CHANGE ORDER NO. 8
PROJECT TITLE: Second Sheet of Ice at EPIC
CONTRACTOR: The Neenan Company
BID NUMBER: P-812
DESCRIPTION: The design and construction of an addition to the Edora Pool Ice Center (EPIC) to house a
full size ice arena and associated facilities and equipment.
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change: To upgrade the current fire alarm system by adding the voice evacuation required
by the Code, per direction from Poudre Fire Authority.
2. Description of change: Provide all materials, labor and equipment necessary to upgrade the fire alarm
system to include: adding one smoke detector above the Fire Alarm Control Panel; adding nineteen (19) 75cd
candela strobes; adding six (6) 75cd, seventeen (17) 30cd and nine (9) 110cd speaker/strobes (fourteen (14)
will be replacing existing strobes); adding one (1) 110cd temporal hom/strobe; adding sixteen (16) intelligent
photoelectric smoke detectors for duct detectors, along with sixteen (16) LED remote alarms and sixteen (16)
air samplers.
3. Change in Contract Cost: $43,604.40
4. Change in Contract Time: 0 Days
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $3,360,896.00
TOTAL APPROVED CHANGE ORDERS 173.256.00
TOTAL PENDING CHANGE ORDERS 0.00
TOTAL THIS CHANGE ORDER 43,604.40
ADJUSTED CONTRACT COST $3,577,756.40
(Assuming all change orders approved)