HomeMy WebLinkAboutCHANGE ORDER - BID - 2203020 BID 5700 CITY OF FORT COLLINS AND CSU TRANCHANGE ORDER NO. 05
PROJECT TITLE: CITY OF FORT COLLINS AND CSU TRANSIT CENTER; BID NO. 5700
CONTRACTOR: ENVIRONMENTAL CONCERNS, INC.
PROJECT NUMBER: 30518000.6
DESCRIPTION: BUS SHELTER DELAY AND LANDSCAPE WALLS
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: Additional time for shelter delay and landscape walls.
2. Description of change: See attachments.
3. Change in contract cost: $26,349.37
Change in contract time: Add 6 additional days, October 29, 2000
(Attach additional sheets as required)
ORIGINAL CONTRACT COST.........................................................................$1,751,650.00
TOTAL APPROVED CHANGE ORDERS........................................................... 115,697.08
TOTAL PENDING CHANGE ORDERS.............................................................. 00.00
TOTAL THIS CHANGE ORDER...................................................................... 26,349.37
TOTAL % OF THIS CHANGE ORDER............................................................. 1.5%
TOTAL C.O. % OF ORIGINAL CONTRACT. .............. .......................... ........... 8.4%
ADJUSTED CONTRACT COST ......................................... ................... $1,893,696.45
(Assuming all change orders approved)
ACCEPTED BY:
ACCEPTED BY:
ACCEPTED BY:
ACCEPTED BY:.
APPROVED BY:
MANAGER
Beitler, U, Project Manager
TOM FRAZIER, GENEFJ4L MANAGER
APPROVED BY:
PURCHASING AGENT OVER $30,000
cc: City Clerk Project File
Contractor Purchasing
Engineer
//^ 'oZ
/ DATE
DATE
DATE