HomeMy WebLinkAboutCHANGE ORDER - BID - 5688 TRAFFIC OPERATIONS COMMUNICATIONS PHASE ICHANGE ORDER NO. 1
PROJECT TITLE: ITS Integration/Advanced TMS
CONTRACTOR: Metrowest Communications
PROJECT NUMBER: ITS M455-049 (13894)
PURCHASE ORDER NO.: 2202706
DESCRIPTION:
1. Reason for change: Increase of project quantities -
Phase I Communications
2. Description of Change: Installation of Fiber Optics at
signalized intersections along the Shields Corridor.
3. Change in Contract Cost: 83,361.00
4. Change in Contract Time: NA
ORIGINAL CONTRACT COST $416,805.00
TOTAL APPROVED CHANGE ORDERS .00
TOTAL PENDING CHANGE ORDERS .00
TOTAL THIS CHANGE ORDER 83,361.00
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.: .20%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.OS: .20%
ADJUSTED CONTRACT COST $500,166.00
(Assuming all change orders approved)
ACCEPTED BY-
o
ACCEPTED BY:
Pr
REVIEWED BY:
Ti
DATE:
Title:
DATE: Jj i6i� L
DATE:
ATE:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: Purchasing