HomeMy WebLinkAboutRESPONSE - BID - 5742 FIBER OPTIC INSTALLATION AT TRANSFORT (2)BID #5742 FIBER OPTIC INSTALLATION AT TRANSFORT
ADDENDUM #1
Bid Schedule
Contractor will provide all labor, equipment, materials and traffic control to install 24 strand single
mode fiber optic feed to Transfort per specification:
2800 linear feet X $ /3 3 per foot = $ 3 % 3 ed TOTAL BASE BID
Firm Name
Corporation, DBAPartnership, or LLC
Signatur
Print Name I ,; t�ooc� s
Address 1301 1U
L"'n ': A, , Gt) 760 2 "7
Phone/Fax# 303-66Y-5�7uo 1303-b6v-0zy6
References
City of Fort Collins Trafic Division $500,000
Ward Stanford (970)221-8820
Eric Bracke (970) 2244788
Metrowest Communications was awarded the contract for the City of
Ft. Collins Traffic Division fiber optic backbone throughout the entire
city.The project was successfully delivered on time despite an
extremely Aggressive schedule. The project involved some 25,000
feet of underground boring and trenching, over 100 hand holes being
placed throughout the city streets, 300 utility potholes, 80,000 feet of
fiber optic cable placement and all necessary splicing and testing.
Otyef Soft# 1.l►Ulm The city officials were very pleased on the professional and timely
installation.
Brown (970) 356-4000 wcL4875
Metrowest installed a total campus backbone build out for the Weld
a County Government. This project involved the installation of a 48-
strand single mode fiber optic cable from their county headquarters in
Greeley to the new North Jail Facility. From the North Jail location
Metrowest installed a redundant fiber optic ring to connect the Human
Resources Building, the new health facility Building, Public Works,
ambulance facility, and Social Services Building.
(970) 350-988
Metrowest Communications installed the Island Grove Fiber Optic
Network for the City of Greeley. This project involved both single
mode and murdmode fiber optic backbone, which connected the City
of Greeley's data center with the Facilities Building, Community
Center, Exhibition Center, and multiple outlying buildings.
US Cable
$1.2 Million
Rick Montoya
(970) 587-2243
Metrowest Communications currently is working with US Cable as a
Primary Contractor. Metrowest currently has a 4.3 mile fiber build in
1 1\
the town of Johnstown Colorado, and a 11.2 mile fiber build in
Wellington Colorado. US Cable in the towns of Miliken, and Ft.
1 1■ 1
Collins Colorado has awarded two other new build construction
_V V
projects to Metrowest Communications. These projects also require
attentive Project Management and coordination, Boring, Trenching,
splicing and activation.
Rick Shannon (720) 490-3927
Metrowest Communications holds a Master Construction Agreement
with AT&T Broadband as a primary contractor. Metrowest has been
contracted to manage 38 existing new build projects in the Denver
MUM_ Metro area. These projects require project management,
MUcoordination with Developers, and builders', directional boring,
backhoe trenching, splicing active and passive devices, and activation
of new plant. Metrowest has also secured two fiber Optic build
projects from AT&T Broadband. These projects combined total over
19 miles of aerial and underground fiber construction.