HomeMy WebLinkAboutCORRESPONDENCE - BID - 5612 ASPHALT OVERLAY PROJECT ANNUALJUL-16-2002 TUE 07:37 AM CFC ENG, FAX NO, 9702216378 P, 01 A PROJECT TITLE: PROJECT NUMBER CONTRACTOR: CHANGE ORDER Nt Change Order Form 2002 Street Maintenance Project 30522121.6 (Asphalt Overlay Project) • Bid #5612 Connell Resources, Inc. (PO #2202547) 2: 2 1. Reason for rhange, 2. Description of change. 3. Change In contract cost. 4. Changa in contract time. 1&2. Sec attached sheet for detail. 3. The contract cost will increase by 4. there will be no change in contract time. ORIGINAL CONTRACT COST TOTAL, APPROVED CHANGE ORDERS TOTAL PENDING CHANGE ORDERS TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL CA, % OF ORIGINAL. CONTRACT ADJUSTED CONTRACT COST (Assuming nil change orders approved) ACCEPTED ACCEPTED REVIEWED APPROVED BY: APPROVED BY: cc: Gonlremor Portaging Preled rile $26,036.95 (PLIrchasing Agent over $30,000) 1.87% 3,43 $1,390,960.50 $21,608.65 $0,00 $26,036.85 $1,438,606.00 -IZ. oL zf- DATE: '% /- -D.2— — DATE: JUL-16-2002 TUE 07 : 37 AM CFC ENG. FAX N0, 9702216378 P. 02 2002 Asphalt Maintenance - Change Order No. 2 Change order No.: 2 Dale: 71'10102 4. Reason ForChanpo: a, Additional milling was needed on 6u5oh Drive In order to meet schedule deadlines, 2. Description Of Change: a. Add additional spare yards or milling. 7. Chanpo In Contract Amount: em Qry a. Milling 10° 4950.4 TOTAL. CHANGE IN CONTRACT AMOUNT 4. Change In Contract Time a, There Is no change in contract time Unit Unit Cost Total Cost 6Y $ 5.25 $ 26,036.65 $ 26,036.05