00.
3. Change in Contract Cost: $39,104.00
4. Change in Contract Time: 0 Days
Attach additional sheets as reouired)
ORIGINAL CONTRACT COST $1,381,470.00
TOTAL APPROVED CHANGE ORDERS 0
TOTAL PENDING CHANGE ORDERS 0
TOTAL THIS CHANGE ORDER 39,104.00
ADJUSTED CONTRACT COST (Assuming all change orders approved) $1,420,574.00
ACCEPTED BY
REVIEWED BY:
0:2:2 0 1
Facilities Project
\-'.)`0Z
Date
l 3 OZ
Date
PJ sing Direct -or Date
cc: City Clerk Project File
D/B Contractor Purchasing
SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: City Park Pool Renovation
CONTRACTOR: Dohn Construction, Inc.
BID NUMBER: 5731
DESCRIPTION: The renovation of the pool with new concrete, pool, features, piping and equipment and
mechanical building, complete with related sitework and landscaping.
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Incorporation of various Proposal Requests.
2. Description of change: PR#: 1) demolish And remove 20' of existing unforeseen concrete wall -
$1,073.00; 2) Miscellaneous pool changes - $22,827.00; 3) Credit to Owner for use of on site facilities for field
office — ($269.00); 4) Miscellaneous site changes - $11,848.00; 5) Add removal of unknown foundation — credit
for partial demolition - $2,609.00; 6) Add ground wire, removal of tree ring & rigid bond breaker - $1016.00.
Change in Contract Cost: $39,104.00
4. Change in Contract Time: 0 Days
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $1,381,470.00
TOTAL APPROVED CHANGE ORDERS 0
TOTAL PENDING CHANGE ORDERS 0
TOTAL THIS CHANGE ORDER 39,104.00
ADJUSTED CONTRACT COST Assuming all change orders approved) $1,420,574.00
ACCEPTED BY: V 't2. OL
ntractor's Representative Date
REVIEWED BY: (a Q�-�
Facilities Project
1 3 OZ
Date
APPROVED BY:
— Purchasing Director Date
U
cc: City Clerk Project File
D/B Contractor Purchasing
SECTION 00950
CHANGE ORDER NO. 1
PROJECT TITLE: City Park Pool Renovation
CONTRACTOR: Dohn Construction, Inc.
BID NUMBER: 5731
DESCRIPTION: The renovation of the pool with new concrete, pool, features, piping and equipment and
mechanical building, complete with related sitework and landscaping.
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Incorporation of various Proposal Requests.
2. Description of change: PR#: 1) demolish And remove 20' of existing unforeseen concrete wall -
$1,073.00; 2) Miscellaneous pool changes - $22,827.00; 3) Credit to Owner for use of on site facilities for field
office — ($269.00); 4) Miscellaneous site changes - $11,848.00; 5) Add removal of unknown foundation — credit
for partial demolition - $2,609.00; 6) Add ground wire, removal of tree ring & rigid bond breaker - $1016.00.
3. Change in Contract Cost: $39,104.00
4. Change in Contract Time: 0 Days
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $1,381,470.00
TOTAL APPROVED CHANGE ORDERS 0
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER 39,104.00
ADJUSTED CONTRACT COST (Assuming all change orders approved) $1,420,574.00
ACCEPTED BY
REVIEWED BY
i
APPROVED BY:
cc: City Clerk Project File
D/B Contractor Purchasing
Date
3 O
Date
7,<3
Dalw