Loading...
HomeMy WebLinkAbout108423 VOGEL CONCETE - CONTRACT - BID - 5717 CONCRETE PROJECT PHASE 1SPECIFICATIONS AND CONTRACT DOCUMENTS FOR CONCRETE PROJECT - PHASE I BID NO. 5717 BID OPENING: PURCHASING DIVISION 215 NORTH MASON, 2ND FLOOR, FORT COLLINS JULY 2, 2002 - 3:00 P.M. (OUR CLOCK) i be submitted in writing to the Engineer and the OWNER. Interpretation or clarifications considered necessary in response to such questions will be issued only by Addenda. Questions received less than seven days prior to the date for opening of the Bids may not be answered. Only questions -� answered by formal written Addenda will be binding. Oral and other -� interpretations or clarifications will be without legal effect. 5.2. All questions concerning the scope of this project should be directed to the Engineer. Questions regarding submittal of bids should be directed i to the City of Fort Collins' Purchasing Division. '! 5.3. Addenda may also be issued to modify the Bidding Documents as deemed advisable by OWNER or Engineer. -� 5.4. Addenda will be mailed or delivered to all parties recorded by the OWNER as having received the Bidding documents. _y 6.0 BID SECURITY :} 6.1. Each Bid must be accompanied by Bid Security made payable to OWNER in the amount stated in the Invitation to Bid. The required security must be in the form of a certified or bank cashier's check payable to OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be executed by a surety meeting the requirements of the General Conditions for surety _F bonds. -� 6.2. The Bid Security of the successful Bidder will be retained until such Bidder has executed the Agreement and furnished the required contract security, whereupon Bid Security will be returned. If the successful Bidder fail's to execute and deliver the Agreement and furnish the required contract security within 15 days of the Notice of Award, OWNER may annul the Notice of Award and the Bid Security of that Bidder will be forfeited. .S The Bid Security of other Bidders whom OWNER believes to have reasonable chance receiving the award may be retained by OWNER until the earlier of the seventh day after the effective date of the Agreement or the thirty- first day after the Bid Opening, whereupon Bid Security furnished by such Bidders will be returned. Bid Security with Bids which are not competitive will be returned within seven days after the Bid opening. F 7.0 CONTRACT TIME. The number of days within which, or the date by which the Work is to be substantially complete and also completed and ready for Final Payment (the Contract Times) are set forth in the Agreement. 8.0 LIQUIDATED DAMAGES. i Provisions for liquidated damages are set forth in the Agreement. 9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT 7/96 Section 00100 Page 3 EICDC GENERAL CONDITIONS 1910-8 (1990 Edition) GC -AI w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/94) z 0 SECTION 00800 SUPPLEMENTARY CONDITIONS SECTION 00800 J`r SUPPLEMENTARY CONDITIONS Conditions of the Contract These Supplementary Conditions amend or supplement the General [[[ Conditions of the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins modifications) and other provisions of the Contract Documents as indicated below. SC-5.4.8 Limits of Liability A. Add the following language at the end of paragraph 5.4.8. The limits of liability for the insurance required by the paragraph numbers of the General Conditions listed below are as follows: a 5.4.1 and 5.4.2 Coverage A - Statutory Limits Coverage B - $100,000/$100,000/$500,000 5.4.3 and 5.4.5 Commercial General Liability policy will have limits of $1,000,000 combined single limits (CSL). This policy will include coverage for Explosion, Collapse, and Underground coverage unless waived by the Owner. 5.4.6The Comprehensive Automobile Liability Insurance policy will have limits of $1,000,000 combined single limits (CSL). 5.4.9This policy will include completed operations coverage/product liability coverage with limits of $1,000,000 combined single limits (CSL). I I I SECTION 00900 ADDENDA, MODIFICATIONS AND PAYMENT 00950 Contract Change Order 00960 Application for Payment I ,� 9/99 a R, C � 3 S N � N a a " o p F- A 0 � \ J F��- »>eeod aieor»ce>.e 000=odo�veoee=�eom o IIJ N M N N µ µ N N N N N N N N M N N µ M N N N µ N N N N M N N µ � e888888888g88888888888SS$S8$8888$8 8 45 NWNNMNN Nw MNNYNN YKNWNM MMNKNNNMNNN 0 3F 0 8 SS$8888888$8888888888888888 8 eeododdeddd do ecmocoddceopdecoedd> ci's N N w N N N N N N N N N N W N N N N N µ N K w W N N µ N N M N N N o N y � c U o g S 3 d'. � 5888888888S88S888$888$$8888888888 8 µ o 0 0 o e o 0 0 o e o o e o d e p e o o d o e v e e e o 0 0 0 0 W M NN Y N N N N N w N N N N N N N N N N N M N N M NN NN N M 0 w - � 9� 8 , 88885888888888888888$88888885888$ NN w N M Y N M M W Y N M K M M M N O O p p p p O O 6 6 6 6 O C O N N N N N N NN N Nw N N N N •888885888888BB8 N M M M M M N N M N N M M M M p S8S888888888588 S 8 ® M N NM N M N M N w N N M s u a �$ F � 88$88888888858$ 8 8 < g »eooee e d e e e e d M N N N N NN M N M N N . N a M e M C 9¢ uy�3 � SS$888885$SS888 a000e>.ee 8 8 oeecco M MNNNN NM M N NM µ N M w w y 4 3 888885888888$8S 8 8 Neoeoocodcio 000d N NNNNMNMNNMNNM o N d N d 7 p� C O pp O .g Gpb�7 O O o b 1z a � 7 _ V i < 6 a4 M MMNIi1 r f=H�MVIN�1M i,H�� N O 8 8 i 1 i 2002 CONCRETE PROJECT — PHASE I GENERAL REQUIREMENTS INDEX SECTION 01010 Summary of Work 01040 Coordination 01310 Construction Schedules 01330 Survey Data 01340 Shop Drawings 01410 Testing 01510 Temporary Utilities 01560 Temporary Controls 01700 Contract Closeout 01800 Method of Measurement and Basis of Payment e PAGE NUMBERS General Requirements 1-2 General Requirements 3-4 General Requirements 5-6 General Requirements 7 General Requirements 8-10 General Requirements 11-12 General Requirements 13 General Requirements 14-15 General Requirements 16 General Requirements 17 No Text The Contract, if awarded, will be on the basis of material and equipment described on the Drawings or specified in the Specifications without consideration of possible substitute or "or equal" items. Whenever it is indicated on the Drawings or specified in the Specifications that a substitute or "or equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the "effective date of the Agreement". The procedure for submittal of any such application by CONTRACTOR and consideration by Engineer is set forth in the General Conditions which may be supplemented in the General Requirements. 10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS 10.1. Each Bidder shall submit at the Bid opening to OWNER a list of subcontractors he principal proposes to use in the Work. Refer to Section 00430 contained within these Documents. 10.2. If OWNER or Engineer after due investigation has reasonable objection to any proposed Subcontractor, either may, before the Notice of Award is given, request the apparent successful Bidder to submit an acceptable substitute without an increase in Bid price. If the apparent successful Bidder declines to make any substitution, OWNER may award the contract to the next lowest responsive and responsible Bidder that proposes to use acceptable subcontractors. Subcontractors, suppliers, other persons or organization listed and to whom OWNER or Engineer does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER subject to revocation of such acceptance after the effective date of the Agreement as provided in the General Conditions. 10.3. CONTRACTOR shall not be required to employ any subcontractor, supplier or other persons or organizations against whom he has reasonable objection. The use of subcontractors listed by the Bidder and accepted by OWNER prior to the Notice of Award will be required in the performance of the Work. 11.0 BID FORM. 11.1. A copy of the Bid Form is bound in the Contract Documents which may be retained by the Bidder. A separate unbound copy is enclosed for submission with the Bid. 11.2. Bid Forms must be complete in ink or typed. All lump sum prices on the form must be stated in words and numerals; in case of conflict, words will take precedence. Unit prices shall govern over extensions of sums. 11.3. Bids by corporations must be executed in the corporate name by the president or a vice-president (or other appropriate officer accompanied by evidence of authority to sign) and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown below the corporate name. 7/96 Section 00100 Page 4 SECTION 01010 SUMMARY OF WORK 1.1 DESCRIPTION OF WORK A. This work shall consist of the removal and/or installation of concrete curbs, gutters, sidewalks, crosspans, aprons, drive approaches and pedestrian access ramps, and placement of temporary asphalt patching adjacent to new concrete, on designated streets in the City of Fort Collins. Specific locations are described in Section 02500, Quantity Estimate. B. Protection and Restoration. 1. Replace to equal or better conditions all items removed and replaced or damaged during construction. Restore all areas disturbed to match surrounding surface conditions. Also see tree protection standards. C. Construction Hours 1. Construction hours, except for emergencies, shall be limited to 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise authorized in writing by the Engineer. After hour equipment operation shall be in accordance with Section 1560. 2. Any work performed by the Contractor outside of the construction hours, whether or not authorized by the Engineer, shall entitle the Owner to deduct from compensation due to the Contractor sufficient funds to cover the Owner's costs in providing field engineering and/or inspection services because of such work. The cost for field engineering and inspection shall be $50.00 per hour. 1.2 NOTICES TO PRIVATE OWNERS AND AUTHORITIES A. Notify private owners of adjacent property, utilities, irrigation canal, and affected governmental agencies when prosecution of the Work may affect them. B. Give notification 48 hours in advance to enable affected persons to provide for their needs when it is necessary to temporarily deny access or services. C. Contact utilities at least 48 hours prior excavating near underground utilities. D. Contact all agencies at least 72 hours prior to start of construction. Notify all agencies of the proposed scope of work schedule and any items which would affect their daily operation. E. Rick Richter and/or Erika Keeton will be the ENGINEER (Project Engineer/Manager). Rick Richter 970-221-6798 Mobile 970-222-1132 Erika Keeton 970-221-6605 Mobile 970-222-0787 F. Names and telephone numbers of affected agencies and utilities in the area are listed below for Contractor's convenience. General Requirements - 1 UTILITIES Water: City of Fort Collins, Colorado 221-6681, Meter Shop 221-6759 Storm Sewer: City of Fort Collins, Colorado 221-6589 Sanitary Sewer: City of Fort Collins, Colorado 221-6681 Electrical: City of Fort Collins, Colorado 482-5922,221-8553 Gas: Public Service Company of Colorado 482-5922,221-8553 Telephone: Qwest Communications 484-0300,226-6310 Traffic Operations: City of Ft. Collins, Colorado 221-6608 Cable Television: AT&T 493-7400 *Utility Locates Under One -call System 1-800-922-1987 AGENCIES Safety: Occupational Safety and Health Administration (OSHA): 844-3061 Fire: Poudre Fire Authority Non -Emergency: 221-6581 Emergency: 911 Police: City of Fort Collins Police Department Non -Emergency: 221-6550 Emergency: 911 Postmaster: US Postal Service: 225-4111 Transportation: Transfort: 221-6620 Traffic Engineering: 221-6608 END OF SECTION General Requirements - 2 Larimer County Sheriffs Department: Non -Emergency: 221-7177 Ambulance: Poudre Valley Hospital Non -Emergency: 484-1227 Emergency: 911 SECTION 01040 COORDINATION 1.1 GENERAL CONTRACTOR RESPONSIBILITIES A. Coordinate operations under contract in a manner which will facilitate progress of the Work. The Contractor shall also coordinate with the Landscape Contractor whose Work is separate from the General Contractor's contract. B. Conform to the requirements of public utilities and concerned public agencies in respect to the timing and manner of performance of operations which affect the service of such utilities, agencies, or public safety. C. Coordinate operations under contract with utility work to allow for efficient completion of the Work. D. Coordinate all operations with the adjoining property owners, business owners, and surrounding neighborhoods to provide satisfactory access at all times and keep them informed at all times. 1.4 CONFERENCES A. A Pre -construction Conference will be held prior to the start of construction. 1. Contractor shall participate in the conference accompanied by all major Subcontractors, including the Traffic Control Supervisor assigned to the project. 2. Contractor shall designate/introduce Superintendent, and major Subcontractors supervisors assigned to project. 3. The Engineer shall invite all utility companies involved. 4. The Utilities will be asked to designate their coordination person, provide utility plans, and their anticipated schedules. 5. The Engineer shall introduce the project Representatives. B. Additional project coordination conferences will be held prior to start of construction for coordination of the Work, refining project schedules, and utility coordination. C. Engineer may hold coordination conferences to be attended by all involved when Contractor's operations affects, or is affected by, the work of others. 1. Contractor shall participate in such conferences accompanied by Subcontractors as required by the Engineer. 1.5 PROGRESS MEETINGS A. Contractor and Engineer's Project Representatives shall schedule and hold regular progress meetings at least weekly and at other times as requested by the Engineer or required by the progress of the Work. B. Attendance shall include: 1. Contractor and Superintendent. 2. Owner's Representatives. 3. Engineer and Resident Project Representative. 4. Traffic Control Supervisor 5. Others as may be requested by Contractor, Engineer or Owner. General Requirements - 3 B. Superintendence: The Contractor shall employ a full time Superintendent to monitor and coordinate all facets of the Work. The Superintendent shall have adequate experience to perform the duties of Superintendent. C. Contractor's quality control system is the means by which he assures himself that his construction complies with the requirements of the Contract Documents. Controls shall be adequate to cover all construction operations and should be keyed to the proposed construction schedule. D. Records: Maintain correct records on an appropriate form for all inspections and tests performed, instructions received from the Engineer and actions taken as a result of those instructions. These records shall include evidence that the required inspections or tests have been performed (including type and number of inspections or test, nature of defects, causes for rejection, etc.) proposed or directed remedial action, and corrective action taken. Document inspections and tests as required by each section of the Specifications. Provide copies to Engineer weekly. END OF SECTION General Requirements - 12 SECTION 01510 TEMPORARY UTILITIES 1.1 UTILITIES A. Furnish all utilities necessary for construction. B. Make arrangements with Owner as to the amount of water required and time when water will be needed. 1. Meters may be obtained through the Water Utility Meter Shop at 221-6759 2. Unnecessary waste of water will not be tolerated. C. Furnish necessary water trucks, pipes, hoses, nozzles, and tools and perform all necessary labor. 1.2 SANITARY FACILITIES A. Furnish temporary sanitary facilities at each site for the needs of construction workers and others performing work or furnishing services on the Project. B. Properly maintain sanitary facilities of reasonable capacity throughout construction periods. C. Enforce the use of such sanitary facilities by all personnel at the site. D. Obscure from public view to the greatest practical extent. END OF SECTION General Requirements - 13 SECTION 01560 TEMPORARY CONTROLS 1.1 NOISE CONTROL A. Take reasonable measures to avoid unnecessary noise when construction activities are being performed in populated areas. B. Construction machinery and vehicles shall be equipped with practical sound muffling devices, and operated in a manner to cause the least noise consistent with efficient performance of the. Work. C. Cease operation of all machinery and vehicles between the hours of 6:00 p.m. and 7:00 a.m. 1.2 DUST CONTROL A. Dusty materials in piles or in transit shall be covered when necessary to prevent blowing. B. Earth and road surfaces subject to dusting due to construction activities and detouring of traffic shall be kept moist with water or by application of a chemical dust suppressant. 1. Chemical dust suppressant shall not be injurious to existing or future vegetation. 1.3 POLLUTION CONTROL A. Prevent the pollution of drains and water courses by sanitary wastes, concrete, sediment, debris and other substances resulting from construction activities. 1. Retain all spent oils, hydraulic fluids and other petroleum fluids in containers for disposal off the site. 2. Prevent sediment, debris or other substances from entering sanitary sewers, storm drains and culverts. 1.4 EROSION CONTROL A. Take such measures as are necessary to prevent erosion of soil that might result from construction activities. Measures in general will include: a. Control of runoff. b. Trapping of sediment. C. Minimizing area and duration of soil exposure. d. Temporary materials such as hay bales, sand bags, plastic sheets, riprap or culverts to prevent the erosion of banks and beds of watercourses or drainage swales where runoff will be increased due to construction activities. B. Preserve natural vegetation to greatest extent possible. C. Locate temporary storage and route construction traffic so as to preserve vegetation and minimize erosion. D. Comply with the City of Fort Collins' Storm Drainage Erosion Control Manual. General Requirements - 14 1.5 TRAFFIC CONTROL A. Maintain traffic control in accordance with the "Manual of Uniform Traffic Control Devices' (MUTCD), the City of Fort Collins' "Work Area Traffic Control Handbook", and the Larimer County Urban Area Street Standards. In the event of a conflict between the MUTCD criteria and the City's criteria, the City's criteria shall govern. 1.6 HAUL ROUTES The Engineer reserves the right to set haul routes in order to protect pavements, both new and old, from heavy loads. These pavements may include, but are not limited to, recently constructed pavements, recently overlaid pavements, and/or pavements whose condition would be significantly damaged by heavy loads. END OF SECTION General Requirements - 15 SECTION 01700 CONTRACT CLOSEOUT 1.1 CLEANING AND RESTORATION A. Return the premises and adjacent properties to conditions existing or better than existing at the time the work was begun. This will include providing labor, equipment and materials for cleaning, repairing and replacing facilities damaged or soiled during construction. The Engineer will be the judge of the degree of restoration required. 1.2 PROJECT RECORD DOCUMENTS A. Maintain on the job site, and make available to the Engineer upon request, one current marked -up set of the drawings which accurately indicate all approved variations in the completed work that differ from the design information shown on the drawings. Further, these drawings should reflect all underground obstacles encountered. B. These record drawings along with any survey records, photographs and written descriptions of said work as may be required by the Engineer shall be submitted prior to project acceptance. END OF SECTION General Requirements - 16 SECTION 01800 METHOD OF MEASUREMENT AND BASIS OF PAYMENT L1 DEFECTIVE WORK A. Owner will not pay for defective work and will not pay for repair or additional work required to bring the project to a point of acceptance. 1.2 BID PRICE A. The Total Bid Price covers all Work required by the Contract Documents. All work not specifically set forth as a pay item in the Bid Form shall be considered a subsidiary obligation of Contractor and all costs in connection therewith shall be included in the prices bid for the various items of Work. B. Prices shall include all costs in connection with the proper and successful completion of the Work, including furnishing all materials, equipment and tools; and performing all labor and supervision to fully complete the Work. C. Unit prices shall govern over extensions of sums. D. Unit prices shall not be subject to renegotiation. 1.3 ESTIMATED QUANTITIES A. All quantities stipulated in the Bid Form at unit prices are approximate and are to be used only as a basis for estimating the probable cost of the Work and for the purpose of comparing the bids submitted to the Work. The basis of payment shall be the actual amount of materials famished and Work done. B. Contractor agrees that he will make no claim for damages, anticipated profits, or otherwise on account of any difference between the amount of Work actually performed and materials actually furnished and the estimated amount therefor. END OF SECTION General Requirements - 17 No Text 11.4. Bids by partnerships must be executed in the partnership name and signed by a partner, his title must appear under his signature and the official address of the partnership must be shown below the signature. 11.5. Bids by joint venture shall be signed by each participant in the joint venture or by an authorized agent of each participant. The full name of each person or company interested in the Bid shall be listed on the Bid Form. 11.6. The Bid shall contain an acknowledgement of receipt of all Addenda (the numbers of which must be filled in on the Bid Form). 11.7. No alterations in Bids, or in the printed forms therefore, by erasures; interpolations, or otherwise will be acceptable unless each such alteration is signed or initialed by the Bidder; if initialed, OWNER may require the Bidder to identify any alteration so initialed. 11.8. The address and telephone number for communications regarding the Bid shall be shown. 12.0 BID PRICING. Bids must be priced as set forth in the Bid Schedule or Schedules. 13.0 SUBMISSION OF BIDS. 13.1. Bids shall be submitted at the time and place indicated in the _= Invitation to Bid and shall be enclosed in an opaque sealed envelope marked with the Project title, Bid No., and name and address of the Bidder and accompanied by the Bid Security, Bid Form, Bid Bond, Statement of Bidders _t Qualifications, and Schedule of Subcontractors as required in Section _E 00430. If the Bid is sent through the mail or other delivery system, the •} sealed envelope shall be enclosed in a separate envelope with the notation "BID ENCLOSED" on the face of it. 13.2. Bids shall be deposited at the designated location prior to the time and date for receipt of Bids indicated in the Invitation to Bid, or any extension thereof made by addendum. Bids received after the time and date for receipt of Bids will be returned unopened. Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. 13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and will not receive consideration. 13.4. No Bidder may submit more than one Bid. Multiple Bids under different names will not be accepted from one firm or association. 14.0 MODIFICATION AND WITHDRAWAL OF BIDS. 7/96 Section 00100 Pag2 5 SECTION 02000 PROJECT SPECIFICATIONS The Colorado Division of Highways "Standard Specifications for Road and Bridge Construction", 1999, and the Larimer County "Urban Area Street Standards", January 2001 (hereafter referred to as the "Standard Specifications") are made apart of this Contract by this reference, except as revised herein, and are hereby adopted as the minimum Standard Specifications of Compliance for this project. In those instances where the Standard Specifications conflict with any ofthe provisions ofthe preceding Sections, the preceding Sections shall govern. INDEX OF REVISIONS SECTION 104 Traffic and Parking Control 105 Cooperation Between Contractors 105 Inspection of Work 105 Maintenance During Construction 107 Protection and Restoration of Property and Landscape 108 Prosecution and Progress 201 Clearing and Grubbing 212 Seeding, Fertilizer, and Sodding 403 Hot Bituminous Pavement —Patching 604 Inlets 608 & 609 Sidewalks, Curb and Gutter, Drive Approaches, Aprons, Crosspans, and Concrete Pavement 614 Traffic Control No Text REVISION OF SECTION 104 TRAFFIC AND PARKING CONTROL Section 104 of the Standard Specifications is hereby revised as follows: Subsection 104.04 shall include the following. It shall be the Contractor's responsibility to clear parking from the streets when such parking will interfere with the work. Prior to work that requires the street(s) to be closed to parking and/or traffic, the street(s) shall be posted for "NO PARKING". The placement of these signs shall take place at least 24 hours prior to the commencement of work and shall clearly show the type of work, and the day, date and times that the message on the sign is in effect. (For example, if a street is to be patched on Wednesday, July 2, the street shall be posted no later than Tuesday, July 1, by 7:00 a.m. with a sign that reads similar to "NO PARKING, WEDNESDAY, JULY 2, 7:00 A.M. TO 6:00 P.M., PATCHING.) See sample "NO PARKING" sign. "NO PARKING" signs shall remain in place until the street is opened to traffic and all clean up operations completed. All information on the "NO PARKING" signs, with the exception of the date, shall be in block letters permanently affixed to the sign. Any information added to a sign, such as dates, shall be clearly legible and written in block style letters. The "NO PARKING" signs shall be in effect for one or two days only. Any work done by the Contractor without traffic control will not be paid for under the terms of this Contract. The Contractor will not be paid for traffic control costs incurred during Contractor caused delays. At or near the end of each work day, a representative of the Contractor, the Traffic Control Supervisor, and the Engineer will meet to discuss the progress of the work and the placement of traffic control devices including "NO PARKING" signs. Any necessary adjustments shall be made. The Contractor shall also review at this time with the Engineer the proposed means of handling parking and traffic control for upcoming work. It is the responsibility of the Contractor to minimize any inconvenience to the public as a result of this work. At the above referenced meeting, the quantity of traffic control devices used that day shall be agreed upon by the Contractor and the Engineer. The Contractor shall utilize forms approved by the Engineer for the tabulation of Traffic Control Devices utilized. The Contractor shall maintain access at all times to all businesses within the project. Any changes in the traffic control, including additional signs, barricades, and/or flaggers needed in the field shall be immediately implemented as directed by the Engineer. The cost for traffic control is covered in "Revision of Section 614, Traffic Control Devices" found herein. Project Specificatim — Page 1 of 25 NO PARKING WED., JULY 2 7mmOO AM - 6:00 PM PATCHING Project Specfcatiom — Page 2 of 25 REVISION OF SECTION 105 COOPERATION BETWEEN CONTRACTORS Section 105 of the Standard Specifications is hereby revised as follows: Subsection 105.07 shall include the following: Concrete construction and/or reconstruction operations at intersections may involve the destruction and replacement of traffic signal loop detectors. The existing traffic signal loop detectors shall be removed by the contractor at no additional cost. New loop detectors may be installed at other intersections where they do not now exist. New and replacement loop detectors will be installed by the City Traffic Division. The Contractor shall cooperate with the schedule of this work to insure the timely installation of new loop detectors. Also, the Contractor shall coordinate with the City Traffic Division to insure that any cleanup required after the installation of the loop detectors will be completed before concrete placement operations begin. Project Specifications — Page 3 of 25 REVISION OF SECTION 105 INSPECTION OF WORK Section 105 of the Standard Specifications is hereby revised as follows: Subsection 105.11 shall include the following: The Contractor shall keep the Engineer informed of his future construction operations to facilitate scheduling of required inspection, measuring for pay quantities, and sampling. The Contractor shall notify the Engineer a minimum of 24 hours in advance of starting any construction operation that will require inspection, measuring for pay quantities, or sampling. Failure of the Contractor to provide such notice will relieve the owner and the Engineer from any responsibility for additional costs or delays caused by such failure. Inspection of the work or materials shall not relieve the Contractor of any of his obligations to fulfill his contract as prescribed. Work and materials not meeting specifications shall be corrected and unsuitable work ormaterialsmay be rejected, notwithstanding that such work or materials have been previously inspected by the Engineer or that payment therefore has been included in the progress estimate. J Project Specifimtiew — Page 4 of 25 REVISION OF SECTION 105 MAINTENANCE DURING CONSTRUCTION Section 105 of the Standard Specifications is hereby revised as follows: Subsection 105.14 shall include the following: The roadway area, including curb, gutter, and sidewalk, adjacent to and through the construction area shall be cleaned of debris by the Contractor at the earliest opportunity, but in no case shall the area be left uncleaned after the completion of the day's work. It shall be the Contractor's responsibility to provide the necessarymanpower and equipment to satisfactorily clean the roadway area. The Contractor shall utilize a combination of pick-up brooms, side brooms and/or other equipment as needed to clean the streets. All sweeping and clean up equipment shall be approved by the Engineer prior to the commencement of work. The Contractor shall maintain the streets during the construction process as prescribed above. If a street requires additional sweeping by City forces, the Owner shall deduct from compensation due the Contractor sufficient funds to cover the Owner's cost to provide said service. All cost of maintaining the work during construction and before the project is accepted, will not be paid for separately, but shall be included in the work. Project Specifications — Page 5 of 25 REVISION OF SECTION 107 PROTECTION AND RESTORATION OF PROPERTY AND LANDSCAPE Section 107 of the Standard Specifications is hereby revised as follows: Subsection 107.12 shall include the following: The fact that any underground facility - sprinkler systems, utility services, etc. - is not shown on the plans, details, or construction documents shall not relieve the Contractor of his responsibilities as provided for in the Contract. It shall be the Contractor's responsibility, pursuant thereto, to ascertain the location of such underground improvements which may be subject to such damage by reason of his operations. Any pruning of vegetation shall require the written permission of the property owner and/or the Engineer. If the area to be repaired is five (5) inches or less in width, the Contractor shall clean the area of all debris (i.e. concrete, road base, etc.) to a minimum depth of four (4) inches, prepare all edges to be clean and vertical, and place (see below) and compact topsoil. The topsoil shall be compacted utilizing a hand operated roller or other method approved by the Engineer. In areas greater than 5 inches, the Contractor shall clean and prepare the area along the entire length of the repair location as stated above to a minimum of one (1) foot, place sod over the entice area, water once, and notify the property owner in writing of the nature of the work that has taken place and that the sod will be watered only once. For concrete repair locations, the placement of topsoil (backfill) shall be completed within two (2) working days of the placement of the concrete. The topsoil shall consist of loose friable loam reasonably free of admixtures of subsoil, refuse, stumps, roots, rocks, brush, weeds, heavy clay, hard clods, toxic substances or other material which would be detrimental to the proper development of vegetative growth. The material to be utilized shall be approved by the Engineer prior to placement. The topsoil shall be in a relatively dry state and placed during dry weather. The topsoil shall be fine graded to eliminate rough and low areas and ensure positive drainage. The existing levels, profiles and contours shall be maintained. If the area to be repaired is only damaged on the surface, the Contractor shall remove the damaged areas of sod to a depth that will allow new sod to be placed, place new sod, water once and notify the property owner in writing of the nature of the work that has taken place and the fact that the sod will be watered only once. The minimum overall width of the area to be sodded shall be one (1) foot. For concrete repair locations, the placement of sod shall be completed by the end of the first working day of the week following the placement of the concrete. Sprinkler systems - Sprinkler systems designated for relocation shall be capped off at the limits of construction and protected from damage by the contractor. Sprinkler heads shall be salvaged and stockpiled on each property for use when reconstructing the sprinkler systems. Sprinkler systems damaged outside of the construction limits as a result of construction operations shall be replaced at the Contractor's expense, within three (3) working days of written notification from the Engineer. In areas where the Engineer directs new work or the reconstruction areas require grade adjustment, the placement of topsoil, sod and sprinkler relocation will be provided by the City under separate contract. Project Specificatiow — Page 6 of 25 REVISION OF SECTION 107 PROTECTION AND RESTORATION OF PROPERTY AND LANDSCAPE All landscaping that is damaged due to construction operations shall be replaced by the Contractor at his expense unless a written waiver is obtained from the property owner and submitted to the Engineer. Re -sodded lawns shall be watered once by the Contractor. All costs for protecting and restoring landscaping and lawns shall be considered a subsidiary obligation of the Contractor in connection with the various items of the Work, and no measurement or payment shall be made separately for the protection and restoration of landscaping and lawns. All restoration of landscaping and lawns damaged by construction operations other than concrete repair shall take place within three (3) working days from the date of damage. In areas where the Engineer directs new work or the reconstruction areas require grade adjustment, the placement of topso44 sod and sprinkler relocation will be provided by the City under separate contract All labor, materials, tools, equipment, incidentals, and work involved in protecting or repairing underground facilities shall be considered incidental to the work being done, and shall not be measured and paid for separately. Project Specificatio — Page 7 of 25 REVISION OF SECTION 108 PROSECUTION AND PROGRESS Section 108 of the Standard Specifications is hereby revised as follows: Subsection 108,04 shall include the following: The work shall be completed within the following calendar months: All Work is to be complete in sixty-five (65) working days. Work in the following areas MUST be complete on or before August 16, 2002: Hillcrest Grandview Crestmore Fairbrooke Goldeneye The remaining areas below shall be completed within the 2002 construction season and within the sixty-five working day time frame: Hampshire Tenth Green Willox Elizabeth Street Prospect Park Subsection 108.06 shall include the following: A schedule ofwork must accompany any bid, and shall include number of working days per area to complete all unit work items covered by the contract. Vicinity maps of each area are included in Section 03500, Project Maps. The schedule should take any priorities into consideration. The schedule should also include projected start and end dates. Individual street quantities are described in Section 02500, Quantity Estimates. Prior to award, mutually acceptable milestones shall be determined by the Contractor and the City based on the schedule of working days discussed above. Subsection 108.07 shall include the following: Failure to meet the agreed upon milestones or fully complete the project in sixty five (65) working days, shall result in damages assessed against the Contractor. At the City's option, liquidated damages in the amount of $1000.00 per day may be retained from any monies due the Contractor, or the City may retain an additional contractor(s) to complete the work, or portion thereof, and retain any costs incurred above and beyond the bid prices of the Contractor from any monies due the Contractor in lieu of liquidated damages. Project Specifications — Page 8 of 25 r 14.1. Bids may be modified or withdrawn by an appropriate document duly executed (in a manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. E 14.2. Bids may also be modified or withdrawn in person by the Bidder or an authorized representative provided he can prove his identity and authority at any time prior to the opening of Bids. 14.3. Withdrawn Bids may be resubmitted up to the time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders. 15.0 OPENINGS OF BIDS. Bids will be opened and (unless obviously non -responsive) read aloud publicly as indicated in the Invitation to Bid. An abstract of the amounts of the Base Bids and major alternates (if any) will be made available after the opening of Bids. 16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE. All Bids shall remain open for forty-five (45) days after the day of the Bid Opening, but OWNER may, in his sole discretion, release any Bid and return the Bid Security prior to that date. 17.0 AWARD OF CONTRACT. 17.1. OWNER reserves the right to reject any and all Bids, to waive any and all informalities not involving price, time or changes in the Work, to negotiate contract terms with the Successful Bidder, and the right to _l disregard all nonconforming, nonresponsive, unbalanced or conditional Bids. . Also, OWNER reserves the right to reject the Bid of any Bidder if OWNER believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by OWNER. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. 17.2. In evaluating Bids, OWNER will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award. 