CHANCE ORDER NO.1
PROJECT TITLE: City Plan Update
CONTRACTOR: EDAW
PROJECT NUMBER:
PURCHASE ORDER NO.: 2204769
DESCRIPTION:
1. Reason for change: Conduct survey to determine an accurate gauge of community
attitudes on the potential expansion of the urban growth area and other key issues
for the City Plan Update.
2. Description of Change: The additional funds will be used to conduct this survey,
per the attached scope of work.
3. Change in Contract Cost: $15,000
4. Change in Contract Time: None
ORIGINAL CONTRACT COST
TOTAL. APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF ORIGINAL CONTRACT, THIS CO.O..
TOTAL % OF ORIGINAL CONTRACT, ALL C.O.'S
AD.T[1STED CONTRACT COST
(Assuming all change orders aooroved)
ACCEPTED BY:
ACCEPTED BY:
� 407
APPROVED BY:
Chief Planner
cc: Purchasing
$388,750
$ 0
$ 0
$ 15,000
0.039%
0.039%
$403,750
DATE: 11 ( OZ—
DATE: l62
TE: ! yl 102-