HomeMy WebLinkAboutCORRESPONDENCE - GENERAL CORRESPONDENCE - CHANGE ORDER NUMBER 406/27/2002 THO 14:04 FAX 970 221 6586 CITY OF IT COLLINS CLRS 13 a 4'n (a 001/008 SECTION 00950 CHANGE ORDER NO.4 PROJECT TITLE: HARMONY PARK; BID NO. 5637 CONTRACTOR: Mark Young Construction, Inc. PROJECT NUMBER: 01269 DESCRIPTION: 1. Reason for Change: Owner Requested 2. Description of Change: CIWR "Q", CTWR "R", CTWR "S", CTVVR "T", CIWR "U", CIWR "V" CIWR "W'• 3. Change in Contract Cost: $16,413.00 4. Change in Contract Time: None ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDER TOTAL PENDING CHANGE. ORDER TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL C.O. % OF ORIGINAL CONTRACT ADJUSTED CONTRACT COST (Assuming all change orders approved) _ ACCEPTED BY: Contractor's Representative $ 1,131,911.32 $ 2,388.34 $ 0.00 $ 16,413.00 — .01 % .02% $ 1,150,712.66 DATE: -0Z- ACCEPTED BY: llpti,/ `-r' DATE: Project Manage REVIEWED BY: Title: APPROVED BY: Title: APPROVED BY: Purchasing Agent over $30,000 CC: City Clerk Contractor Project File Architect Engineer Purchasing DATE: DATE: DATE: 06/$7/2002 THU 14:05 FAX 970 221 6586 CITY OF FT COLLINS CLRS 0 002/008 ent By: HP LaserJet 3100; 2240392; May-21.02 2:38PM; Page 6/6 CHANGE TN WORK 9EQUE&F "(r Initiation Datc: 5/7/02 Project: Harmony Park ownet: City of Fort Collins Park Planning and Development To: Mark Young Construction Requested by: Mat(Day Authorized by: Mau Day, Pinja:l Manager Please ihndsh change in contreol sum for the change in work described below. Do not order material or start any work until approval is received Every q fforr w111 be made to incorporate /his change into the work withaui affrr:ting thr, rontraet dale_ a breakdown which lisle all costa of labor, matetiais, taxes, overhead, profit, and all otter changes and/or charges involved, Signature of the Ctmtraetnr indicatex his agreement herew)th, imladiag any adiostmcnt in the Contmet Sum or Contract Time. The Contract Time will be (increased) (deermow d) unehaoged) by -DAYS- No change in Contract Sum (initial if no clunge) ADP to the Contract Sum $ ao-7 1 . C 0 ❑WUCP from the Cotnraot Sum S This information shall be valid for thirty (30) calendar days from the date of siguature below, CONTRACTOR'S SIGNA'111itLr: DATE: Q . p z CnNmnnr rarttl rr.1ala au. (i) mpy and ream OMClNAL to Owner APPROVIil7 BY OWNER: DAB: p Z Acreptad change in work roque9l will be inc1wkd in a fuhim formal change order. DO NOrbillfor thin change until a formal change order has boon executed by all parties. Acceptance it dire+Clion io proceed with doe work described herein. Not valid unlau .signed by the owner and the oontramor. 06/27/2002 THU 14:05 FAX 970 221 6586 CITY OF FT COLLINS CLRS CHANGE IN WORK REQUEST "R" Z 003/008 .vitiation Date: 5/29/02 Project: Harmony Park Owner: City of Fort Collins Park Planning and Development To: Mark Young Construction Requested by: Matt Day via Jeff Lakcy Authorized by: Matt Day, Project Manager Please furnish change in contract aum for the change in work described below_ Do not order material or start any work until approval is received. Every effort will be made to incorporate this change into the work without affecting the contract data sung block outs in Cone] ;me and have a 2 1/2" reveal to the top of concrete. Slope concrett Per existing __, of concrete ate w unacrcur existing replace 2 sections of walk. One 4'M4 piece at the preston eirol ne walk and one 1 1/2ax 8 piece by traiwalk' Per nmarkinryge Foy ancut and d Po�2 r sections to above specifications. a 4n concrete base for —m K r uuag uonstruction , agrees to change the work desonbed above for the change m pnce shows below. I have attached a breakdown which lists all costs of labor, materials taxes, overhead, prof'% and all other changes and/or charges involved. Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time. The Contract Time will be (increased) (decrees (ugcha °g by Days. No change in Contract Sum UniHal if no change) ADD to the Contract Sum $ Lit Z. /] t l DEDUCT from the Contract Sum S This information shall be valid for thirty (30) calendar days from the date of signature below_ CONTRACTOR'S SIGNATURE: DATE;_g_l OZO — Convacter shall rMift are (/) copy and return ORIGINAL to Owner APPROVED 13Y OWNER: DATE: Accepted change in work request will be included in a future formal change order. DO NOT bill for this change until a formal change order has been executed by all parties. Acceptance is direction to proceed with the work described herein. Not valid unless signed by the owner and the contractor. 06/Z7/2002 THLT 14:05 FAX 970 221 6586 CITY OF FT COLLINS CLRS "" ~p CHANGE, IN WORK REQUEST "S" Initiation Date; 6/6/02 Project: Harmony park Owner: City of Post Collins park Planning and Development To: Mark Young Construction Requested by: Man Day Authorized by; Matt Day, Project Manager Q004/008 Please fitwish change in contract sam for the change in work dcscnbed below. Do not order material or start any work until approval is received Every e�ori will be made to rncorporare this ekange bdo the work without afjecling rho eonrraer dare. ----�� � • Wd..d d wau os moor, matermrs, to M m=bced, profit, and an other changes and/or charW =Volved. Sigaaio a of the Contractor tndicates his agreement herewith, including any atVushueat in the Contnsct Sum or Contract Time. The Contract Time will be (increased) (deerenae unchanged) by Days. No change in Copimct Sum (initial if,, change) ADD to Ow Contract Sum S DEDUCT from the Conmot Sum S This information shall be valid for thirty (70) calendar days from the date of signature below. CONTRACTOR'S STGNATLrRE: _ DATE: (rj//(Y6 -7 ConlmdarAd i rmfir a" (V Copy o,d ratum ORI(MVAL 10 Ownbr APPROVED BY OWNER: DATE: b 1a 71 Accepted change in work request will be included in a}utum formal change order. DO NOT bill for this change unrll a formal change order hat barn executed by all partks, Acceptance (s direction ra proceed with the work described heron. Not valid unless signed by the owner and the contractor. 06/27/2002 THU 14:06 FAX 970 221 6586 CITY OF FT COLLINS CLRS 00:/U/2002 FRI 09:20 FAX 970 221 6566 CITY OF F1' COLLINS CLRS CHANGE IN WORK RE0113M f T- Ioidation Data: 617/02 Project Harmony Park Owner: City of Fort Collins Park r1t ding and Development To: Mark Young Construction Requested by: Matt Day Authurimod by: Mau Day, Project. Managcr Q 005/008 4002/003 Please fam9sh change In contract a= for the change in work described below. Do not order material or slate any work until approval is reccived. Every gVrort will be merle to incorporate this Change Into the WOrh without q(%cling the contract date. u$ and grade Ure ama behind the now curb ad 9111W. Match the height of the club and getter and blend grade out to Owner's representative to inspect in field as grading operations occur_ Please provide per enbio yard ptioing . a rascmown winch lute as costs of labor, materials, taace, overboad, profit, and all other c1 mges and/or charges involved, Sighatm of the Contractor ludieates his agmcment herewitb, mclading any ad)ustttlatt In the ODotrut Sum or Contract Time, The Contract Time will be (increased) (deersa unchanged) by Dayu. No change in Contract Sum (initial if no obnago) ADD to the Contract sum $ `t S-1 _Q p DEDUCT from the Contract Sum S This information shall be valid for thirty (30) caleadar days &ern the date of signature below. CONTRACi'OR's SIGNATURE: 4.01,p Ae.4 DATE: G I dIU Coarrnasrrlmll miWn ono ill copy and reerrn ORtt 1WAL to Owner APPROVED BY OWNER: DATE: is O b' Accepted change in work request will be Included in a future formal change order. DO NOT bill for this change until a formal charge order has been executed by all parties. Acmodnce is dtrearion to pmend with the work described herein. Not valid unless signori by the owner and the contractor. 