HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 2207330SECTION 00950 CHANGE ORDER NO. 3 PROJECT TITLE: City Park Pool Renovation CONTRACTOR: Dohn Construction, Inc. BID NUMBER: 5731 DESCRIPTION: The renovation of the pool with new concrete, pool, features, piping and equipment and mechanical building, complete with related sitework and landscaping. In preparing change orders show in order as separate numbered paragraphs the following: 1. Reason for change: Incorporation of Proposal Request #8. 2. Description of change: PR#: 8) Furnish and install Play Structure SCS 107 — NTE $38,454.00. 3. Change in Contract Cost: $38,454.00 4. Change in Contract Time: 0 Days (Attach additional sheets as required) ORIGINAL CONTRACT COST $1,381,470.00 TOTAL APPROVED CHANGE ORDERS f TOTAL PENDING CHANGE ORDERS 138 584.00 TOTAL THIS CHANGE ORDER 38,454.00 ADJUSTED CONTRACT COST (Assuming all change orders approved) $1,558,508.00 ACCEPTED BY: A13 QZ C ra tor's Representative Date/ REVIEWED BY: APPROVED BY: Facilities Project Purchasing Director cc: City Clerk Project File Contractor Purchasing Architect I b Date DatbDat SECTION 00950 CHANGE ORDER NO. 3 PROJECT TITLE: City Park Pool Renovation CONTRACTOR: Dohn Construction, Inc. BID NUMBER: 5731 DESCRIPTION: The renovation of the pool with new concrete, pool, features, piping and equipment and mechanical building, complete with related sitework and landscaping. In preparing change orders show in order as separate numbered paragraphs the following: 1. Reason for change: Incorporation of Proposal Request #8. 2. Description of change: PR#: 8) Furnish and install Play Structure SCS 107 — NTE $38,454.00. 3. Change in Contract Cost: $38,454.00 4. Change in Contract Time: 0 Days (Attach additional sheets as required) ORIGINAL CONTRACT COST $1,381,470.00 TOTAL APPROVED CHANGE ORDERS r TOTAL PENDING CHANGE ORDERS 138,584.00 TOTAL THIS CHANGE ORDER 38,454.00 ADJUSTED CONTRACT COST (Assuming all change orders approved) $1,558,508.00 ACCEPTED BY: Representative REVIEWED BY: (R Facilities Project APPROVED BY: i Pbrchathinq Director cc: City Clerk Project File Contractor Purchasing Architect Date �/ 3.0Z, Date Dat \` SECTION 00950 CHANGE ORDER NO. 3 PROJECT TITLE: City Park Pool Renovation CONTRACTOR: Dohn Construction, Inc. BID NUMBER: 5731 DESCRIPTION: The renovation of the pool with new concrete, pool, features, piping and equipment and mechanical building, complete with related sitework and landscaping. In preparing change orders show in order as separate numbered paragraphs the following: 1. Reason for change: Incorporation of Proposal Request #8. 2. Description of change: PR#: 8) Furnish and install Play Structure SCS 107 — NTE $38,454.00. 3. Change in Contract Cost: $38,454.00 4. Change in Contract Time: 0 Days (Attach additional sheets as required) ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER ADJUSTED CONTRACT COST (Assuming all change orders approved) ACCEPTED BY REVIEWED BY: APPROVED BY Facilities Project $1,381 470.00 0 138,584.00 38.454.00 $1,558,508.00 `'�'NZ Date oZ Date P&rcha sing Director at cc: City Clerk Project File Contractor Purchasing Architect