17.3. OWNER may consider the qualification and experience of Subcontractors, Suppliers, and other persons and organizations propo:-d for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations is submitted as requested by OWNER. OWNER also may consider the operating costs, maintenance 7/96 Section 00100 Page 6 REVISION OF SECTION 201 CLEARING AND GRUBBING Section 201 of the Standard Specifications is hereby revised as follows: Subsection 201.03 shall be amended to include the following: When any tree roots are encountered during construction operations, the Contractor shall notify the Engineerprior to any root removals. The Engineer and the City Forester's representative shall then make a determination regarding removal. Tree roots shall be removed with a sharpened, sanitized saw, cut orthogonally to its longitudinal axis as closely as practical, to leave the freshly cut root surface in a clean and smooth condition. Axes, or other blunt objects shall not be used to cut tree roots. Where it is anticipated that tree roots may be encountered, great care shall be taken by the Contractor to prevent any damage to the roots with tools or equipment. f All costs for removing tree roots shall be considered a subsidiary obligation of the Contractor in connection with the various items of the Work, and no measurement or payment shall be made separately for the removal of tree roots. Project SpecP;caliom — Page 9 of 25 REVISION OF SECTION 212 SEEDING, FERTIIdZER AND SODDING Section 212 of the Standard Specifications is hereby revised as follows: Subsection 212.01 is revised to include the following: This work shall consist of soil preparation and furnishing and placing topsoil and blue grass sod, in accordance with these specifications, accepted horticulture practice, and in reasonably close conformity with the locations and details shown on the plans or as designated by the Engineer. See "Protection and Restoration of Property" found herein. Subsection 212.02 is revised to include the following: Topsoil Topsoil shall conform to the requirements of 'Protection and Restoration of Property" found herein Sod Bluegrass sod shall be nursery grown, 99%Kentucky Blue Grass and 99% weed free. Other sod type may be used only if approved in writing by the Engineer. The 1 % allowable weeds shall not include any undesirable perennial or annual grasses or plants. Soil thickness of sod cuts shall not be less than 3/4 inch nor more than one inch. Sod shall be cut in uniform strips with minimum dimensions of 12 inches in width and 48 inches in length. The Contractor shall submit a sample of the sod he proposes to furnish. Said sample shall serve as a standard. Any sod furnished, whether in place or not, that is not up to the standard of the sample may be rejected. Sod that has been cut for more than 24 hours shall not be used. Each load of sod shall be accompanied by a certificate from the grower stating the type of sod, and the date and time of cutting. Subsection 212.05 is revised to include the following: Sodding: (a) Soil Preparation. The area shall be cleaned with a minimum depth of four (4) inches (where topsoil does not exist) and a minimum width of one (1) foot, all irregularities in the ground surface shall be removed, and all edges clean and vertical. Sticks, stones, debris and other similar material more than 1/2 inch in diameter shall be removed. Any objectionable depressions or other variances from a smooth grade shall be corrected. (b) Topsoil Placement Topsoil shall be placed and compacted with a minimum depth of four (4) inches. The amount of compaction required shall be as directed by the Engineer. (c) Sod Placement The minimum width for sod shall be one (1) foot. The area to be sodded shall be smooth. The sod shall be laid by staggering joints with all edges touching. On any slopes, the sod shall run approximately parallel to the slope contours. The Contractor shall water the sod once and notify the property owner in writing of the nature of the work that has taken place and that the sod will only be watered once. Sod placement/replacement required due to Contractor negligence shall follow the requirements ofthis section, but will not be measured and paid for under the terms of this contract. Project Specifications — Page 10 of 25 I I REVISION OF SECTION 212 SEEDING, FERITLIZER AND SODDING Subsection 212.08 is revised to include the following: No measurement for payment shall be made for re -sodding lawn damaged by the Contractor adjacent to new concrete, when the grade of the existing lawn reasonably matches the grade of the new concrete. Re-soddingm this instance shall be considered incidental to the work being performed. No measurement for payment shall be made when the re -sodding is incidental to the work performed or is contained within any other pay item in section 02000. Project Specifications — page 11 of 25 REVISION OF SECTION 403 HOT BITUMINOUS PAVEMENT - PATCHING Section 403 of the Standard Specifications is hereby revised as follows: In all concrete repair locations, the Contractor shall remove no more than six (6) inches of asphalt pavement. The pavement areas shall be temporarily patched with a minimum of two (2) inches of hot mix asphalt. These locations shall he paid under the Contract Unit Price for Temporary Patching. Subsection 403.04 is revised to include the following: Temporary Patching will be measured by the ton. Pavement cutting, excavation, subgrade preparation, haul, disposal, and bituminous materials will not be measured or paid for separately, but shall be included in the contract price for Temporary Patching. Load slips shall be consecutively numbered for each day and shall include the batch time. Subsection 403.05 is revised to include the following: The accepted quantities for Temporary Patching will be paid for at the Contract Unit Price per Ton. Payment will be made under: Pay Item Pay Unit 403.50 Temporary Patching Ton The above prices and payments shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all the work involved in Temporary Patching, including pavement cutting, excavation, haul, disposal, surface preparation, and bituminous materials, complete-jn-place, as shown on these plans, as specified in these specifications, and as directed by the Engineer. Project Specifications — Page 12 of 25 REVISION OF SECTION 604 INLETS Section 604 of the Standard Specifications is hereby revised as follows: Subsection 604.01 is revised to include the following: This work shall consist of the removal and replacement of existing inlets and/or inlet decks, in accordance with these specifications, and in reasonably close conformity with the lines and grades shown on the plans or established by the Engineer. Subsection 604.05 is revised to include the following: As part of the "Reconstruct Inlet Deck" items, the concrete around the inlet as marked shall be removed and hauled from the site. The existing frame, grate, and angle iron face shall be salvaged and reused in the reconstruction of the inlet deck. All reinforcing steel encountered during removal shall be replaced with new steel of the grade and size as shown on the detail found herein. Reconstruct Inlet Deck shall include the deck reconstruction of existing inlets, including two, three and a half foot (3.5) transitions, measured from inside face of box, on each side. Inlets with openings greater than those defined on the detail shall be paid for as Reconstruct Inlet Deck, per each, plus Inlet Deck - Additional Opening, per lineal foot. Subsection 604.07 is revised to include the following: When concrete is to be removed and replaced around an existing grate without disturbing the deck or box, this shall not constitute Reconstruct Inlet Deck. These locations shall be measured and paid for separately under the items described in Revision of Sections 608 and 609 - Sidewalks, Curb and Gutter, Drive Approaches, Aprons and Crosspans found herein. Subsection 604.08 is revised to include the following: Payment will be made under: PAY ITEM 604.10 Reconstruct Inlet Deck - Catch Basin Each 604.11 Reconstruct Inlet Deck - Catch Basin Additional Foot Opening Lineal Foot 604.12 Reconstruct Curb Inlet Deck 4' Opening Each 604.13 Reconstruct Curb Inlet Deck - 4' Opening Additional Foot Opening Lineal Foot 604.14 Type 13 - Curb Inlet with Frame, Grate, and Adjustable Curb Bonnet Each 604.15 Concrete Sidewalk Culvert Each 604.16 Metal Sidewalk Culvert - %,, Plate Each Project Specificatiom — Page 13 of 25 REVISION OF SECTION 604 INLETS 604.17 Additional Square Foot W Plate Square Foot The above prices and payments shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and for doing all work involved in Inlets, including demolition, disposal, reinforcement and replacement, complete -in -place, as specified in these specifications, as shown on the plans, and as directed by the Engineer. Project SpedBimfio - Page 14 of 25 REVISION OF SECTIONS 608 AND 609 SIDEWALKS, CURB & GUTTER, DRIVE APPROACHES, APRONS, CROSSPANS, AND CONCRETE PAVEMENT Sections 608 and 609 of the Standard Specifications are to be deleted and replaced with the City of Fort Collins "Design Criteria and Standards for Streets" July 1996, except as noted herein. Monolithic hybrids of curb, gutter, sidewalk and highback vertical curb and gutter will be replaced using the same configuration as it was originally installed, unless a flaw in its engineering should become apparent. In these cases the design may be modified by the Engineer. The finished exposed surface and edging of the concrete will match as closely as possible the surface treatment of the surrounding existing concrete. The mix designs for all types of concrete to be utilized shall be determined by the Contractor and submitted to the Engineer and approved a minimum of one week prior to the beginning of construction. Cement used shall conform to the Standard Specification for Portland Cement, ASTM C 150-85, AASHTO M85, Type I, Type Ml, or Type III. ° The air content shall be four (4) to seven (7) percent. "High Early" concrete shall be used for concrete repair locations. "High Early" concrete shall have a specified compressive strength of 4000 psi and a minimum 48 hour compressive strength of 3000 psi. The type of concrete used for a particular location shall be approved by the Engineer. See also Section 2.05,'Rigid Pavement Design', and Section 4.2.4., 'Concrete Streets', of the City of Fort Collins Design Criteria and Standards for Streets." Water Reducing Agents shall conform to ASTM C 494-82. Accelerating Agents shall conform to ASTM C 494-82. Calcium Chloride shall not be utilized as an accelerating agent. The Contractor shall famish a load slip containing the information required by AASHTO M157, Section 13, Subsection 13.1 and 13.2, with each batch of concrete. In addition, the type of concrete (mix code) shall be shown on each load slip. Concrete delivered without a load slip containing complete information as specified will be subject to rejection. In locations where concrete pavement is replaced, the new pavement shall have a minimum thickness of 7" or a thickness of I" thicker than the existing adjacent pavement slab. Existing pavement shall be saw cut to obtain a straight and neat edge for paving and shall be deep enough to cut through the entire pavement thickness. Alljoints shall be sealed with an asphalt, or approved equal, filler compound. The top of the new pavement shall be even with the existing concrete pavement. The concrete shall be consolidated with a mechanical vibrator. All construction joints shall be doweled except for expansion joints and joints along existing curb and gutter. In locations where concrete pavement is being replaced, the construction joint (s) shall be constructed in accordance with the detail for "Concrete Construction Joint" contained herein. This item will not be measured or paid for separately under the terms of this contract. The maximum spacing for transverse joints in crosspans and concrete pavement shall be ten (10) feet. Curing materials shall be white pigmented liquid linseed oil based or paraffin based curing compound, and shall conform to ASTM Specification C 309-81 Type II, Class B. The application rate for curing compound shall be 150 sq. ft./gal. for all concrete. The curing compound shall be applied immediately upon completion of the finishing. In locations where a portion of the apron and/or crosspan, the apron or crosspan only are being replaced, or a crosspan is poured in sections, the construction joint (s) shall be constructed in accordance with the detail for "Concrete Construction Joint" contained herein. This item will not be measured or paid for separately under the terms of this contract. Project Spwfflmtio — Page 15 of 25 REVISION OF SECTIONS 608 AND 609 SIDEWALKS, CURB & GUTTER, DRIVE APPROACHES, APRONS, CROSSPANS, AND CONCRETE PAVEMENT Aggregate Base Course shall meet the grading requirement for Class 5 (Road Base) or Class 1 (Pit Run) Aggregate Base Course. Class 5 Aggregate Base Course shall be used in all locations where the depth is less than two feet. In locations where the depth is greater than two feet, both Class 1 and Class 5 Aggregate Base Course shall be used as directed by the Engineer. Restoration of landscape shall be in accordance with "Revision of Section 107 - Protection and Restoration of Property and Landscape" found herein. The time framefor restoration shall be within two (2) working days from the timethe concrete was placed for backfill with topsoil and by no later than the end of the first working day of the following week for sod replacement. The Contractor shall be responsible for the protection of the subgrade/base course until the concrete is placed. The Contractor shall protect the concrete against moisture loss, rapid temperature change, rain, flowing water, mechanical injury, pedestrian and vehicular traffic, and Contractor's equipment for a minimum of 36 hours after the placement ofcuring compound for 48 hour high early concrete. Asphalt patching against fresh concrete shall not be permitted during the time frames for protection of concrete stated above. The debris immediately adjacent to a concrete repair location shall be completely cleaned up on the work day following the placement of the concrete. If required, the concrete shall be protected as stated above. Any damage caused during the cleanup process shall be the Contractor's responsibility. The Contractor shall utilize forms approved by the Engineer for the tabulation of concrete quantities. Payment will be made under: PAY ITEM 608.01 Remove and Haul Fillets EA 608.02 Apron - Remove & Replace SF 608.03 Crosspan - Remove & Replace SF 608.04 Driveover Curb, Gutter and 4" Sidewalk Remove & Replace LF 608.05 Driveover Curb, Gutter and 6" Sidewalk Remove & Replace LF 608.06 Driveover Curb and Gutter - No Sidewalk Remove & Replace LF 608.07 Driveover Curb, Gutter and Drive Approach Remove and Replace LF 608.08 Vertical Curb, Gutter and 4" Sidewalk Remove & Replace LF Project Specifications — Page 16 of 25 REVISION OF SECTIONS 608 AND 609 SIDEWALKS, CURB & GUTTER, DRIVE APPROACHES, APRONS, CROSSPANS, AND CONCRETE PAVEMENT PAY ITEM UNIT 608.09 Vertical Curb, Gutter and 6" Sidewalk Remove & Replace LF 608.10 Vertical Curb and Gutter - No Sidewalk Remove & Replace LF 608.11 Vertical Curb, Gutter and Drive Approach Remove & Replace LF 608.12 Vertical Curb, Gutter and Drive Approach No Sidewalk - Remove & Replace LF 608.13 Vertical Outfall Curb and Gutter Remove & Replace LF 608.14 Hollywood Curb, Gutter and 4" Sidewalk LF Remove & Replace 608.15 Hollywood Curb, Gutter and 6" Sidewalk LF Remove & Replace 608.16 Hollywood Curb and Gutter - No Sidewalk LF Remove & Replace 608.17 Hollywood Curb, Gutter and Drive Approach Remove and Replace LF 608.18 Highback Curb and Gutter - No Sidewalk LF I- Remove & Replace 608.19 Highback Curb, Gutter and Drive Approach LF Remove & Replace 608.20 Pedestrian Access Ramp, Driveover Curb Remove & Replace LF 608.21 Pedestrian Access Ramp, Vertical Curb Remove & Replace LF 608.22 Pedestrian Access Ramp, Hollywood Curb Remove and Replace LF 3 j 608.23 Pedestrian Access Ramp, Highback Curb Remove and Replace SF f 608.24 i 4" Flatwork - Remove & Replace SF 608.25 6 " Flatwork - Remove & Replace SF - Project Specflimtio — Page 17 of 25 REVISION OF SECTIONS 608 AND 609 SIDEWALKS, CURB & GUTTER, DRIVE APPROACHES, APRONS, CROSSPANS, AND CONCRETE PAVEMENT PAY ITEM 608.26 Replace Flatwork - I" Additional Depth SF 608.27 4' Valley Pan - 6" Depth SF 608.28 Aggregate Base Course - CIP TON 608.29 Aggregate Base Course — Placement Only TON 608.30 8" Alley Paving Remove & Replace SF 608.31 Highback Alley Approach(8") Remove & Replace LF 608.32 Expansion & Caulking LF Sawcutting shall be considered a subsidiary obligation of the Contractor, and shall not be measured or paid for separately under the terms of this contract. Pay Item 608.23, Pedestrian Access Ramp, Highback Curb, shall be measured by the square foot. The length shall be measured from the lip of the gutter to the top of the transition at the back of the ramp, and the width shall be measured at the midpoint. Highback Curb, Gutter and Drive Approach and I4ighback Alley Approach shall include 4 feet behind the back of the curb. Expansion joint material shall be installed every 500' in long runs and between new structure slabs and existing concrete slabs, where called for and around fire hydrants, poles, inlets, sidewalk underdrains, mid -block ramps, radius points at intersections, and other fixed objects, i.e. ends of sidewalk slabs and curbs. Expansion joint material must be set vertical and installed in accordance with the CDOT M&S Standards for Concrete Pavement Joints. The joint shall be edged with a suitable edging tool and sealed in accordance with CDOT Section 412.18 In general, Aggregate Base Course used in preparation of the subbase will not be measured and paid for separately unless approved by the Engineer. Aggregate Base Course used in areas where the subbase requires over excavation will be measured and paid for separately, and the cost shall include excavation. The Contractor shall notify the Engineer of areas to be excavated that may require payment for Aggregate Base Course. The Engineer shall determine if payment shall be made for Aggregate Base Course. The above prices and payments shall include full compensation for fwnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in Sidewalks, Curb & Gutter, Drive Approaches, Aprons, Crosspans, and Concrete Pavement, complete -in -place, including removal, haul and disposal, as shown on the plans, as specified in these specifications, and as directed by the Engineer. Project Spedticatio —Page 18 of25 requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award. 17.4. -OWNER may conduct such investigations as OWNER deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications and financial ability of the Bidder's proposed Subcontractors, Suppliers and other persons and organizations to do the Work in accordance with the Contract Documents to OWNER's satisfaction within the prescribed time. 17.5. If the Contract is to be awarded, it will be awarded to the lowest responsive and responsible Bidder whose evaluation by OWNER indicates to OWNER that the award will be in the best interest of the OWNER. Award j shall be made on the evaluated lowest base bid excluding alternates. The basis for award shall be the lowest Bid total for the Schedule or, in the j case of more than one schedule, for sum of all schedules. Only one contract will be awarded. 17.6. If the Contract is to be awarded, OWNER will give the Successful Bidder a Notice of Award within forty-five (45) days after the date of the Bid opening. 18.0 CONTRACT SECURITY. The General Conditions and the Supplementary Conditions set forth OWNER's requirements as to performance and other Bonds. When the Successful Bidder delivers the executed Agreement to the OWNER, it shall be accompanied by the required Contract Security. 19.0 SIGNING OF AGREEMENT. When OWNER gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement with all other written Contract Documents attached. Within fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the required number of counterparts of the Agreement and attached documents to OWNER with the required Bonds. Within ten (10) days thereafter, OWNER shall deliver one fully signed counterpart to CONTRACTOR. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification. 20.0 TAXES. OWNER is exempt from Colorado State Sales and Use Taxes on materials and `? equipment to be incorporated in the Work. Said taxes shall not be included in the Contract Price. Reference is made to the General and Supplementary Conditions. 21.0 RETAINAGE. 7/96 Section 00100 Page 7 REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES Section 614 of the Standard Specifications is hereby revised as follows: Subsection 614.15 shall be revised as follows: This work shall consist of famishing, installing, moving maintaining and removing temporary traffic signs, advance warning arrows panels, barricades, channelizing devices, and delineators as required by the latest revision of the "Manual on Uniform Traffic Control Devices for Streets and Highways" (MUTCD), the City ofFort Collins' "Work Area Traffic Control Handbook", June 1989 with Revisions dated May 29, 1991, and the City of Fort Collins' "Design Criteria and Standards for Streets, Subsection 1.4, "Barricades, Warning Signs, Signal Lights", July,1986. hi the event of a conflict between the MUTCD criteria and the City's criteria, the City's criteria shall govern. When a device is not in use, the Contractor shall remove it from the project for the period it is not needed. Devices temporarily not in use shall, as a minimum, be removed from the area. Moving will include devices removedfrom the project and later returned to use. Payment shall be made for the maximum number of each type oftmffic control device being used at one given time per day. Traffic control devices shall be placed and/or stored in the City right-of-way in such a manner that minimizes the hazards to pedestrians, bicyclists and vehicles. Traffic control devices shall be removed from the site immediately upon completion of the work for any street(s). Subsection 614.16 shall include the following: All traffic control devices placed for this project must meet or exceed the minimum standards set forth in the MUTCD. All traffic control devices shall be clean and in good operating condition when delivered and shall be maintained in that manner on a daily basis. All traffic control devices shall be clearly marked and free of crossed out information or any other form of defacement that detracts from the purpose for which they are intended (i.e. crossed out information, information written in long -hand style, etc.) Additionally, any sign blank with sign faces on both sides must have the back sign face covered when in use to avoid confusion to motorists traveling in the opposite direction and other potentially affected parties, such as residents affected by any information the sign may present. Subsection 614.20 shall be revised as follows: Traffic control through the construction areas is the responsibility of the Contractor. For all locations, a Traffic Control Plan shall be prepared. The Traffic Control Plans shall be on City supplied forms. The Traffic Control Plans shall be submitted for approval to the Engineer by 12:00 noon, two working days prior to the commencement of work. (Note: Traffic Control Plans for work done on Monday and Tuesday" be submitted the previous Friday by 9:00 a.m.) All plans shall be delivered to City Engineering, 281 North College Avenue. Facsimiles of plans shall not be allowed. No phase of the construction shall start until the Traffic Control Plan has been approved. Failure to have an approved Traffic Control Plan shall constitute cause for the City to stop work, as well as the Contractor's forfeiture of payment for all work and materials at that location, with no adjustment in the contract time, Project Specifications — Page 19 of 25 REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES The Traffic Control Plan shall include, as a minimum, the following: (1) A detailed diagram which shows the location of all sign placements, including advance construction signs (if not previously approved) and speed limit signs; method, length and time duration for lane closures, and location of flag persons. (2) A tabulation of all traffic control devices shown on the detailed diagram including, but not limited to: construction signs; vertical panel; vertical panel with light; Type I, Type II, and Type III barricades; cones; drum channelizing devices; advance waming flashing or sequencing arrow panel. Certain traffic control devices may be used for more than one operation or phase. However, all devices required for any particular phase must be detailed and tabulated for each phase. (3) Number of flaggers to be used. (4) Parking Restrictions to be in affect. Approval of the proposed method of handling traffic is intended to indicate those devices for which payment is to be made. Such approval does not relieve the Contractor of liability specifically assigned to him under this contract. Parking Restriction Plans shall be submitted and approved which show the location and quantity of "NO PARKING" signs, the date to be placed, and the date to be removed. The plans shall be prepared on City supplied forms. The Parking Restriction Plans shall be submitted to the Engineer by 12:00 noon, two working days prior to the commencement of work. (Note: Parking Restriction Plans for work done on Monday and Tuesday shall be submitted the previous Friday by 9:00 a.m.) All plans shall be delivered to City Engineering, 281 North College Avenue. Facsimiles of plans shall not be allowed. No phase of the construction shall start until the Parking Restriction Plan has been approved. Failure to have an approved Parking Restriction Plan shall constitute cause for the City to stop work, as well as the Contractor's forfeiture of payment for all work and materials at that location, with no adjustment in the contract time. Subsection 614.21 shall be revised as follows: Traffic Control Management shall be performed by a Traffic Control Supervisor (TCS). The TCS(s) shall possess a current American Traffic Safety Services Association (ATSSA) certification as a Worksite Traffic Control Supervisor or Colorado Contractor's Association (CCA) certification as a Traffic Control Supervisor. (Proof of certification shall be presented to the City Traffic Control Manager, and when requested by a City representative, for each TCS utilized on this project.) One TCS shall be designated as the Head TCS. The Head TCS shall have a minimum of one year experience as a certified TCS. The Head TCS she be on site at all times during the construction. Qualifications shall be submitted to the Engineer for approval a minimum of one week prior to commencement of the work. The TCS shall be equipped with a cellular phone. The cost of this phone shall be incidental to the day or hour pay unit for TCS. It is the intent of the specifications that the Head TCS be the same throughout the project. If the Head TCS is to be replaced during the project, the Engineer shall be given a minimum of one (1) weeks notice and qualifications shall be submitted for approval for the replacement. The Head TCS will be paid for under the TCS item Project Specificatiooa - Page 20 of 25 s— REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES The TCS's duties shall include, but not be limited to: (1) Preparing, revising and submitting Traffic Control Plans as required. (2) Direct supervision of project flaggers. (3) Coordinating all traffic control related operations, including those of the Subcontractors and suppliers. (4) Coordinating project activities with appropriate police and fire control agencies, Transfort, school districts and other affected agencies and parties prior to construction. Typed hand delivered notification to all businesses and residents at least 24 hours prior to construction. (The notification of residents and businesses may be accomplished by a representative of the TCS.) (5) Maintaining a project traffic control diary which shall become part of the City's project records. (6) Inspecting traffic control devices on every calendar day for the duration of the project. (7) Insuring that traffic control devices are functioning as required. (8) Overseeing all requirements covered by the plans and specifications which contribute to the convenience, safety and orderly movement of traffic. (9) Flagging (10) Setting up traffic control devices Notification of residents and businesses shall be the responsibility of the TCS and shall consist of distributing letters indicating the nature of the work to be completed, any special instructions to the residents (i.e. limits on lawn watering during concrete pouring, etc.), the dates and times of the work, and the parking and access restrictions that will apply, as well as thorough information placed on "NO PARKING" signs. Sample letters will be provided by the Engineer and shall be distributed prior to the commencement of each phase of the work. Letters shall be submitted with the Traffic Control Plans for approval. Approved letters shall be distributed aminimum of24 hours prior to the commencement of work. (Note: The time frame criteria for distributing letters is the same as for posting "NO PARKING" signs.) The cost for preparing and distributing the letters shall be included in the cost for TCS. Traffic control management shall be maintained on a 24 hour per day basis. The Contractor shall make arrangements so that the Traffic Control Supervisor or his approved representative will be available on every working day, "on call" at all times and available upon the Engineer's request at other than normal working hours. The TCS's will be paid only for days the Contractor works, and as directed by the Engineer. On weekends and other days the Contractor is not working, the TCS will not be paid. Time spent maintaining signs on the weekends, holidays, bad weather days, and other days the Contractor does not work shall be included in the unit prices for the equipment. Time spent setting up equipment, modifying equipment, and maintaining equipment shall be included in the unit prices for the equipment. All traffic control devices shall be placed under the supervision of a Traffic Control Supervisor The Traffic Control Supervisor shall have up to date copies of the City of Fort Collins' "Work Area Traffic Control Handbook", and Part VI of the MUTCD, pertaining to traffic controls for street and highway construction, available at all times. Project Specifications— Page 21 of 25 REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES Subsection 614.23 shall be revised as follows: Quantities to be measured for construction traffic control devices shall be the number of units of the various sizes and descriptions listed below: Construction Traffic Signs: Size A Signs - 0.01 to 9.00 Square Feet Size B Signs - 9.01 to 16.00 Square Feet "NO PARKING" Sign with Stand will be measured and paid for separately and not included in the item for Size A Signs. "NO PARKING" Sign with Stand shall consist of a metal sign attached to a device (stand) such as a Vertical Panel or Type I Barricade. The sign material and stand shall be approved by the Engineer. The sign material and stand will not be measured and paid for separately but shall be included in the Contract Unit Price for "NO PARKING" Sign with Stand. The cost for "NO PARKING" Sign with Stand shall include delivery, rental, setup, modification, maintenance, and pickup. "NO PARKING" signs must remain in place until the street is open to traffic. The "NO PARKING" signs shall be, in effect for one or two days only. Traffic channelizing devices consisting of vertical panel, cones, or drum channelizing devices will be measured by the unit. Barricade warning lights shall be measured and paid for separately if approved by the Engineer. Advance Warning Flashing or Sequencing Arrow Panels will be measured by the unit. The number of Traffic Control Supervisors shall be approved by the Engineer prior to each days work. The quantity to be measured for Traffic Control Supervisor will be the number of authorized days performed by the Traffic Control Supervisor or his approved representative. An authorized day shall be any day, or portion of a day, authorized by the Engineer, that construction operation would require a Traffic Control Supervisor. "On Call" and project inspections on all other days will not be measured and paid for separately but shall be included in the work. The cost for setting up equipment, modifying equipment, and maintaining equipment (not including "NO PARKING" Sign with Stand) during authorized days shall be included in the Contract Unit Price for Traffic Control Supervisor per day. If a TCS(s) is used for an authorized day, but not for the entire day, the TCS shall be paid at the Contract Unit Price for "Traffic Control Supervisor" at the per hour rate. The quantity to be measured for flagging will be the total number of hours that flagging is actually used as authorized. Hours of flagging in excess of those authorized shall be at the Contractor's expense. Flagger breaks shall be included in the Contract Unit Price for Flagging. The method for covering flagger breaks shall be approved by the Engineer. Flagging outside of the construction work hours will not be paid for under the terms of this contract unless authorized in writing by the Engineer. Flagger stand-by time will not be paid for under the terms of this contract. In locations where traffic control is set up and the work is not performed due to Contractor caused delays, the traffic control shall not be paid for under the temis of this contract. The costs for advance warning "NO PARKING" signs for periods in excess of 24 hours prior to the advancement of work, including those instances when said signs have been changed or otherwise updated to reflect current schedules, will not be paid for under the terms of this contract unless authorized by the Engineer in writing, In addition, the Owner shall deduct from compensation due the Project Specifications -Page 22 of 25 REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES Contractor $10.00 for each traffic control device per day for said conditions, including "NO PARKING" signs and any signs which are not removed from the site immediately upon completion of the work. Subsection 614.24 shall be revised as follows: The cost for Traffic Control Devices, not including "NO PARKING" Sign with Stand, shall include delivery, rental, and pickup. The cost for setting up equipment, modifying equipment, and maintaining equipment will be paid for under the Contract Unit Price for TCS as described above. The cost for "NO PARKING" Sign with Stand shall include delivery, rental, setup, modification, maintenance, and pickup. Payment shall be full compensation for furnishing, erecting, maintaining, moving, removing and disposing of construction traffic control devices necessary to complete the work. All construction traffic control devices which are not permanently incorporated into the project will remain the property of the Contractor. The accepted quantities will be paid for at the contract unit price for each of the pay items listed below: Pay Item Unit 614.01 "NO PARKING" Sign with Stand Per Day Per Each 614.02 Vertical Panel Without Light Per Day Per Each 614.03 Type I Barricade Without Light Per Day Per Each 614.04 Type II Barricade Without Light Per Day Per Each 614.05 Type III Barricade Without Light Per Day Per Each 614.06 Size A Sign With Stand Per Day Per Each 614.07 Size B Sign With Stand Per Day Per Each 614.08 Size A Specialty Sign Cost of Manufacturing Each 614.09 Size B Specialty Sign Cost of Manufacturing Each 614.10 Cone With Reflective Strip Per Day Per Each 614.11 Safety Fence Per Day Per Roll 614.12 Light - Steady Bum Per Day Per Each 614.13 Light - Flashing Per Day Per Each 614.14 Advance Warning Flashing or Sequencing Arrow Panel Per Unit Per Day Project 4mifications — Page 23 of 25 REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES 614.15 Traffic Control Supervisor Per Day 614.16 Traffic Control Supervisor Per Hour 614.17 Flagging Per Each Per Hour The initial manufacturing will be paid for Specialty Signs per unit and the actual use paid for under the appropriate unit cost for Size A or Size B sign. This item shall apply to new signs only. Once manufactured, they may be used throughout the project. Upon completion of the work, the Specialty Signs shall be returned to the Contractor. Flagger hand signs will not be measured and paid for separately, but shall be included in the work. The flaggers shall be provided with electronic communication devices when required. These devices will not be measured and paid for separately, but shall be included in the work. The cost of batteries, electricity and/or fuel for all lighting or wanting devices will not be paid for separately but will be considered subsidiary to the item. Sand bags will not be measured and paid for separately, but shall be included in the work. The Contractor may provide larger construction traffic signs than those typically used in accordance with the MUTCD, if approved; however, payment will be made for the typical panel size. The City shall not be responsible for any losses or damage due to theft or vandalism. Project Specificatioaa — Page 24 of 25 4 i REVISION OF SECTION 614 TRAFFIC CONTROL DEVICES SPECIAL CONDITIONS FOR WORK ON ARTERIALS AND COLLECTORS NOTE: CROSS STREET TRAFFIC SHALL BE MAINTAINED AT ALL TIMES UNLESS AUTHORIZED BY THE ENGINEER IN WRITING, NOTE: FULL CLOSURES ON ARTERIALS AND COLLECTORS, INCLUDING THOSE LISTED ABOVE, WILL BE ALLOWED UNDER EXTREME CIRCUMSTANCES AND ONLY UPON APPROVAL OF THE ENGINEER. PLANS SHALL BE APPROVED A MINIMUM OF ONE WEEK PRIOR TO THE COMMENCEMENT OF WORK AND/OR THE TIME REQUIRED TO ADEQUATELY NOTIFY THE PUBLIC THROUGH THE MEDIA. SPECIAL CONDITIONS FOR WORK ON RESIDENTIAL STREETS NOTE: FULL CLOSURES ON ALL RESIDENTIAL STREETS SHALL BE ALLOWED AS SHOWN ON THE { TRAFFIC CONTROL PLANS. Project Specifications — Page 25 of 25 I oo 888888 . . . . . me - - eee . . . . . . - - - - . . . . . . . . . . . . . eee o. ease$ . . . . Y ay 8 8og ti- t T . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . o. $$$$$� oeeep8 pees pppe poo00mee 8 8 pe O0000 opg 88?888 ??8688 ep000p� eepo� eeme 8 8 8mgo�00 Oho v 885888^ a RB.pp�me'.. 8 8% �t 888888 o$. G op o� S 8 C'� 8 $88888 pp e p p4 ai ee000p 08o a o0008 eeo omry„o 0000poo� Bob eo G N r1 .) 'fit � 888888 eeoo ^eeoo-o � -. e000 eoop. 8g S58o ST 8, 8, e000peo. 3r� � . i� ?+ u s , �%' 888888 g g e e ( I vi3JIM 33 w' 333� 333w3, of aio3m m'! 3"* zga 33m�3� z3uls X m3H P 0 mB 0 s<�b m m $mA 8g' g8 Ai,. A�ao ?g o` <gsM. yy I 1.N €o15A .u3lyy m y 6.$u"8v;33 gF 3t�3iim'Y3 4 ui Z rcx. z3 SECTION 03000 DETAILS INDEX Street Markings Vertical Curb and Gutter Driveover Curb, Gutter and Sidewalk Median Curb - Outfall Curb and Gutter Hollywood Curb, Gutter and Sidewalk Driveway Approaches Alley Intersections Street Intersection Crosspan Standard Sidewalk Sidewalk Details Detached Walk/Intersection Details Pedestrian Ramp Details Access Ramp Location Access Ramp Scoring Under -walk Drains Curb Inlets Catch Basin Replace Concrete Pavement Concrete Construction Joint Rigid Pavement Joint Detail Provisions concerning retainage are set forth in the Agreement. 22.0 PURCHASING RESTRICTIONS. Purchasing restrictions: The Bidder's authorized signature of this Bid assures the Bidder's compliance with the City's purchasing restrictions. A copy of the resolutions are available for review in the Purchasing and Risk Management Division or the City Clerk's office. A. Cement Restrictions: City of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that burn hazardous waste as a fuel. 23.0 COLLUSIVE OR SHAM BIDS. Any Bid deemed by the City in its sole discretion to be a collusive or sham Bid will be rejected and reported to authorities as such. Your authorized signature of this Bid assures that such Bid is genuine and is not a collusive or sham Bid. 24.0 BID RESULTS. I 6 I For information regarding results for individual Bids send a self- addressed, self -stamped envelope and a Bid tally will be mailed to you. Bid results will be posted in the Purchasing office seven (7) days after the Bid Opening. e END OF SECTION 7/96 Section 00100 Page 8 7 I R = STREET MARKINGS PATCH G = GRIND /= FABRIC LIMITS OF REPAIR >'DEWALK 3 � iJTTER NOTE: ALL MARKS ARI FLOURESCENT PINK PAINT. CONCRETE JOINT N 2"R. n 'D Ginter edge may be tapered or battered. (Typical for all Curb & tO , & Gutter Types) ro IMI VERTICAL 30" ROLL-OVER (LOVELAND) CURB AND GUTTER LARIMER COUNTY APPROVED: DRAWING CONSTRUCTION URBAN AREA DATE: 0e/11/00 STREET STANDARDS DRAWINGS 7-20A DRAWN BY. HKP i J LL O LLI N °m U •. N z: O H WW (n IL y LL r LL yl Z) U U UA w x C_ > rt !�rt �1 Cb LIL � Q VJ J LL i0 a U v N -I n � Q / W --I �-� Q - 0 �- m m U a { , CURB AND GUTTER/SIDEWALK LARWR COUNTY REVISION NO: 1 DRAWING CONSTRUCTION URBAN AREA CONSTRUCTION STREET STANDARDS DATE: 03/01/02 70 N OUT FALL CURB & GUTTER 1 1/2" R (typ.) —,�j6(min ' - T6. with Conn, Pvmt. S" with Asphalt Asphalt or Concrete Epoxy Adhesive Pavement (finished Surface) GLUE DOWN CURB 8" BARRIER CURB 6" MOUNTABLE CURB Bottom of curb shall be poured to a depth no less than on the compacted subgrade of the pavement. MEDIAN (ISLAND CURBS) LARD= COUNTY CONSTRUCTION DYED: DRAWING STRM STANDARDS DRAWINGS D"�'°°/°'/°° 7-20C Dum HY:mv I -COMBINATION CUR GUTTER D SIDEWALK wHOLLYWOOlf _ OBSO_LET P - - r FOR RECONSTRUCTION ONLY! HOLLYWOOD CURB; GUTTER AND WAS OF FORT COLLINS? COLORADO ENGINEERING DIVISION Sidewalk Addition 2- Existing Sidewalk ADDITION TO EXISTING SIDEWALK NOTES: 1. New walk additions shall be placed to the same line and grade as the existing walk. 2. Match transverse tooled joints to existing tooled joints. DUMMY JOINT FOR WALKS NOTES: 1. Joint shall be out 1/4 thickness of initial concrete; dummy joint for walks. I SIDEWALK DETAILS LARIMER COUNTY APPROVED: DRAWING URBAN AREA CONSTRUCTION DATE: 08/07/00 STREET STANDARDS DRAWINGS DRAWN BY. BHP 25-1 10' ARTERIAL / ARTERIAL ARTERIAL ROW Line 11 ARTERIAL / COLLECTOR ARTERIAL / COLLECTOR For Comer Radius > 35" DETACHED WALK / INTERSECTION DETAIL LARIMER COUNTY j�PRD'OVEDRAWING URBAN AREA CONSTRUCTION DATE: O8/07/00 STREET STANDARDS DRAWINGS DRA11N BY: B%P 16-4B LOCAL w 24 w cc a ARTERIAL/LOCAL r DETACHED WALK / INTERSECTION DETAILS LARIMER COUNTY APPRDVBD: DRAWING URBAN AREA CONSTRUCTION DATE: OB/07/00 STREET STANDARDS DRAWINGS Du . 8 HRP 16-4C I I A W W W W W W W W W W W ar W W W W W W W W W W W FLARE OPTION W W W W W W W A 4' MIN. COLORED MAX.I I OPE 1"/FT CONCRETE OPTION 0.5' TYP. COLORED CONCRETE (FT. COLLINS ONLY) TOOL JOINT 6" CENTERS COLUNS ONLY) STANDARD GRAY CONCRETE �cuNtl 1 7z SLOP I/4 MAX. FL UP -�E MAX 6 � .2U46RLb CyNLgE1.E.. 6" FLOWLNE OF GUTTER ... g• �..1 RAMP YAM PARTIALLY COLORED CONCRETE PLAN VIEW SECTION A -A N.T.S. N.T.S. RAMP LANDING SHALL BE CONCRETE COLORED WITH 4 LEIS/ SACK DAMS NO. 1117 (TILE RED) PIGMENT OR APPROVED EQUAL, DAMS CLEAR SEALANT OR APPROVED ECUAL SHALL BE APPLIED ON ALL COLORED CONCRETE SURFACES. (FT. COLLINS ONLY) COLORED PORTION OF THE RAMP SHALL BE POURED SEPARATELY AND DOWELLED .INTO ADJACENT CONCRETE WITH A MINIMUM OF 8 EQUALLY SPACED, 18 INCH 14 DEFORMED BARS DRIVEN 8 INCHES MINIMUM. (FT. COLUNS ONLY) TRANSITIONS ARE TO BE SCORED PERPENDICULAR TO TRAVEL DIRECTION WITH SIX 1/4 INCH DEEP TOOLED JOINTS 6 INCHES ON CENTER AS SHOWN. NO JOINTS ARE ALLOWED IN THE FLOWUNE. SIX INCH WOE CURB OR 'DUMMY JOINT" MAY BE TOOLED NO CLOSER THAN 6 INCHES FROM FLOW LINE AS SHOWN. MINIMUM CONCRETE THICKNESS IS 6 INCHES. JOINT PATTERN TO BE ACCORDING TO 'INTERSECTION GUTTER DETAIL' OR AS DETERMINED BY THE LOCAL ENTITY. WOOD FLOAT FINISH IS REQUIRED OVER ENTIRE SURFACE OF RAMP AND TRANSITIONS. A 6 INCH WOE CURB MAY BE POURED AT THE BACK OF THE RAMP AS SHOWN IF REQUIRED. IF CURB IS USED IT SHALL MATCH ME CURB AND GUTTER STYLE OF ADJACENT CURB AND GUTTER. MINIMUM RAMP WIDTH SHALL BE FOUR FEET, OR THE SAME AS THE WIDEST ADJACENT SIDEWALK. WHICHEVER IS GREATER. UP TO A MAXIMUM WOTH OF B FEET. THE RAMP LANDING MAY BE POURED MONOLITHIC WITH THE ADJACENT TRANSITIONS PROVIDED THAT AN APPROVED "SHAKE -ON" PIGMENT BE USED TO COLOR THE LANDING AREA. PEDESTRIAN RAMP DETAIL (For New Const. & Alterations) LARIMER COUNTY APPROVED: DRAWING 7 CONSTRUCTION URBAN AREA DATE: 11/13/00 16-4D STREET STANDARDS DRAWINGS DRAWN BY: RESIDENTIAL STREET WITH DRI% EOVER CURB iD-1 1 i 1 F 0 LLJ LLJ m a, ry I— ::) V U J Q 0 F- 0 Z W � J � J LLB O - ry _ 4' MIN. 4' OF CURB MIN. 2' 4.43' n GRADE BREAK TO FULL WIDTH PLAN VIEW 6" CURB AS NEEDED FOR LANDSCAPING 1,17' 6" CURB AS REQUIRED FOR LANDSCAPING CONCRETE i, RANP WIDP♦r. M BE CCM7RIE COICRED WON 4 IBS/ SACK WAS NM 1117 (ILE RED) PCIRO OR APPR%9 Eux DNAS aTAR MW OR APPRM MA SNNL SILYL BE APRIED ON ALL CLUED CUMEIE SURAM 2 CDIDBD PORION OF 11E.RAIP SHNL BE POUTED SEPI IMY AND BONEW MD ADi10EM CONCRETE AN A WM OF 8 ECWLY SPACED, 15 BM:H 14 DUMB NRS DRNEN 8 WM MNWJL S. 1RINSIIBNS ARE M BE SCORED PEAPQ61N " TD TW& 06ECRON WM SIX 1/4 NCH DEEP TOOUD: JCNIS 6 NM CI COTTER AS SHM. 4. K JWM ARE NLONED N THE ROWNE SIX = WOE CURB OR VSNNY JONT' MY BE TOOLM ND a= DM 6 PMES FRW PLOW LIE AS SIM 5. MWUI CO XROE ➢I MM B 6 NM 6. JOUO PATIFAN M BE ACMMM TD 'NIDBECCII@I CURER DEDL" (DEFAL D-16 and D-M OR AS , DEMUM BY THE MY EIACWM 7. S'MYRID WOOD RW MEN DS REp = OVER OW MACE OF RAID AND TR/NSIDC6 & A 6 10 610E CUB MY BE PMM AT PE PACK W THE PAW AS SHORN F REBMWD. F CUB 6 USED R SHNL WATM THE CUB AND ODDER MU OF NMCEM CUB NO WM 6' 1,24 max. 1/4" MAX. FL LIP .!f:::S::6�:A ::��:}"C61.GpCDvav: �•..wC:i:.