HomeMy WebLinkAboutCHANGE ORDER - RFP - P812 SECOND SHEET OF ICE AT EPIC (3)SECTION 00950
CHANGE ORDER NO. 3
PROJECT TITLE: Second Sheet of Ice at EPIC
CONTRACTOR: The Neenan Company
BID NUMBER: P-812
DESCRIPTION: The design and construction of an addition to the Edora Pool Ice Center (EPIC) to house a
full size ice arena and associated facilities and equipment.
In preparing change orders show in order as separate numbered paragraphs the following:
Reason for change: To provide dehumidification for the existing rink.
2. Description of change: Add to the dessicant system for the new addition to provide dehumidification for
the existing rink.
Change in Contract Cost: $19,705.00
4. Change in Contract Time: 0 Days
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $3,360,896.00
TOTAL APPROVED CHANGE ORDERS a
TOTAL PENDING CHANGE ORDERS 51,949.00
TOTAL THIS CHANGE ORDER 19,705.00
ADJUSTED CONTRACT COST $3,432,550.00
(Assuming all change orders approved)
ACCEPTED BY:
APPROVED BY
7 L---
Kepresentative
Facilities Project
cc: City Clerk Project File
D/B Contractor Purchasing
Date
7 Z I E3 Z02