HomeMy WebLinkAboutCHANGE ORDER - BID - 5705 FOSSIL CREEK IMPROVEMENTSChange Order Form
woos
aftyort Collins
PROJECT TITLE: Fossil Creek Parkway Street Improvements Project
PROJECT NUMBER: 30523230.6 (Bid #5707)
CONTRACTOR: Connell Resources, Inc. (PO#2204044)
CHANGE ORDER NUMBER: 1
n preparing cnange oraers snow in oraer as separate numoerea paragrapns the ronowing
1. Reason for change. 2. Description of change.
3. Change in contract cost. 4. Change in contract time.
1&2. See attached sheet for detail.
3. The contract cost will increase by
4. There will be no change in contract time.
ORIGINAL CONTRACT COST
TOTAL APPROVED CHANGE ORDERS
TOTAL PENDING CHANGE ORDERS
TOTAL THIS CHANGE ORDER
TOTAL % OF THIS CHANGE ORDER
TOTAL C.O. % OF ORIGINAL CONTRACT
ADJUSTED CONTRACT COST
(Assuming all change orders approved)
ACCEPTED
ACCEPTED
REVIEWED
APPROVED
APPROVED BY:
a: Purchasing
Accounting
Contractor
Project File
$55,089.30
Agent over $30,000)
9.84%
9.84%
$559,892.50
$0.00
$0.00
$55,089.30
$614,981.80
7 /d
FOSSIL CREEK PARKWAY STREET IMPROVEMENTS PROJECT
Connell Resources, Inc.
Installed fly ash along north side of Fossil Creek Parkway.
- See attached submittal -
Item
1 Unit / Unit
Total
Son Haul North side of Fossil Creek Parkway
7653 SY
1 $ 5.60
1 $ 42,856.80
TOTAL $ 42,858.80
Due to pumping and rolling along the north side of the job it was
determined that to fly ash was more economical and time efficient for
the job.
Posted to Pay Estimate 4 1
FOSSIL CREEK PARKWAY STREET IMPROVEMENTS PROJECT
Connell Resources, Inc.
Installed additional silt fence as directed by inspector
- See attached submittal -
Item
Unit / Unit
I Total
lConnell Resources Silt Fence
400 LF
1 $ 4.25
1,700.00
TOTAL $ 1,700.00
The designer had failed to display the need for silt fence within there
design so it was decided that the need was present to place silt fence
at the outfalls of the storm sew er pipe.
Posted to Pay Estimate # f
FOSSIL CREEK PARKWAY STREET IMPROVEMENTS PROJECT
Connell Resources, Inc.
Extra Flow Fill for storm sewer pipes
See attached submittal -
Item
Unit $ / Unit
Total
lGonnell Resources, Inc. Non -Shrink ow Fill75.5
CY
$ 75.00
5,662.50
Connellesources,Inc. Concrete loin encasement4
EA
800.00
(3,200.00
TOTAL $ 2,462.50
To decrease the delay time on the road, flow fill was used
around and over the roadway crossings of the storm sewer
pipe.
Posted to Pay Estimate # f
FOSSIL CREEK PARKWAY STREET IMPROVEMENTS PROJECT
Connell Resources, Inc.
Additional irrigation Sleeving
See attached submittal -
Item
Unit $ /Unit
Total
onne Resources irrigation eeving
140 LF
13.00
1,820.00
I U I AL $ 1,820.00
Due to landscaping requirements and future need to preserve
the roadway irrigation sleeving was added to the medians near
College Avenue
Posted to Pay Estimate # 1
FOSSIL CREEK PARKWAY STREET IMPROVEMENTS PROJECT
Connell Resources, Inc.
Install additional 24" pipe at Parkway Circle West
See attached submittal -
Item
I Unit $ / Unit
1 Total
lGonnell Resources, Inc. Lxtra
105 LF
$ 50.00
$ 5,250.00
TOTAL $ 5,250.00
Installed an additional amount of pipe under Parkway Circle
West to accomidate the Side Walk and slope restrictions for
the site
Posted to Pay Estimate # 1
FOSSIL CREEK PARKWAY STREET IMPROVEMENTS PROJECT
Connell Resources, Inc.
Remove Section of median
See attached submittal -
Item
Unit / Unit
I Total
lGonnell Resources, Inc. Median emova
1 LS
1,000.00
1 $ 1,000.00
TOTAL $ 1,000.00
Removed a section of the third median from College Avenue to
create the entrance for the future Discount Tire Company and
the future Snead Drive Connection
Posted to Pay Estimate # f