`.�i:6!:�ti:.e.:. . 6' SECTION A -A PEDESTRIAN RAMP DETAIL FOR NEW CONSTRUCTION AND ALTERATIONS �l STANDARD DiLP D-12.1' CITY OF FORT COLLINS, COLORADO ENGINEERING DEPARTMENT APPROVED REVISIONS 2-'96 i j 0 e SECTION 00300 BID FORM Nt=tN I IAL 51 KLLI WI I H DRIVEOVER CURB (D-11) I I ILLJ � � W m l_ U J � Q O F- LLJ ` 1 �J I(. U LLJ O 4' 1/ ON MIN. 4' TOP OF CLRB MIN. 2' TRANSI 18' '- 4.43 S. GRADE BREAK TO FULL WIDTH PLAN VIEW 6" CURB AS NEEDED FOR LANDSCAPING 6- 6" CURB AS REQUIRED FOR LANDSCAPING CONCRETE I 1.17' 1. RW LAW %Ml BE COMOIETE COLORED FDH 4 Iffi/ SACK DAYS NM 1117 (RE RED) PCWIT OR APPVC FOWL OM CLEAR MM.AMT OR APPROYFD MX SHALL SHALL BE APRED ON ALL COLORED OM CPEIE SATFMM I COLM POLODM OF THE RMIP SHALL BE POOLED SfPJRA1FLY AND DOWDIER NNO ADUCDHT O M&TE WON A MINW OF 8 MLIALLY SPMED, ID OFMH i4 ODDIWED am we 8 HIM MIMWWL S TRAMSMONS AFE TO IE SCORED PERPE OMWAR To TRAVEL DRECRON MRH So( 1/4 MMI DEEP MMM MIS 6 MMES ON CDOM AS WK 4. NO JI MIS AFE ALLOWED M THE MMf♦E SM MMH WM MMB OR 'MBAO' J(*(r MAY BE TOOLED NO CLOSER THAN 6 100 FROM FLAW LME AS SM. 5. MIMN CONCRETE mum 6 6 MCHM & JOMI PATLDM TO BE ACO)SMW TO YBUM M1 WS OEM: (DETALL D-16 and D-17) OR AS DEMUMEO BY THE CITY VIGIM t. 7. SRWFD WOOD RMT FIMW 6 RMWO OLFH EMRE SIW A E OF RAMP AND TRMNSIOH6. & A 6 10 WDE MMB MAY BE POLIAED AT THE BALM OF THE RAMP AS SM F M WHD. F CIWB 6 USED O SNALL MATCH THE CURB AND OMER MU OF ADJAC M CURB AHO WM PEDESTRIAN RAt.MP DETAIL FO STANDARD DETAIL AND ALTERATIONSTION D-12.2 CITY OF FORT COLLINS, COLORADO ENGINEERING DEPARTMENT APPRnVFn REVISIONS 2-'96 ARTERIAL / COLLECTOR WITH 6" VERTICAL CURB (D-11) m ry U J Q U F— ry L.1 7 �V 2 (r 0 U LJ J J O U m J �Q EY W y LL Q 1/4' 4' TOOL JOINT CENTERS / 6' M 1I4^ y y y. W y y W Y y 1:12 SLOPE CONCRETE BREAK r- y y y y y y Y �� NOT ES 1. RIAP IAIDIQIC SWLL BE Ca1tlh7E carom M6M 4 tB5/ SACK aN5 NQ nn (TlF Am) FMMENf " OR AF4 M EQUAL Dwa MW SEAIAM OR APPMED EQUAL MAIL MALL BE APPLIED ON ALL NYI1M� MY.��..F�EfE n WACES .w"amfY N.M�GIG SU6ACES ' '- 2 OM MD POM OF THE RAW MALL 6E POURED SEPARATELY AND DDMmm KIO ADAAMIT mnrJeTE MmrA NMIW OF a EaALLY SPACED. 1e Mlal +A DEFORED 80 DME11 a aUES NNMY. I TRAAAillab ARE TO BE SCDIED PENPE1mIQANt To 1RAYE1. ORECTgN MRH soc 1/4 N01 DEFP roam k- y y JOKIS 6 INKM ON CDIIER AS MMIM L y Jr t NO MIS ARE NLOMED IN THE FIDMPE SIX NO WIDE CURB OR TUW Mr MAY BE TOOLED ND 1 y y aDSER 11VN 6 NCIES FROM FLOW UK AS SWWL y y S. MUAMY CONGiIE TNDDOESS IS 6 IIaE'S y y E MIT PATRIN TD BE ACCaI0114 TO WMASSC110N DUIM DEEW (DETAIL D-16 and D-11) OR AS W y DETFAIM BY THE CRY 912M W y I. SM ED MOOD RW FMIMI 6 MUD D 00 DUK SUWACE OF RNJP AND TRA SIM y + e. A 6 DIW WE CURB MAY BE POURm AT THE BACJE OF THE RAP AS WRI F FEDOMEa F WE IS •r •�' USED R SFWL AATCN DE CURB AND GUM MU OF ADAMIT CURB AND GUf1FR. 1' y y y y r y W y y ` y y y MIN. 4' 0 1/4"/FT 1 4" MAX. FL UP IIy I--VARIES—+--VARIES 1 . r_ 6' PLAN VIEW SECTION A —A ` N.T.S. F L FOR NEW CONSTRUCTION `STANDARD DEf#JL PEDESTRIAN RAMP DETAIL AND ALTERATIONS D-12.d- CITY OF FORT COLLINS, COLORADO favFsTom ' ENGINEERING DEPARTMENT APPROVED z- 96 TOP " PER FT. TOP OF �_4' MIN NOTES SIDEWALK AS REQUIRIED FOR LANDSCAPING RANSITION TO FULL WIDTH TYPIC HOLLYWOOD CURB (D-1 1—A) CURB AS REQUIRIED FOR LANDSCAPING r s.I DRIVE —OVER CURB 1 (D-11) I AS REQUIRIED FOR LANDSCAPING 6" VERTICAL CURB (D-1 1) I. RAT LNONG AWL BE CONWIE CDDRED RDN 4 LSS/ SACK D@IS NO. 1117 ME RED) - 4. NO JWS ARE ALDAED N THE ROKI E. M NIDI WIDE CLFB OR 'DWW JW r MAY BE MOO PIGLFIN OR APPRDED EDIWL 131015 DIEM SFNANE OR APPRM EDUAL AWL SHOAL BE APRO ON NO DDsfll TNA1 6 NDES FIXIM RDR UE AS AONIL ALL MMED CONCNEIE Mom' 5. IBBRY CONC EIE TFIDDESS S 6 MEL 2 CD M PORIIDR OF THE RW SHU BE POIIIED SEPARATELY MO DDKLLM BID A011M & JOM PANE TD BE A=aw TD 'MR m7m am DErw (BEIAL 0-16 a l (-17) OR AS ODNDEIE BIN A WARN OF B EMM SPAED, 18 NCN 14 09=0 BV5 Wa B IC ES MINIM DEIEINBED BY THE CDY BIGNI tt L MA149106 ARE M BE SDIRED PDT90MM M 1ADEL D6E M WIN SIX 1/4 WM DEEP TOOLED T SBRIED RODD RD4 1114% B WINVED DOER ENBE AREACE OF RAMP AND VAIMIONS MIS 6 NDIES ON CENSER AS SHOWN. & A 6 NCH PADS DAB WY BE ERRED AT THE BMX OF TIE RAT AS 9 M F REMED. F DRB B USED R AWL W.0 THE CM NO DIfIFR MU OF ADKW CURB AND QRER VARIES 1/2' PER FT' WAR 1/4' WX FL UP ii 6' CURB AS NEEDED FOR LANDSCAPING 6• TYPICAL RAMP CROSS—SECTION N.T.S. MID -BLOCK PEDESTRIAN RAMP DETAILS STANDARD D,-TAM FOR NEW CONSTRUCTION AND AL"L'RGTIONS D-12.6 CITY OF FORT COLLINS, COLORADO REWSIDR9 ENGINEERING DEPARTMF' IT �Apppnvrn 2-'96 J, D Refer to SD 1S-". NOTES: 1. All T-intersections shall have a minimum of three (3) curb ramps, as shown. 2. A driveway may be used as access ramp if it is designed to meet access ramp requirements, is within the intersection, and is directly across from the other ramps. 3. Refer to SD 1 S-4 for details of ramps. 8' Min. ACCESS RAMP LOCATION (T-INTERSECTION) LARIMER COUNTY URBAN AREA STREET STANDARDS CONSTRUCTION DRAWINGS APPROVED: DRAWING 16 VF DATE: 08/07/00 DRA11N BY: BHP 8'-0" (Min.) Length 2% Slope 3/8" a a QT 8„ (Min.) a IA p. SCORING DETAIL NOTES: 1. The scoring shall be 3/8" deep, with the scoring oriented in the direction of pedestrian travel. 2. =or Fort Collins, the concrete at the base of the ramp shall be colored Tile Red (conforming to Davis color no. 1117, Bayferrox Pigment 130, or equal). ACCESS RAMP SCORING LARIMER COUNTY APPROVED: DRAWING CONSTRUCTION URBAN AREA DRAWINGS DATE: 08/07/00 16-6F STREET STANDARDS DRAWN BY: BKP A RE 3/8" Rolled Steel Tread PI (diamond pattern) Dimension Variable I Notes: 1. Length of steel plate varies. 2. Chase and cover plate run from Right of Way line to flow line unless approved by the Engineer. With curb walk, cover plate extends from property line to top of walk face. C Retai 4'_C PLAN VIEW L- 1 1 /4" x 1 1 /4" x 1 1 /4" 3" #4 Bar Welded at 12" on Nelson Standard Anchor SECTION C-C (typical both sides) - e 5/8" Rolled Steel Tread Plate _ 1/2" x 1" Flat Head Mach. Screw Brass or Electro-galy. finish. - Angle iron to be drilled and threaded to receive screw. Concrete to be drilled to allow screw (typical both sides). b 0 '-.vlvllJnvH I IUN UURB, GUTTER, AND SIDEWALK 6" VERTICAL CURB, GUTTER, AND SIDEWALK SECTION A -A (2 VIEWS) STANDARD DETAILS FOR DRAINAGE UNDER SIDEWALK LARIMER COUNTY CONSTRUCTION ApPRovgD: DRAINING URBAN AREA DATE: oB/o�/oo STREET STANDARDS DRAWINGS '7-31 DRAWN BY: BKP 6" TH I CK SIDEWALK (TYR) I 0= I TYP U IBC 9.5 FLUSH WITH CURB, FACE *P4 BARS 12" D.C. 3' 6" Ao� 6 .fARS AT XTEND WALK ISO I " BEYOND NORMAL IQCE . BACK OF WALK. I 3�1 I S �S BARS AT 9 QC. ^ I -}y 2ftS BARS AT 6"QC. O BACK OF CURB ( !-.SEE DETAIL "A" FLOWLINE WARPED CURB e GUTTER (TYR) A-*J PLAN VIEW 3. 6" I 1/2"R. 1 4"-1" LEG x4 BAR 418 LONG NORMAL .�'•'• ' �:' A•. FLOWLINE ♦s I %A - •A, ,11/2"PIPE SPACER AND 1 1/4" LOCK N//T. U6IUy L AROD-THREAOEp 3 1/2"gEEL o ; 66., u 3"x3"m3/e PLATE DETAIL mBW BC 8.5 WITH 1 112" DUL HOLE IN CENTER — E7CTEND CHANNEL TO OUTSIDE \ EDGE OF WALL WI DETAIL mA' )" 5'6SEE DETAIL"B" *4 BARB y I SLOPE'—� BARS' m To *4 BARS-12"O.C! SOIWAYS SECTION A -A 4' O" 1 3'6" DEPRESSED GUTTER WARPED OUTTER re •. N '/r. ALTERED FLOWLIME SECTION B-B (REINFORCEMENT NOT SHOWN) I I' or i O" �4 BARS y3 6AR 1} ADD I N BAR • ADD 104 BAR hit— GENERAL NOTES: 1. SIDEWALK SHALL BE 6' THICK FOR 3.0' ON EITHER SIDE OF CULVERT. 2. TOP SLAB OF CULVERT SHALL BE SLOPED TO MATCH SIDEWALK. SEE D-6. 3. EXPOSED STEEL SHALL BE GALVANIZED IN ACCORDANCE WIT" AASHTO M-111. 4. KEY JOINTS WHERE WALLS CONNECT TO TOP SLAB AND BASE. S. REINFORCEMENT IN WALLS AND BASE SHALL 1 BE 3' FROM THE SIDE EXPOSED TO EARTH, ! REINFORCEMENT IN TOP SLAB SHALL BE t' 1 1/2' CLEAR. 4 4 BARS -12'O.C. SECTION C-C BOTHWAYS CONCRETE SIDEWALK CULVERT FOR VERTICAL CURB, GUTTER AND SIDEWALK CITY OF FORT COLLINS, COLORADO ENGINEERING SERVICES UNIT APPROVED 8Y:%-;C NI "e DATE: 5,3 REVISIONS: D-12 12 c IC a i A �8 =1'4 BARS AT 11"0. C. dTHICK SIDEWALK IMEM.N immmmi A--*J PLAN VIEW EXTEND WALK I'0" BEYOND NORMAL BACK OF WALK. ---4-W5 BARS I /� Y AT S"O.C. -� 2 -3 BARS AT : O.C. 8 BACK OF CURB 1--SEE DETAIL"... FLUSH CURB \ I I/7'R. *4 BAR 14"-1" G 10" LONG 4,1 _ n• 2-1 *5 BAR - 1 1/2" PIPE SPACER �' a.. -•. AND I LOCK NUT " �,' �,• 1 1/4" DIA. IB 1/2" GALM x STEEL ROD -THREADED 3 I/2' AT TOP. e ..R"•, I•' 3"X3"a3/8" PLATE, DETAIL "B' FLOWLINE GENERAL NOTES: 1. SIDEWALK SHALL BE S- THICK FOR 3.0. ON EITHER SIDE OF CULVERT. 2. TOP SLAB OF CULVERT SHALL BE SLOPED TO MATCH SIDEWALK. SEE D-e. 3. EXPOSED STEEL SHALL BE GALVANIZED IN ACCORDANCE WITH AASHTO M-111. 4. KEY JOINTS WHERE WALLS CONNECT TO TOP SLAB AND BASE. 3. REINFORCEMENT IN WALLS AND BASE SHALL BE 3- FROM THE SIDE EXPOSED TO EARTH. REINFORCEMENT IN TOP SLAB SHALL BE 1 1/20 CLEAR. s4 BARS DETAIL `A" BARS BARS �4 BURS -IC O.C. BDTHWAYS SECTION A -A 3. 81. 4.0. 3'6.1 WARPED GUTTER DEPRESSED GUTTER WARPED GUTTER _MP OF CURB �- NORMAL - FLOWLINE SECTION B-B (REINFORCEMENT NOT SHOWN) ADD 1 -4 BAR SECTION C-C FLOWUNE I I i BAR -ADD I -4 BAR 1( x4 BARS-12"O.0 BOTHWAYS CONCRETE SIDEWALK CULVERT FOR DRIVE -OVER CURB, GUTTER AND WALK CITY OF FORT COLLINS, COLORADq ENGINEERING SERVICES UNIT APPROVED SY: I DATE: S REVISIONS: D-1i_ 1 ea I- 6"THICK SIDEWALK (TYPICAL BOTH SIDES) 1,B 11 d•k 114.1 WARPED CURB S SEE DETAIL -0 GUTTER (TYPICAL A" a BOTH SIDES) 4 0" OPENIN r'F III 0" I / MACLEAR OR APPROVED EQUAL y p• I 3, 0" d' .BACK OF A-w1 PLAN VIEW 8[ IL5 FLUSH*k4 BAR WITH CURB,,,,I I/2"R ICI_ F�f_ Id, Lp 0 FACE iN 44 O 5 BAR 1 1/2" PIPF SPACER O' , AND 11/4' LOCK NUT b v' I VIC DIA.a 24" GALV. 9 TEE6 ROD -THREADED ' 31/2 AT 70B 3 1/4" ( W 3" K 3"% 3/8" PLATE C CURB FACE ASSEMBLY DETAIL ' GENERAL NOTES: { 1. SEE D-7b FOR REINFORCEMENT. 1 2. FLOOR OF INLET SHALL BE SHAPED WITH t = ADDITIONAL CONCRETE TO FORM INVERT TO PIPE CONNECTIONS. 3. MANHOLE RUNGS SHALL BE REQUIRED FOR INLET HEIGHTS 4' AND GREATER. `1 4. SIDEWALK SHALL BE S' THICK FOR 3' 0' ON EITHER SIDE OF INLET. 5. TOP SLAB OF INLET SHALL BE SLOPED TO MATCH SIDEWALK. SEE D-6. 6. EXPOSED STEEL SHALL BE GALVANIZED IN 1 ACCORDANCE WITH AASHTO M-111 L W, 3. 6" RPED GUTTER TOP OF C NORMAL FLOWLINE 8,. RUNGS-12"OC\ I' I% SLOPE D 7�n . ,I SECTION A -A 4' 0" )EPRESSED GUTTER O N 2'6"MINIMUM (UNLESS SQUASH PIPE IS USED.) �•'. •.': �'. `.:..• 6O SLOPE FOR DRAINAGE SECTION B-B D 3. 6" WARPED GUTTER EXTEND CHANNEL TO OUTSIDE EDGE OF WALL DETAIL "A" CURB INLET — 4' OPENING FOR VERTICAL CURB & GUTTER CITY OF FORT COLLINS, COLORADO ENGINEERING SERVICES UNIT APPROVED BY: DATE: REVISIONS: D-7a DIP. O.L. TYPE NO LENGTH IR NG REO'O. e" a 4 3' 10' 12" mr F 2 S 6 74 1/2" 12" II 14 12" a: 3 12" a' 4 12" It 2 9' O" 408 12" I TNa 4 3'4" Sol 5ro" 9" II 2 9'O" $02 5ro 9" TI 1 ♦ 8 503 518" 6" n I 9'0" 504 5/8" G" a 2 1' e' Sol 3R" 8.10. BC 1 5'O" 10,1111 I/2" 24" — 2 116" .44444 �.-141,14 I SEEM. A-4J PLAN VIEW TABLE I BAR LIST FOR CURB INLET LENGTH TYPE 7 StrOigt TYPE: 1L� 1 "U" ��►34''--r{ 2110� I TYPES 1 nun Fe4s"+{ VARIABLE WITH HEIGHT, REFER —� TO TABLE 2. 88" TYPE MZ Bmr TYPE LOOP BAR BENDING DIAGRAM GENERAL NOTES: a SECTION A -A SECTION B-B TABLE 2 QUANTITIES VARIABLE WITH HEIGHT NQ REO'0 LENGTH C.Y LIL H CONIC, STEEL 402 1 405 404 406 3 e 10 6 ! 2 1 2.7 219 4'O" 12 8 3'6" 2'7" 2.B 240 4' 8" 12 8 4' 2" 3' 1" 3.0 246 5' O" 14 10 d 8" 3' 7" 3.1 266 S'6" 14 10 S'2" 4'1' 3.3 272 e'0" 16 12 5'8" 4'7" 3.5 293 6' 8" IB 12 6' 2" VI* 36 299 7'O" 18 14 6'6" 3S 320 Yd' Is 14 T2" 39 326 do" 20 Is Ye" 4.1 3478' G" 20 IS d 2" 15'7" 4.2 353 9'O" 22 18 e'd' 4.4 373 9'8" 22 Is 9'2" 46 379 HYO" 24 20 9'S" 4.7 40D (DIMENSIONS ARE OUT CURB INLET - 4' OPENING TO OUT OF BAR) 1. QUANTITIES INCLUDE VOLUMES OCCUPIED BY PIPES. STRUCTURAL STEEL AND REINFORCEMENT AROUND PIPES ARE NOT INCLUDED. 2. KEY JOINTS WHERE WALLS CONNECT TO TOP SLAB AND BASE. 3. REINFORCEMENT IN WALLS AND BASE SHALL BE 30 FROM THE SIDES EXPOSED TO EARTH. REINFORCEMENT IN TOP SLAB SHALL BE 1 1/20 CLEAR. 0 L. A FOR VERTICAL CURB & G, TTEII, (REINFORCEMENT) IL CITY OF FORT COLLINS, COLORAD(" ENGINEERING SERVICES UNIT L APPROVED BY: DATE: vv REVISIONS: D-7L SECTION 00300 BID FORM PROJECT: CONCRETE PROJECT - PHASE I; BID NO. 5717 Place , %7,- � 5 Date/pa/p 1. In compliance with your Invitation to Bid dated and subject to all conditions thereof, the undersigned 1%jr",/ �.vmrP% ,TyG . a **(Corporation, • Limited Liability ComKany, Partnership, Joint Venture, or Sole Proprietor)** authorized to do business in the State of Colorado hereby proposes to furnish and do everything required by the Contract Documents to which this refers for the construction of all items listed on the following Bid Schedule or Bid Schedules. 2. The undersigned Bidder does hereby declare and stipulate that this proposal is made in good faith, without collusion or connection with any other person or persons Bidding for the same Work, and that it is made in pursuance of and subject to all the terms and conditions of the Invitation to Bid and Instructions to Bidders, the Agreement, the detailed Specifications, and the Drawings pertaining to the Work to be done, all of which have been examined by the undersigned. 3. Accompanying this Bid is a certified or cashier's check or standard Bid bond in the sum of ,3—�� ($ ) in accordance with the Invitation To Bid and Instructions to Bidders. 4. The undersigned Bidder agrees to execute the Agreement and a Performance Bond and a Payment Bond for the amount of the total of this Bid within fifteen (15) calendar days from the date when the written notice of the award of the contract is delivered to him at the address given on this Bid. The name and address of the corporate surety with which the Bidder proposes to furnish the `specified performance and payment bonds is as follows: $�,�/0n2� �ctSu�n/c�• , 5. All the various phases of Work enumerated in the Contract Documents with their individual jobs and overhead, whether specifically mentioned, included by implication or appurtenant thereto, are to be performed by the CONTRACTOR under one of the items listed in the Bid Schedule, irrespective of whether it is named in said list. 6. Payment for Work performed will be in accordance with the Bid Schedule or Bid Schedules subject to changes as provided in the Contract Documents. 7. The undersigned Bidder hereby acknowledges receipt of Addenda No. O through 7/96 Section 00300 Page 1 1 I / MACLEAR OR ARIIgVED EQUAL 3 0"1 3-0- 1 KI S"THICK SIDEWALK p ' (TYPICAL t BOTH SIDES) i P - ( WARPED CURB S SEE DETAIL p'• t GUTTER (TYPICAL _ BOTH SIDES) 4'0" OPENING ! Ie0" r A--*] PLAN VIEW f BE &5 FLUSH t WITH CURB \ I I/2"R. 1 "_I" Id* FACE N 411 _ .t 9 Q• . ( �S BAR 11/2" PIP SPACER ',,•a; '° AND 1 I/4'F`LOCK NUT •. n:• 2.1 H' A I V4`DIA.a 24" GALV. STEEL ROD -THREADED a 31/2"AT TOP. O % :.4 •. 1 4u 3"a3"s 3/8" PLATE CURB FACIE A�--�SSEIMBLY DETAIL L� GENERAL NOTES: 1. SEE 0-8b FOR REINFORCEMENT. 2. FLOOR OF INLET SHALL BE SHAPED WITH ADDITIONAL CONCRETE TO FORM INVERT TO PIPE CONNECTIONS. 13. MANHOLE RUNGS SHALL BE REOUIRED FOR INLET HEIGHTS 4'AND GREATER. ( 4. SIDEWALK SHALL BE 6- THICK FOR 3'0' ON EITHER SIDE OF INLET. S. TOP SLAB OF INLET SHALL BE SLOPED TO MATCH SIDEWALK. SEE 0-8. 6. EXPOSED STEEL SHALL BE GALVANIZED IN ACCORDANCE WITH AASHTO M-111 TOP OF CURB B SECTION A -A 6.40Y 6" GUTTER DEPRESSED GUTTER WARPED GUTTER NORMAL FLOWLINE b w; N 6° Q 2'6" MINIMUM ( ( UNLESS SQUASH F PIPE L4 USED) s ao 7W_ . S LDPE FOR O DRAINS E u SECTION B-B EXTEND CHANNEL TO OUTSIDE EDGE OF WALL DETAIL 6A" CURB INLET - 4' OPENING FOR DRIVE -OVER CURB & GUTTER CITY OF FORT COLLINS, COLORADO ENGINEERING SERVICES UNIT APPROVED BY: DATE: 361N REVISIONS: ME 0 9"OC. d'ac. WITH 11/2".ou OF CURB SECTION A —A A I . 0 1 z'o' s'o" PLAN VIEW 409 4ANCHM 7.1 TABLE I 503 BAR LIST FOR CURB INLET r 1 is (DIMENSIONS ARE OUT CURB INLET — 4' OPENING FOR TO OUT OF BAR) DRIVE -OVER CURB & GUTTER { GENERAL NOTES: (REINFORCEMENT) QUANTITIES INCLUDE VOLUMES OCCUPIED BY CITY OF FORT COLLINSe COLORAD PIPES. STRUCTURAL STEEL AND REINFORCEMENT AROUND PIPES ARE NOT INCLUDED. ENGINEERING SERVICES UNIT 2. KEY JOINTS WHERE WALLS CONNECT TO APPROVED BY: TOP SLAB AND BASE.Awe S. REINFORCEMENT IN WALLS AND BASE SHALL BE DATE: 43 G 4 3' FROM THE SIDES EXPOSED TO EARTH. REVISIONS: REINFORCEMENT IN TOP SLAB SHALL BE 1 1/2' CLEAR. ��Sb MARK DIA OC. TYPE Na lf]isM IK FACM REO'0 402 12" = + Y 10" 404 12" a 14 i1t 406 2" a 4 407 1/2" 12" a 2 9'O" 409 e" 3 4 3' 4" 410 Iz" 3c 6 6'10" 412 12" $ 4 3' 6" 601 9" a 2 V 0" 502 3 9" 3 1 4'9" 306 s" m i 9'd 304 T 6" a I e s" 601 3r14" — I e'10" c6 I LENOfH TYPE II Straight 04 404 411 411 TYPE �I I 402 �. U s4" 410 T SECTION B—B TYPES TABLE 2 'U QUANTITIES VARIABLE WITH HEIGHT I /2" 24" — 2 I'B" TO VARIABLE LLEE WITH HEIGHT, REFER AB — 9 TYPES 3 Bud TYPE L oopp BAR BENDING DIAGRAMS RE00. LENGTH C.Y. LL H ooNC. STEEL 114702 406 404 406 3' 6" 10 6 3'2 2 1' 2.3 210 4'0" 12 a Vito 2'7" Le 230 4'6" 12 6 4'2" 3'1" 2A 236 3'0" 14 10 4'6" 3'7" 2.9 236 S s I4 10 3 2 4 1 31 262 6'0" 1s 12 5`6" 47" 32 2e2 d s" 16 12 6' 2" el" 3A 2e9 7Or le 14 dd' S'7" 3.3 306 7'd' Ie 14 7' 2" s' 1" 37 314 it O" 20 K 7' 6" 6`7" 3.0 334 e's" 20 0d 2" Y I" 40 340 9'0" 22 16 d d' 7Y 41 340 22 16 WE' 6'1" I 43 366 Id O" 24 20 d 6" dT" 4.4 3e6 r oy j0 ML� � x W VV �4~iN e l x p x W n 02 jp y e h._u O� Q LLI m Z Q z 6 1n F- 20 0 N O Z/1 L4 J i o �i ki z 3 O p2 m i .B L.t/l I—� aaU3U W k` O z F . 31MO ,4/I 6f " o2 U z af Ld ~ 0000 z, 0000 1iJi T a Pr J 0 0 U_ � 4, D O� mamr C L 4j tam B rn L NBC ZaE �N 6 O NN odld mr a ip N N -mp LIW �.ZL 4 in ,.E N 1. a L N 4 •N fn .' lY ' ^ l . O - Ea ,c?i E v r 1X 7 N L �u V c� u C0 'Q V T T oa0000 N cr E 14 L oU hty Q V f•1 Q .L.. C E� m N H OCg'= cu U p Nr=q d W O Z ;ZiL Z A f'ma" N L U- J Q W 0 4WLLI Q m Pon rZ V / Q� a m cr O SO W U Z i U N �- Q W > z C, J a O �. 2 w O LL �I Z OW L �_ No Text CONCRETE CONSTRUCTION JOINT I r 4 G ui N Q 2 2 CA IN ID C uj W O O • J O HN O a W C3 1.- C9 W Q Q V 2 F 2 J W W ►+ SN Wcm � JJ m nZ• W LaiLa = m 4A H in Vf f^ 2 N �•s oqcim o 1-- W d W C F to C7 J W O D O d Ln W Z F i 2 CD U -6 2 H O C.J U. Vf 1 2° 1/8" R a a 5' TYPE A EXPANSION JOINT FILL WITH JOINT SEALER �1/8„ R d d d 3' 4° KEYWAY FORMED BY FASTENING METAL KEY TO FORM TYPE B LONGITUDINAL CONSTRUCTION JOINT PREMOLDED STRIP i (LUSH WITH SURFACE BACKER ROD i i i d i d �I TYPE C SAW -CUT OR PREMOLDED STRIP (LONGITUDINAL OR TRANSVERSE) RIGID PAVEMENT JOINT DETAILS IARIMER COUNTY CONSTRUCTION APPROVED: DRAWING URBAN AREA DATE: 08/07/00 STREET STANDARDS DRAWINGS DRAWN BY: BKP 8-14 SECTION 03500 PROJECT MAPS In Order of Area Priority: Hillcrest Crestmore Goldeneye Grandview Fairbrooke Hampshire Willox Lane Prospect Park Tenth Green Elizabeth street d 4 awNe � A n 4 g "nd Ttll s.Cr ndT l CL n� 4 4 « In. a 51. F i G 3gg' i 3 P R A F 3 G. Wx Fl.tl- oaed F Le«N W��n a SG G� Pye F n wl a 63 Oww A n q d. St. F R i r!'B R R4 3, n.N 6L D n F F S g Rn Ps.r bT g a q tt D« = g f g g gg S Tmbx Ian! .-0 P C. sss Dr. N' 3 g C`e.f1 FJ 9 s n — TYIx A. u F s.'W a. Fu j Q ANI Dr Vi P s! R v .rt s. o maemr vDr. g W v n i. ce ¢$FgF F rH�md R4 ?P ? Q Q &YrvmE R1 Mnn. ro = St. All Rd b. T.RHII R& po F Mrdwbo b P F p$ W Dr, 66 ad VJ ' Lark i arA ma q«Dc y C er 3�5 c Cn M g y Y\'O LnN Q L s Cl. � PC C A R undM Son.«Dr. 4 'pf 3 ct A9� ct o tt M.. S Dr. g € N. . � CaoF R. � 1 e� Do Ln. 4'6 BnnMo.d G. 'ORPn e N. F ai S.B 5 C cn.tlNtl« Ave. p �Nlun Are. 8y O9. A S nv 6 b: Aw. X Fl.�ad $ 'g� uMYD CL @ F i f Sd Dru Are. n F 1 Ron. tll Avesco a n H«IMri a Rd. . _ SOr b ,dddd 7 f l SL I 4 LYn«ae $ . Q q CA CRY Perk Ave. .Valk Ar . F Av.. `xP i f � v $ gel nG. tlry 3 F A' co S e L J.tlVan ABI 9 Co.` PR .M ? n e. �i BI bw11 A JamXM1 {yj Dr. Dr. t L b. lNdv St. nlev P� y W 3 Otl n BYAn W. . "I. N.M a NrM g O 9 lad weRyp.A� A G �a Pa s. q /y��a 1 P A i Z F 1 co i F S. WThombR s, I ane a F \ 4 � BraW.n tl F F P Dr. 3. N. N� Z cant.Av u s n m I No Text I/�/ to ,.G, P z�✓ t� . CO—N��/o� BY: V/��✓!/fX�E%� ADDRESS: 1313,81Ue *iY/GP 8. BID SCHEDULE (Base Bid) Please use the attached Bid Schedule. 9. PRICES The foregoing prices shall include all labor, materials, transportation, shoring, removal, dewatering, overhead, profit, insurance, etc., to cover the complete Work in place of the several kinds called for. Bidder acknowledges that the OWNER has the right to delete items in the Bid or change quantities at his sole discretion without affecting the Agreement or prices of any item so long as the deletion or change does not exceed twenty-five percent (25%) of the total Agreement Price. t RESPECULLY SUBMITTED: Signe IDate Title License Number (If Applicable) (Seal - if Bid Asbycorporation) Attest:_ Address Telephone 7/96 Section 00300 Page 2 n S. Sunset St. � ? � Stephens S' St. ; m i Dr. n 3 TT �RL Hillcrest Dr. �gPo S 0 Briarwood Rd. A Rd. Penns h St. BOO ct. m • e �r,eQo 0 .10 o �ooS �MoP o ° a �c .�� 6 0o a� ? n P� � d a y 'PN N r N ° �a 2i N \ N0A t N. Colleae Ave. Redcedar Cir n 0 m (nI v Blue Spruce Dr. wor Redwood St. Bre k, G) m v � m k d m c X m Valleyview, Ln. m o � •moo v a ae Suga rAi m � •�C v2S Muddler Yew Ste �CD aa�oP �� S Ct. o Ct. S hot �aaaoP Matuka =k m cn cn : r d ea St. G� c W @ Ct. � o� M N E3 Renegade D Ct. Go o c v, IsFO �a -o. Briarcliff Rd. c� Mary 9s�o Cir.AC Ridgecrest • �0 • C' z auatj r I 00330 i BID SCHEDULE r City of Fort Collins 2002 Concrete Project - Phase I Bid No.5717 202.01 Sawcut 4" L.F. 0 $ 3.00 $ 403.50 Temporary Patching Ton 425 $ 155.18 $ 65,951 50 604.10 Reconstruct Inlet Deck - Catch Basin Each I $ 1,000.00 $ 1,000.00 604.11 Reconstruct Inlet Deck - Catch Basin Additional Foot OpeningL.F. 0 $ 120.00 $ - 604.12 Reconstruct Curb Inlet Deck - 4' O enin Each t $ I,100.00 $ 1,100.()0 604.13 Reconstruct Curb Inlet Deck - Additional Foot Opening L.F. 0 $ 170.00 $ - 604.14 Type 13 - Curb Inlet with Frame, Grate and Adjustable Curb Bonnet Each 1 $ 1,560.00 $ 1,560.00 604.15 Concrete Sidewalk Culvert Each 0 $ 1,200.00 $ - 604.16 Metal Sidewalk Culvert - 5/8" Plate Each 2 $ 1,450.00 $ 2,900.00 604.17 Additional Square Foot 5/8" Plate S.F. 0 $ 120.00 $ - 604.18 Catch Basin Inlet Each 0 608.01 Remove and Haul Fillets Each 0 $ 120.00 $ 608.02 Apron - Remove and Replace S.F. 6100 $ 6.60 $ 40,260.00 608.03 Cross an - Remove and Replace S.F. 4800 $ 6.60 $ 31,680.00 608.04 Driveover Curb, Gutter & 4" Sidewalk - Remove and R lace L.F. 1350 $ 34.25 $ 46,237.50 608.05 Driveover Curb, Gutter and 6" Sidewalk - Remove and R lace L.F. 750 $ 36.75 $ 27,562.50 608.06 Driveover Curb and Gutter - No Sidewalk - Remove and Re lace L.F. 25 S 21.40 $ 535.00 60807 Driveover Curb, Gutter & Drive Approach - Remove and Replace L.F. 20 $ 36.00 $ 720.00 608.08 Vertical Curb, Gutter & 4" Sidewalk - Remove and Replace L.F. 300 $ 39.00 $ 11,700.00 608.09 Vertical Curb, Gutter & 6" Sidewalk - Remove and Replace L.F. I50 $ 41.00 $ 6,150.00 608.10 Vertical Curb and Gutter - No Sidewalk - Remove and R lace L.F. 2900 $ 25.50 $ 73,950.00 608.11 Vertical Curb, Gutter and Drive Approach - Remove and Replace L F. 550 $ 39.00 $ 21,450.00 608A2 Vertical Curb, Gutter and Drive Approach - No Sidewalk - Remove and Replace L.F. 75 $ 25.50 $ 1,912.50 608.13 Vertical Outfall Curb and Gutter - Remove and Replace L.F. 25 $ 22.00 $ 550.00 608.14 Hollywood Curb, Gutter & 4" Sidewalk - Remove and R lace L.F. 2800 $ 31.50 $ 88,200.00 608.15 Hollywood Curb, Gutter & 6" Sidewalk - Remove and Re lace L.F. 900 $ 33.00 $ 29,700.00 608.16 Hollywood Curb and Gutter - No Sidewalk - Remove and Replace L.F. 35 $ 21.00 $ 735.00 608.17 Hollywood Curb, Gutter & Drive Approach - Remove and Replace L.F. 475 $ 33.00 $ 15,675.00 608.18 Highback Curb & Gutter -No Sidewalk- Remove and Replace L.F. 0 $ 32.00 $ 608.19 Highback Curb, Gutter and Drive Approach - Remove and Replace L.F. 0 $ 38.00 $ 608.20 Pedestrian Access Ramp, Driveover Curb Remove and R lace L.F. 500 $ 44.00 $ 22,000,00 608.21 Pedestrian Access Ramp - Vertical Curb - Remove and Replace L.F. 200 $ 40.50 $ 8,100.00 608.22 Ren Access Ram p - Hollywood Curb - Remove and Replace L.F. 375 $ 38.00 $ 141250.00 608.23 Pedestrian Access Ramp - Highback Curb - Remove and Re lace S.F. 0 $ 9.00 $ 608.24 4" Fla[work -Aemove & R lace EM S.F. 1050 $ 4.90 $ 5 145.00 Pagel of 2 CONTRACT DOCUMENTS TABLE OF CONTENTS Section BID INFORMATION 00020 Notice Inviting Bids 00100 Instruction to Bidders 00300 Bid Form 00400 Supplements to Bid Forms 00410 Bid Bond 00420 Statements of Bidders Qualifications 00430 Schedule of Major Subcontractors CONTRACT DOCUMENTS t 00500 Agreement Forms 00510 Notice of Award 00520 Agreement t 00530 Notice to Proceed 00600 Bonds and Certificates 00610 Performance Bond 00615 Payment Bond 00630 Certificate of Insurance 00635 Certificate of Substantial Completion 00640 Certificate of Final Acceptance 00650 Lien Waiver Release(Contractor) 00660 Consent of Surety 00670 Application for Exemption Certificate j CONDITIONS OF THE CONTRACT 00700 General Conditions Exhibit GC -A 00800 Supplementary Conditions 00900 Addenda, Modifications, and Payment 00950 Contract Change Order 00960 Application for Payment SPECIFICATIONS Pages 00020-1 - 00020-2 00100-1 - 00100-9 00300-1 - 00300-4 00400-1 00410-1 - 00410-2 00420-1 - 00420-3 00430-1 00500-1 00510-0 00520-1 - 00520-6 00530-1 00600-1 00610-1 - 00610-2 00615-1 - 00615-2 00630-1 00635-1 00640-1 00650-1 - 00650-2 00660-1 00670-1 - 00670-2 00700-1 - 00700-34 GC -Al - GC-A2 00800-1 - 00800-2 00900-1 00950-1 - 00950-2 00960-1 - 00960-2 00330 BID SCHEDULE City of Fort Collins 2002 Concrete Project - Phase 1 Bid No.5717 Six Hundred Seven Thousand, Seven Hundred T renty Eight lars, and Ten Cents. Signed ( Address - t Company f PhonelFax ' Check One: Individual Doing Business in Company Name Corporation Partnership Page 2 of 2 SECTION 00400 SUPPLEMENTS TO BID FORMS 1 i 00410 Bid Bond A A 00420 Statement of Bidder's Qualifications 00430 Schedule of Subcontractors 7/96 Section 00410 Page 1 BID BON '.,:-\iCW ALL MEN BY THESE PRESENTS: that we, the undersigned Vogel Concrete. Inc. P j Fort Collins, Colorado as Principal, and Inland Insurance Company as Surec;,, are hereby held and firmly bound unto the City of Fort Collins, Colorado, as Owner, in the penal sum of Five Percent of Bid for the paywenc of which, well and tr,ily to be made, we heraby jointly and severally bind ourselves, successors, and assigns. TEE CvYD_==ON of_ this obiigaz_ois sc^: th'- whereas the F:'_ac_pa_ has submitted to the City of Fort Collins, Colorado the accompanying bid and hereby mace a pare hereof to enter i.^.co a C,^struction zgrsenent `or the construc.'_en of City of Fort Collins ?rcject, Bid No. 5717, Concrete Project - Phase I, Fort Collins, Colorado W'ERZ-AS, the Owner, as a condition for receiving said bid, recir ued the Principal to deposit with the Owner a Bid Guaranty equal to five percent (5z) of the amount of said bid. NOW, THEREFORE, (aj =E said bid shall be reject=_d; or in the alternate, (b) If said bid shall be accepted and the Principal shall execute and deliver a Construction Agreement (properly completed in accordance with said bid) and shall furnish a Performance and Payment Bond upon the Earns prescribed by the Owner for the faithful performance of said Agreement; and shall in all other respects perform the agreement created by the acceptance of said bid; then this obligation shall be void, other -wise the same shall remain in force and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated. The Surety, for value received, hereby stipulates and agrees that,, the obligations of said Surety and its bond shall be in no way impaired or affected by any extension of the time within which the Owner may accept such bid; and said Surety does hereby waive notice of any such extension. IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals this 2nd day of July , MOW and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above. pRINCI?9L 5ti ;rTy Name: Vogel Concrete, Inc. Inland Insurance Company Address:1313 Blue S ruce Drive, Suite B P. 0. Box 80468 F t Colliry;, C 0524 Lincoln, NE 68501 Bv: Title: Celeste T. Moore -Helms ttorney-in-Fact (SEAL) (S=?L) NOTE: Suret7 Companies executing bands must be authcrized to transact business i.. the State_ c Colorado and be acceptable to t^.e Owner. LOCKTM LOCKTON COMPANIES Post Office Box 469000 / Denver, CO 80246.9000 (303) 753.2000 / Fax: (303) 753.2099 INLAND INSURANCE COMPANY Lincoln, Nebraska POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That the INLAND INSURANCE COMPANY, a corporation of the State of Nebraska having its principal office in the City of Lincoln, Nebraska, pursuant to the following Bylaw, which was adopted by the Board of Directors of the said Company on July 23, 1981, to wit: "Article V-Section 6. RESIDENT OFFICERS AND ATTORNEYS -IN -FACT. The President or any Vice President, acting with any Secretary or Assistant Secretary, shall have the authority to appoint Resident Vice Presidents and Attorneys -In -Fact, with the power and authority to sign, execute, acknowledge and deliver on its behalf, as Surety: Any and all undertakings of suretyship and to affix thereto the corporate seal of the corporation. The President or any Vice President, acting with any Secretary or Assistant Secretary, shall also have the authority to remove and revoke the authority of any such appointee at any time." does hereby make, constitute and appoint GARRY L. WESSELINK OR KAREN A. FEGGESTAD OR SHELLEY CZAJKOWSKI OR ➢EBBIE POPPE OR CELESTE T. MOORE—HELMS OR DEBBIE A. HASLAM OR WILLIAM M. O'CONNELL, DENVER, COLORADO its true and lawful Attomey(s)-in-Fact, to make, execute, seal and deliver for and on its behalf, as Surety: Any and all undertakings of suretyship And the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon said Company, as fully and amply, to all intents and purposes, as if they had been duly executed and acknowledged by the regularly elected officers of the Company at its offices in Lincoln, Nebraska, in their own persons. The following Resolution was adopted at the Regular Meeting of the Board of Directors of the INLAND INSURANCE COMPANY, held on July 23, 1981: "RESOLVED, That the signatures of officers of the Company and the seal of the Company may be affixed by facsimile in any Power of Attorney executed in accordance with Article V-Section 6 of the Company Bylaws: and that any such Power of Attorney bearing such facsimile signatures, including the facsimile signature of a certifying Assistant Secretary and facsimile seal shall be valid and binding upon the Company with respect to any bond, undertaking or contract of suretyship to which it is attached." All authority hereby conferred shall remain in full force and effect until terminated by the Company. IN WITNESS WHEREOF, INLAND INSURANCE COMPANY has caused these presents to be signed by its Vice President and its corporate seal to be hereunto affixed this 29 day of JANUARY 20 02 . l Secretary By State of Nebraska ) ) ss. County of Lancaster ) INLAND INSURANCE COMPANY �VV V Vice President On this 29 day of JANUARY , 20-02_, before me personally carve Robert L. Pnvett, to me known, who being by me duly swom, did depose and say that (s)he resides in the County of Seward, State of Nebraska; that (s)he is the Vice President of the INLAND INSURANCE COMPANY, the corporation described in and which executed the above instrument; that (s)he knows the seal of the said corporation; that the seal affixed to the said instrument is such corporate seal; that it was so affixed by order of the Board of Directors of said corporation; that (s)he signed (his) (her) name by like order, and that Bylaw, Article V-Section 6, adopted by the Board of Directors of said Company, referred to in the preceding instrument, is now in force. II GENERAL NOTARY -Sate of Nebruh CHERYL A. BROWN Mr creme. Elm. AprN tz !M My Commission Expires April 12, 2003. Notary Public Cx 4 4yt: 6 1, Jeanne Beno, Assistant Secretary of INLAND INSURANCE COMPANY, do hereby certify that the above and foregoing is a out mud correct copy of a Power of Attorney executed by mid INLAND INSURANCE COMPANY, which is still in full [force and effect. Signed and sealed at the City of Lincoln, Nebraska this grid day of July , 2002 .y Assistant secretary eoaroamrE 9Eal SECTION 00420 STATEMENT OF BIDDER'S QUALIFICATIONS All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires. 1. Name of Bidder: %Oq c.pi/OI^�i✓y 2. Permanent main office address: �y�UG2 dr, �T (011--b-5 3. When organized: / % 7 IR 4. If a corporation, where incorporated: (n� 5. How many years have you been engaged in the contracting business under your present firm or trade name? ,�%'Y 6. Contracts on hand: (Schedule these, showing the amount of each contract and the appropriate anticipated dates of completion.) 7. General character of Work perform ed by your company: XZ �N✓C.!^elC� 2. &5 �rd� �iT✓es 8. Have you ever failed to If so, where and why? complete any Work awarded to you? XVO 9. Have your ever defaulted If so, where and why? on a contract? X/ o 10. Are you debarred by any If yes list agency name. government agency? tie) 7/96 Section 00420 Page 1 11. List the more important projects recently completed by your company, stating the approximate cost of each, and the month and year completed, location and tvpe of construction. 12. List your major equipment available for this contract. 13. Experience in construction Work similar in importance to this project: I 14. Background and experience of the principal members of your organization, including officers: / as 15. Credit available: $ cSS��D00� 16. Bank reference: V¢S 17. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the OWNER? 18. Are you licensed as a General CONTRACTOR? 16�ce9-111 If yes, in what city, county and state? What class, license and numbers? 19. Do you anticipate subcontracting Work under this Contract? q/p If yes, what percent of total contract? and to whom? 20. Are any lawsuits pending against you or your firm at this time? 041 If yes, DETAIL 7/96 Section 00420 Page 2 I I 9 21. What are the limits of ypur public liability? DETAIL t company? 22. What are your company's bonding limitations? 23. The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by the OWNER in verification of the recital comprising this Statement of Bidder's Qualifications. Dated at Wtjb NC -his ___L— day of 20(�. Title: State of dLIg 45l c County of Iarj'04 CO being duly sworn deposes and says that he is ✓cri�c .7i c-- and that (name of organization) the answers to the foregoing questions and all statements therein contained are true and correct. Subscribed, and sworn to before me this / day of .]^ca 20PAJ Q�. Nota y Pub c �Vv - ^0:16, My commission expires �A MY 7/96 Section 00420 Page 3 SECTION 00430 SCHEDULE OF SUBCONTRACTORS List all subcontractors for the work items listed below and all subcontractors performing over 100 of the contract. ITEM SUBCONTRACTOR 7/96 Section 00430 Page 1 SECTION 00500 AGREEMENT FORMS 00510Notice of Award 00520Agreement 00530Notice to Proceed I I SECTION 00020 INVITATION TO BID I f SECTION 00510 NOTICE OF AWARD Date: August 7, 2002 TO: Vogel Concrete, Inc. PROJECT: CONCRETE PROJECT - PHASE I; BID NO. 5717 OWNER: CITY OF FORT COLLINS (hereinafter referred to as "the OWNER") You are hereby notified that your Bid dated July 2, 2002 for the above project has been considered. You are the apparent successful Bidder and have been awarded an Agreement for CONCRETE PROJECT - PHASE I; BID NO. 5717. The Price of your Agreement is Six Hundred Seven Thousand Seven Hundred Twenty- eight Dollars and Ten cents ($607 728.10). Three (3) copies of each of the proposed Contract Documents (except Drawings) accompany this Notice of Award. Three (3) sets of the Drawings will be delivered separately or otherwise made available to you immediately. You must comply with the following conditions precedent within fifteen (15) days' of the date of this Notice of Award, that is by August 22, 2002. 1. You must deliver to the OWNER three (3) fully executed counterparts of the Agreement including all the Contract Documents. Each of the Contract Documents must bear your signature on the cover of the page. 2. You must deliver with the executed Agreement the Contract Security (Bonds) as specified in the Instructions to Bidders, General Conditions (Article 5.1) and Supplementary Conditions. Failure to comply with these conditions within the time specified will entitle OWNER to consider your Bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited. Within ten (10) days after you comply with those conditions, OWNER will return to you one (1) fully -signed counterpart of the Agreement with the Contract Documents attached. Cit of Fort Collins 0 ER A1 n By / / Al mes B. O'Neill II, CPPO, FNIGP Dire to of Purchasing and Risk Management Title 9/12/01 Section 00510 Page 1 SECTION 00520 AGREEMENT THIS AGREEMENT is dated as of the 7th day of August in the year of 2002 and shall be effective on the date this AGREEMENT is signed by the City. The City of Fort Collins (hereinafter called OWNER) and Vogel Concrete, Inc. (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: ARTICLE 1. WORK CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Project for which the Work under the Contract Documents may be the whole or only a part is defined as the removal and/or installation of concrete curbs, gutters, sidewalks, crosspans, aprons, drive approaches and pedestrian access ramps, and placement of temporary asphalt patching adjacent to new concrete, on designated streets in the City of Fort Collins and is generally described in Section 01010. ARTICLE 2. ENGINEER The Project has been designed by City ` hereinafter called ENGINEER and who will and will have the rights and authority Documents in connection with completion Contract Documents. ARTICLE 3. CONTRACT TIMES of Fort Collins Engineering, who is assume all duties and responsibilities assigned to ENGINEER in the Contract of the Work in accordance with the 3.1 Contract Period. This Agreement shall commence when this contract is signed by the City, and shall continue in full force until June 30, 2003, unless sooner terminated as herein provided. In addition at the option of the City, the agreement may be extended for additional one year periods not to exceed two (2) additional one year periods. Pricing changes, if any, shall be negotiated by and agreed to by both parties in writing. 3.2 The Work shall be Substantially Complete within 65 working days after the date when the Contract Times commence to run as provided in the General Conditions and completed and ready for Final Payment and Acceptance in accordance with the General Conditions within 70 working days after the date when the Contract Times commence to run. 3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1. above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. 9/12/01 Section 00520 Page 1 } They also recognize the delays, expenses and difficulties involved in proving in a legal proceeding the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as penalty) CONTRACTOR shall pay OWNER the amounts set forth hereafter. 1) Substantial Completion: One Thousand Dollars ($1,000.00) for each calendar day or fraction thereof that expires after the Sixty-five (65) working day period for Substantial Completion of the Work until the Work is Substantially Complete. 2) Final Acceptance: After Substantial Completion, Five Hundred Dollars ($500.,00) for each calendar day or fraction thereof that expires after the Five (5) working day period for Final Payment and Acceptance until the Work is ready for Final Payment and Acceptance. ARTICLE 4. CONTRACT PRICE 4.1. OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: ($607,728.10), Six Hundred Seven Thousand Seven Hundred Twenty-eight Dollars and Ten cents, in accordance with Section 00300, attached and incorporated herein by this reference. ARTICLE 5. PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Application for Payment as recommended by ENGINEER, once each month during construction as provided below. All progress payments will be on the basis of the progress of the Work measured by the schedule of values established in paragraph 2.6 of the General Conditions and in the case of Unit Price Work based on the number of units completed, and in accordance with the General Requirements concerning Unit Price Work. 3.1.1. Prior to Substantial Completion, progress payments will be in the amount equal to the percentage indicated below, but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with paragraph 14.7 of the General Conditions. 90% of the value of Work completed until the Work has been 50% completed as determined by ENGINEER, when the retainage equals 5% of the Contract Price, and if the character and progress of the Work have been satisfactory to OWNER and ENGINEER, OWNER on recommendation of ENGINEER, may determine that as long as the character and progress of the Work remain satisfactory to them, there will be no additional retainage on account of Work 9/12/O1 Section 00520 Page 2 completed in which case the remaining progress payments prior to Substantial Vj Completion will be in an amount equal to 100% of the Work completed. 90% of materials and equipment not incorporated in the Work (but delivered, suitably stored and accompanied by documentation satisfactory to OWNER as provided in j paragraph 14.2 of the General Conditions) may be included in the application for payment. 