HomeMy WebLinkAboutCHANGE ORDER - GENERAL CORRESPONDENCE - 9931560CHANGE ORDER NO. 01
PROJECT TITLE: Nix Farm
CONTRACTOR: Cottier Construction. Inc.
PROJECT NUMBER: 30547107
DESCRIPTION: Remodel of Main Farm House and new Maintenance Building.
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change: Owner adds and unforeseen conditions.
2. Description of change: See Attached.
3. Change in contract cost: $27,278.00
4. Change in contract time: No change in time.
(Attach additional sheets as required)
ORIGINAL CONTRACT COST..........................................................$1,558,956.00
TOTAL APPROVED CHANGE ORDERS .............................................
00.00
TOTAL PENDING CHANGE ORDERS ................................................
00.00
TOTAL THIS CHANGE ORDER...
27,278.00
ADJUSTED CONTRACT Cy03i............/
......................................$1,586,234.00
ACCEPTED BY:
REVIEWED BY:
REVIEWED BY:
REVIEWED BY
APPROVED BY
Cottier
,JR
, Aller
Project Manager, Steve White
cc: City Clerk Project File
Contractor Purchasing
Engineer
12 �Z
Date
az-
ate
2d 15-z-
Dare
i zeo z
D to
/ & p2
Date