CHANGE ORDER NO.1
]PROJECT TITLE: East Mulberry Corridor Plan
CONTRACTOR: EDAW
PROJECT NUMBER:
PURCHASE ORDER NO.: ,.uiw''
DESCRIPTION:
1. Reason for change: Modifications to the final Framework Plan transportation
model.
2. Description of Change: Per attached Scope of Work, the additional funds will be
used to extract volume to capacity ratios from the model between 7:00 am and
7:00 pm for both the final Framework Flan and for the null Alternative. Adding
level of service information to the traffic volume graphic fnr the final Framework
Plan, and other graphic modifications. $1,00o will come from the department's
existing budget for the project and the balance of $1,000 will be paid to EDAW
by Larimer County.
3. Change in Contract Cost: $2,000
4. Change in Contract Time. None
ORIGINAL CONTRACT COST $160,000
TOTAL APPROVED CHANGE ORDERS $ 0
TOTAL PENDING CHANGE ORDERS $ 0
TOTAL THIS CHANGE ORDER $ 2,000
TOTAL % OF ORIGINAL CONTRACT, THIS CO.O.: 0.0125%
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S 0.0125%
ADJUSTED CONTRACT COST $ 162,000
(Assuming all change orders approved)