5.1.2. Upon Substantial Completion payment will be made in an amount sufficient to increase total payments to CONTRACTOR to 95% of the Contract Price, less such amounts as ENGINEER shall determine or OWNER may withhold in accordance with paragraph 14.7 of the General Conditions or as provided by law. v 5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER,shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.13. ARTICLE 6. CONTRACTOR'S REPRESENTATION In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: 6.1. CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents, Work, site, locality, and with all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work. 6.2. CONTRACTOR has studied carefully all reports of explorations and tests of subsurface conditions and drawings of physical conditions which are identified in the Supplementary Conditions as provided in paragraph 4.2 of the General Conditions. } 6.3. CONTRACTOR has obtained and carefully studied or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests, reports, and studies (in addition to or to supplement those referred to in paragraph 6.2 above) which pertain to the subsurface or physical condition at or contiguous to the site or otherwise may affect the cost, progress, performance or furnishing of the Work as CONTRACTOR considers necessary for the performance or furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of paragraph 4.2 of the General Conditions; and no additional examinations, investigations, explorations, tests, reports, studies or similar information or data are or will be required by CONTRACTOR for such purposes. 6.4. CONTRACTOR has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, tests, reports, studies or similar information or data in respect of said Underground Facilities are or will be required by 9/12/O1 Section 00520 Page 3 -r CONTRACTOR in order to perform and furnish the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provision of paragraph 4.3. of the General Conditions. 6.5. CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports and data with the terms and conditions of the Contract Documents. 6.6. CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. ARTICLE 7. CONTRACT DOCUMENTS 7.1 The Contract Documents which comprise the entire Agreement between OWNER and CONTRACTOR concerning the Work consist of the General Conditions, Supplementary Conditions, those items included in the definition of "Contract Documents" in Article 1.10 of the General Conditions, and such other items as are referenced in this Article 7, all of which are incorporated herein by this reference. 7.2 Forms for use by CONTRACTOR in performing the Work and related actions in carrying out the terms of this Agreement are deemed Contract Documents and incorporated herein by this reference, and include, but are not limited to, the following: 7.2.1 Certificate of Substantial Completion 7.2.2 Certificate of Final Acceptance 7.2.3 Lien Waiver Releases 7.2.4 Consent of Surety 7.2.5 Application for Exemption Certificate 7.2. 6 Application for Payment 7.4. Addenda Numbers NA to NA, inclusive. 7.5. The Contract Documents also include all written amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to paragraphs 3.5 and 3.6 of the General Conditions. 7.6. There are no Contract Documents other than those listed or incorporated by reference in this Article 7. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of the General Conditions. ARTICLE 8. MISCELLANEOUS 8.1. Terms used in this Agreement which are defined in Article I of the General Conditions shall have the meanings indicated in the General Conditions. 8.2. No assignment by a party hereto of any rights under or interests in 9/12/O1 Section 00520 Page 4 the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but not without limitations, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge that assignor from any duty or responsibility under the Contract Document. 8.3. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, Agreement and obligations contained in the Contract Document. OWNER: CITY OF FORT COLLINS By. Plas JOHjE. 1SCHBACH MA'N(AGi BY: 1L- uUJAMO'NEI L II, CPPO, FNIGP TOR OF PURCHASING RISK NAGEM T Date: `7 (� �� i Attest: . It Address for � 4ig5'—inb,tlice: P. O. Box 58 Fort Collins, Approved as to Form City Assistant City Attorney CONTRACTOR, Vogel Concrete, C. Title: Date: (CORPORATE SEAL) Attest: Address for giving notices: 1313 BLUE SPRUCE DR. FT m INg LICENSE NO.: 9/12/01 Section 00520 Page 5 t SECTION 00530 '. NOTICE TO PROCEED Description of Work: CONCRETE PROJECT - PHASE I; BID NO. 5717 To: This notice is to advise you: That the contract covering the above described Work has been fully executed by the CONTRACTOR and the OWNER. That the required CONTRACTOR's Performance Bond and Payment Bond have been received by the OWNER. i That the OWNER has approved the said Contract Documents. Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and directed to proceed within ) calendar days from receipt of this notice as required by the Agreement. Dated this day of 20 The dates for Substantial Completion and Final Acceptance shall be and 20_, respectively. City of Fort Collins OWNER By: Title: ACKNOWLEDGMENT OF NOTICE Receipt of the above Notice to Proceed is hereby acknowledged this day of 20 CONTRACTOR By: Title: 7/96 Section 00530 Page 1 SECTION 00600 t 1 BONDS AND CERTIFICATES t 00610Performance Bond 00615 Payment Bond 00630Certificate of Insurance 00635Certificate of Substantial Completion 00640 Certificate of Final Acceptance 00650Lien Waiver Release (CONTRACTOR) y 00660 Consent of Surety t 00670Application for Exemption Certificate 00600 PERFORMANCE BOND Bond No. 791820 t KNOW ALL MEN BY THESE PRESENTS: that i (Firm) Vogel Concrete, Inc (Address) 1313 Blue Spruce Drive, Suite B Fort Collins, CO 80524 (� €scxesls, (a Corporation), hereinafter referred to as "the Principal," and (Firm) Inland Insurance Company (Address) P. O. Box 80468 Lincoln, NE 68501 hereinafter referred to as "the Surety", a corporation authorized to do business in the State of Colorado, are held and firmly bound unto the City of Fort Collins, 300 West LaPorte Avenue, Post Office Box 580, Fort Collins, Colorado 80522, a Municipal Corporation, hereinafter referred Siz Huntlretl Seven Thous Seven ($ 607,728.10 ) in lawful to as "the Owner", in the penal SUM of Huntlun led nryelg�tooerd16vonand ,00 money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Construction Agreement with the Owner, dated the 7th day of August 2002, a copy of which is hereto attached and made a part hereof for the performance of City of Fort Collins Bid No. 5717; Concrete Project - Phase I, Fort Collins, Colorado NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Construction Agreement during the original term thereof, and any extensions thereof which may be granted by the Owner, Page 1 of 3 with or without Notice to the Surety and during the life of the guaranty period, and if the Principal shall satisfy all claims and demands incurred under such Contract Agreement, and shall fully indemnify and save harmless the Owner from all cost and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, and then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Agreement or to the work to be performed thereunder or the specifications accompanying the same shall in anyway affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Agreement or to the work or to the specifications. PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. IN WITNESS WHEREOF, this instrument is executed in three counterparts, each one of which shall be deemed an original, this 14th day of August 2002. IN PRESENCE OF: (CORPORATE SEAL) Principal Vogel Conc �ieklnc By: -eWW (Title) 1313 Blue Spruce Drive, Suite B Fort Collins, CO 80524 (Address) Page 2 of 3 SECTION 00020 INVITATION TO BID Date: June 10, 2002 Sealed Bids will be received by the City of Fort Collins (hereinafter referred to as OWNER), at the office of the Purchasing Division, 3:00 P.M., our clock, on July 2, 2002, for the CONCRETE PROJECT PHASE I; Bid No. 5717. If delivered, they are to be delivered to 215 North Mason Street, 2"d Floor, Fort Collins, Colorado, 80524. If mailed, the mailing address is P. 0. Box 580, Fort Collins, CO 80522- 0580. At said place and time, and promptly thereafter, all Bids that have been duly received will be publicly opened and read aloud. The Contract Documents provide for removal and/or installation of concrete curbs, gutters, sidewalks, crosspaps, aprons, drive approaches and pedestrian access ! ramps, and placement of temporary asphalt patching adjacent to new concrete, on designated streets in the City of Fort Collins. Specific locations are described in Specifications, Section 02500, Quantity Estimate. All Bids must be in accordance with the Contract Documents on file with The City of Fort Collins, 215 North Mason St., 2nd floor, Fort Collins, Colorado 80524. -; Contract Documents will be available June 12, 2002. _E Copies of the Contract Documents, complete with Construction Specifications and Drawings, may be obtained from Purchasing Division at 215 North Mason St., 2nd floor, Fort Collins, Colorado, 80521 upon payment of a refundable fee of Fifty Dollars ($50.00) per set. No partial sets will be issued. . The Contract Documents and Construction Drawings may be examined at: •� 1. City of Fort Collins, Purchasing Division. 2. The Daily Journal, 2000 S. Colorado Blvd. Suite 2000, Denver, Colorado. 3. CMD Denver Plan Room, 9250 E Costilla Ave, STE 400, Englewood, CO 4. Builders Exchange, 223 South Link Lane, Fort Collins, Colorado. 5. The Plan Room, 2176 South Jasmine St. Door "E"/Suite 219, Denver, Colorado. A prebid conference and job walk with representatives of prospective Bidders will be held at 9:00 a.m. on June 19, 2002, at 215 North Mason, 2"d Floor, Conference Room 2A. Prospective Bidders are invited to present their questions relative to this Bid proposal at this meeting. Bids will be received as set forth in the Bidding Documents. The Work is expected to be commenced within the time as required by Section 2.3 of General Conditions. Substantial Completion of the Work is required as specified in the Agreement. 07/2001 Section 00020 Page 1 Other Partners IN PRESENCE OF: _ 1 By: I0 I0 Surety IN PRESENCE OF: Inland I u nce On mp By. _ t Attorney -in -Far Celeste T. Moore -Helms s Karen A. Feggestad P. O. Box 80468 Lincoln, NE 68501 (Address) (SURETY SEAL) NOTE: Date of Bond must not be prior to date of Construction Agreement. If Contractor is Partnership, all parmers should execute Bond. IOCKTON LOCKTON COMPANIES Post Office Box 4690001 Denver, CO 80246.9000 (303) 753-2000 /Fax: (303) 753.2099 Page 3 of 3 n 00601 PAYMENT BOND Bond No.791820 KNOW ALL MEN BY THESE PRESENTS: that (Firm) Vogel Concrete Inc. (Address) 1313 Blue Spruce Drive Suite B Fort Collins CO 80524 (an Individual), (a Partnership), (a Corporation), hereinafter referred to as "the Principal", and (Firm) Inland Insurance Company (Address) P. O. Box 80468 Lincoln, NE 68501 hereinafter referred to as "the Surety", a corporation authorized to do business in the State of Colorado, are held and firmly bound unto the City of Fort Collins, 300 West LaPorte Avenue, Post Office Box 580, Fort Collins, Colorado 80522, a Municipal Corporation, hereinafter referred to as "the Owner," in the penal sum of sixWnaeasevenThousanaseven $607,728.10 HunNeC Twenty Eigl,l dollars and iWlW 1 1 in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Construction Agreement with the Owner, dated the 7th day of August 2002, a copy of which is hereto attached and made a part hereof for the performance of City of Fort Collins Bid No. 5717; Concrete Project - Phase I, Fort Collins, Colorado NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such Construction Agreement, and any authorized extension or Page I of 3 modification thereof, including all amounts due for materials, lubricants, repairs on machinery, equipment and tools, consumed, rented or used in connection with the construction of such work, and all insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Construction Agreement or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Construction Agreement or to the work or to the specifications. PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. IN WITNESS WHEREOF, this instrument is executed in three counterparts, each one of which shall be deemed an original, this 14th day of August 2002. IN PRESENCE OF: (CORPORATE SEAL) Prince al Vogel Concr e Inc. By: r� (Title) 1313 Blue Spruce Drive, Suite B Fort Collins, CO 80524 (Address) Other Partners Page 2 of 3 IN PRESENCE OF: IN PRESENCE OF: By: By: By: Surety Attorney -in - Celeste T. Karen A. Feggestad P. O. Box 80468 Lincoln, NE 68501 (Address) (SURETY SEAL) NOTE: Date of Bond must not be prior to date of Construction Agreement. If Contractor is Partnership, all partners should execute Bond. qnp LOCKTON LocKTON COMPANIES Post Office Box 469000 / Denver, CO 80246.9000 (303) 753.2000 /Fax: (303) 753.2099 Page 3 of 3 INLAND INSURANCE COMPANY Lincoln, Nebraska POWER OF ATTORNEY KNOW ALL NLEN BY THESE PRESENTS: That the INLAND INSURANCE COMPANY, a corporation of the State of Nebraska having its principal office in the City of Lincoln, Nebraska, pursuant to the following Bylaw, which was adopted by the Board of Directors of the said Company on July 23, 1981, to wit: "Article V-Section 6. RESIDENT OFFICERS AND ATTORNEYS-IN-FAC—r. The President or any Vice President. acting with any Secretary or Assistant Secretary, shall have the authority to appoint Resident Vice Presidents and Attomeys-In-Fact, with the power and authonty to sign, execute, acknowledge and deliver on its behalf, as Surety: Any and all undertakings of suretyship and to affix thereto the corporate seal of the corporation. The President or any Vice President, acting with any Secretary or Assistant Secretary, shall also have the authority to remove and revoke the authority of any such appointee at any time." does hereby make, constitute and appoint GARRY L. WESSELINK OR KAREN A. FEGGESTAD OR SHELLEY CZAJKOWSKI OR DEBBIE POPPE OR CELESTE T. MOORE—HELMS OR DEBBIE A. HASLAM OR WILLIAM M. O'CONNELL, DENVER, COLORADO its true and lawful Attonrcy(s)-in-Fact, to make, execute, scat and deliver for and on its behalf, as Surety: Any and all undertakings of suretyship And the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon said Company, as fully and amply, to all intents and purposes, as if they had been duly executed and acknowledged by the regularly elected oficets of the Company at its offices in Lincoln, Nebraska, in their own persons. The following Resolution was adopted at the Regular Meeting of the Board of Directors of the INLAND INSURANCE COMPANY, held on July 23. 1981: "RESOLVED, That the signatures of ofcen of the Company and the seal of the Company may be affixed by facsimile to any Power of Attorney executed in accordarim with Article VSection 6 of the Company Bylaws: and that any such Power of Attorney bearing such facsimile signatures, including the facsimile signature of a certifying Assistant Secretary and facsimile seal shall be valid and binding upon the Company with respect to any bond, undertaking or contract of suretyship to which it is attached." All authority hereby conferred shall remain in full force and et&ct until terminated by the Company. IN WITNESS WHEREOF, INLAND INSURANCE COMPANY has caused these presents to be signed by its Vice President and its corporate seal to be hereunto affixed this 29 day of JANUARY I 20 02 . ��l� / Secrehary By State of Nebraska ) ) ss. County of Lancaster ) INLAND INSURANCE COMPANY Vice President On this 29 day of JANUARY , 20--Q2_, before me personally came Robert L. Pnveh, to me known, who being by me duly swum, did depose and say that (s)he resides in the County of Seward State of Nebraska; that (s)he is the Vice President of the INLAND INSURANCE COMPANY, the corporation described in and which executed the above mstrumenC that (s)he knows the seal of the said corporation; that the seal affixed to the said instrument is such corporate seal; that it was so affixed by order of the Board of Directors of said corporation; that (s)he signed (his) (her) name by like order, and that Bylaw, Article V-Section 6, adopted by the Board of Directors of said Company, referred to in the preceding instrument, is now in force. 6ENEAAL NODIRKSWe of NRblazka CHl3iYL A. BROWN NY Conran. F3�. Apol 12, 20IXi My Commission Expires April 12, 2003. Notary Public ( U G 1, Jeanne Beno. Assistant Secretary of INLAND INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney executed by said INLAND INSURANCE COMPANY, which is still in full force and effect Signed and sealed at the City of Lincoln, Nebraska this 14th day of August , 2o02 CORPoRRIF jjjjjj SF14 � � ��� Assistant Secrr.2ary ('I icn i-4k- 10anQ ACORO. CERTIFICATE OF LIABILITY INSURANCE DATE 25///0 06/2 PflODUCER THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION Flood & Peterson Insurance Inc ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE 4821 Wheaton Drive HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. P O Box 270370 Fort Collins, CO 80527 INSURERS AFFORDING COVERAGE INSURER Vogel Concrete Inc. INSURER A: P1nnaC01 Assurance INSURER B: 1313 Blue Spruce Dr #B INSURER C: — Fort Collins, CO 80524 INSURER 0: _ 11 ICI � � OA� INSURER E: THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING j ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR j MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS, NSR I LTR TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE DATE MM/DD/YY POLICY E%PIRATION DATE MM/DD/YY --- LIMITS I GENERAL LIABILITY COMMERCIAL GENERAL LIABILITY CLAIMS MADE II OCCUR EACH OCCURRENCE $ FIRE DAMAGE (Any one fire) $ MED EXP (Any one person) $ PERSONAL B ADV INJURY $ -- — GENERAL AGGREGATE $ GEN'L AGGREGATE LIM IT APPLIES PER: POLICY E I PEo- LOC— PRODUCTS - COMP/GP AGO $ AUTOMOBILE LIABILITY ANY AUTO ALL OWNED AUTOS SCHEDULEDAUTOS HIRED AUTOS NON -OWNED AUTOS COMBINED SINGLE LIMIT (Ea accident) $ BODILY INJURY (Per person) $ BODILY INJURY (Per accident) $ PROPERTY DAMAGE (Per accident) $ - GARAGE LIABILITY ANY AUTO AUTO ONLY - EA ACCIDENT __.—_ $ � _ OTHER THAN EA ACC AUTO ONLY: AGO _-- $ $ EXCESS LIABILITY OCCUR E CLAIMS MADE -- DEDUCTIBLE RETENTION $ EACH OCCURRENCE _ _ $ AGGREGATE _ - $ $ A WORKERS COMPENSATION AND EMPLOYERS' LIABILITY 2086850 07/01/02 07/01/03 X WC STATU- OTH- CRY L E E.L. EACH ACCIDENT $100 000 E.L. DISEASE - EA EMPLOYEE $100, 000 E.L. DISEASE -POLICY LIMIT $500 000 OTHER DESCRIPTION OF OPERAT M&LOCATIONSNEHICLES/EXCLUSIONS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS City of Ft Collins Purchasing Dept Attn: Jan 256 W. Mountain Fort Collins, CO 80521 SHOULD ANYOFTHE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 10 DAYS WRITTEN NOTICETOTHE CERTIFICATE HOLDERNAMED TOTHE LEFT, BUTFAILURE TODOSOSHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANYKIND UPON THE INSURER,ITS AGENTS OR ACORD26-S(v97)1 0f 2 #S219500/M219497 Lg o IORDCOR ATION1988 CERTIFICATE OF LIABILITY I1451..;ANCE American Family Insurance Company American Family Mutual Insurance Company if selection In ,x is not checked. - 6000 American Pky Madison, Wisconsin 5370001 1 Agent's Name, Address and Phone Number (Agt./Dist.) Insured's Name and Address: -) Harold F Lee Agency (127-305) Vogel Colic, inc 2600 S Parker Rd #1-117 1313 Blue S;;r rc Or B 1 Aurora, CO 80014 Ft Collins, U- :05-,4 303-695-1040 This certificate Is Issued as a matter of information only and confers no rights upon the Ce ,i'.I :ate holder. This certificate does not amend, extend or alter the coverage afforded by the policies lis a c. ;. r: N. oyE µ� y�u1t,' . This is to certify that policies of Insurance listed below have been Issued to the insured namec requirement, term or condition of any contract or other document with respect to which this cei by the policies described herein is subject to all the terms, exclusions, and conditions of such POLICY TYPE TYPE OF INSURANCE POLICY NUMBER Effective Expiration (Mo,Day, Yr) (Mo,Day,Yr) Homeowners/ Mobilehomeowners Liability Boatuwners Liability Personal Umbrella Liability Farm/Ranch Liability Workers Compensation and Employers Liability+ General Liability ® Commercial General 05-X60979 1/l/2002 1/1/2003 Liability (occurrence) El Businessowners Liability Automobile Liability ® Owned Autos (Basic form) 05-X60979 1/1/2002 1/1/2003 ❑ Owned Autos (Comp form) Hired Autos Non -owned Autos ❑ Garage liability Excess Liability ❑ Commercial Blanket Excess 05-X60979 1/1/2002 1/1/2003 DESCRIPTION OF OPERATIONS/LOCATIONSNEHICLES/RESTRICTIONS/SPECIAL ITEMS Additional Insured- Larimer County , CITY OF FT. COLLINS PURCHASING DEPT. ATTN: JAN 256 W. MOUNTAIN FT. COLLINS, CO 80521 e , ..,r ie policy period indicated, notwithstanding any til. r:cI be issued or may pertain, the insurance afforded tot e:es. LIMITS OF LIABILITY i -,Jy ,Iu: y and Property Damage I;rll,, and Property Damage .:cL,,irence AlL ry and Property Damage C!rcurrence .. ;---'ersonal Liability Each Occurrence - player's Liability Each Occurrence _- ..>ry .... cadent :-.;.., - Each Employee Policy Limit _ _ . c:I Aggregate $ 2,000,000 P: - Completed Operations Aggregate $ 2,000,000 ca I and Advertising Injury $1,000,000 'I (cc.crence $1,000,000 :.:, (Any One Fire) $ 100,000 _ -nse (Any One Person) $ 5,000 - .,..::once++ -de ,-+ lury - Each Person $ 1,000,000 •Gury - Each Accident $ 1,000,000 Dainage $ 1,000,000 ijury & Property Damage Combined :-.currence/Aggregate $1,000,000 ,I ur partners shown as Insured '.. elected to be i,loyees under this policy. Oompleted Operations aggregate is equal to each I and is included in policy aggregate. 15,__— . ® Should ,. , -, above described policies be canceled before the expiration c :> -,f, w. company will endeavor to mall'( 30 days) written notice to the _ , ,e !colder named, but failure to mail such notice shall impose no oL or liability of any kind upon the company, Its agents or representaner:.. :lava. unless different number of days shown. ® This cc: :...... crane on the date of Issue only. The above described policies are s,l l' :..can,:ellation in conformity with their terms and by the laws of the s',: i'. ..,. TE 1/4/,C:"' o.s, `.gent SECTION 00635 CERTIFICATE OF SUBSTANTIAL COMPLETION TO: CITY OF FORT COLLINS (OWNER) DATE OF SUBSTANTIAL COMPLETION: PROJECT TITLE: CONCRETE PROJECT - PHASE I; BID NO. 5717 PROJECT OR SPECIFIED PART SHALL LOCATION: Fort Collins, Colorado INCLUDE: '- OWNER: City of Fort Collins CONTRACTOR: I CONTRACT DATE: The Work performed under this contract has been inspected by authorized ! representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or specified part of the project, as indicated above) is hereby declared to be substantially completed on the above date. A tentative list of items to be completed or corrected is appended hereto. This list may not be exhaustive, and the failure to include an item on it does not alter the responsibility of the CONTRACTOR to complete all the Work in accordance with the Contract Documents. ENGINEER AUTHORIZED REPRESENTATIVE- DATE The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to complete and correct the items on the tentative list within the time indicated. By: CONTRACTOR AUTHORIZED REPRESENTATIVE DATE The OWNER accepts the project or specified area of the project as substan- tially complete and will assume full possession of the project or specified area of the project at 12:01 a.m., on The responsibility for heat, utilities, security, and insurance under the Contract Documents shall be as set forth under "Remarks" below. CITY OF FORT COLLINS, COLORADO By: OWNER REMARKS: 7/96 AUTHORIZED REPRESENTATIVE DATE Section 00635 Page 1 SECTION 00640 CERTIFICATE OF FINAL ACCEPTANCE TO: Gentlemen: , 20 You are hereby notified that on the day of 20, the City of Fort Collins, Colorado, has accepted the Work completed by for the City of Fort Collins project, A check is attached hereto in the amount of $ as Final Payment for all Work done, subject to the terms of the Contract Documents which are dated In conformance with the Contract Documents for this project, your obligations and guarantees will continue for the specified time from the following date: Sincerely, OWNER: By: i Title: ATTEST: Title: f Fort Collins 7/96 Section 00640 Page 1 SECTION 00650 LIEN WAIVER RELEASE (CONTRACTOR) TO: City of Fort Collins, Colorado (OWNER) FROM: (CONTRACTOR) PROJECT: CONCRETE PROJECT - PHASE I; BID NO. 5717 1. The CONTRACTOR acknowledges having received payment, except retainage from the OWNER for all work, labor, skill and material furnished, delivered and performed by the CONTRACTOR for the OWNER or for anyone in the construction, design, improvement, alteration, addition or repair of the above described project. 2. In consideration of such payment and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights which the CONTRACTOR may now or may afterward have, claim or assert for all and any work, labor, skill or materials furnished, delivered or performed for the construction, design, improvement, alteration, addition or repair of the above described project, against the OWNER or its officers, agents, employees or assigns, against any fund of or in the possession or control of the OWNER, against the project or against all land and the buildings on and appurtenances to the land improved by the project. 3. The CONTRACTOR affirms that all work, labor and materials, furnished, delivered or performed to or for the construction, design, improvement, alteration, addition or repair of the project were furnished, delivered or performed by the CONTRACTOR or its agents, employees, and servants, or by and through the CONTRACTOR by various Subcontractors or materialmen or their agents, employees and servants and further affirms the same have been paid in full and have released in full any and all existing or possible future mechanic's liens or rights or claims against the project or any funds in the OWNER'S possession or control concerning the project or against the OWNER or its officers, agents, employees or assigns arising out of the project. 4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender, if any, and the Surety on the project against and from any claim hereinafter made by the CONTRACTOR'S Subcontractors, materialmen, employees, servants, agents or assigns against the project or against the OWNER or its officers, employees, agents or assigns arising out of the project for all loss, damage and costs, including reasonable attorneys fees, incurred as a result of such claims. 7/96 Section 00650 Page 1 The successful Bidder will be required to furnish a Performance Bond and a _T Payment Bond guaranteeing faithful performance and the payment of all bills and `{ obligations arising from the performance of the Contract. 1 No Bid may be withdrawn within a period of forty-five (45) days after the date fixed for opening Bids. The OWNER reserves the right to reject any and all Bids, and to waive any informalities and irregularities therein. Bid security in the amount of not less than 5% of the total Bid must accompany „ each Bid in the form specified in the Instructions to Bidders. Sales Prohibited/Conflict of Interest: No officer, employee, or member of City Council, shall have a financial interest in the sale to the City of any real or personal property, equipment, material, suppliesor services where such officer ., or employee exercises directly or indirectly any decision -making authority concerning such sale or any supervisory authority over the services to be rendered. This rule also applies to subcontracts with the City. Soliciting or accepting any gift, gratuity favor, entertainment, kickback or any items of monetary value from any person who has or is seeking to do business with the City of Fort Collins is prohibited City of Fort Collins Y� L Jar J es B. O'Neill, II, CPPO, FNIGP Purchasing/Risk Management Director 07/2001 Section 00020 Page 2 CONTRACTOR: PROJECT: CONTRACT DATE: SECTION 00660 CONSENT OF SURETY TO: City of Fort Collins, Colorado (hereinafter referred to as the 'OWNER") CONCRETE PROJECT - PHASE I; BID NO. 5717 In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR as indicated above, for (Surety) on bond of hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final Payment to the CONTRACTOR shall not relieve the Surety Company of any of its obligations to the OWNER, as set forth in the said Surety Company's Bond. IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this day of , (Surety Company) MM ATTACH: Power of Attorney and Certificate of Authority of Attorney (s)-in-Fact. 7/96 Section 00660 Page 1 SECTION 00670 APPLICATION FOR EXEMPTION CERTIFICATE Insert State certificate here. l 1, i 1 -I i DR 0172 (12/96) COLORADO DEPARTMENT OF REVENUE DENVER CO 80261 (303)232-2416 CONTRACTOR APPLICATION FOR EXEMPTION CERTIFICATE Pursuant to Statute Section 39-26.1140)(a)(M) vv rvvi vVtn It IN I111J SYADE The exemption certificate for which you are applying must be used only for the purpose of purchasing construction and building materials for the exempt project described below. This exemption does not include or apply to the purchase or rental of equipment, supplies, and materials which are purchased, rented, or consumed by the contractor and which do not become a part of the structure, highway, road, street, or other public works owned and used by the exempt organization. Any unauthorized use of the exemption certificate will result in revocation of your exemption certificate and other penalties provided by law. A separate certificate is required for each contract. Subcontractors will not be issued Certificates of Exemption by the Department of Revenue. It is the responsibility of the prime contractor to issue certificates to each of the subcontractors. (See reverse side.) FAILURE TO ACCURATELY COMPLETEALL BOXES WILL CAUSE THE APPLICATION TO BE DENIED. No. (to be assigned by DOR) Period registration(Account - 0170-750 (999) $0.00 V - el • (,L"Y� :•`y�.'{d Y„ IS V q �yyn ex. ,�{ `-": �t *'l 'iif.: _.. .law-.4r?'y .m.n r»' 4 .>ti�C t n � 1 e A....,k _'��" i ; , k-' Trade nam0/DBA. Owner, partner, or corporate name. Mailing address (City, State, Zip): Contact Person E-Mail address: Federal Employers Identification Number: Bid amount for your contract: Fax number. Business telephone number: j . - Colorado withholding tax account number. • xalRd4ai ._ .. ayr , _ ame of exempt organization (as shown on contract) Exempt organization's number. 98 - Address of exempt organizatbn (City, State, Zip): Principal contact at exempt organization: Principal contacts telephone number: Physical location of project site (give actual address when applicable and Cities and/or County (ies) where project is located) Scheduled Month Day Year Month Day y Year corretruction start date: completion date; g, ry � ,.// u l y[ r a tili r i �y } "� tl`hf y,�p�� `)SO r$¢T• f'f' �I� `I' �f n11 P ;�q,� yP a $ « e f . �' ° i 'i �S J,',`t' tip. Ea1 C.i r =. T, #�. » vfti�'F`n'3iAA�i'">� w c ,.{. rV� if x r1z a ti. I r � .. v. ;i K ��'j„ �A'�'hry L•, ; �' ,,i i, ti ` r�+� 3 I yt >A , e n, Ra,gr. i s `J�„k izt f�c '�i.�u�'�� F.�k•Y �•',n ✓'a"�i s e16Xc ��:lr��, 3` �, I declare under penalty of perjury in the second degree that the statements made in this application are true and Complete to the best of my knowledge. Signature of owner, partner or corporate officer. Title of corporate officer.. Date: a A SECTION 00700 GENERAL CONDITIONS GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT These GENERAL CONDITIONS have been developed by using the STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT prepared by the Engineers Joint Contract Documents Committee, EJCDC No. 1910-8 (1990 Edition), as a base. Changes to that document are shown by underlining text that has been added and striking through text that has been deleted. EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) WITH CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) TABLE OF CONTENTS OF GENERAL CONDITIONS Article or Paragraph Page Article or Paragraph Number & Title Number Number & Title DEFINITIONS 1.1 Addenda,,,.... ..................................... 1 1.2 Agreement 1 1.3 Application for Payment ...................... 1 1.4 Asbestos ....................... L5Bid .....................................................1 1.6 Bidding Documents I 1.7 .............................I Bidding Requirements ......................... 1 1.8 Bonds 1.9 ........................ Change Order......................................1 1.10 Contract Documents ............................1, 1.11 Contract Price......................................1 ' ? 1.12 Contract Times.., 1 1.13 CONTRACTOR,. 1 1.14 defective..............................................I . T 1.15 Drawings ............................................ ` 1.16 Effective Date of the Agreement I 1.17 . ENGINEER ......................... 1.18 ENGINEER's Consultant I 1.19 Field Order.........................................1 1.20 General Requirements ......... ................. 2 1.21 Hazardous Waste ...................... ,2 . ,. 1.22.a Laws and Regulations; Laws or Regulations......................................2 1.22.b Legal Holidays....................................2 1.23 Liens.................................................2 - . 1.24 Milestone............................................2 1.25 Notice of Award..................................2 1.26 Notice to Proceed ................... 2 1,21 OWNER ........................................... 2 1.28 Partial Utilization 2 1.29 PCBs ................ 1.30 Petroleum...........................................2 1.31 Project ................ .. ..............................2 1.32.a Radioactive Material ......................... 2 1.32.b Regular Working Hours,,,,,,.. .......2 - 1.33 Resident Project Representative ............. 2 1.34 Samples..............................................2 1.35 Shop Drawings ................... .............. 2 1.36 Specifications _,...,,_......... 2 1.37 Subcontractor...... 2 1.38 Substantial Completion. .......................2 1.39 Supplementary Conditions,,.,,.,..... 2 e; 1.40 Supplier .............................. 1.41 Underground Facilities .....................2-3 1-42 Unit Price Work 1.43 Work,......_ ......................................... 3 1.44 Work Change Directive ........................3 1.45 Written Amendment, .......................... Page Number 2. PRELIMINARY MATTERS 3 2.1 Delivery of Bonds ............................. 2.2 Copies of Documents ........................3 2.3 Commencement of Contract Times; Notice to Proceed..............3 2.4 Starting the Work,_,,,,,...,. 2.5-2.7 Before Starting Construction; CONTRACTOR's Responsibility to Report; Preliminary Schedues; Delivery of Certificates of Insurance ................................... 3-4 2.8 Preconstruction Conference 4 2.9 Initially Acceptable Schedules,_„_.....4 3. CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE ......................................... 4 3.1-3.2 Intent ................................. 4 3.3 Reference to Standards and Speci- fications of Technical Societies; Reporting and Resolving Dis- crepancies... ................... .......... 4-5 3.4 Intent of Certain Terms or Adjectives,,,,,,,,,,,,,,,,,,,, 5 3.5 Amending Contract Docunents......... 5 3.6 Supplementing Contract Documents .................................... 5 3.7 Reuse of Documents ..............„........5 4. AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINTS,.,,,.., 4.1 Availability of Lands..................„.5-6 4.2 Subsurface and Physical Conditions .................................... 6 4.2.1 Reports and Drawings ....................... 6 4.2.2 Limited Reliance by CONTRAC- TOR Authorized; Technical Data.............................................6 4.2.3 Notice of Differing Subsurface or Physical Conditions..................6 4.2.4 ENGINEER's Review.......................6 4.2.5 Possible Contract Documents Change.........................................6 4.2.6 Possible Price and Times Adjustments...............................6-7 4.3 Physical Conditions --Underground Facilities ....................................... 7 4.3.1 Shown or Indicated .................7 4.3.2 Not Shown or Indicated ................ 7 4.4 Reference Points ........................... 7 a E1CDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Article or Paragraph Page Article or Paragraph Page Number & Title Number Number & Title Number 4.5 Asbestos, PCBs, Petroleum, 6.25 Submittal Proceedures; CON - Hazardous Waste or TRACTOR's Review Prior Radioactive Material„...............„7-8 to Shop Drawing or Sample 5. BONDS AND INSURANCE ....... . . ........ . 8 6.26 ,. . ........................ SSubmittal ......16 Shop Drawing & Sample Submit- 5.1-5.2 Performance, Payment and Other tals Review by ENGINEER 16-17 Bonds ..................... 8 6.27 ...... Responsibility for Variations 5.3 Licensed Sureties and Insurers; From Contract Documents17 Certificates of Insurance....* ............... $ 6.28 Related Work Performed Prior 5.4 CONTRACTOR's Liability to ENGINEER's Review and Insurance..........................................9 Approval of Required 5.5 OWNER's Liability Insurance .............. 9 Submittals 17 5.6 Property Insurance ......................9-10 6.29 ................................... Continuing the Work,,, 17 5.7 Boiler and Machinery or Add]- 6.30 ...... CONTRACTOR'S General ..... tional Property Insurance ..... I ............ 10 Warranty and Guarantee 5.8 Notice of Cancellation Prodsion.,....... 10 6.31-6.33 ...............17 Indemnification ................... 17-18 5.9 CONTRACTOR's Responsibility 6.34 Survival of Obligations........ 18 or Deductible Amotints....................10 ............ 5.10 Other Special Insurance.,,, . ............... 10 7. OTHER WORK.................................................1g 5.11 Waiver of Rights,,,„...........................I1 7.1-7.3 Related Work at Site..........,.,.,....,., j8 5.12-5.13 Receipt and Application of 7.4 Coordination 18 Insurance Proceeds .................... 10-I I ................. 5.14 Acceptance of Bonds and Insv- 8. OWNER'S RESPONSIBILITIES ........................ 18 ance; Option to Replace ................... 11 8.1 Communications to CON- 5.15 Partial Utilization --Property TRACTOR 18 Insurance ................... 11 8.2 ......................... Replacement of ENGINEER 18 8.3 Furnish Data andPay Promptly 6. CONTRACTOR'S RESPONSIBILITIES ............... I1 When Due 18 6.1-6.2 Supervision and Superintendence...... 11 8.4 ,,,.,.....,. Lands and Easeme....nts;..R.ep. orts 6.3-6.5 Labor, Materials and Equipment... 11-12 and Tests 18-19 6.6 Progress Schedule ........................... 12 8.5 .......................... Insurance,,. 19 6.7 Substitutes and "Or -Equal" Items; 8.6 _ Change. Orders,,.... 19 CONTRACTOR'S Expense; 8.7 ...................... Inspections, Tests and Substitute Construction Approvals ................................... 19 Methods or Procedures; 8.8 Stop or Suspend Work; ENGINEER's Evaluation.............12-13 Terminate CONTRACTOR's 6.8-6.11 Concerning Subcontractors, Services,,,,,,,,,,,,,,,,,,,,,,, 19 Suppliers and Others; 8.9 Limitations on OWNER'S Waiver of Rights .......................... 13-14 Responsibilities,......,.,...., 6.12 Patent Fees and Royalties...................14 8.10 .................. _.. Asbestos, PCBs, Petroleum, _ ...19 6.13 Permits ..:......... ....... .... ......... ............. 14 Hazardous Waste or 6.14 Laws and Regulations.... .................... 4. Radioactive Material 6.15 Taxes ... .. ................. 14-15 8.11 „.,...19 Evidence of Financhl „..,......... 6.16 Use of Premises ...... ...................... 15 Arrangements..........,...,.............. 19 6.17 Site Cleanliness ................................ 15 6.18 Safe Structural Loading.....................15 9. ENGINEER'S STATUS DURING 6.19 Record Documents .............................15 CONSTRUCTION 6.20 Safety and Protection .................... 15-16 9.1 ..._...........,..............................19 OWNER'S Representative.....,.,,...,, 19 6.21 Safety Representative ............. ........... 16 9.2 Visits to Site 19 6.22 Hazard Communication Program$...... 16 9.3 .................................. Project Representative„ 19-21 6.23 Emergencies,,,,,,,,,,,,,,,,,, 16 9.4 ........ Clarifications and Interpre- 6.24 Shop Drawings and Samples es..............16 tations....,._..,................... ............21 9.5 Authorized Variations in Wrk 21 D1 E]CDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Article or Paragraph Page Article or Paragraph Page Number & Title Number Number & Title Number 9.6 Rejecting Defective Work ,,,,,,,,,..„....„21 13.8-13.9 Uncovering Work at ENGI- j 9.7-9.9 Shop Drawings, Change Orders NEER's Request .....................27-28 fand Payments,,,,.. 21 13.10 OWNER May Stop the Work........,.,28 9.10 Determinations for Unit Prices,,,,,, 21-22 13.11 Correction or Removal of 9.11-9.12 Decisions on Disputes; ENGI- Defective Work,,,,,,,,,,,,,,,,, 2g _ NEER as Initial Interpreter..............22 13.12 Correction Period, , i 9.13 Limitations on ENGINEER's 13.13 ........................28 Acceptance ofDefective Work 28 Authority and Responsibilities,.,. 22-23 13.14 ......... OWNER May Correct Defective CHANGES IN THE WORK................... .................... 23 Work ..................................... 28-29 10.1 OWNER's Ordered Change...............23 14. PAYMENTS TO CONTRACTOR AND 10.2 Claim for Adjustment ................... 23 COMPLETION,,.,,,,_.,.,..,.,.,... 29 10.3 Work Not Required by Contract 14.1 Schedule of Values, 29 Documents ...................................... 23 14.2 Application for Progress t 10.4 Change Orders..................................23 Payment ..................................... 