HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 14801 2202988 CHANGE ORDER 1OCHANGE ORDER NO. #10
PROJECT TITLE:
FOSSIL CREEK COMMUNITY PARK PHASE 1 B
CONTRACTOR:
Clark Construction Company, Inc.
PROJECT NUMBER:
5681
PURCHASE ORDER NO.:
2202988
DESCRIPTION: A. Change Catch Basin at Skate Park (Clark #14)
B. Change Concrete at Skate Park (Clark #10)
C. Change Tennis Court Top Layer (Clark #20)
1. Reason for change: A. Change catch basin at skate park - installed in incorrect location in earlier phase
B. Change concrete details at skate park - at request of skate park designer
C. Change tennis court top layer - per clarification with subcontractor
2. Description of Change: A. Change catch basin = no change in price
B. Change concrete details = $2,685
C. Change tennis court top layer = no change in price
3. Change in Contract Cost: $2,685.00
4. Change in Contract Time:
TOTAL APPROVED CHANGE ORDER
TOTAL PENDING CHANGE ORDER
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
ADJUSTED CONTRACT COST
$0 00
$2,685.00
0.04%
2.80%
$6,263,650.56
(Assuming all change orders approved)
ACCEPTED BY:� L— DATE: y Q Z
Contractor's Representative —�
ACCEPTED BY:
Project Manager
REVIEWED BY:
Title:
APPROVED BY
Title:
APPROVED BY:
Purchasing Agent over $30,000
ccCity Clerk Architect
Contractor Engineer
Project File Purchasing
DATE: /Z • P* • O L
DATE: /Z- `elIV417.
DATE:
DATE: