HomeMy WebLinkAboutCHANGE ORDER - RFP - P680 PERONNEL CONSULTANTS CHANGE ORDER 3CHANGE ORDER NO. 3
PROJECT TITLE: JOB EVALUATION STUDY
CONTRACTOR: Public Sector Personnel Consultants
PROJECT NUMBER: P-680
PURCHASE ORDER NO.:
DESCRIPTION:
1. Reason for Change: Extend time for completion of services
2. Description of Change: Contracted Services to be completed by December 31, 2002
3. Change in Contract Cost: N/A
4. Change in Contract Time: December 31, 2002.
ORIGINAL CONTRACT COST $30,000
TOTAL APPROVED CHANGE ORDERS $ 2,000
TOTAL PENDING CHANGE ORDERS $
TOTAL THIS CHANGE ORDER $
TOTAL % OF ORIGINAL CONTRACT, THIS C.O.: _%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.S: 15%
ADJUSTED CONTRACT COST $32,000
ACCEPTED BY: DATE: / !�pZ
ConTrar.Tnr's Rarer anr�fi..c
REVIEWED BY: DATE:
Title:
APPROVED BY:
Title:
APPROVED BY: DATE:
Purchasing Agent over $30,000
cc: Purchasing