10.5 Notification of Surety.......................23 14.3 CONTRACTOR's Warranty of Title ......... CHANj GE OF CONTRACT PRICE 23 14.4-14.7 .............. ...................29 Review of Applications for 11.1-11.3 Contract Price; Claim for Progress Payments... _ Adjustment; Value of 14.8-14.9 ..............29-30 Substantial Completion,,,,,_.,. 30 the Work .... ................................ 23-24 14.10 Partial Utilization... 11.4 Cost of the Work ............... 24-25 14.11 ...... ....... Final Inspection,,,, ..30-31 31 11. Exclusions to Cost of the Work,._....... 25 14.12 Final Application for Payment 31 11.6 CONTRACTOR'S Fee ........................ 25 14.13-14.14 ........ Final Payment and Acceptance 31 11.7 Cost Records .................... 25-26 14.15 Waiver of Claims,,..........,..... ....... 31-32 11.8 Cash Allowances, ............ . 26 11.9 Unit Price Work ........................ 26 15. SUSPENSION OF WORK AND TERMINATION ......32 CHANGE OF CONTRACT TIMES .................... 26 15.1 OWNER May Suspend Work..........32 12.1 Claim for Adjustment .............._......,, 26 15.2-15.4 OWNER May Terminate,,,,.,.......... 32 12.2 Time of the Essence.,,,,..... .......26 15.5 CONTRACTOR May Stop 12.3 Delays Beyond CONTRACTOR's Work or Terminate„ Control ................. .................... 26-27 ...............32-33 12.4 Delays Beyond OWNER's and 16. DISPUTE RESOLUTION .................... 33 CONTRACTOR's Control...............27 . 17, MISCELLANEOUS TESTS AND INSPECTIONS; CORRECTION, 17.1 ...........................................33 Giving Notice 33 REMOVAL OR ACCEPTANCE OF 17,2 ........................ Computation of Times...,..,_,..,,., 33 DEFECTIVE WORK,.,...... 27 17.3 Notice of Claim,_. 13.1 Notice of Defects ....................... 27 17.4 . ........................33 CumulativeRemedies 33 13.2 Access to the Work ......... 27 17.5 ...................... Professional Fees and Court 13.3 Tests and Inspections; Costs Included .............................33 CONTRACTOR's Cooperation,,,.,,... 27 17.6 Applicable State Laws,,,,,,,,,,,,,,, 33-34 13.4 OWNER's Responsibilities; Intentionally left blank .................. 35 ' Independent Testing Laboratory,.,... 27 ................ 13.5 CONTRACTOR's EXHIBIT GC -A: (Optional) Responsibilities...............................27 Dispute Resolution Agreement,,....._......,,,,, GC -Al 13.6-13.7 Covering Work Prior to Inspec- 16.1-16.6 Arbitration ....... GC -AI tion, Testing or Approval.................27 16.7 ..,. Mediation ,,,,...,,..,,,. ,. GC -Al 1° EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) INDEX TO GENERAL CONDITIONS City of Fort Collins modifications to the General Conditions of the Construction Contract are not shown in this index Article or Paragraph Number Acceptance of - Bonds and Insurance „ ,5.14 defective Work............................10.4.1, 13.5, 13.13 final payment,,,,,,.., ......... .......9.12, 14.15 insurance.........................................................5.14 other Work, by CONTRACTOR.....* ...................7.3 Substitutes and "Or -Equal" Items,,,,,,,,,,,, 6.7.1 Work by OWNER .... ........... 2.5, 6.30, 6.34 Access to the -- Lands, OWNER and CONTRACTOR responsibilities ............................................. 4.1 site, related Work., ........................ ...................7.2 Work...........................................13.2, 13.14, 14.9 Acts or Omissions--, Acts and Omissions-- CONTRACTOR...................................6.9-1, 9.13.3 ENGINEER..........................................6.20, 9.13.3 OWNER................................................... 6.20, 8.9 Addenda --definition of (also see definition of Specifications) ....... (1.6, 1.10, 6.19), 1.1 Additional Property Insurances .................................. 5.7 Adjustments -- Contract Price or Contract Times ...........................1.5, 3.5, 4.1, 4.3.2, 4.5.2, .............................4.5.3, 9.4, 9.5, 10.2-10.4, .....................................1. 11, 12, 14. 8, 15.1 progress schedule .............................................. 6.6 Agreement-- - definition of.....................................................1.2 "All -Risk" Insurance, policy form............................5.6.2 Allowances, Cash,,,,,,,,,,,,,,,,,,,,,,, 11.8 Amending Contract Documents, 3.5 Amendment, Written -- in general................J.10, 1.45, 3.5, 5.10, 5.12, 6.6.2 .......................... 6.8.2, 6.19, 10.1, 10.4, 11.2 ....................................12.1, 13.12.2, 14.7.2 Appeal, OWNER or CONTRACTOR intent to9.10, 9.11, 10.4, 16.2, 16.5 Application for Payment -- definition of......................................................1.3 ENGINEER's Responsibility 9.9 final payment,,,,,,,,,,,,,,,,, 9.13.4, 9.13.5, 14.12-14.15 in general ..........................2.8, 2.9, 5.6.4, 9.10, 15.5 progress payment ........ 14.1-14.7 review of........................................... :14.4-14.7 Arbitration 16.1-16.6 ............... Asbestos -- claims pursuant thereto..........................4.5.2, 4.5.3 CONTRACTOR authorized to stop Work..........4.5.2 definition of ........................................... 1.4 Article or Paragraph Number OWNER responsibility for,,,,,,,,,,,,,,,,,,,,,,, 4.5.1, 8.10 possible price and times change ...................... 4.5.2 Authorized Variations in Work,,,,,,,,, 3.6, 6.25, 6.27, 9.5 Availability of Lands,,,,,,,,,,,,,,,,,,,,,,„................. 4.1, 8.4 Award, Notice of --defined,,,,,,,,,,,,,,,,,,, „ 1.25 Before Starting Construction...............................2.5-2.8 Bid --definition of,,,,,,,,,,,,,,,,,,,,,,,, 1.5 (1.1, 1.10, 2.3, 3.3, ........................4.2.6.4, 6,13, 11.4.3, 11.9.1) Bidding Documents --definition of...................................................1.6 (6.8.2) Bidding Requirements --definition - of .......................................... 1.7(L1,4.2.6.2) Bonds -- acceptance of....................................................5.14 additional bonds,,,,,,,,,,,,,,,,,,,,,,, 10.5, 11.4.5.9 Cost of the Work...........................................11.5.4 definition of ........................... ...:.......... ..... 1.8 delivery of...................................................11, 5.1 final Application for Payment .................14.12-14.14 general ................................ I ...... 1.10, 5.1-5.3, 5.13, ........................................9.13, 10.5, 14.7.6 Performance, Payment and Othe1...................5.1-5.2 Bonds and Insurance --in general.................................5 -- Builder's risk "all-risk" policy form,,,,,,,,,,,,,, „ ....5.6.2 Cancellation Provisions, Insurance,,,,_,., 5.4.11, 5.8, 5.15 Cash Allowances....................................................11.8 Certificate of Substantial Completion ........ L38, 6.30.2.3, ..................................................14.8, 14.10 Certificates of Inspection ...................9.13.4, 13.5, 14.12 Certificates of Insurance,,,,,,,,,,,,,, 2.7, 5.3, 5.4.11, 5.4.13, .....................5.6.5, 5.8, 5.14, 9.13.4, 14.12 Change in Contract Price -- Cash Allowances...............................................11.8 claim for price adjustment,,.,,,_.,.,, 4.1, 4.2.6, 4.5, 5.15, 6.8.2, 9.4 ...................9.5, 9.11, 10.2, 10.5, 11.2, 13.9, .......................13.13, 13.14, 14.7, 15.1, 15.5 CONTRACTOR's fee.........................................1 1.6 Cost of the Work general ............................................... 11.4-11.7 Exclusions to...............................................11.5 Cost Records.....................................................11.7 ' in general.............J.19, 1.44, 9.11, 10.4.2, 10.4.3, 11 Lump Sum Pricing..........................................11.3.2 Notification of Surety ,,,,,,,,,,,,,,„_ ............ ..... ....... 10.5 Scope of....................................................10.3-10.4 Testing and Inspection, Uncovering the Work... ............................... 13.9 - - EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99 Unit Price Work...........................................11.9 Article or Paragraph Number Value of Work..................................................11.3 Change in Contract Times-- Claim for times adjustment ........ 4.1, 4.2.6, 4.5, 5.15, ............ 6.8.2, 9.4, 9.5, 9.11, 10.2, 10.5, 12.1, ...............13.9, 13.13, 13.14, 14.7, 15.1, 15.5 Contractual time limits.....................................122 Delays beyond CONTRACTOR's control......... ... .............. ..............................12.3 W Delays beyond ONER's and CONTRACTOR's control............................12.4 Notification of surety.........................................10.5 Scope of change ..... ................................... 10.3-10.4 Change Orders -- Acceptance of Defective Work ......................... 13.13 Amending Contract Documents ............... 3.5 Cash Allowances .................. ....................11.8 Change of Contract Price„...................................I I Change of Contract Times .................. 12 Changes in the Work ......... .............. 10 CONTRACTOR's fee..,,. Cost of the Work, ................ ..................... 11.4-11,7 Cost Records,,........ ............................. .............11.7 definition of ............................................ ........... 1.9 emergencies............................... 6.23 ....................... ENGINEER's responsibility ....... 9.8, 10.4, 11.2, 12.1 execution of.....................................................10.4 Indemnifiction .........................6.12, 6.16, 6.31-6,33 Insurance, Bonds and......................5.10, 5.13, 10.5 OWNER may terminate ......... .............15.2-15.4 OWNER's Responsibility ...... ...................... Physical Conditions -- Subsurface and,... ............... .. ... ................... 4.2 Underground Facilities--... ............... 4.3.2 Record Documents .............. Scope of Change ................... ........ ....... ..... 10.3-10.4 Substitutes, ........................ .................... 6.7.3, 6.8.2- Unit Price Work .......................................... .....11.9 value of Work, covered by ................... 113 Changes in the Work ............. 10 Notification of surety. ........... .......................... 10.5 OWNER's and CONTRACTOR's responsibilities ............................................ 10.4 Right to an adjustment......................................10.2 Scope of change ............. ........................... 10.3-10.4 Claims -- against CONTRACTOR ........................ 6.16 against ENGINEER ......... .. ... 6.32 againstOWNER...............................................6.32 Change of Contract Price ............. 9.4, 11.2 Change of Contract Times ... I....................... 9.4, 12.1 CONTRACTOR's.............4, 7.1, 9.4, 9.5, 9.112 10.2, ...........................11.2, 11.9, 12.1, 13.9, 14.8, ............................................15.1, 15.5, 17.3 vi CONTRACTOR's Fee.......................................11.6 Article or Paragraph Number CONTRACTOR's liability ........... 5.4, 6.12, 6.16, 6.31 Cost of the Work.......................................11.4, 11.5 Decisions on Disputes ......................... 9.11, 9.12 Dispute Resolution............................................16.1 Dispute Resolution Agreement, ..... .......... .16.1-16.6 ENGINEER as initial interpretor.................. 9.11 Lump Sum Pricing ......................................... 11.3.2 Noticeof .................................................. .... ..................... ..17.3 OWNER' s.....,,_......... 9.4, 9.5, 9.11, 10.2, 11.2, 11.9 ......................12.1, 13.9, 13.13, 13.14, 17.3 OWNER's liability .............................................. 5.5 OWNER may refuse to make payment....,...., 14.7 Professional Fees and Court Costs Included.....................................................17.5 request for formal decision on ................ Q.11 Substitute Items.............................................0.7.1.2 Time Extension ................................. ................ 12-1 Time requirements ..................... .......... . .9.11, 12.1 Unit Price Work .....,... . .......... ............11.9.3 Value of .................. ............... ......................... 1,1.3 Waiver of --on Final Payment .................14,14, 14.15 Work Change Directive,,.._.. ...................................... 10.2 written notice required ......................9.11, 11.2, 12.1 Clarifications and Interpretations............ 3.6.3, 9.4, 9.11 CleanSite............................................................6.17 Codes of Technical Society, Organization or Association ................................................. 3.3.3 Commencement of Contract Times ............... 2.3 Communications-- general..............................................6.2, 6.9.2, 8.1 Hazard Communication Programs .....................6.22 Completion -- Final Application for Payment .........................14.12 Final Inspection .................. ... ........................14.11 Final Payment and Acceptance ..............14.13-14.14 Partial Utilization— ............... ................. ........14.10 Substantial Completion ......................1.38, 14.8-14.9 Waiver of Claims.,, ...., .................14.15 Computation of Times .......................... ..17.2.1-17.2.2 Concerning Subcontractors, Suppliers and Others..................................................6.8-6.11 Conferences -- initially acceptable schedules .... ................... 2.9 preconstruction. .. . .. . ..... ...... ................................ 2.8 Conflict, Error, Ambiguity, Discrepancy-- CONTRACTOR to Report ............ ... ....... 2.5, 3.3.2 Construction, before starting by CONTRACTOR............................................2.5-2.7 Construction Machinery, Equipment, etc, ....... ......6.4 Continuing the Work .................................... . 6.29, 10.4 Contract Documents-- Amending..........................................................3.5 Bonds............................................................. 5.1 EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) SECTION 00100 INSTRUCTIONS TO BIDDERS I G { 0 Cash Allowances..............................................11.8 Stop Work requirements............................ 4.5.2 CONTRACTOR'sb Article or Paragraph Number Article or Paragraph Change of Contract Price....................................11 Number Change of Contract Times .......................... ......... 12 Compensation P Changes in the Work 10.4-10.5 . ......, Continuing Obligation,.,,,, .,11.1-11.2 check and verify, ................................... ....... 2.5 ......................14.15 Defective Work .......................... 9.6, 13.10-13.14 Clarifications and Duty to correct defective Work 13.11 nterpretations.......................... . 3.2, 3.6, 9.4, 9.11 ........................... Duty to Report - definition of,,,,, ......................... ..................... 1.10 Changes in the Work caused by ENGINEER as initial interpreter of .................. 9.11 Emergency....,.......,.. 6.23 ENGINEER as OWNER's representative,,.,_ .._....9.1 Defects in Work of Others 7.3 gene .......Insurance 4.2.3 Insurance .............................. „ j,3 Discrepancy in Documents ......... 2.5, 3.3.2, 6.14.2 Intent ... 3.1-3.4 Underground Facilities not indicate minor variations in the Work . ............ . 3.6 Emergencies .... _ .......... OWNER's responsibility to furnish datq..............8.3 , Equipment and Machinery Rental, Cost OWNER's responsibility to make of the Work .......................... 11.4.5.3 prompt payment,,,,,,,,,,,,,,,, 8.3, 14.4, 14.13 ................. Fee -Cost Plus,,,,,,,. ,,..... , „ 11.5.1, 11.6 precedence ............... .........3.1, 3.3.3 .11.4.5.6, General Warranty and Guarantee,.,.,.....,,....... Record Documents.... ............................. 6.19 Hazard Communication Programs.,..,,, ..0.30 Reference to Standards and Specifications .0.22 ....6, 6. 1 Indemnification, .... ..... 6.12, 6 16, 6.31-6.33 of Technical Societies.,,, . 3.3 Inspection of the Work. Related Work ................... 7.2 Labor, Materials and Equipment,,,,,. 6.3-6.5 Reporting and Resolving Discrepancies .... .... 2.5, 3.3 Laws and Regulations, Compliance by,,,,.....,.. „ 6.14.1 Reuse of.............................................................3.7 Liability Insurance............................. 5.4 Supplementing ................ ,3.6 .................. Notice of Intent to Appeal,..,,......, 10.4 Termination of ENGINEER's Employment .......... 8.2 obligation to perform and complete ,.,..._. .9.10, Unit Price Work..............................................11.9 the Work.......................... 6.30 variations.,,,,... .......................... 3.6, 6.23, 6.27 .................... Patent Fees and Royalties, paid for by ...... 6.12 Visits to Site, ENGINEER s......, ................. 9.2 ................. Performance and Other Bonds.,,,, 5.1 Contract Price- ....... Permits, obtained and paid for by,,,.,_...... ........... adjustment of ...............3.5, 4.1, 9.4, 10.3, 11.2-11.3 .6.13 .......... . Progress Schedule ,......._,......._..,, 2.6, 2.8, 2.9, 6.6, Change of ............................11 6.29, 10.4, 15.2.1 Decision on Disputes................ ................ . 9,11 Request for formal decisionon disputes,,,.,,,.....,, 9.11 definition of ............. 1.1I Responsibilities - Contract Contract Times-- Changes in the Work 10.1 adjustment of .................. 3.5, 4.1, 9.4, 10.3, 12 .................................. Concerning Subcontractors, Suppliers Change of................................................12.1-12.4 and Others.............. 6.8-6.11 Commencement Of., ............ 2.3 ................. Continuing the Work.,.,_.,...._,........, 10.4 definition of .............................................. 1.12 .6.29, CONTRACTOR'S expense 6,7.1 CONTRACTOR CONTRACTOR'S General Warranty "rra Acceptance of Insurance.................................... 5.14 and Guarantee 6.30 Communications ....... ........ 6.2, 6.9.2 ............... ...... CONTRACTOR'S review prior to Shop Continue Work,,,, ..................................... 6.29, 10.4 Drawing or Sample submittal,,,,,,,,,,,,,,,,, 6.25 coordination and scheduling ..................... 6.9.2 Coordination of Work.,,,,.... 6.9.2 definition of , .,,,,,,,, ........................................... 1.13 ..................... Emergencies,,,,, Limited Reliance on Technical ..iva.t........ ub,stitut... ,,,,,..,,,..6.23 ENGINEER'S evaluation, Substitutes Data Authorized.......................................4.2.2 or "Or -Equal" Items............................. 6.7.3 May Stop Work or Terminate............................J5.5 For Acts and Omissions provide site access to others,,, , ....... ............... 7.2, 13.2 of Others .................... 0.9.1-6.9.2, 9.13 Safety and Protection ...................4.3.1.2, 6.16, 6.18, for deductible amounts, insurance...........,,,....,5.9 .............. ........ ................ 6.21-6.23, 7.2, 13.2 general...... .................... . ............6, 7.2, 7.3, 8.9 Shop Drawing and Sample Review Hazardous Communication Programs..,.,,,.., 6.22 Prior to Submittal,.........,, 6.25 Indemnification ......................... 6.31-6.33 °p EICDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) .i Labor, Materials and Equipment..............6.3-6.5 CONTRACTORS --other,,...,.,.,.....,,,..... 7 Laws and Regulations....... ........, ., _....6.14 Contractual Liability Insurance ......... 5. 4.10 Liability Insurance ......................... . 5.4 Contractual Time Limits,,,.....,.........,, ......... . 12.2 Article or Paragraph Article of Paragraph Number Number Notice of variation from Contract Coordination -- Documents„ 6.27 CONTRACTOR's responsibility .......................6.9.2 Patent. Fees and Royalties ........................... .6.12 Copies of Documents............................... 2.2 Permits .......................... .....6.13 Correction Period .............................. 13.12 Progress Schedule...* ........................... 6.6 Correction, Removal or Acceptance Record Documents ...... . .............. 6.19 of Defective Work -- related Work performed prior to in general ............................ 10.4.1, 13.10-13.14 ENGINEER's approval of required i Acceptance of Defective Work ..................... submittals ......................................... 6.28 Correction or Removal of .13.13 safe structural loading,,,,, ......_. ..... .6.18 Defective Work .................. 6.30, 13.11 Safety and Protection 6 20 7.2, 13.2 Correction Period,,,,, 13.12 Safety Representative ................................... 6.21 OWNER May Correct Defective Work .......13.14 Scheduling the Work..................................6.9.2 OWNER May Stop Work ......... 13.10 Shop Drawings and Samples ........................ 6.24 ,......... ,.............. Cost-- Shop Drawings and Samples Review of Tests and Inspections .......................... 13.4 by ENGINEER ............................... 6.26 Recordsll.7 Site Cleanliness ........ ... ............... I..........., .6.17 Cost of the Work-- Submittal Procedures ....................... 6.25 Bonds and insurance, additional Substitute Construction Methods .,...,..........,..11.4.5.9 Cash Discounts,,, ,,.. ,,,. r......... and Procedures ......... ......... .......6.7.2 CONTRACTOR's Fee _,,,......... .... ......... .11.4.2 11.6 Substitutes and "Or -Equal" Items.................6.7.1 ....................... Employee Expenses.......................... 11.4.5.1 = j Superintendence,,,,,,, ...., ......... .......6.2 Exclusions to ......... Supervision,,.,,,,.. ................................. . 6.1 General11.4-11.5 ...11.5 Survival of Obligations...............................6.34 Home office and overhead expenses,,,,,.,,........... 11.5 Taxes,,,,,,,,,,,, ,,,,,, ......... ......_...15 Losses and damages,,,,,,, . .......... .............11.4.5.6 Tests and Inspections.....,__ ....................... .13.5 Materials and equipmen(,.................._.._..... 11.4.2 . l To Report„_.... ......... ......... ...... 2.5 Minor expenses ,,,,,.,,,,. , Use of Premises ......... ............. 6.16-6.18, 6.30.2.4 ., Payroll costs on changes................................. .....11.4.5.8 11.4.1 I Review Prior to Shop Drawing or performed by Subcontractors ........................... 11.4.3 " 1 Sample Submittal ................................ 6.25 Recordsl l.7 Right to adjustment for changes in the Work,,,.. 10.2 Rentals of construction equipment right to claim.,,,....,., 4, 7.1, 9.4, 9.5, 9.11, 10.2,11.2, and machinery.......................................11.4.5.3 ,_„ 11.9, 12.1, 13.9, 14.8, 15.1, 15.5, 17.3 Royalty payments, permits and - 1 Safety and Protection Y n.................6.20-6.22, T2, 13.2 license fees...,.__..._................................ 11.4.5.5 Safety Representative ........................... 6.21 .Site office and temporary facilities ................ 11.4.5.2 Shop Drawings and Samples Submittals ..... 6.24-6.28 Special Consultants, CONTRACTOR s 11.4.4 Special Consultants........................................11.4.4 Supplemental ...................... Substitute Construction Methods and Procedures„6.7 .................. Taxes related to the Work ................_......._.._ .........11.4.5 J..1.4.5.4 Substitutes and "Or -Equal" Items, Tests and Inspection,,,.... ............................ 13.4 Expense ........................................ 6.7.1, 6.7.2 Trade Discounts ........................................11.4.2 . " Subcontractors, Suppliers and Others,,,,,,,,,. 6.8-6.11 Utilities, fuel and sanitary facilities .............. J 1.4.5.7 Supervision and Superintendence ... _..... 6.1, 6.2, 6.21 Work after regular hours.,, 1 Taxes, Payment by .............. ............................. 6.15 ,,,,,„.......................11.4.1 Covering Work ....... ................ 13.6-13.7 J Use of Premises .. ..... ................................. 6.16-6.18 ......... ............... Cumulative Remedies.,.,.......,........................ 17.4-17.5 Warranties and guarantees ..........................f.5, 6.30 Cutting, fitting and patching,.,,,.,.................... 7.2 Warranty of Title„ ......... ....... .......14.3 Data, to be furnished by OWNER,,,,,,,. $.3 Written Notice Required-- Day --definition of ............................... .............. 17.2.2 CONTRACTOR stop Work or terminate ....... 15.5 Decisions on Disputes,.,,,,,,. ......, 9.11, 9.12 Reports of Differing Subsurface defective --definition of ............. ............. ............... 1.14 and Physical Conditions ....................... 4.2.3 defective Work-- Substantial Completion ..............:............. 14.8 Acceptance of ...................................... 10.4.1, 13.13 v°i EICDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Notification to Surety..............................................J0.5 Observations, by ENGINEER...........................6.30, 9.2 Occupancy of the Work,,,,,,,,,,,,,,,,,,, 5.15, 6.30.2.4, 14.10 Omissions or acts by CONTRACTOR ,,,,.,,.„..... 0.9, 9.13 Open Peril policy form, Insurance .........................5.6.2 Option to Replace....................................................5.14 Article or Paragraph Number "Or Equal" Items ................................................ ......6.7 Other work 7 Overtime Work --prohibition of.................................6.3 OWNER -- Acceptance ofdefective Work ..........................13.13 appoint an ENGINEER......................................8.2 as fiduciary ....................................... ........ 5.12-5.13 Availability of Lands, responsibility ..................„ 4.1 definition of....................................................1.27 „ data, furnish .............-,--,-,-,,,,... .................. ...... 8.3 May Correct Defective Work „,,,,,,,,,,,,,,*.......... 13.14 May refuse to make payment„..................„----.--J4.7 May Stop the Work,,,,,,,,,,,,, May Suspend Work, Terminate............................8.8, 13.10, 15.1-15.4 Payment, make prompt.....................8.3, 14.4, 14.13 performance of other work ................................„ 7.1 permits and licenses, requirements ...................6.13 purchased insurance requirements,,,,,,,,,,,,,, 5.6-5.10 OWNER's-- Acceptance of the Work..............................6.3042.5 Change Orders, obligation to execute.,,,,.,,,, 8.6, 10.4 Communications , 8.1 Coordination of the Work 7.4 Disputes, request for decisiorl ......... .................. %I I Inspections, tests and approvals..................8.7, 13.4 Liability Insurance., .................... 4 ....................... 45.5 Notice of Defects ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,13.1 Representative --During Construction, ENGINEER's Status......................................9.1 Responsibilities -- Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material 8.10 Change Orders, ............... ............................. 8.6 Changes in the Work..................................10.1 communications ........................ ........... ......... 8.1 CONTRACTOR's responsibilities,,,,,,,,,,,,,,,,,,, 8.9 evidence of financial arrangements ..... I., ....... 8.11 inspections, tests and approvals,,,,,,,,,,,;,,,,, 8.7 insurance,,,,,,,,,,,,,,,,,,,,, lands and easements.....................................8.4 prompt payment by ........................................ 8.3 replacement of ENGINEER ...........................8.2 reports and tests............................................8.4 stop or suspend Work..................8.8, 13.10, 15.1 terminate CONTRACTOR's services..........................................8.8, 15.2 separate representative at site...... I ... ................ 4... .3 testing, independent.........................................13.4 use or occupancy of the Work_......................5.15, 6.30.2.4, 14.10 written consent or approval required.........................................9.1, 6.3, 11.4 i x' EICDC GENERAL CONDITIONS 1910-8 (1990 EDITION' w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99, Y 0 Article or Paragraph Article or Paragraph Number Number written notice required ........................7.1, 9.4, 9.11, ....................................11.2, 11.9, 14.7, 15.4 PCBs -- definition of.....................................................1.29 general..............................................................4.5 OWNER'S responsibility for .............................. 8.10 Partial Utilization— definitionof......................................................1.28 general 6.30.2.4, 14.10 Property Insurance ............................................ 5.15 Patent Fees and Royalties ........................... . .. 6.12 Payment Bonds,,,,,,,,,,,,,,,,,,, Payments, Recommendation of ... .......... 14.4-14.7, 14.13 Payments to CONTRACTOR and Completion -- Application for ProgressPayments .................... .14.2 CONTRACTOR's Warranty of Title...............„..14.3 Final Application for Payment .........................14.12 Final Inspection, ............................................. 14.11 Final Payment and Acceptance ................14.13-14.14 general.........................................................$.3, 14 Partial Utilization..........................I.................14.10 Retainage.............. ........ .............................. 14.2 Review of Applications for....... Progress Payments...............................14.4-14.7 prompt payment ............. ..................................... $.3 Schedule of Values ........................ 14.1 Substantial Completion...............................14.8-14.9 Waiver of Claims.,._.,.. .....14.15 when payments due ................................ _ 14.4, 14.13 withholding payment.........................................14.7 Performance Bonds ............................................ 5.1-5.2 Permits ......................................... ................. .. 6.13 Petroleum -- definition of.....................................................i.30 general..............................................................4.5 OWNER's responsibility for .......................... 8.10 Physical Conditions -- Drawings of, in or relating to ......................„ 4.2.1.2 ENGINEER'S review, .. ..... .......... 4.2.4 existing structures.,.....,... I ........................... 4.2.2 general 4.2.1.2 ............................................... Notice of Differing Subsurface or, .................... 4.2.3 Possible Contract Documents Change ........... ...4.2.5 Possible Price and Times Adjustments „............4.2.6 Reports and Drawings ........................ ......... 4.2.1 Subsurface and, .................................................... 4.2 Subsurface Conditions ........................... . 4.2.1.1 Technical Data, Limited Reliance by CONTRACTOR Authorized ....................... 4.2.2 Underground Facilities— general........................................................ 4.3 Not Shown or Indicated .................. 4.3.2 Protection of ................. ......I ........... .. .. 4.3, 6.20 Shown or Indicated ................................................ 4.3.1 Technical Data ............................................... 4.2.2 Preconstruction Conference ................ 2.8 Preliminary Matters 2 Preliminary Schedules.............................................. 16 Premises, Use of ............................................. 6.16-6.18 Price, Change of Contract,,,,,,,, ,.. ...................... ....._....11 Price, Contract --definition of .................. 1.11 Progress Payment, Applications for,,,,,,,,,,,,,,,,,,,,,,,, )4.2 Progress Payment--retainage,......... ........................ 14.2 Progress schedule, CONTRACTOR s.,.........2.6, 2.8, 2.9, ................................. 6.6, 6.29, 10.4, 15.2.1 Project --definition of...............................................1.31 Project Representative_ ENGINEER'S Status During Construction.............9.3 Project Representative, Resident --definition of ......... 1.33 prompt payment by OWNER., ................................... Property Insurance -- .8.3 Additional.........................................................5.7 general5.6-5.10 Partial Utilization................................5.15, 14.10.2 receipt and application of proceeds,....... .... 5.12-5.13 Protection, Safety and ....................... 6.20-6.21, 13.2 Punch list..........................................................14.11 Radioactive Material-- defintion of.....................................................1.32 genera14.5 OWNER'S responsibility for...............................8.10 Recommendation of Payment.................14.4, 14.5, 14.13 Record Documents,,,,,,,,,,,,,,, .......................... .19, 14.12 Records, procedures for maintaining ....................... „2.8 Reference Points ......................... ....................... 4.4 Reference to Standards and Specifications ... of Technical Societies .................................... 3.3 Regulations, Laws and (or),,,,,,,, ............................. 6.14 Rejecting Defective Work ................................. .,..9.6 ..... Related Work -- atSite ................................... ...... ............... 7.1-7.3 Performed prior to Shop Drawings and Samples submittals review.....................6.28 Remedies, cumulative ...................... ............. 17.4, 17.5 Removal or Correction ofDefective Work................13.11 rental agreements, OWNER approval required ..... 11.4.5.3 replacement of ENGINEER, by OWNER .................... 8.2 Reporting and Resolving Discrepancies.................................2.5, 3.3.2, 6.14.2 Reports -- and Drawings.................................................4.2.1 and Tests, OWNER's responsibility ................... . g.4 Resident and Project Representative -- definition of....................................................1.33 provision for............................................................ 9.3 xii EICDC GENERAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) Article or Paragraph Number Resident Superintendent, CONTRACTOR'g............... 6.2 Responsibilities-- CONTRACTOR's-in general..................................6 ENGINEER's-in general.......................................9 Limitations on.............................................9.13 OWNER'S -in general ......................... ... ..................8 Retainage ............................... ................... . ... ......14.2 Reuse of Documents ................................................ 3.7 Review by CONTRACTOR: Shop Drawings and Samples Prior to Submittal, ......................... 6.25 Review of Applications for Progress Payments ... ....... .................. ......... 14.4-14.7 Right to an adjustment............................................10.2 Rights of Way .................... ......... .............. . ............. .. 4.1 Royalties, Patent Fees and ............................... 6.12 Safe Structural Loading ........................ 6.18 Safety -- and Protection ......................... .4.3.2, 6.16, 6,18, .. ......... .......6.20-6.21, 7.2, 13.2 general..................................................... ................................................... 6.20-6.23 Representative, CONTRACTOR's.......................6.21 Samples -- definition of ..................................................... 1.34 general.................................................... 6.24-6.28 Review by CONTRACTOR ..... ......... .. _..,.....,....6.25 Review by ENGINEER .............. ............ ....0.26, 6.27 related Work.................................................... 6.28 submittal of....................................................6.24.2 submittal procedures.........................................6.25 Schedule of progress..............................6, 2 2.8-2.9, 6.6, ......................................... 6.29, 10.4, 15.2.1 Schedule of Shop Drawing and Sample Submittals.............................2.6, 2.8-2.9, 6.24-6.28 Schedule of Values.............................2.6, 2.8-2.9, 14.1 Schedules -- Adherence to..................................................15.2.1 Adjusting...........................................................6.6 Change of Contract Times.................................10.4 Initially Acceptable,,,, „_,..... . 2.8, 2.9 Preliminary ......................... ....... .................. ...... 2.6 Scope of Changes.......................................10.3-10.4 Subsurface Conditions,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, .4.2.1.1 Shop Drawings -- and Samples, general ................................ 6.24-6.28 Change Orders & Applications for Payments, and . ............... .....................9.7-9.9 definition o(......................................................1.35 ENGINEER's approval of .................... ............ .3.6.2 ENGINEER's responsibility for review ................................... 9.7, 6.24-6.28 related Work,,,,,,,,,,,,,,,,,,, .......................... ........6.28 review procedures................................2.8, 6.24-6.28 Article or Paragraph Number submittal required ............................................... 6.24.1 Submittal Procedures ....................................... 6.25 use to approve substitutions .............................. 6.7.3 Shown or Indicated,.,.....,, ..................................... 4.3.1 Site Access......................................................7.2, 13.2 Site Cleanliness..............................................I........0.17 Site, Visits to -- by ENGINEER...........................................9.2, 13.2 by others..........................................................13.2 "special causes of loss" policy form, insurance........................................................5.6.2 definition of., ..... ................. ........................... J.36 Specifications-- defination of....................................................1.36 of Technical Societies, reference tp.................... 3.1 precedence..................................... .........3.3.3 Standards and Specifications of Technical SocietieS ............................... 3.3 Starting Construction, Befor@................... 2.5-2.8 Starting the Work,,,.,., .......................................... . 2.4 Stop or Suspend Work-- by CONTRACTOR...........................................15.5 by OWNER ..................................... 8.8, 13.10, 15.1 Storage of materials and equipment .....................4.1, 7.2 _ Structural Loading, Safety.....,..... ......................._, 6.18 Subcontractor -- Concerning ................................................ 6.8-6.11 definition of .............. ................................ .......1.37 delays ....... ..... ........... ........... .............. 12.3 waiver of rights................................................6.11 Subcontractors --in general ......................... .....6.8-6.11 Subcontracts --required provisions,,,,,..,. 5 11, 6.11, 11.4.3 Submittals -- Applications for Payment ................................ . 14.2 Maintenance and Operation Manuals .........14.12 Procedures ................................ 2 Progress Schedules.......................................2.6, 2.9 Samples ................................................... 0.24-6.28 Schedule of Values ............................ 2.6, 14.1 Schedule of Shop Drawings and Samples Submissions......................................2.6, 2.8-2.9 Shop Drawings ........................................ 6.24-6.28 Substantial Completion-- certification of ............................. 6.30.2.3,14.8-14.9 definition of.....................................................1.38 Substitute Construction Methods or Procedure$ ........ .7.2 Substitutes and "Or Equal" Items ................ .......... 6.7 CONTRACTOR's Expense............................6.7.1.3 . ENGINEER's Evaluation ................................. 6.7.3 "Or -Equal" ................................................... Substitute Construction Methods EJCDC GENERAL CONDITIONS 1910-8 (1990 EDITION w/ CITY OF FORT COLLINS MODIFICATIONS f REV 9/99' Article or Paragraph Number or Procedures.............................................6.7.2 Substitute Items ........................................... 6.7.1.2 Subsurface and Physical Conditions -- Drawings of, in or relatng to ........................ 4.2.1.2 ENGINEER's Review,,,,,....,.. .... ....................... 4.2.4 general..............................................................4.2 Limited Reliance by CONTRACTOR Authorized4.2 ................................................. 2 Notice of Differing Subsurface or Physical Conditions ......................................... 4.2.3 Physical Conditions.......................................4.2.1.2 Possible Contract Documents Change...............4.2.5 Possible Price andTimes Adjustments„.. .......4.2.6 Reports and Drawings :.................................... 4.2.1 Subsurface and ................................................... 4.2 Subsurface Conditions at the Site ................ .4.2.1.1 Technical Data„ .................. .. ................... 4.2.2 . Supervision— CONTRACTOR's responsibility ................... 6.1 OWNER shall not supervise ,...,_.,,.._..... 8.9 ENGINEER shall not supervise,,,,_..,...._., 9.2, 9.13.2 Superintendence, .................. .......................... 6 2 Superintendent, CONTRACTOR's resident„ .............6.2 Supplemental costs .............................................. 1 1.4.5 Supplementary Conditions -- definition of......................................................1.39 principal references to...................1.1o, 1.18, 2.2, 2.7, ..................4.2, 4.3, 5.1, 5.3, 5.4, 5.6-5.9, ................. 5.11,6.8,6.13,7.4,8.11,9.3,9.10 Supplementing Contract Documents ...............:...... ..3.6 Supplier -- definition of.....................................................1.40 principal references to ........ .... 3.7, 6.5, 6.8-6.11, 6.20, ..........................................0.24, 9.13, 14.12 Waiver of Rights...............................................6.1 l Surety -- consent to final payment ................. 14.12, 14.14 ENGINEER has no duty to ............. 9.13 Notification of.............................10.1, ..... 10.5, 15.2 qualification of ... ... ......... I'll .... I ..................... 5.1-5.3 Survival of Obligations .......................................... 6.34 Suspend Work, OWNER May,.........., 13.10, 15.1 Suspension of Work and Termination-- .................. 15 CONTRACTOR May Stop Work or Terminate..............................:................15.5 OWNER May Suspend Work....,..,,.., 1.5.1 OWNER May Terminate,,,,,_,. ..................... 15.2-15.4 Taxes --Payment by CONTRACTOR ........................ 6.15 Technical Data -- Limited Reliance by CONTRACTOR ........ _._,....4.2.2 Possible Price and Times Adjustments...............4.2.6 Reports of Differing Subsurface and Physical Conditions., .................................. 4.2.3 xiv Temporary construction facilities 4.1 Article or Paragraph Number Termination-- by CONTRACTOR...........................................15.5 by OWNER........................................8.8, 15.1-15.4 of ENGINEER's employment.... ................. 8.2 Suspension of Work-in general ........................ 15 Terms and Adjectives .............._.. ............................. 3.4 Tests and Inspections -- Access to the Work, by others ....... ............._... .13.2 CONTRACTOR's responsibilities ......................13.5 cost of 13.4 covering Work prior to..............._.............13.6-13.7 Laws and Regulations (or) ................... 13.5 Notice of Defects .............. OWNER May Stop Work ................................. 13.10 OWNER's independent testing ..................... 13.4 special, required by ENGINEER ....................... .9.6 timely notice required,,,,,,,,,,,,,,, ...................................... 13.4 Uncovering the Work, at ENGINEER's request ......................... ........ ................ 13.8-13.9 Times-- Adjusting.......................................................... 6.6 Change of Contract..............................................12 Computation of .............................. ... ............... IT2 Contract Times --definition of...........................1.12 day.........................................................1.7.2.2 Milestones ............................. .........12 Requirements-- appeals.................................................9.10, 16 clarifications, claims and disputes.,-,..............9.11, 11.2, 12 Commencement of Contract Time$ ................ 2.3 Preconstruction Conference ............................ 2.8 schedules.........................................2.6, 2.9, 6.6 Starting the Work..........................................2.4 Title, Warranty of .............................. ................. 14.3 Uncovering Work ......................................... .... 13.8-13.9 Underground Facilities, Physical Conditions -- definition of .................................................... 1.41 Not Shown or Indicated...................................4.3.2 protection of..............................................4.3, 6.20 Shown or Indicated..........................................4.3.1 Unit Price Work-- claims..........................................................11.9.3 definition of....................................................1.42 generalll.9, 14.1, 14.5 Unit Prices-- general11.3.1 Determination for.............................................9.10 Use of Premises„_ ............ .. ...... 6.16, 6.18, 6,30.2.4 Utility owners, ..... ... 6.13, 6.20, 7.1-7.3, 13.2 Utilization, Partial...................1.28, 5,15, 6.30.2.4, 14.10 Value of the Work ................................................... 11.3 Values, Schedule of .............................. 2.6, 2.8-2.9, 14.1 EJCDC GENEIEAL CONDITIONS 1910-8 (1990 EDITION) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) certificates of insurance (and other evidence of insurance requested by OWNER) which CONTRACTOR is required to purchase and maintain in accordance with paragraphs 5 ^, s6 and 5.°.''. Preconstruction Conference: 2.8. Within twenty days after the Contract Times start to run, but before any Work at the site is started, a conference attended by CONTRACTOR, ENGINEER and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2.6, procedures for handling Shop Drawings and other submittals processing Applications for Payment and maintaining required records. Initially Acceptable Schedules: 2.9. Unless otherwise provided in the Contract Documents, at le. n a s befere submission ef the first before any work at the site hggi s a conference attended by CONTRACTOR, ENGINEER and others as apprepriate designated by OWNER, will be held to review for acceptability to ENGINEER as provided below the schedules submitted in accordance with paragraph 2.6. and Division 1 - General Requirements CONTRACTOR shall have an additional ten days to make corrections and adjustments and to complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until the schedules are submitted to and acceptable to ENGINEER as provided below. The progress schedule will be acceptable to ENGINEER as providing an orderly progression of the Work to completion within any specified Milestones and the Contract Times, but such acceptance will neither impose on ENGINEER responsibility for the sequencing, scheduling or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOWs full responsibility therefor. CONTRACTOR's schedule of Shop Drawing and Sample submissions will be acceptable to ENGINEER as providing a workable arrangement for reviewing and processing the required submittals CONTRACTOR's schedule of values will be acceptable to ENGINEER as to form and substance. ARTICLE 3—CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE Intent: 3.1. The Contract Documents comprise the entire agreement between OWNER and CONTRACTOR concenting the Work. The Contract Documents are complementary; what is called for by one is as binding as if called for by all. The Contract Documents will be construed in accordance with the law of the place of the Project. 3.2. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance with the Contract Documents. Any Work, materials or equipment that may reasonably be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the intended result will be fumished and performed whether or not specifically called for. When words or phrases which have a well-known technical or construction industry or trade meaning are used to describe Work, materials or equipment, such words or phrases shall be interpreted in accordance with that meaning. Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in paragraph 9.4, 3.3. Reference to Standards and Specifications of Technical Societies; Reporting and Resolving Discrepancies: 3.3.1. Reference to standards, specifications, manuals or codes of any technical society, organization or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard, specification, manual, code or Laws or Regulations in effect at the time of opening of Bids (or, on the Effective Date of the Agreement if there were no Bids), except as may be otherwise - specifically stated in the Contract Documents. 3.3.2. If, during the performance of the Work, CONTRACTOR discovers any conflict, error, ambiguity or discrepancy within the Contract Documents or between the Contract Documents and any provision of any such Law or Regulation applicable to the performance of the Work or of any such standard, specification, manual or code or of any instruction of any Supplier referred to in paragraph 6.5, CONTRACTOR shall report it to ENGINEER in writing at once, and, CONTRACTOR shall not proceed with the Work affected thereby (except in an emergency as authorized by paragraph 6.23) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in paragraph 3.5 or 3.6; provided, however, that CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any such conflict, error, ambiguity or discrepancy unless CONTRACTOR knew or reasonably should have known thereof. 3.3.3. Except as otherwise specifically stated in the Contract Documents or as may be provided by amendment or supplement thereto issued by one of the methods indicated in paragraph 3.5 or 3.6, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the Contract Documents and: 3.3.3.1. the provisions of any such standard, specification, manual, code or instruction (whether or not specifically incorporated by reference in the Contract Documents); or E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 3.3.3.2: the provisions of any such Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation). No provision of any such standard, specification, manual, code or instruction shall be effective to change the duties I and responsibilities of OWNER, CONTRACTOR or ENGINEER, or any of their subcontractors, consultants, agents or employees from those set forth in the Contract Documents, nor shall it be effective to assign to OWNER, ENGINEER or any of ENGINEER's Consultants, agents or employees any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of paragraph 9.13 or any other provision of the Contract Documents. 3.4. Whenever in the Contract Documents the terms "as ordered" "as directed", "as required", "as allowed", "as approved" or temvs of like effect or import are used, or the adjectives "reasonable", "suitable", "acceptable", "proper" or "satisfactory" or adjectives of like effect or import are '. used to describe a requirement, direction, review or judgment of ENGINEER as to the Work, it is intended that such requirement, direction, review or judgment will be solely to evaluate, in general, the completed Work for ' compliance with the requirements of and information in the - Contract Documents and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to ENGINEER any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility contrary to the provisions of paragraph 9.13 or any other provision of the Contract Documents. Amending and Supplementing Contract Documents: 3.5. The Contract Documents may be amended to provide for additions, deletions and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways: I 3.5.1. a formal Written Amendment, 3.5.2. a Change Order (pursuant to paragraph 10.4), or EJCDC GENERAL CONDITIONS 1910-6 (1990 Edition) w/ CITY OF FORT COLLINS MODEFICATIONS (REV 4/2000) 3.5.3. a Work Change Directive (pursuant to paragraph 10.1). 3.6. In addition, the requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, in one or more of the following ways: 3.6.1. A Field Order (pursuant to paragraph 9.5), 3.6.2. ENGINEER's approval of a Shop Drawing or Sample (pursuant to paragraphs 6.26 and 6.27), or 3.6.3. ENGINEER's written interpretation or clarification (pursuant to paragraph 9.4). Reuse of Documents: 3.7. CONTRACTOR, and any Subcontractor or Supplier or other person or organization performing or furnishing any of the Work under a direct or indirect contract with OWNER (i) shall not have or acquire any title to or ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER or ENGINEER's Consultant, and (ii) shall not reuse any of such Drawings, Specifications, other documents or copies on extensions of the Project or any other project without written consent of OWNER and ENGINEER and specific written verification or adaptation by ENGINEER. ARTICLE 4—AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; REFERENCE POINTS Availability of Lands: 4.1. OWNER shall fumish, as indicated in the Contract Documents, the lands upon which the Work is to be performed, rights -of -way and easements for access thereto, and such other lands which are designated for the use of CONTRACTOR. Upon. a of or filing a h r, a b OWNER shall identify any encumbrances or restrictions not of general application but specifically related to use of lands so furnished with which CONTRACTOR will have to comply in performing the Work. Easements for permanent structures or permanent changes in existing facilities will be obtained and paid for by OWNER, unless otherwise provided in the Contract Documents. If CONTRACTOR and OWNER are unable to agree on entitlement to or the amount or extent of any adjustments in the Contract Price or the Contract Times as a result of any delay in OWNER's furnishing these lands, rights -of - way or easements, CONTRACTOR may make a claim therefor as provided in Articles 11 and 12, CONTRACTOR shall provide for all additional lands and access thereto that may be required for temporary construction facilities or storage of materials and equipment. 4.2. Subsurface and Physical Conditions: 4.2.1. Reports and Drawings: Reference is made to the Supplementary Conditions for identification of 4.2.1.1. Subsurface Conditions: Those reports of explorations and tests of subsurface conditions at or contiguous to the site that have been utilized by ENGINEER in preparing the Contract Documents; and 4.2.1.2. Physical Conditions: Those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) that have been utilized by ENGINEER in preparing the Contract Documents. 4.2.2. Limited Reliance by CONTRACTOR Authorized; Technical Data: CONTRACTOR may rely upon the general accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Except for such reliance on such "technical data", CONTRACTOR may not rely upon or make any claim against OWNER, ENGINEER or any of ENGINEER's Consultants with respect to: 4.2.2.1. the completeness of such reports and drawings for CONTRACTOR's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto, or 4.2.2.2. .other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings, or 4.2.2.3. any CONTRACTOR interpretation of or conclusion drawn from any "technical data" or any such data, interpretations, opinions or information. 4.2.3. Notice of Differing Subsurface or Physical Conditions: If CONTRACTOR believes that any subsurface or physical condition at or contiguous to the site that is uncovered or revealed either: 4.2.3.1. is of such a nature as to establish that any "technical data" on which CONTRACTOR is entitled to rely as provided in paragraphs 4.2.1 and 4.2.2 is materially inaccurate, or 4.2.3.2. is of such a nature as to require a change in the Contract Documents, or 4.2.3.3. differs materially from that shown or indicated in the Contract Documents, or 4.2.3.4. is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents; then CONTRACTOR shall, prefftA immediately after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as permitted by paragraph 6.23), notify OWNER and ENGINEER in writing about such condition. CONTRACTOR shall not further disturb such conditions or perform any Work in connection therewith (except as aforesaid) until receipt of written order to do so. 4.2.4. ENGINEER's Review: ENGINEER will promptly review the pertinent conditions, determine the necessity of OWNER's obtaining additional exploration or tests with respect thereto and advise OWNER in writing (with a copy to CONTRACTOR) of ENGINEER's findings and conclusions. 4.2.5. Possible Contract Documents Change: If ENGINEER concludes that a change in the Contract Documents is required as a result of a condition that meets one or more of the categories in paragraph 4.2.3, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document the consequences of such change. 4.2.6. Possible Price and Times Adjustments: An equitable adjustment in the Contract Price or in the Contract Times, or both, will be allowed to the extent that the existence of such uncovered or revealed condition causes an increase or decrease in CONTRACTOR's cost of, or time required for performance of, the Work; subject, however, to the following: 4.2.6.1. such condition must meet any one or more of the categories described in paragraphs 4.2.3.1 through 4.2.3.4, inclusive; 4.2.6.2. a change in the Contract Documents pursuant to paragraph 4.2.5 will not be an automatic authorization of nor a condition precedent to entitlement to any such adjustment; 4.2.6.3. with respect to Work that is paid for on a Unit Price Basis, any adjustment in Contract Price will be subject to the provisions of paragraphs 9.10 and 11.9; and 4.2.6.4. CONTRACTOR shall not be entitled to any adjustment in the Contract Price or Times if; 4.2.6.4.1. CONTRACTOR knew of the existence of such conditions at the time CONTRACTOR made a final commitment to OWNER in respect of Contract Price and Contract Times by the ErCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) submission of a bid or becoming bound under a negotiated contract; or 4.2.6.4.2. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test or study of the site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for CONTRACTOR prior to CONTRACTOR's making such final commitment; or 4.2.6.4.3. CONTRACTOR failed to give the written notice within the time and as required by paragraph 4.2.3. If OWNER and CONTRACTOR are unable to agree on entitlement to or as to the amount or length of any such equitable adjustment in the Contract Price or Contract Times, a claim may be made therefor as Y provided in Articles 11 and 12. However, OWNER, ENGINEER and ENGINEER's Consultants shall not be liable to CONTRACTOR for any claims, costs, losses or damages sustained by CONTRACTOR on or in connection with any other project or anticipated project. 4.3. Physical Conditions —Underground Facilities: 4.3.1. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the site is based on information and data furnished to OWNER or ENGINEER by the owners of such Underground Facilities or by others. Unless it is otherwise expressly provided in the Supplementary Conditions: 4.3.1.1. OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or data; and 4.3.1.2. The cost of all of the following will be included in the Contract Price and CONTRACTOR shall have full responsibility for: (i) reviewing and checking all such information and data, (ii) locating all Underground Facilities shown or indicated in the Contract Documents,(iii) coordination of the Work with the owners of such Underground Facilities during construction, and (iv) the safety and protection of all such Underground Facilities as provided in paragraph 6.20 and repairing any damage thereto resulting from the Work. 4.3.2. Not Shown or Indicated: - If an Underground Facility is uncovered or revealed at or contiguous to the site which was not shown or indicated in the Contract Documents, CONTRACTOR shall, promptly immediately after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by paragraph 6.23), identify theowner of such Underground Facility and EJCDC GENERAL CONDMONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) give written notice to that owner and to OWNER and ENGINEER. ENGINEER will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence of the Underground Facility. If ENGINEER concludes that a change in the Contract Documents is required, a Work Change Directive or a Change Order will be issued as provided in Article 10 to reflect and document such consequences. During such time, CONTRACTOR shall be responsible for the safety and protection of such Underground Facility as provided in paragraph 6.20. CONTRACTOR shall may be allowed an increase in the Contract Price or an extension of the Contract Times, or both, to the extent that they are attributable to the existence of any Underground Facility that was not shown or indicated in the Contract Documents and that CONTRACTOR did not know of and could not reasonably have been expected to be aware of or to have anticipated. If OWNER and CONTRACTOR are unable to agree on entitlement to or the amount or length of any such adjustment in Contract Price or Contract Times, CONTRACTOR may make a claim therefor as provided in Articles 1 I and 12. However, OWNER, ENGINEER and ENGINEER's Consultants shall not be liable to CONTRACTOR for any claims, costs, losses or damages incurred or sustained by CONTRACTOR on or in connection with any other project or anticipated project. Reference Points: 4.4. OWNER shall provide engineering surveys to establish reference points for construction which in ENGINEER's judgment are necessary to enable CONTRACTOR to proceed with the Work. CONTRACTOR shall be responsible for laying out the Work, shall protect and preserve the established reference points and shall make no changes or relocations without the prior written approval of OWNER. CONTRACTOR shall report to ENGINEER whenever any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations, and shall be responsible for the accurate replacement or relocation of such reference points by professionally qualified personnel. 4.5. Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material. 4.5.1. OWNER shall be responsible for any Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material uncovered or revealed at the site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work and which may present a substantial danger to persons or property exposed thereto in connection with the Work at the site. OWNER shall not be responsible for any such materials brought to the site by CONTRACTOR, Subcontractors, Suppliers or anyone else for whom CONTRACTOR is responsible. No Text KNOW ARM .. �. ., l •, ..144,.. ARTICLE 5—BONDS AND INSURANCE Performance, Payment and Other Bonds: 5.1. CONTRACTOR shall furnish Performance and Payment Bonds, each in an amount at least equal to the Contract Price as security for the faithful performance and payment of all CONTRACTOR's obligations under the Contract Documents. These Bonds shall remain in effect at least until one year after the date when final payment becomes due, except as provided otherwise by Laws or Regulations or by the Contract Documents. CONTRACTOR shall also furnish such other Bonds as are required by the Supplementary Conditions, All Bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations and shall be executed by such sureties as are named in the current list of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Audit Staff, Bureau of Government Financial Operations, U.S. Treasury Department. All Bonds signed by an agent must be accompanied by a certified copy of such agent's authority to act. 5.2. If the surety on any Bond furnished by CONTRACTOR is declared a bankrupt or becomes insolvent or its right to do business is terminated in any state where any part of the Project is located or it ceases to meet the requirements of paragraph 5.1, CONTRACTOR shall within ten days thereafter substitute another Bond and surety, both of which must be acceptable to OWNER. 5.3. Licensed Sureties and Insurers; Certificates of Insurance: 5.3.1. All Bonds and insurance required by thr Contract Documents to be purchased and maintaine< by OWNER or CONTRACTOR shall be obtaineo from surety or insurance companies that are duly licensed or authorized in the jurisdiction in which the Project is located to issue Bonds or insurance policies for the limits and coverages so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5.3.2. CONTRACTOR shall deliver to OWNER, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by OWNER or any other additional insured) which CONTRACTOR is required to purchase and maintain in accordance with paragraph 5.4. OAq*mil FJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) t CONTRACTOR's Liability Insurance: 5.4. CONTRACTOR shall purchase and maintain such liability and other insurance as is appropriate for the Work being performed and famished and as will provide protection from claims set forth below which may arise out of or result from CONTRACTOR's performance and furnishing of the Work and CONTRACTOR's other obligations under the Contract Documents, whether it is to be performed or furnished by CONTRACTOR, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform or furnish any of the Work, or by anyone for whose acts any of them may be liable: 5.4.1. claims under workers' compensation, disability benefits and other similar employee benefit acts; i 5.4.2. claims for damages because of bodily injury, t occupational sickness or disease, or death of CONTRACTOR's employees; 1 5.4.3. claims for damages because of bodily injury, sickness or disease, or death of any person other than I CONTRACTOR's employees; i t ���n; 5.4.5. claims for damages, other than to the Work itself, because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom; and 5.4.6. claims for damages because of bodily injury or death of any person or property damage arising out of ' the ownership, maintenance or use of any motor i vehicle. The policies of insurance so required by this paragraph 5.4 to be purchased and maintained shall: 5.4.7. with respect to insurance required by paragraphs 5.4.3 through 5A.6 inclusive and 5.4.9, include as additional insureds (subject to any customary exclusion in respect of professional liability), OWNER, ENGINEER, ENGINEER's Consultants and any other persons or entities identified in the Supplementary Conditions, all of whom shall be listed as additional insureds, and include coverage for the respective officers and employees of all such r additional insureds; 5.4.8. include the specific coverages and be written for not less than the limits of liability provided in the Supplementary Conditions or required by Laws or Regulations, whichever is greater; 5.4.9. include completed operations insurance; - - EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 5.4.10. include contractual liability insurance covering CONTRACTOR's indemnity obligations under paragraphs 6,12, 6.16 and 6.31 through 6.33; 5.4.11. contain a provision or endorsement that the coverage afforded will not be cancelled, materially changed or renewal refused until at least thirty days' prior written notice has been given to OWNER and CONTRACTOR and to each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued (and the certificates of insurance famished by the CONTRACTOR pursuant to paragraph 5.3,2 will so provide); 5.4.12. remain in effect at least until final payment and at all times thereafter when CONTRACTOR may be correcting, removing or replacing defective Work in accordance with paragraph 13.12; and 5.4.13. with respect to completed operations insurance, and any insurance coverage written on a claims -made basis, remain in effect for at least two years after final payment (and CONTRACTOR shall fiunish OWNER and each other additional insured identified in the Supplementary Conditions to whom a certificate of insurance has been issued evidence satisfactory to OWNER and any such additional insured of continuation of such insurance at final payment and one year thereafter). OWNER's Liability Insurance: 5.5. In addition to insurance required to be provided by CONTRACTOR under paragraph 5.4, OWNER, at OWNER's option, may purchase and maintain at OWNER's expense OWNER's own liability insurance as will protect OWNER against claims which may arise from operations under the Contract Documents. Property Insurance: NUNN ....... �.•. �. 5.9. OWNER shall not be responsible for purchasing and maintaining any property insurance to protect the interests of CONTRACTOR, Subcontractors or others in iA the c••--leFmnta y Conditions The Fisk of Imp ...:.L:.......1.:.1.. 'G d A a 'ble. amgimt ill I 1, eme h Feh M POW" k1�1�i3�Y_'.'�,'�►.1�'�.�!iii�ilF��4l_�l�il�., :'`_ : OM • .. 10 E1CDC GENERAL CONDITIONS 1910-8 (1990 Edidon) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) Receipt and Application oflnsurance Proceeds: 5.12. Any insured loss under the policies of insurance required by paragraphs 5.6 and 5.7 will be adjusted with OWNER and made payable to OWNER as fiduciary for the insureds, as their interests may appear, subject to the requirements of any applicable mortgage clause and of paragraph 5.13. OWNER shall deposit in a separate account any money so received, and shall distribute it in accordance with such agreement as the parties in interest may reach. If no other special agreement is reached the damaged Work shall be repaired or replaced, the moneys so received applied on account thereof and the Work and the cost thereof covered by an appropriate Change Order or Written Amendment. 5.13. OWNER as fiduciary shall have power to adjust and settle any loss with the insurers unless one of the parties in interest shall object in writing within fifteen days after the occurrence of loss to OWNER's exercise of this power. If such objection be made, OWNER as fiduciary shall make settlement with the insurers in accordance with such agreement as the parties in interest may reach. If no such agreement among the parties in interest is reached, OWNER as fiduciary shall adjust and settle the loss with the insurers Acceptance of Bonds and Insurance; Option to Replace: 5.14. If either PaA�- (OWNER or CONTRACTOR) OWNER has any objection to the coverage afforded by or other provisions of the Bends-ee insurance required to be purchased and maintained by the ether--� CONTRACTOR in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the OWNER will notify CONTRACTOR in writing within ten fifteen days after reeeipt delivery of the certificates (or ce requested) to OWNER as required by paragraph 2.7. J part) does not purchase or maintain afl of the Bands animufmee D required volt paFty shall netiG the _ Wo*, of of sueb fail, - the fequifed eavefage. Other Fight ma- eleat to ebta ieh .. L pf tGentmet Wipe � sr Partial Utilization —Property Insurance: 5.15. If OWNER finds it necessary to occupy or use a portion or portions of the Work prior to Substantial EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) Completion of all the Work, such use or occupancy may be accomplished in accordance with paragraph 14.10; provided that no such use or occupancy shall commence before the insurers providing the property insurance have acknowledged notice thereof and in writing effected any changes in coverage necessitated thereby. The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be cancelled or permitted to lapse on account of any such partial use or occupancy. ARTICLE 6—CONTRACTOR'S RESPONSIBILITIES Supervision and Superintendence: 6.1. CONTRACTOR shall supervise, inspect and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. CONTRACTOR shall be solely responsible for the means, methods, techniques, sequences and procedures of construction, but CONTRACTOR shall not be responsible for the negligence of others in the design or specification of a specific means, method, technique, sequence or procedure of construction which is shown or indicated in and expressly required by the Contract Documents. CONTRACTOR shall be responsible to see that the completed Work complies accurately with the Contract Documents. 6.2. CONTRACTOR shall keep on the Work at all times during its progress a competent resident superintendent, who shall not be replaced without written notice to OWNER and ENGINEER except under extraordinary circumstances. The superintendent will be CONTRACTOR's representative at the site and shall have authority to act on behalf of CONTRACTOR. All communications to the superintendent shall be as binding as if given to CONTRACTOR. Labor, Materials and Equipment: 6.3. CONTRACTOR shall provide competent, suitably qualified personnel to survey, lay out and construct the Work as required by the Contract Documents. CONTRACTOR shall at all times maintain good discipline and order at the site. Except as otherwise required for the safety or protection of persons or the Work or property at the site or adjacent thereto, and except as otherwise indicated in the Contract Documents, all Work at the site shall be performed during regular working hours and CONTRACTOR will not permit overtime work or the performance of Work on Saturday, Sunday or any legal holiday without OWNER's written consent given after prior written notice to ENGINEER. CONTRACTOR shall submit requests to the ENGINEER no less than 48 hours in advance of any Work to be performed on Saturday Sunday Holidays or outside the Regular Working Hours 6.4. Unless otherwise specified in the General Requirements, CONTRACTOR shall furnish and assume full responsibility for all materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities and all other facilities and incidentals necessary for the furnishing, performance, testing, start-up and completion of the Work. 6.4.1. Purchasing Restrictions CONTRACTOR must comply with the City's purchasing restrictions A copy of the resolutions are available for review in the offices of the Purchasing and Risk Mana ement Division or the City Clerk's office 6.4.2. Cement Restrictions: City of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that burn hazardous waste as a fuel. 6.5. All materials and equipment shall be of good quality and new, except as otherwise provided in the Contract Documents. All warranties and guarantees specifically called for by the Specifications shall expressly run to the benefit of OWNER. If required by ENGINEER, CONTRACTOR shall famish satisfactory evidence (including reports of required tests) as to the kind and quality of materials and equipment. All materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with instructions of the applicable Supplier, except as otherwise provided in the Contract Documents. Progress Schedule: 6.6. CONTRACTOR shall adhere to the progress schedule established in accordance with paragraph 2.9 as it may be adjusted from time to time as provided below: 6.6.1. CONTRACTOR shall submit to ENGINEER for acceptance (to the extent indicated in paragraph 2.9) proposed adjustments in the progress schedule that will not change the Contract Times (or Milestones). Such adjustments will conform generally to the progress schedule then in effect and additionally will comply with any provisions of the General Requirements applicable thereto. 6.6.2. Proposed adjustments in the progress schedule that will change the Contract Times (or Milestones) shall be submitted in accordance with the requirements of paragraph 12.1. Such adjustments may only be made by a Change Order or Written Amendment in accordance with Article 12. 6.7. Substitutes and "Or -Equal "Items: 6.7.1. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent or "or -equal" item or no substitution is permitted, other items of material or equipment or material or equipment of other Suppliers may be accepted by ENGINEER under the following circumstances: 6.7.1.1. "Or -Equal": If in ENGINEER's sole discretion an item of material or equipment proposed by CONTRACTOR is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by ENGINEER as an "or -equal" item, in which case review and approval of the proposed item may, in ENGINEER's sole discretion, be accomplished without compliance with some or all of the requirements for acceptance of proposed substitute items. 6.7.1.2. Substitute Items: If in ENGINEER's sole discretion an item of material or equipment proposed by CONTRACTOR does not qualify as an "or -equal" item under subparagraph 6.7.1.1, it Will be considered a proposed substitute item. CONTRACTOR shall submit sufficient information as provided below to allow ENGINEER to determine that the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. The procedure for review by the ENGINEER will include the following as supplemented in the General Requirements and as ENGINEER may decide is appropriate under the circumstances. Requests for review of proposed substitute items of material or equipment will not be accepted by ENGINEER from anyone other than CONTRACTOR. If CONTRACTOR wishes to furnish or use a substitute item of material or equipment, CONTRACTOR shall first make written application to ENGINEER for acceptance thereof, certifying that the proposed substitute will perform adequately the functions and achieve the results called for by the general design, be similar in substance to that specified and be suited to the same use as that specified. The application will state the extent, if any, to which the evaluation and acceptance of the proposed substitute will prejudice CONTRACTOR's achievement of Substantial Completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) to adapt the design to the proposed substitute and whether or not incorporation or use of the substitute in connection with the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service will be indicated. The application will also contain an itemized estimate of all costs or credits that will result directly or indirectly from acceptance of such substitute, including costs of redesign and claims of other contractors affected l2 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000) by the resulting change, all of which will be considered by ENGINEER in evaluating the proposed substitute. ENGINEER may require CONTRACTOR to furnish additional data about the proposed substitute. 6.7.1.3. CONTRACTOR's Expense: All data to be provided by CONTRACTOR in support of any proposed "or -equal" or substitute item will be at CONTRACTOR's expense. 6.7.2. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence or procedure of construction is shown or indicated in and expressly required by the Contract Documents, CONTRACTOR may furnish or utilize a substitute means, method, technique, sequence or procedure of construction acceptable to ENGINEER. CONTRACTOR shall submit sufficient information to allow ENGINEER, in ENGMEER's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. The procedure for review by ENGINEER will be similar to that provided in subparagraph 6.7.1.2. 6.7.3. Engineer's Evaluation: ENGINEER will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to paragraphs 6.7.1.2 and 6.7.2. ENGINEER will be the ' sole judge of acceptability. No "or -equal" or substitute will be ordered, installed or utilized without ENGINEER's prior written acceptance which will be evidenced by either a Change Order or an approved Shop Drawing. OWNER may require CONTRACTOR to furnish at CONTRACTOR's expense a special performance guarantee or other surety with respect to any "or -equal" or substitute. ENGINEER will record time required by ENGINEER and ENGINEER'S Consultants in evaluating substitutes proposed or submitted by 6_9. CONTRACTOR pursuant to paragraphs 6.7.1.2 and 6.7.2 and in making changes in the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) occasioned thereby. Whether or not ENGINEER accepts a substitute item so proposed or submitted by CONTRACTOR, CONTRACTOR shall reimburse OWNER for the charges of ENGINEER and ENGINEER's Consultants for evaluating each such proposed substitute item. 6_8. Concerning Subcontractors, Suppliers and Others: 6.8.1. CONTRACTOR shall not employ any ` Subcontractor, Supplier or other person or organization (including those acceptable to OWNER and ENGINEER as indicated in paragraph 6.8.2), whether initially or as a substitute, against whom OWNER or ENGINEER may have reasonable objection. CONTRACTOR shall not be required to employ any Subcontractor, Supplier or other person or organization to furnish or perform any of the Work against whom CONTRACTOR has reasonable objection. CONTRACTOR shall perform not less than 20 Percent of the Work with its own forces (that is without subcontracting)The 20 percent requirement shall be understood to refer to the Work the value of which totals not less than 20 percent of the Contract Price. 6.8.2. if thO Suppleffleiafial=y Condition Bidding Documents require the identity of certain Subcontractors, Suppliers or other persons or organizations (including those who are to furnish the principal items of materials or equipment) to be submitted to OWNER in date prior to the Effective Date of the Agreement for acceptance by OWNER and ENGINEER, apid--a c ..------- - ---------- OWNER's or ENGINEER's acceptance (either in writing or by failing to make written objection thereto by the date indicated for acceptance or objection in the bidding documents or the Contract Documents) of ...ti...ti, e rntrr rrn t. n submit a MR be issued of 3AFFit will constitute a condition of the Contract requiring the use of the named subcontractors suppliers or other persons or organization on the Work unless prior written approval is obtained from OWNER and ENGINEER. No acceptance by OWNER or ENGINEER of any such Subcontractor, Supplier or other person or organization shall constitute a waiver of any right of OWNER or ENGINEER to reject defective Work. 6.9.1. CONTRACTOR shall be fully responsible to OWNER and ENGINEER for all acts and omissions of the Subcontractors, Suppliers and other persons and organizations performing or furnishing any of the Work under a direct or indirect contract with CONTRACTOR just as CONTRACTOR is responsible for CONTRACTOR's own acts and omissions. Nothing in the Contract Documents shall create for the benefit of any such Subcontractor, Supplier or other person or organization any contractual relationship between OWNER or ENGINEER and any such Subcontractor, Supplier or other person or organization, nor shall it create any obligation on the part of OWNER or ENGINEER to pay or to see to the payment of any moneys due any such Subcontractor, Supplier or other person or organization except as may otherwise be required by Laws and Regulations. OWNER or ENGINEER may furnish to any subcontractor, supplier or other person or organization evidence of amounts paid to CONTRACTOR in accordance with CONTRACTOR'S "Applications for Payment" .. EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 13 w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 6.9.2. CONTRACTOR shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers and other persons and organizations performing or furnishing any of the Work under a direct or indirect contract with CONTRACTOR. CONTRACTOR shall require all Subcontractors, Suppliers and such other persons and organizations performing or furnishing any of the Work to communicate with the ENGINEER through CONTRACTOR. 6.10. The divisions and sections of the Specifications and the identifications of any Drawings shall not control CONTRACTOR in dividing the Work among Subcontractors or Suppliers or delineating the Work to be performed by any specific trade. 