06/27/2002 THU 14:06 FAX 970 221 6586 CITY OF FT COLLINS CLRS 06/07/2002 FRI 05:20 FAX 970 221 6586 CITY OF FT COLLINS CLRS C9ANGE IN WORK RE,QUM uV" Initiation Data: 0102 Project Harmony Park Owner: City of Fort Collins Park Planning and Developmont To: Mark Young Construction Regaostedby: MattDay Aalhoaruul by. Matt Day, Project Manages Q 006/008 F0003/003 Please intniab ehango in contract sum for the ebange in work descnbedbalew. Do not order material or start any work until approval is received lsvery gprl will be mode to incorporate this change into rlre work mi"i affecting the contract dote. ie wash all landscape boulders and apply graffiti coating lnfonmtion on VWEti coating obtained fr )CO and the material is "sacrificial coating" and they were purebasmg it from Rio Groude (Denver). graffiti coating per manufacturers speoifirations. , agrees a bmakdown which Hats all costs of labor, materials, tam, overhead, poll; and all other charges and/or charges involved. Stgttatere or the Contractor todieates his agrecmaat herawitb, incladins any adjosttuent in the Contmol Sam or Contract Inne. The C ona-Ad Time will be (increased).(deeraas unclean ed) by Days. No Change is Contract Stuu (rnidal if 110 d nee) ADD to the Contract Sam 3 ��� • l� t� — DEDUCT from the Contract Sum S This information shall be valid for thirty (30) 0alendar days from the date of sistlatora below. CONTRACTOR'S SIGNATURE: I 67 r a DAT& Contrwwrthall retain one (1) copy and ratwe 012101 M m Omer APPROVED IYY OWNER: DATE: {a / J b Accepted change in work request will be Included in a fuhtre formal change order. DO NOT bill for this change until a formal chwrga order hay been exeataed by all parties, Acceptance it dkeoaon to proceed wMrh the work described hardn. Nor valid ttnlras signed by de owner and the contractor. 06/27/2002 THU 14:06 FAX 970 221 6586 CITY OF FT COLLINS CLRS CHANGE IN WORK REQUEST "V" Q 007/008 Initiation Date: 6/12/02 Project: Harmony Park Owner: City of Fort Collins Park Planning and Development To. Mark Young Construction Requested by: Matt Day Authorized by: Mart Day, Project Manager Please furnish change in contract sum for the change in work dcsen'bcd below. Do not order material or start any work until approval is received. Every effort will be made to incorporate this change into the work without affecting the contract date, a breakdown which lists all costs of labor, materials, taxes, overhead, profit, and all other obauges and/or charges involved. Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time. The Contract Time will be (increased) (decreas (unchanged) by Days. No change in Contract Sum (initial it no manse) ADD to the Contract Stan $ 51 S. CPO DEDUCT from the Contract Sum $ This information shall be valid for thirty (30) calendar days from the date of signature below. CONTRACTOR'S remin ane (I) ropy and rennin ORIGINAL io Owner DATE: 6A APPROVED BY OWNER: DATE: (p 2 Accepted change in work request will be included in a future farina! change order. DO NOT bill far this change until a formal change order has been executed by all parties. Acceptance is direction to proceed with the work described herein. Not valid unless signed by Me owner and the contractor 06/,27/2002 THLI 14:07 FAX 970 221 6586 CITY OF FT COLLINS CLRS CHANGE IN WORK REQUEST "W i [a 008/008 Initiation Date: 6/12/02 Project: Harmony Park Owner: City of Fort Collins Park Planning and Development To: Mark Young Construction Requested by: MattDay Authorized by: Matt pay, Project Manager Please furnish change in contract sum for the change in work described below. Do not order material or start any work until approval is received. Tsvery effort will be made to incorporate this change into the work without affecting the contract date. a orcaenown wmcn asts all costs of labor, materials, taxes, overhead, profit, and all other changes aridlor charges involved Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time. The Contract Time will be (increased) (dncreased) �b .-- y Days. No change in Contract Sum (Initial if no change) ADD to the Contract Sum $ 1 QO(p, pp DEDUCT from the Contract Sum $ This information shall be valid for thirty (30) calendar days from the date of signature below. CONTRACTOR'S SIGNATURE LTV DATE: Corawdorrhall regain one (1) copy and ronun ORlotNAL to owner APPROVED BY OWNER: DATE: x, Accepted change in work request will be included in a future formal change order. DO NOT bill far this change until a formul change order has been executed by all parties. Acceptance is direction to proceed with the work described herein. Not valid unless signed by the owner and the contractor.