HomeMy WebLinkAboutCHANGE ORDER - RFP - P812 SECOND SHEET OF ICE AT EPIC (2)SECTION 00950
CHANGE ORDER NO. 2
PROJECT TITLE: Second Sheet of Ice at EPIC
CONTRACTOR: The Neenan Company
BID NUMBER: P-812
DESCRIPTION: The design and construction of an addition to the Edora Pool Ice Center (EPIC) to house a
full size ice arena and associated facilities and equipment.
In preparing change orders show in order as separate numbered paragraphs the following:
1. Reason for change: To extend the piping from the ice refrigeration system in the new addition to
accommodate adding the existing rink for a two -rink operation in the future.
2. Description of change: Addition of the piping from the ice refrigeration system mechanical room in the
new addition to the existing rink wall for connection at a later date.
Change in Contract Cost: $20,362.00
4. Change in Contract Time: 0 Days
(Attach additional sheets as required)
ORIGINAL CONTRACT COST $3,360,896.00
TOTAL APPROVED CHANGE ORDERS 0
TOTAL PENDING CHANGE ORDERS 31,587.00
TOTAL THIS CHANGE ORDER 20,362.00
ADJUSTED CONTRACT COST $3,412,845.00
(Assuming all change orders approved)
ACCEPTED BY:
Representative
APPROVED BY: C;p col1
Facilities Project Mai
cc: City Clerk Project File
D/B Contractor Purchasing
�21tg/O?,
Date
$ 0
Date