6.11. All Work performed for CONTRACTOR by a Subcontractor or Supplier will be pursuant to an appropriate agreement between CONTRACTOR and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of OWNER and ENGINEER. Whenp.• -- �!!IMMr fY1Mil*..01 O;Wffllu, ., .. Patent Fees and Royalties: 6.12. CONTRACTOR shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product or device is specified in the Contract Documents for use in the performance of the Work and if to the actual knowledge of OWNER or ENGINEER its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by OWNER in the Contract Documents. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless OWNER ENGINEER, ENGINEER's Consultants and the officers, directors, employees, agents and other consultants of each and any of them from and against all claims, costs, losses and damages arising out of or resulting from any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product or device not specified in the Contract Documents. Permits: 6.13. Unless otherwise provided in the Supplementary Conditions, CONTRACTOR shall obtain and pay for all construction permits and licenses. OWNER shall assist CONTRACTOR, when necessary, in obtaining such permits and licenses. CONTRACTOR shall pay all governmental charges and inspection fees necessary for the prosecution of the Work, which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement. CONTRACTOR shall pay all charges of utility owners for connections to the Work, and OWNER shall pay all charges of such utility owners for capital costs related thereto such as plant investment fees. 6.14. Laws and Regulations. 6.14.1. CONTRACTOR shall give all notices and comply with all Laws and Regulations applicable. to furnishing and performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither OWNER nor ENGINEER shall be responsible for monitoring CONTRACTOR's compliance with any Laws or Regulations. 6.14.2. If CONTRACTOR performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, CONTRACTOR shall bear all claims, costs, losses and damages caused by, arising out of or resulting therefrom; however, it shall not be CONTRACTOR's primary responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve CONTRACTOR of CONTRACTOR's obligations under paragraph 3.3.2, Taxes: 6.15. CONTRACTOR shall pay all sales, consumer, use and other similar taxes required to be paid by CONTRACTOR in accordance with the Laws and Regulations of the place of the Project which are applicable during the performance of the Work. 6.15.1. OWNER is exempt from Colorado State and local sales and use taxes on materials to be permanently incorporated into the project Said taxes shall not be included in the Contract Price Address: Colorado Department of Revenue State Capital Annex 14 E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) 1375 Sherman Street Denver, Colorado, 80261 Sales and Use Taxes for the State of Colorado Regional Transportation District (RTD) and certain Colorado counties are collected by the State of Colorado and are included in the Certification of Exemption. All applicable Sales and Use Taxes (including State collected taxes) on any items other than construction and building materials physically incorporated into the prole ct are to be paid by CONTRACTOR and are to be included in appropriate bid items Use of Premises: 6,16. CONTRACTOR shall confine construction equipment, the storage of materials and equipment and the operations of workers to the site and land and areas identified in and permitted by the Contract Documents and other land and areas permitted by Laws and Regulations, rights -of -way, permits and easements, and shall not unreasonably encumber the premises with construction equipment or other materials or equipment. CONTRACTOR shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof or of any adjacent land or areas, resulting from the performance of the Work. Should any claim be made by any such owner or occupant because of the performance of the Work, CONTRACTOR shall promptly settle with such other party by negotiation or otherwise resolve the claim by arbitration or other dispute resolution proceeding or at law. CONTRACTOR shall, to the fullest extent permitted by Laws and Regulations, indemnify and hold harmless OWNER, ENGINEER, ENGINEER's Consultant and anyone directly or indirectly employed by any of them from and against all claims, costs, losses and damages arising out of or resulting from any claim or action, legal or equitable, brought by any such owner or occupant against OWNER, ENGINEER or any other party indemnified hereunder to the extent caused by or based upon CONTRACTOR's performance ofthe Work. 6.17. During the progress of the Work, CONTRACTOR shall keep the premises free from accumulations of waste materials, rubbish and other debris resulting from the Work. At the completion of the Work CONTRACTOR shall remove all waste materials, rubbish and debris from and about the premises as well as all tools, appliances, construction equipment and machinery and surplus materials. CONTRACTOR shall leave the site clean and ready for occupancy by OWNER at Substantial Completion of the Work. CONTRACTOR shall restore to original condition all property not designated for alteration by the Contract Documents. 6.18. CONTRACTOR shall not load nor permit any part Of any structure to be loaded in any manner that will endanger the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses or pressures that will endanger it. Record Documents: EICDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 42000) 6.19. CONTRACTOR shall maintain in a safe place at the site one record copy of all Drawings, Specifications, Addenda, Written Amendments, Change Orders, Work Change Directives, Field Orders and written interpretations and clarifications (issued pursuant to paragraph 9.4) in good order and annotated to show all Changes made during construction. These record documents together with all approved Samples and a counterpart of all approved Shop Drawings will be available to ENGINEER for reference. Upon completion of the Work, and prior to release of final payment these record documents, Samples and Shop Drawings will be delivered to ENGINEER for OWNER. Safety and Protection: 6.20. CONTRACTOR shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. CONTRACTOR shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 6.20.1. all persons on the Work site or who may be affected by the Work; 6.20.2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the site; and 6.20.3. other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and Underground Facilities not designated for removal, relocation or replacement in the course of construction. CONTRACTOR shall comply with all applicable Laws and Regulations of any public body having jurisdiction for safety of persons or property or to protect them from damage, injury or loss; and shall erect and maintain all necessary safeguards for such safety and protection. CONTRACTOR shall notify owners of adjacent property and of Underground Facilities and utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation and replacement of their property. All damage, injury or loss to any property referred to in paragraphs 6.20.2 or 6.20.3 caused, directly or indirectly, in whole or in part, by CONTRACTOR, any Subcontractor, Supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, shall be remedied by CONTRACTOR (except damage or loss attributable to the fault of Drawings or Specifications or to the acts or omissions of OWNER or ENGINEER or ENGINEER's Consultant or anyone employed by any of them or anyone for whose acts any of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of CONTRACTOR or any Subcontractor, Supplier or other, person or organization directly or indirectly employed by any of them). CONTRACTOR's duties and responsibilities for the safety and protection of the Work shall continue until such time as all the Work is completed and ENGINEER has issued a 15 notice to OWNER and CONTRACTOR in accordance with paragraph 14.13 that the Work is acceptable (except as otherwise expressly provided in connection with Substantial Completion). 6.21. Safety Representative. CONTRACTOR shall designate a qualified and experienced safety representative at the site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs. Hazard Communication Programs: 6.22. CONTRACTOR shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the site in accordance with Laws or Regulations. Emergencies: 6.23. In emergencies affecting the safety or protection of persons or the Work or property at the site or adjacent thereto, CONTRACTOR, without special instruction or authorization from OWNER or ENGINEER, is obligated to act to prevent threatened damage, injury or loss. CONTRACTOR shall give ENGINEER prompt written notice if CONTRACTOR believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby. If ENGINEER determines that a change in the Contract Documents is required because of the action taken by CONTRACTOR in response to such an emergency, a Work Change Directive or Change Order will be issued to document the consequences of such action. 6.24. Shop Drawings and Samples: 6.24.L CONTRACTOR shall submit Shop Drawings to ENGINEER for review and approval in accordance with the accepted schedule of Shop Drawings and Sample submittals (see paragraph 2.9). All submittals will be identified as ENGINEER may require and in the number of copies specified in the General Requirements. The data shown on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and design criteria, materials and similar data to show ENGINEER the materials and equipment CONTRACTOR proposes to provide and to enable ENGINEER to review the information for the limited purposes required by paragraph 6.26. 6.24.2. CONTRACTOR shall also submit Samples to ENGINEER for review and approval in accordance with said accepted schedule of Shop Drawings and Sample submittals. Each Sample will be identified clearly as to material, Supplier, pertinent data such as catalog numbers and the use for which intended and otherwise as ENGINEER may require to enable ENGINEER to review the submittal for the limited purposes required by paragraph 6.26. The numbers of each Sample to be submitted will be as specified in the Specifications. 6.25. Submittal Procedures: 6.25.1. Before submitting each Shop Drawing or Sample, CONTRACTOR shall have determined and verified: 6.25.1.1. all field measurements, quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers and similar information with respect thereto, 6.25.1.2. all materials with respect to intended use, fabrication, shipping, handling, storage, assembly and installation pertaining to the performance of the Work, and 6.25.1.3. all information relative to CONTRACTOR's sole responsibilities in respect of means, methods, techniques, sequences and procedures of construction and safety precautions and programs incident thereto. CONTRACTOR shall also have reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents. 6.25.2. Each submittal will bear a stamp or specific written indication that CONTRACTOR has satisfied CONTRACTOR's obligations under the Contract Documents with respect to CONTRACTOR's review and approval of that submittal. 6.25.3. At the time of each submission CONTRACTOR shall give ENGINEER speci written notice of such variations, if any, that the Sh(. Drawing or Sample submitted may have from th; requirements of the Contract Documents, such notice to be in a written communication separate from the submittal; and, in addition, shall cause a specific notation to be made on each Shop Drawing and Sample submitted to ENGINEER for review and approval of each such variation. 6.26. ENGINEER will review and approve Shop Drawings and Samples in accordance with the schedule of Shop Drawings and Sample submittals accepted by ENGINEER as required by paragraph 2.9. ENGINEER's review and approval will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. ENGINEER's review and approval will not extend to means, methods, techniques, sequences or procedures of construction (except where a particular means, method, technique, sequence or procedure of 16 EICDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. CONTRACTOR shall make corrections required by ENGINEER, and shall return the required number of corrected copies of Shop Drawings and submit as required new Samples for review and approval. CONTRACTOR shall direct specific attention in writing to revisions other than the corrections called for by ENGINEER on previous submittals. 6.27. ENGINEER's review and approval of Shop Drawings or Samples shall not relieve CONTRACTOR from responsibility for any variation from the requirements of the Contract Documents unless -CONTRACTOR has in writing called ENGINEER's attention to each such variation at the time of submission as required by paragraph 6.25.3 and ENGINEER has given written approval of each such variation by a specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample approval; nor will any approval by ENGINEER relieve CONTRACTOR from responsibility for complying with the requirements of paragraph 6.25.1. 1 6.28. Where a Shop Drawing or Sample is required by the Contract Documents or the schedule of Shop Drawing and Sample submissions accepted by ENGINEER as required by paragraph 2.9, any related Work performed prior to ENGINEER's review and approval of the pertinent submittal will be at the sole expense and responsibility of CONTRACTOR. Continuing the Work: 6.29. CONTRACTOR shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 15.5 or as OWNER and CONTRACTOR may otherwise agree in writing. 6.30. CONTRACTOR's General Warranty and Guarantee: 6.30.1. CONTRACTOR warrants and guarantees to OWNER, ENGINEER and ENGINEER's Consultants that all Work will be in accordance with the Contract Documents and will not - be defective. CONTRACTOR's warranty and guarantee hereunder excludes defects or damage caused by: 6.30.1.1. abuse, modification or improper maintenance or operation by persons other than CONTRACTOR, Subcontractors or Suppliers; or 6.30.1.2. normal wear and tear under normal usage. 6.30.2. CONTRACTOR's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in EJCDC GENERAL, CONDITIONS 1910-8 (1990, Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) accordance with the Contract Documents or a release of CONTRACTOR's obligation to perform the Work in accordance with the Contract Documents: 6.30.2.1. observations by ENGINEER; 6.30.2.2. recommendation of any progress or final payment by ENGINEER; 6.30.2.3. the issuance of a certificate of Substantial Completion or any payment by OWNER to CONTRACTOR under the Contract Documents; 6.30.2.4. use or occupancy of the Work or any part thereof by OWNER; 6.30.2.5. any acceptance by OWNER or any failure to do so; 6.30.2.6. any review and approval of a Shop Drawing or Sample submittal or the issuance of a notice of acceptability by ENGINEER pursuant to paragraph 14.13; 6.30.2.7. any inspection, test or approval by others; or 6.30.2.8. any correction of defective Work by OWNER. Indemnification: 6.31. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless OWNER, ENGINEER, ENGINEER's Consultants and the officers, directors, employees, agents and other consultants of each and any of them from and against all claims, costs, losses and damages (including, but not limited to, all fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs) caused by, arising out of or resulting from the performance of the Work, provided that any such claim, cost, loss or damage: (i) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom, and (ii) is caused in whole or in part by any negligent act or omission of CONTRACTOR, any Subcontractor, any Supplier, any person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, regardless of whether or not caused in part by any negligence or omission of a person or entity indemnified hereunder or whether liability is imposed upon such indemnified party by Laws and Regulations regardless of the negligence of any such person or entity. 6.32. In any and all claims against OWNER or ENGINEER or any of their respective consultants, agents, officers, directors or employees by any employee (or the survivor or personal representative of such employee) of CONTRACTOR, any Subcontractor, any Supplier, any person or organization directly or indirectly employed by 17 SECTION 00100 INSTRUCTIONS TO BIDDERS 1.0 DEFINED TERMS Terms used in these Instructions to Bidders which are defined in the Standard General Conditions of the Construction Contract (No. 1910-8, 1990 ed.) have the meanings assigned to them in the General Conditions. The term "Bidder" means one who submits a Bid to OWNER, as distinct from a sub - bidder, who submits a Bid to Bidder. The terms "Successful Bidder" means the lowest, qualified, responsible and responsive Bidder to whom OWNER (on basis of OWNER's evaluation as hereinafter provided) makes an award. The term "Bidding Documents" includes the Advertisement or Invitation to Bid, -� Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). T� 2.0 COPIES OF BIDDING DOCUMENTS ,t 2.1. Complete sets of Bidding Documents may be obtained as stated in the Invitation to Bid. No partial sets will be issued. The Bidding Documents may be examined at the locations identified in the Invitation to Bid. 2.2. Complete sets of Bidding Documents shall be used in preparing Bids; neither OWNER nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding - Documents. 2.3. The submitted Bid proposal shall include Sections 00300, 00410, 00420, and 00430 fully executed. -( 2.4. OWNER and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use. 3.0 QUALIFICATION OF BIDDERS 3.1 To demonstrate qualifications to perform the Work, each Bidder must submit at the time of the Bid opening, a written statement of qualifications including financial data, a summary of previous experience, previous commitments and evidence of authority to conduct business in the jurisdiction where the Project is located. Each Bid must contain evidence of Bidder's qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the contract. The Statement of Qualifications shall be prepared on the form 't provided in Section 00420. 3.2. In accordance with Section 8-159 of the Code of the City of Fort Collins in determining whether a bidder is responsible, the following shall be considered: (1) The ability, capacity and skill of the bidder to perform ': 7/96 Section 00100 Page 1 any of them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, the indemnification obligation under paragraph 6.31 shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for CONTRACTOR or any such Subcontractor, Supplier or other person or organization under workers' compensation acts, disability benefit acts or other employee benefit acts. 6.33. The indemnification obligations of CONTRACTOR under paragraph 6.31 shall not extend to the liability of ENGINEER and ENGINEER's Consultants, officers, directors, employees or agents caused by the professional negligence, errors or omissions of any of them. Survival of Obligations: 6.34. All representations, indemnifications, warranties and guarantees made in, required by or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion and acceptance of the Work and termination or completion of the Agreement. ARTICLE 7—OTHER WORK Related Work at Site: 7.1. OWNER may perform other work related to the Project at the site by OWNER's own forces, or let other direct contracts therefor which shall contain General Conditions similar to these, or have other work performed by utility owners. If the fact that such other work is to be performed was not noted in the Contract Documents, then: (i) written notice thereof will be given to CONTRACTOR prior to starting any such other work and (ii) CONTRACTOR may make a claim therefor as provided in Articles 11 and 12 if CONTRACTOR believes that such performance will involve additional expense to CONTRACTOR or requires additional time and the parties are unable to agree as to the amount or extent thereof. 7.2. CONTRACTOR shall afford each other contractor who is a parry to such a direct contract and each utility owner (and OWNER, if OWNER is performing the additional work with OWNER's employees) proper and safe access to the site and a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work and shall properly connect and coordinate the Work with theirs. Unless otherwise provided in the Contract Documents, CONTRACTOR shall do all cutting, fitting and patching of the Work that may be required to make its several parts come together properly and integrate with such other work. CONTRACTOR shall not endanger any work of others by cutting, excavating or otherwise altering their work and will only cut or alter their work with the written consent of ENGINEER and the others whose work will be affected. The duties and responsibilities of CONTRACTOR under this paragraph are for the benefit of such utility owners and other contractors to the extent that there are comparable provisions for the benefit of CONTRACTOR in said direct contracts between OWNER and such utility owners and other contractors. 7.3. If the proper execution or results of any part of CONTRACTOR's Work depends upon work performed by others under this Article 7, CONTRACTOR shall inspect such other work and promptly report to ENGINEER in writing any delays, defects or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of CONTRACTOR's Work. CONTRACTOR's failure so to report will constitute an acceptance of such other work as fit and proper for integration with CONTRACTOR's Work except for latent or nonapparent defects and deficiencies in such other work. Coordination: 7.4. If OWNER contracts with others for the performance of other work on the Project at the site,, the following will be set forth in Supplementary Conditions: 7.4.1. the person, firm or corporation who will have authority and responsibility for coordination of the activities among the various prime contractors will be identified; T4.2. the specific matters to be covered by such authority and responsibility will be itemized; and 7.4.3. the extent of such authority and responsibilities will be provided. Unless otherwise provided in the Supplementary Conditions, OWNER shall have sole authority and responsibility in respect of such coordination. ARTICLE 8—OWNER'S RESPONSIBILITIES 8.1. Except as otherwise provided in these General Conditions, OWNER shall issue all communications to CONTRACTOR through ENGINEER. 8.2. In case of termination of the employment of ENGINEER, OWNER shall appoint an engineer against Whom CONTRACTOR makes no Feasonable objeetien whose status under the Contract Documents shall be that of the former ENGINEER. 8.3. OWNER shall famish the data required of OWNER under the Contract Documents promptly and shall make payments to CONTRACTOR promptly when they are due as provided in paragraphs 14.4 and 14.13. 8.4. OWNER's duties in respect of providing lands and easements and providing engineering surveys to establish reference points are set forth in paragraphs 4.1 and 4.4. Paragraph4.2 refers to OWNER's identifying and making available to CONTRACTOR copies of reports of explorations and tests of subsurface conditions at the site and drawings of physical conditions in existing 18 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) structures at or contiguous to the site that have been utilized by ENGINEER in preparing the Contract Documents. 8.6. OWNER is obligated to execute Change Orders as indicated in paragraph 10.4. 8.7. OWNER's responsibility in respect of certain inspections, tests and approvals is set forth in paragraph 13.4. 8.8. In connection with OWNER's right to stop Work or suspend Work, see paragraphs 13.10 and 15.1. Paragraph 15.2 deals with OWNER's right to terminate services of CONTRACTOR under certain circumstances. 8.9. The OWNER shall not supervise, direct or have control or authority over, nor be responsible for, -? CONTRACTOR's means, methods, techniques, sequences j or procedures of construction or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations ? applicable to the furnishing or performance of the Work. _ OWNER will not be responsible for CONTRACTOR's failure to perform or furnish the Work in accordance with the Contract Documents. s in nxxrnrnnt. _e «..:�:r ARTICLE 9—ENGINEER'S STATUS DURING CONSTRUCTION -OWNER's Representative: 9.1. ENGINEER will be OWNER's representative during the construction period. The duties and responsibilities and the limitations of authority of ENGINEER as OWNER's representative during construction are set forth in the Contract Documents and shall not be extended without written consent of OWNER and ENGINEER. Visits to Site: 9.2. ENGINEER will make visits to the site at intervals appropriate to the various stages of construction as ENGINEER deems necessary in order to observe as an experienced and qualified design professional the progress ECDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) that has been made and the quality of the various aspects of CONTRACTOR's executed Work. Based on information obtained during such visits and observations, ENGINEER will endeavor for the benefit of OWNER to determine, in general, if the Work is proceeding in accordance with the Contract Documents. ENGINEER will not be required to make exhaustive or continuous on - site inspections to check the quality or quantity of the Work. ENGINEER's efforts will be directed toward providing for OWNER a greater degree of confidence that the completed Work will conform generally to the Contract Documents. On the basis of such visits and on - site observations, ENGINEER will keep OWNER informed of the progress of the Work and will endeavor to guard OWNER against defective Work. ENGINEER's visits and on -site observations are subject to all the limitations on ENGINEER's authority and responsibility set forth in paragraph 9.13, and particularly, but without limitation, during or as a result of ENGINEER's on -site visits or observations of CONTRACTOR's Work ENGINEER will not supervise, direct, control or have authority over or be responsible for CONTRACTOR's means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of the Work. Project Representative: 9.3. If OWNER and ENGINEER agree, ENGINEER will furnish a Resident Project Representative to assist ENGINEER in providing more continuous observation of the Work. The responsibilities and authority and limitations thereon of any such Resident Project Representative and assistants will be as provided in paragraphs 9.3 and 9.13 Canditigns of these General Conditions. If OWNER designates another representative or agent to represent OWNER at the site who is not ENGINEER's Consultant, agent or employee, the responsibilities and authority and limitations thereon of such other person will be as provided in the `uppief-- won paragraph 9.3 9.3.2. Duties and Responsibilities Representative will: 9.3.2.1. Schedules Review the progress 19 schedule and other schedules prepared by the CONTRACTOR and consult with the ENGINEER concemingacceptability 9.3.2.2. Conferences and Meeting - Attend meeting with the CONTRACTOR such as preconstruction conferences progress meetings and other job conferences and prepare and circulate conies of minutes of meetings 9.3.2.3. Liaison 9.3.2.3.1. Serve as ENGINEER'S liaison with CONTRACTOR. working pnncinally through CONTRACTOR'S superintendent to assist the CONTRACTOR in understanding the Contract Documents. 9.3.2.3.2. Assist in obtaining from OWNER additional details or information when required, for proper execution of the Work 9.3.2.3.3. Advise the ENGINEER and CONTRACTOR of the commencement of any Work requiring a Shop Drawing or sample submjssion if the submission has not been approved by the ENGINEER 9.3.2.4.Review of Work, Rejection of Defective Work. Inspections and Tests - 9.3.2.4.1. Conduct on -site observations of the Work in progress to assist the ENGINEER in determining that the Work is proceeding in accordance wjth the Contract Documents. 9.3.2.4.3. Accomroany visiting inspectors representing public or other agencies having jurisdiction over the Project, record the results of these inspections and report to the ENGINEER. 9.3.2.5. Inte retation of Contract Documents. Report to ENGINEER when clarifications and jnterpretations of the Contract Documents are needed and transmit to CONTRACTOR clarification and interpretation of the Contract Documents as issued by the ENGINEER. 9.3.2.6. Modifications. Consider and evaluate CONTRACTOR'S suggestions for modification in Drawings or Specifications and report these recommendations to ENGINEER Accurately transmit to CONTRACTOR decisions issued by the ENGINEER 9.3.2.7. Records. 9.3.2.8. Reports. 9.3.2.8.1. Fumish ENGINEER periodic reports, as required, of the progress of the Work and of the CONTRACTOR'S compliance with the progress schedule and schedule of shop Drawing and sample submjttals. 9.3.2.8.2. Consult with ENGINEER in advance of scheduling major tests inspections or start of important phases of the Work. 9.3.2.8.3. Draft proposed Change Orders and Work Directive Changes obtain] backup material from the CONTRACTOR and recommend to ENGINEER Change Orders, Work Directive Changes and field orders. 9.3.2.8.4. Report immediately to ENGINEER and OWNER the occurrence of any accident. 9.3.2.9. Payment Requests Review applications for payment with CONTRACTOR for compliance with the established procedure for their submission and forward with recommendation to 20 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) .I i ENGINEER noting particularly the relationship of the payment requested to the schedule of values work completed and materials and equip delivered at the site but not incorporated in the Work. 9.3.2.10. Completion. 9.3.2.10.1. Before ENGINEER issues a Certificate of Substantial Completion submit to CONTRACTOR a list of observed items requiring correction or completion 9.3.2.10.2 Conduct final inspection in the company of the ENGINEER. OWNER and CONTRACTOR and prepare a final list of items to be corrected or completed 9.3.2.10.3. Observe that all items on the final list have been corrected or completed and l make recommendations to ENGINEER concerning acce Nance j 9.3.3 Limitation of Authority The Representative shall j 9.3.3.1. Authorize any deviations from the Contract Documents or accept any substitute materials or equipment unless authorized by the ENGINEER. t 9.3.3.2. Exceed limitations of ENGINEER'S _ authority as set forth in the Contract Documents ° 9.3.3.3. Undertake any of the re onsibilities of the CONTRACTOR Subcontractors or CONTRACTOR'S superintendent 1 9.3.3.4. Advise on, or issue directions relative to, or assume control over any aspect of the means, methods techniques sequences or procedures for construction unless such is specifically called for in the Contract Documents 9.3.3.5. Advise on or issue directions regarding or assume control over safety precautions and programs in connections with the Work. 9 3 3 6 Accept Shop Drawings or sample submittals from anyone other than the CONTRACTOR. 9.3.3.7. Authorize OWNER to occupy the Work in whole or in part. 9 3 3 8 Participate in specialized field or laboratory tests or inspections conducted by others except as specifically authorized by the ENGINEER. Clarifications and Interpretations: 9.4. ENGINEER will issue with reasonable promptness such written clarifications or interpretations of the EJCDC GENERAL CONDITIONS 1910-5 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) requirements of the Contract Documents (in the form of Drawings or otherwise) as ENGINEER may determine necessary, which shall be consistent with the intent of and reasonably inferable from the Contract Documents. Such written clarifications and interpretations will be binding on OWNER and CONTRACTOR. If OWNER or CONTRACTOR believes that a written clarification or interpretation justifies an adjustment in the Contract Price or the Contract Times and the parties are unable to agree to the amount or extent thereof, if any, OWNER or CONTRACTOR may snake a written claim therefor as provided in Article I I or Article 12. Authorized Variations in Work: 9.5. ENGINEER may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Times and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on OWNER and also on CONTRACTOR who shall perform the Work involved Promptly. If OWNER or CONTRACTOR believes that a Field Order justifies an adjustment in the Contract Price or the Contract Times and the parties are unable to agree as to the amount or extent thereof, OWNER or CONTRACTOR may make a written claim therefor as provided in Article 11 or 12. Rejecting Defective Work: 9.6. ENGINEER will have authority to disapprove or reject Work which ENGINEER believes to be defective, or that ENGINEER believes will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. ENGINEER will also have authority to require special inspection or testing of the Work as provided in paragraph 13.9, whether or not the Work is fabricated, installed or completed. Shop Drawings, Change Orders and Payments: 9.7. In connection with ENGINEER's authority as to Shop Drawings and Samples, see paragraphs 6.24 through 6.28 inclusive. 9.8. In connection with ENGINEER's authority as to Change Orders, see Articles 10, 11, and 12. 9.9. In connection with ENGINEER's authority as to Applications for Payment, see Article 14. Determinations for Unit Prices 9.10. ENGINEER will determine the actual quantifies and classifications of Unit Price Work performed by CONTRACTOR. ENGINEER will review with CONTRACTOR the ENGINEER's preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application 21 for Payment or otherwise). ENGINEER's written decision thereon will be final and binding upon OWNER and CONTRACTOR, unless, within ten days after the date of any such decision, either OWNER or CONTRACTOR delivers to the other and to ENGINEER written notice of intention to appeal from ENGINEER's decision and: (i) an appeal from ENGINEER's decision is taken within the time limits and in accordance with the procedures set forth in Exhibit GC -A, "Dispute Resolution Agreement", entered into between OWNER and CONTRACTOR pursuant to Article 16, or (ii) if no such Dispute Resolution Agreement has been entered into, a formal proceeding is instituted by the appealing party in a forum of competent jurisdiction to exercise such rights or remedies as the appealing party may have with respect to ENGINEER's decision, unless otherwise agreed in writing by OWNER and CONTRACTOR. Such appeal will not be subject to the procedures of paragraph 9.11. Decisions on Disputes: 9.11. ENGINEER will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other matters relating to the acceptability of the Work or the interpretation of the requirements of the Contract Documents pertaining to the performance and furnishing of the Work and claims under Articles 11 and 12 in respect of changes in the Contract Price or Contract Times will be referred initially to ENGINEER in writing with a request for a formal decision in accordance with this paragraph. Written notice of each such claim, dispute or other matter will be delivered by the claimant to ENGINEER and the other party to the Agreement promptly (but in no event later than thirty days) after the start of the occurrence or event giving rise thereto, and written supporting data will be submitted to ENGINEER and the other party within sixty days after the start of such occurrence or event unless ENGINEER allows an additional period of time for the submission of additional or more accurate data in support of such claim, dispute or other matter. The opposing party shall submit any response to ENGINEER and the claimant within thirty days after receipt of the claimant's last submittal (unless ENGINEER allows additional time). ENGINEER will render a formal decision in writing within thirty days after receipt of the opposing party's submittal, if any, in accordance with this paragraph. ENGINEER's written decision on such claim, dispute or other matter will be final and binding upon OWNER and CONTRACTOR unless: (i) an appeal from ENGWEER's decision is taken within the time limits and in accordance with the procedures set forth in EXHIBIT GC -A, "Dispute Resolution Agreement", entered into between OWNER and CONTRACTOR pursuant to Article 16, or (ii) if no such Dispute Resolution Agreement has been entered into, a written notice of intention to appeal from ENGINEER's written decision is delivered by OWNER or CONTRACTOR to the other and 'to ENGINEER within thirty days after the date of such decision and a formal proceeding is instituted by the appealing party in a forum of competent jurisdiction to exercise such rights or remedies as the appealing party may have with respect to such claim, dispute or other matter in accordance with applicable Laws and Regulations within sixty days of the date of such decision, unless otherwise agreed in writing by OWNER and CONTRACTOR. 9.12. When functioning as interpreter and judge under paragraphs 9.10 and 9.11, ENGINEER will not show partiality to OWNER or CONTRACTOR and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity. The rendering of a decision by ENGINEER pursuant to paragraphs 9.10 or 9.11 with respect to any such claim, dispute or other matter (except any which have been waived by the making or acceptance of final payment as provided in paragraph 14.15) will be a condition precedent to any exercise by OWNER or CONTRACTOR of such rights or remedies as either may otherwise have under the Contract Documents or by Laws or. Regulations in respect of any such claim, dispute or other matter. 9.13. Limitations on ENGINEER's Authority and Responsibilities: 9.13.1. Neither ENGINEER's authority or responsibility under this Article 9 or under any other provision of the Contract Documents nor any decision made by ENGINEER in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise or performance of any authority or responsibility by ENGINEER shall create, impose or give rise to any duty owed by ENGINEER to CONTRACTOR, any Subcontractor, any Supplier, any other person or organization, or to any surety for or employee or agent of any of them. 9.13.2. ENGINEER will not supervise, direct, control or have authority over or be responsible for CONTRACTOR's means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of the Work. ENGINEER will not be responsible for CONTRACTOR's failure to perform or famish the Work in accordance with the Contract Documents. 9.13.3. ENGINEER will not be responsible for the acts or omissions of CONTRACTOR or of any Subcontractor, any Supplier, or of any other person or organization performing or furnishing any of the Work. 9.13.4. ENGINEER's review of the final Application for Payment and accompanying documentation and all maintenance and operating instructions, schedules, guarantees, Bonds and certificates of inspection, tests and approvals and other documentation required to be delivered by paragraph 14.12 will only be to determine generally that their content complies with the requirements of, and in the case of certificates of inspections, tests and approvals that the results certified indicate compliance with, the Contract Documents. 9.13.5. The limitations upon authority and 22 E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) responsibility set forth in this paragraph 9.13 shall also apply to ENGINEER's Consultants, Resident Project Representative and assistants. ARTICLE 10--CHANGES IN THE WORK 101. Without invalidating the Agreement and without notice to any surety, OWNER may, at any time or from time to time, order additions, deletions or revisions in the Work. Such additions, deletions or revisions will be authorized by a Written Amendment, a Change Order, or a Work Change Directive. Upon receipt of any such document, CONTRACTOR shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). 10.2. If OWNER and CONTRACTOR are unable to agree as to the extent, if any, of an adjustment in the Contract Price or an adjustment of the Contract Times that should be allowed as a result of a Work Change Directive, a claim may be made therefor as provided in Article 11 or Article 12. 10.3. CONTRACTOR shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any Work performed that is not required by the Contract Documents as amended, modified and supplemented as provided in paragraphs 3.5 and 3.6, except in the case of an emergency as provided in paragraph 6.23 or in the case of uncovering Work as provided in paragraph 13.9. 10.4. OWNER and CONTRACTOR shall execute appropriate Change Orders recommended by ENGINEER (or Written Amendments) covering: 10.4.1. changes in the Work which are (i) ordered by OWNER pursuant to paragraph 10.1, (ii) required because of acceptance of defective Work under paragraph 13.13 or correcting defective Work under paragraph 13.14, or (iii) agreed to by the parties; 10.4.2. changes in the Contract Price or Contract Times which are agreed to by the parties; and 10.4.3. changes in the Contract Price or Contract - Times which embody the substance of any written decision rendered by ENGINEER pursuant to paragraph 9.11; provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance with the provisions of the Contract Documents [ and applicable Laws and Regulations, but during any such appeal, CONTRACTOR shall carry on the Work and adhere to the progress schedule as provided in paragraph 6.29. 10.5. If notice of any change affecting the general scope of the Work or the provisions of the Contract Documents i EICDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) (including, but not limited to, Contract Price or Contract Times) is required by the provisions of any Bond to be given to a surety, the giving of any such notice will be CONTRACTOR's responsibility, and the amount of each applicable Bond will be adjusted accordingly. ARTICLE 11—CHANGE OF CONTRACT PRICE 11.1. The Contract Price constitutes the total compensation (subject to authorized adjustments) payable to CONTRACTOR for performing the Work. All duties, responsibilities and obligations assigned to or undertaken by CONTRACTOR shall be at CONTRACTOR's expense without change in the Contract Price, 11.2. The Contract Price may only be changed by a Change Order or by a Written Amendment. Any claim for an adjustment in the Contract Price shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty days) after the start of the occurrence or event giving rise to the claim and stating the general nature of the claim. Notice of the amount of the claim with supporting data shall be delivered within sixty days after the start of such occurrence or event (unless ENGINEER allows additional time for claimant to submit additional or more accurate data in support of the claim) and shall be accompanied by claimant's written statement that the adjustment claimed covers all known amounts to which the claimant is entitled as a result of said occurrence or event. All claims for adjustment in the Contract Price shall be determined by ENGINEER in accordance with paragraph 9.11 if OWNER and CONTRACTOR cannot otherwise agree on the amount involved. No claim for an adjustment in the Contract Price will be valid if not submitted in accordance with this paragraph 11.2. 11.3. The value of any Work covered by a Change Order or of any claim for an adjustment in the Contract Price will be determined as follows: 11.3.1. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved (subject to the provisions of 23 paragraphs 11.9.1 through 11.9.3, inclusive); 11.3.2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed payment basis, including lump sum (which may include an allowance for overhead and profit not necessarily in accordance with paragraph 11.6.2); 11.3.3. where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum is not reached under paragraph 11.3.2, on the basis of the Cost of the Work (determined as provided in paragraphs 11.4 and 11.5) plus a CONTRACTOR's fee for overhead and profit (determined as provided in paragraph 11.6). Cost of the Work: 11.4. The term Cost of the Work means the sum of all costs necessarily incurred and paid by CONTRACTOR in the proper performance of the Work. Except as otherwise may be agreed to in writing by OWNER, such costs shall be in amounts no higher than those prevailing in the locality of the Project, shall include only the following items and shall not include any of the costs itemized in paragraph 11.5: 11.4.1. Payroll costs for employees in the direct employ of CONTRACTOR in the performance of the Work under schedules of job classifications agreed upon by OWNER and CONTRACTOR. Such employees shall include without limitation superintendents, foremen and other personnel employed full-time at the site. Payroll costs for employees not employed full-time on the Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall inelude,but net be limited to; salaries and wages plus the cost of fringe benefits which shall include social security contributions, unemployment, excise and payroll taxes, workers' compensation, health and ret4em benefits, bonuses applicable thereto. The expenses of performing Work after regular working hours, on Saturday, Sunday or legal holidays, shall be included in the above to the extent authorized by OWNER. 11.4.2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers' field services required in connection therewith. All cash discounts shall accrue to CONTRACTOR unless OWNER deposits funds with CONTRACTOR with which to make payments, in which case the cash discounts shall accrue to OWNER. All trade discounts, rebates and refunds and returns from sale of surplus materials and equipment shall accrue to OWNER, and CONTRACTOR shall make provisions so that they may be obtained. 11.4.3. Payments made by CONTRACTOR to the Subcontractors for Work performed or furnished by Subcontractors. If required by OWNER, CONTRACTOR shall obtain competitive bids from Subcontractors acceptable to OWNER and CONTRACTOR and shall deliver such bids to OWNER who will then determine, with the advice of ENGINEER, which bids, if any, will be accepted. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall be determined in the same manner as CONTRACTOR's Cost of the Work and fee as provided in paragraphs 11.4, 11.5, 11.6 and 11.7. All subcontracts shall be subject to the other provisions of the Contract Documents insofar as applicable. 11.4.4. Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys and accountants) employed for services specifically related to the Work. 11.4.5. Supplemental costs including the following: 11.4.5.1, The proportion of necessary transportation, travel and subsistence expenses of CONTRACTOR'S employees incurred in discharge of duties connected with the Work. 11.4.5.2. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office and temporary facilities at the site and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost less market value of such items used but not consumed which remain the property of CONTRACTOR. 11.4.5.3. Rentals of all construction equipment and machinery and the parts thereof whether rented from CONTRACTOR or others in accordance with rental agreements approved by OWNER with the advice of ENGINEER, and the costs of transportation, loading, unloading, installation, dismantling and removal thereof —all in accordance with terms of said rental agreements. The rental of any such equipment, machinery or parts shall cease when the use thereof is no longer necessary for the Work. 11.4.5.4. Sales, consumer, use or similar taxes related to the Work, and for which CONTRACTOR is liable, imposed by Laws and Regulations. 11.4.5.5. Deposits lost for causes other than negligence of CONTRACTOR, any Subcontractor or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses. 11.4.5.6. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by CONTRACTOR in connection with the 24 EJCDC GENERAL CONDITIONS 1910-5 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) performance and furnishing of the Work (except z losses and damages within the deductible amounts of property insurance established by OWNER in accordance with paragraph 5.9), provided they have resulted from causes other than the negligence of CONTRACTOR, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and ( approval of OWNER. No such losses, damages and expenses shall be included in the Cost of the Work for the purpose of determining CONTRACTORS fee. If, however, any such loss or damage requires reconstruction and CONTRACTOR, is placed in charge thereof, CONTRACTOR shall be paid for services a fee proportionate to that stated in paragraph 11.62. 11.4.5.7. The cost of utilities, fuel and sanitary facilities at the site. j 114.5.8. Minor expenses such as telegrams, long distance telephone calls, telephone service at the site, expressage and similar petty cash items in connection with the Work. 11.4.5.9. Cost of premiums for additional Bonds and insurance required because of changes in the Work. 11.5. The term Cost of the Work shall not include any of the following: 11.5.1. Payroll costs and other compensation of CONTRACTOR's officers, executives, principals (of partnership and sole proprietorships), general managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks and other personnel employed by CONTRACTOR whether at the site or in CONTRACTOR's principal or a branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in paragraph 11.4.1 or specifically covered by paragraph l 1.4.4—all of which are to he considered administrative costs covered by the CONTRACTOR's fee. 11.5.2. Expenses of CONTRACTORS principal and branch offices other than CONTRACTOR's office at the site. 11.5.3. Any part of CONTRACTOR's capital expenses, including interest on CONTRACTOR'S capital employed for the Work and charges against CONTRACTOR for delinquent payments. r 11.5.4. Cost of premiums for all Bonds and for all insurance whether or not CONTRACTOR is required by the Contract Documents to purchase and maintain the same (except for the cost of premiums covered by subparagraph 11.4.5.9 above). EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 11.5.5. Costs due to the negligence of CONTRACTOR, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied and making good any damage to property. 11.5.6. Other overhead or general expense costs of any kind and the costs of any item not specifically and expressly included in paragraph 11.4. 11.6. The CONTRACTOR's fee allowed to CONTRACTOR for overhead and profit shall be determined as follows: 11.6.1. a mutually acceptable fixed fee; or 11.6.2. if a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions of the Cost of the Work: 11.6.2.1. for costs incurred under paragraphs 11.4.1 and 11.4.2, the CONTRACTOR's fee shall be fifteen percent; 11.6.2.2. for costs incurred under paragraph 11.4.3, the CONTRACTOR's fee shall be five percent; 11.6.2.3. where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of paragraphs 11.4.1, 11.4.2, 11.4.3 and 11.6.2 is that the Subcontractor who actually performs or furnishes the Work, at whatever tier, will be paid a fee of fifteen percent of the costs incurred by such Subcontractor under paragraphs 11.4.1 and 11.4.2 and that any higher tier Subcontractor and CONTRACTOR will each be paid a f the He) ,, � , to be negotiated in good faith with the OWNER but not to exceed five percent of the amount paid to the next lower tier Subcontractor. 11.6.2.4. no fee shall be payable on the basis of costs itemized under paragraphs 11.4.4, 11.4.5 and 11.5; 11.6.2.5, the amount of credit to be allowed by CONTRACTOR to OWNER for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in CONTRACTOR' fee by an amount equal to five percent of such net decrease; and 11.6.2.6. when both additions and credits are involved in any one change, the adjustment in CONTRACTOR' fee shall be computed on the basis of the net change in accordance with paragraphs 11.6.2.1 through 11.6.2.5,inclusive. 11.7. Whenever the cost of any Work is to be 25 determined pursuant to paragraphs 11.4 and 11.5, CONTRACTOR will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in form acceptable to ENGINEER an itemized cost breakdown together with supporting data. Cash Allowances: 11.8. It is understood that CONTRACTOR has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be famished and performed for such sums as may be acceptable to OWNER and ENGINEER. CONTRACTOR agrees that: 11.8.1. the allowances include the cost to CONTRACTOR (less any applicable trade discounts) of materials and equipment required by the allowances to be delivered at the site, and all applicable taxes; and 11.8.2. CONTRACTOR's costs for unloading and handling on the site, labor, installation costs, overhead, profit and other expenses contemplated for the allowances have been included in the Contract Price and not in the allowances and no demand for additional payment on account of any of the foregoing will be valid. Prior to final payment, an appropriate Change Order will be issued as recommended by ENGINEER to reflect actual amounts due CONTRACTOR on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted. 11.9. Unit Price Work: 11.9.1. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the established unit prices for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by CONTRACTOR will be made by ENGINEER in accordance with paragraph 9.10. 11.9.2. Each unit price will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR's overhead and profit for each separately identified item. 11.9.3.OWNER or CONTRACTOR may make a claim for an adjustment in the Contract Price in accordance with Article 11 if. 11.9.3.1. the quantity of any item of Unit Price Work performed by CONTRACTOR differs materially and significantly from the estimated quantity of such item indicated in the Agreement; and 11.9.3.2. there is no corresponding adjustment with respect to any other item of Work; and 11.9.3.3. if CONTRACTOR believes that CONTRACTOR is entitled to an increase in Contract Price as a result of having incurred additional expense or OWNER believes that OWNER is entitled to a decrease in Contract Price and the parties are unable to agree as to the amount of any such increase or decrease. 11.9.3.4. CONTRACTOR acknowledges that the OWNER has the right to add or delete items in the Bid or change quantities at OWNER'S sole discretion without affecting the Contract Price of any remaining item so long as the deletion or addmon does not exceed twenty-five percent of the original total Contract Price ARTICLE 12—CHANGE OF CONTRACT TIMES 12.1. The Contract Times (or Milestones) may only be changed by a Change Order or a Written Amendment. Any claim for an adjustment of the Contract Times (or Milestones) shall be based on written notice delivered by the party making the claim to the other party and to ENGINEER promptly (but in no event later than thirty days) after the occurrence of the event giving rise to the claim and stating the general nature of the claim. Notice of the extent of the claim with supporting data shall be delivered within sixty days after such occurrence (unless ENGINEER allows additional time to ascertain more accurate data in support of the claim) and shall be accompanied by the claimant's written statement that the adjustment claimed is the entire adjustment to which the claimant has reason to believe it is entitled as a result of the occurrence of said event. All claims for adjustment in the Contract Times (or Milestones) shall be determined by ENGINEER in accordance with paragraph 9.11 if OWNER and CONTRACTOR cannot otherwise agree. No claim for an adjustment in the Contract Times (or Milestones) will be valid if not submitted in accordance with the requirements of this paragraph 12.1. 12.2. All time limits stated in the Contract Documents are of the essence of the Agreement. 12.3. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or Milestones) due to delay beyond the control of CONTRACTOR, the Contract Times (or Milestones) will be extended in an amount equal to time lost due to such delay if a claim is made therefor as provided in paragraph 12.1. Delays beyond the control of CONTRACTOR shall include, but not be limited to, acts or neglect by OWNER, acts or neglect of utility owners or other contractors performing other work as contemplated by Article 7, fires, floods, epidemics, abnormal weather conditions or acts of God. Delays attributable to and 26 E1CDC GENERAL CONDITIONS 1910-8 (1990 Fditioa) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) 1 within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of CONTRACTOR. 12.4. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or Milestones) due to delay beyond the control of both OWNER and CONTRACTOR, an extension of the Contract Times (or Milestones) in an amount equal to the I time lost due to such delay shall be CONTRACTOR's sole 1 and exclusive remedy for such delay. In no event shall { OWNER be liable to CONTRACTOR, any Subcontractor, any Supplier, any other person or organization, or to any surety for or employee or agent of any of them, for damages arising out of or resulting from (i) delays caused by or within the control of the CONTRACTOR, or (ii) delays beyond the control of both parties including, but not limited to, fires, floods, epidemics, abnormal weather conditions, acts of God or acts or neglect by utility owners or other contractors performing other work as contemplated by Article 7. .1 ARTICLE 13—TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 0 13.1. Notice of Defects: Prompt notice of all defective Work of which OWNER or ENGINEER have actual knowledge will be given to CONTRACTOR. All defective Work may be rejected, corrected or accepted as provided in this Article 13. Access to Work: 13.2. OWNER, ENGINEER, ENGINEER's Consultants, other representatives and personnel of OWNER, independent testing laboratories and governmental agencies with jurisdictional interests will have access to the Work at reasonable time for their observation, inspecting and j testing. CONTRACTOR shall provide them proper and safe conditions for such access and advise them of CONTRACTOR's site safety procedures and programs so that they may comply therewith as applicable. Tests and Inspections: 13.3. CONTRACTOR shall give ENGINEER timely notice of readiness of the Work for all required inspections, tests or approvals, and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. 13.4. OWNER shall employ and pay for the services of an independent testing laboratory to perform all inspections, tests, or approvals required by the Contract Documents except: 13.4.1. for inspections, tests or approvals covered by paragraph 13.5 below; 13.4.2. that costs incurred in connection with tests or inspections conducted pursuant to paragraph 13.9 E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) below shall be paid as provided in said paragraph 13.9; and 13.4.3. as otherwise specifically provided in the Contract Documents. 13.5. If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested or approved by an employee or other representative of such public body, CONTRACTOR shall assume full responsibility for arranging and obtaining such inspections, tests or approvals, pay all costs in connection therewith, and furnish ENGINEER the required certificates of inspection, or approval. CONTRACTOR shall also be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests or approvals required for OWNER's and ENGINEER's acceptance of materials or equipment to be incorporated in the Work, or of materials, mix designs, or equipment submitted for approval prior to CONTRACTOR's purchase thereof for incorporation in the Work. 13.6. If any Work (or the work of others) that is to be inspected, tested or approved is covered by CONTRACTOR without written concurrence of ENGINEER, it must, if requested by ENGINEER, be uncovered for observation. 13.7. Uncovering Work as provided in paragraph 13.6 shall be at CONTRACTOR's expense unless CONTRACTOR has given ENGINEER timely notice of CONTRACTOR's intention to cover the same and ENGINEER has not acted with reasonable promptness in response to such notice. Uncovering Work. 13.8. If any Work is covered contrary to the written request of ENGINEER, it must, if requested by ENGINEER, be uncovered for ENGINEER's observation and replaced at CONTRACTOR's expense. 13.9. If ENGINEER considers it necessary or advisable that covered Work be observed by ENGINEER or inspected or tested by others, CONTRACTOR, at ENGINEER's request, shall uncover, expose or otherwise make available for observation, inspection or testing as ENGINEER may require, that portion of the Work in question, furnishing all necessary labor, material and equipment. If it is found that such Work is defective, CONTRACTOR shall pay all claims, costs, losses and damages caused by, arising out of or resulting from such uncovering, exposure, observation, inspection and testing and of satisfactory replacement or reconstruction, (including but not limited to all costs of repair or replacement of work of others); and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, may make a claim therefor as provided in Article 11. If, however, such Work is not found to be defective, CONTRACTOR shall be allowed an increase in the Contract Price or an extension of the Contract Times (or Milestones), or both, directly attributable to such 27 the contract or provide the services required, (2) whether the bidder can =, perform the contract or provide the service promptly and within the time - specified without delay or interference, (3) the character, integrity, reputation, judgment, experience and efficiency of the bidder, (4) the quality of the bidder's performance of previous contracts or services, (5) _ the previous and existing compliance by the bidder with laws and ordinances relating to the contract or service, (6) the sufficiency of the financial resources and ability of the bidder to perform the contract or provide the service, (7) the quality, availability and adaptability of the materials and services to the particular use required, (8) the ability of the bidder to provide future maintenance and service for the use of the subject of the contract, and (9) any other circumstances which will affect the bidder's performance of the contract. 3.3. Each Bidder may be required to show that he has handled former Work so that no just claims are pending against such Work. No Bid will be accepted from a Bidder who is engaged on any other Work which would impair his ability to perform or finance this Work. 3.4 No Bidder shall be in default on the performance of any other contract with the City or in the payment of any taxes, licenses or other monies due to the City. 4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE 4.1. It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the Work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work, (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents. 4.2. Reference is made to the Supplementary Conditions for identification of: Subsurface and Physical Conditions SC-4.2. ' 4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, thatwithoutexception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 5.0 INTERPRETATIONS AND ADDENDA. 5.1. All questions about the meaning or intent of the Bidding Documents are to 7/96 Section 00100 Page 2 uncovering, exposure, observation, inspection, testing, replacement and reconstruction; and, if the parties are unable to agree as to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in Articles 1 I and 12. OWNER May Stop the Work: 13.10. If the Work is defective, or CONTRACTOR fails to supply sufficient skilled workers or suitable materials or equipment, or fails to furnish or perform the Work in such a way that the completed Work will conform to the Contract Documents, OWNER may order CONTRACTOR to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of OWNER to stop the Work shall not give rise to any duty on the part of OWNER to exercise this right for the benefit of CONTRACTOR or any surety or other party. Correction or Removal of Defective Work. 13.11. If required by ENGINEER, CONTRACTOR shall promptly, as directed, either correct all defective Work, whether or not fabricated, installed or completed, or, if the Work has been rejected by ENGINEER, remove it from the site and replace it with Work that is not defective. CONTRACTOR shall pay all claims, costs, losses and damages caused by or resulting from such correction or removal (including but not limited to all costs of repair or replacement of work of others). 13.12. Correction Period: 13.12.1.If within one-year two years after the date of Substantial Completion or such longer period of time as may be prescribed by Laws or Regulations or by the terns of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents, any Work is found to be defective, CONTRACTOR shall promptly, without cost to OWNER and in accordance with OWNER's written instructions: (i) correct such defective Work, or, if it has been rejected by OWNER remove it from the site and replace it with Work that is not defective, and (ii) satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom. If CONTRACTOR does not promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, OWNER may have the defective Work corrected or the rejected Work removed and replaced, and all claims, costs, losses and damages caused by or resulting from such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by CONTRACTOR. 13.12.2.In special circumstances where a particular item of equipment is placed in continuous service before Substantial Completion of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Specifications or by Written Amendment. 13.12.3. Where defective Work (and damage to other Work resulting therefrom) has been corrected, removed or replaced under this paragraph 13.12, the correction period hereunder with respect to such Work will be extended for an additional period of ere -year two Years after such correction or removal and replacement has been satisfactorily completed. Acceptance of Defective Work. 13.13. If, instead of requiring correction or removal and replacement of defective Work, OWNER (and, prior to ENGINEER's recommendation of final payment, also ENGINEER) prefers to accept it, OWNER may do so. CONTRACTOR shall pay all claims, costs, losses and damages attributable to OWNER'S evaluation of and determination to accept such defective Work (such costs to be approved by ENGINEER as to reasonableness). If any such acceptance occurs prior to ENGINEER's recommendation of final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article 11. If the acceptance occurs after such recommendation, an appropriate amount will be paid by CONTRACTOR to OWNER. OWNER May Correct Defective Work:. 13.14. If CONTRACTOR fails within a reasonable time after written notice from ENGINEER to correct defective Work or to remove and replace rejected Work as required by ENGINEER in accordance with paragraph 13.11, or if CONTRACTOR fails to perform the Work in accordance with the Contract Documents, or if CONTRACTOR fails to comply with any other provision of the Contract Documents, OWNER may, after seven days' written notice to CONTRACTOR, correct and remedy any such deficiency. In exercising the rights and remedies under this paragraph OWNER shall proceed expeditiously. In connection with such corrective and remedial action, OWNER may exclude CONTRACTOR from all or part of the site, take possession of all or part of the Work, and suspend CONTRACTOR's services related thereto, take possession of CONTRACTOR's tools, appliances, construction equipment and machinery at the site and incorporate in the Work all materials and equipment stored at the site or for which OWNER has paid CONTRACTOR but which are stored elsewhere. CONTRACTOR shall allow OWNER, OWNER's representatives, agents and employees, OWNER's other .contractors and ENGINEER and ENGINEER's Consultants access to the site to enable OWNER to exercise the rights and remedies under this paragraph. All claims, costs, losses and damages incurred or sustained by OWNER in exercising such rights and remedies will be charged against CONTRACTOR and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article 11. Such claims, costs, losses and 28 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) damages will include but not be limited to all costs of repair or replacement of work of others destroyed or damaged by correction, removal or replacement of CONTRACTOR's defective Work. CONTRACTOR shall not be allowed an extension of the Contract Times (or Milestones) because of any delay in performance of the Work attributable to the exercise by OWNER of OWNER's rights and remedies hereunder. ARTICLE 14—PAYMENTS TO CONTRACTOR AND COMPLETION Schedule of Values: 14.1. The schedule of values established as provided in paragraph 2.9 will serve as the basis for progress payments and will be incorporated into a form of Application for Payment acceptable to ENGINEER. Progress payments on account of Unit Price Work will be based on the number of units completed. Application for Progress Payment: 14.2. At least twenty days before the date established for each progress payment (but not more often than once a month), CONTRACTOR shall submit to ENGINEER for review an Application for Payment filled out and signed by CONTRACTOR covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that OWNER has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect OWNER's interest therein, all of which will be satisfactory to OWNER. The amount of retainage with respect to progress payments will be as stipulated in the Agreement. Anv funds that are withheld by the OWNER shall not be subject to substitution by the CONTRACTOR with securities or any arrangements involving an escrow or custodianship. By executing the application for payment form the CONTRACTOR expressly waives his right to the benefits of Colorado Revised Statutes Section 24-91-101 et sea. CONTRACTOR Is Warranty of Title: 14.3. CONTRACTOR warrants and guarantees that title to all Work, materials and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to OWNER no later than the time of payment free and clear of all Liens. Review of Applications for Progress Payment: 14.4. ENGINEER will, within ten days after receipt of each Application for Payment, either indicate in writing a E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) recommendation of payment and present the Application to OWNER, or retain the Application to CONTRACTOR indicating in writing ENGINEER's reasons for refusing to recommend payment. In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application. Ten days after presentation of the Application for Payment to OWNER with ENGINEER's recommendation, the amount recommended will (subject to the provisions of the last sentence of paragraph 14.7) become due and when due will be paid by OWNER to CONTRACTOR. 14.5. ENGINEER's recommendation of any payment requested in an Application for Payment will constitute a representation by ENGINEER to OWNER, based on ENGINEER's on -site observations of the executed Work as an experienced and qualified design professional and on ENGINEER's review of the Application for Payment and the accompanying data and schedules, that to the best of ENGINEER's knowledge, information and belief: 14.5.1. the Work has progressed to the point indicated, 14.5.2. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents, to a final determination of quantities and classifications for Unit Price Work under paragraph 9.10, and to any other qualifications stated in the recommendation), and 14.5.3. the conditions precedent to CONTRACTOR's being entitled to such payment appear to have been fulfilled insofar as it is ENGINEER's responsibility to observe the Work. However, by recommending any such payment ENGINEER will not thereby be deemed to have represented that: (i) exhaustive or continuous on -site inspections have been made to check the quality or the quantity of the Work beyond the responsibilities specifically assigned to ENGINEER in the Contract Documents or (ii) that there may not be other matters or issues between the parties that might entitle CONTRACTOR to be paid additionally by OWNER or entitle OWNER to withhold payment to CONTRACTOR. 14.6. ENGINEER's recommendation of any payment, including final payment, shall not mean that ENGINEER is responsible for CONTRACTOR's means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the furnishing or performance of Work, or for any failure of CONTRACTOR to perform or furnish Work in accordance with the Contract Documents. 14.7. ENGINEER may refuse to recommend the whole. or any part of any payment if, in ENGINEER's opinion, it would be incorrect to make the representations to 29 OWNER referred to in paragraph 14.5. ENGINEER may also refuse to recommend any such payment, or, because of subsequently discovered evidence or the results of subsequent inspections or tests, nullify any such payment previously recommended, to such extent as may be necessary in ENGINEER's opinion to protect OWNER from loss because: 14.7.1. the Work is defective, or completed Work has been damaged requiring correction or replacement, 14.7.2. the Contract Price has been reduced by Written Amendment or Change Order, 14.7.3. OWNER has been required to correct defective Work or complete Work in accordance with paragraph 13.14, or 14.7.4. ENGINEER has actual knowledge of the occurrence of any of the events enumerated in paragraphs 15.2.1 through 15.2.4 inclusive. OWNER may refuse to make payment of the full amount recommended by ENGINEER because: 14.7.5. claims have been made against OWNER on account of CONTRACTOR's performance or furnishing of the Work, 14.7.6. Liens have been filed in connection with the Work, except where CONTRACTOR has delivered a specific Bond satisfactory to OWNER to secure the satisfaction and discharge of such Liens, 14.7.7. there are other items entitling OWNER to a set- off against the amount recommended, or 14.7.8. OWNER has actual knowledge of the occurrence of any of the events enumerated in paragraphs 14.7.1 through 14.7.3 or paragraphs 15.2.1 through 15.2.4 inclusive; but OWNER must give CONTRACTOR immediate written notice (with a copy to ENGINEER) stating the reasons for such action and promptly pay CONTRACTOR the amount so withheld, or any adjustment thereto agreed to by OWNER and CONTRACTOR, when CONTRACTOR corrects to OWNER's satisfaction the reasons for such action. Substantial Completion: 14.8. When CONTRACTOR considers the entire Work ready for its intended use CONTRACTOR shall notify OWNER and ENGINEER in writing that the entire Work is substantially complete (except for items specifically listed by CONTRACTOR as incomplete) and request that ENGINEER issue a certificate of Substantial Completion. Within a reasonable time thereafter, OWNER, CONTRACTOR and ENGINEER shall make an inspection of the Work to determine the status of completion. If ENGINEER does not consider the Work substantially complete, ENGINEER will notify CONTRACTOR in writing giving the reasons therefor. If ENGINEER considers the Work substantially complete, ENGINEER will prepare and deliver to OWNER a tentative certificate of Substantial Completion which shall fix the date of Substantial Completion. There shall be attached to the certificate a tentative list of items to be completed or corrected before final payment. OWNER shall have seven days after receipt of the tentative certificate during which to make written objection to ENGINEER as to any provisions of the certificate or attached list. If, after considering such objections, ENGINEER concludes that the Work is not substantially complete, ENGINEER will within fourteen days after submission of the tentative certificate to OWNER notify CONTRACTOR in writing, stating the reasons therefor. If, after consideration of OWNER's objections, ENGINEER considers the Work substantially complete, ENGINEER will within said fourteen days execute and deliver to OWNER and CONTRACTOR a definitive certificate of Substantial Completion (with a revised tentative list of items to be completed or corrected) reflecting such changes from the tentative certificate as ENGINEER believes justified after consideration of any objections from OWNER. At the time of delivery of the tentative certificate of Substantial Completion ENGINEER will deliver to OWNER and CONTRACTOR a written recommendation as to division of responsibilities pending final payment between OWNER and CONTRACTOR with respect to security, operation, safety, maintenance, heat, utilities, insurance and warranties and guarantees. Unless OWNER and CONTRACTOR agree otherwise in writing and so inform ENGINEER in writing prior to ENGINEER's issuing the definitive certificate of Substantial Completion, ENGINEER's aforesaid recommendation will be binding on OWNER and CONTRACTOR until final payment. 14.9. OWNER shall have the right to exclude CONTRACTOR from the Work after the date of Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to complete or correct items on the tentative list. Partial Utilization: 14.10. Use by OWNER at OWNER's option of any substantially completed part of the Work, which: (i) has specifically been identified in the Contract Documents, or (ii) OWNER, ENGINEER and CONTRACTOR agree constitutes a separately functioning and usable part of the Work that can be used by OWNER for its intended purpose without significant interference with CONTRACTOR's performance of the remainder of the Work, may be accomplished prior to Substantial Completion of all the Work subject to the following: 14.10.1.OWNER at any time may request CONTRACTOR in writing to permit OWNER to use any such part of the Work which OWNER believes to be ready for its intended use and substantially complete. If CONTRACTOR agrees that such part of the Work is substantially complete, CONTRACTOR will certify to OWNER and ENGINEER that such part of the Work is substantially complete and request ENGINEER to issue a certificate of Substantial Completion for that part of the Work. 30 EJCDCGENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) CONTRACTOR at any time may notify OWNER and ENGINEER in writing that CONTRACTOR considers any such part of the Work ready for its intended use and substantially complete and request ENGINEER to issue a certificate of Substantial Completion for that part of the Work. Within a reasonable time after either such request, OWNER, CONTRACTOR and ENGINEER shall make an inspection of that part of the Work to determine its status of completion. If ENGINEER does not consider that part of the Work to 1 be substantially complete, ENGINEER will notify OWNER and CONTRACTOR in writing giving the reasons therefor. If ENGINEER considers that part of the Work to be substantially complete, the provisions of paragraphs 14.8 and 14.9 will apply with respect to certification of Substantial Completion of that part of the Work and the division of responsibility in respect thereof and access thereto. 14.10.2. No occupancy or separate operation of part T of the Work will be accomplished prior to compliance with the requirements of paragraph 5.15 in respect of j property insurance. Final Inspection: 14.11. Upon written notice from CONTRACTOR that the entire Work or an agreed portion thereof is complete, ENGINEER will make a final inspection with OWNER and CONTRACTOR and will notify CONTRACTOR in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. CONTRACTOR shall immediately take such measures as are necessary to complete such work or remedy such deficiencies. Final Application for Payment 14.12. After CONTRACTOR has completed all such corrections to the satisfaction of ENGINEER and delivered in accordance with the Contract Documents all maintenance and operating instructions, schedules, guarantees, Bonds, certificates or other evidence of insurance required by paragraph 5.4, certificates of inspection, marked -up record documents (as provided in paragraph 6.19) and other documents, CONTRACTOR may make application for final payment following the procedure for progress payments. The final Application for Payment shall be accompanied (except as previously delivered) by: (i) all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by subparagraph 5.4.13, (ii) consent of the surety, if any, to final payment, and (iii) complete and legally effective releases or waivers (satisfactory to OWNER) of all Liens arising out of or filed in connection with the Work. In lieu of such releases or waivers of Liens and as approved by OWNER, CONTRACTOR may furnish receipts or releases in full and affidavit of CONTRACTOR that: (i) the releases and receipts include all labor, services, material and equipment for which a Lien could be filed, and (ii) all payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or OWNER's property might in any way be responsible have been paid or otherwise satisfied. If any Subcontractor or Supplier fails EJCDC GENERAL. CONDITIONS 1910-8(1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) to furnish such a release or receipt in full, CONTRACTOR may furnish a Bond or other collateral satisfactory to OWNER to indemnify OWNER against any Lien. Releases or waivers of liens and the consent of the surety to finalize payment are to be submitted on forms conforming to the format of the OWNER'S standard fortes bound in the Project manual Final Payment and Acceptance: 14.13. If, on the basis of ENGINEER's observation of the Work during construction and final inspection, and ENGINEER's review of the final Application for Payment and accompanying documentation as required by the Contract Documents, ENGINEER is satisfied that the Work has been completed and CONTRACTOR's other obligations under the Contract Documents have been fulfilled, ENGINEER will, within ten days after receipt of the final Application for Payment, indicate in writing ENGINEER'S recommendation of payment and present the Application to OWNER for payment. At the same time ENGINEER will also give written notice to OWNER and CONTRACTOR that the Work is acceptable subject to the provisions of paragraph 14.15. Otherwise, ENGINEER will return the Application to CONTRACTOR, indicating in writing the reasons for refusing to recommend final payment, in which case CONTRACTOR shall make the necessary corrections and resubmit the Application. Thirty days after presentation to OWNER of the Application and accompanying documentation, in appropriate form and substance and with ENGINEER's recommendation and notice of acceptability, the amount recommended by ENGINEER will become due and will be paid by OWNER to CONTRACTOR subject to paragraph 17 6 2 of these General Conditions. 14.14. If, through no fault of CONTRACTOR, final completion of the Work is significantly delayed and if ENGINEER so confirms, OWNER shall, upon receipt of CONTRACTOR's final Application for Payment and recommendation of ENGINEER, and without terminating the Agreement, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by OWNER for Work not fully completed or corrected is less than the retainage stipulated in the Agreement, and if Bonds have been furnished as required in paragraph 5.1, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by CONTRACTOR to ENGINEER with the Application for such payment. Such payment shall be made under the terms and conditions governing final Payment, except that it shall not constitute a waiver of claims. Waiver of Claims: 14.15. The making and acceptance of final payment will constitute: 14.15.La waiver of all claims by OWNER against CONTRACTOR, except claims arising from unsettled Liens, from defective Work appearing after 31 final inspection pursuant to paragraph 14.11, from failure to comply with the Contract Documents or the teens of any special guarantees specified therein, or from CONTRACTOR's continuing obligations under the Contract Documents; and 14.15.2. A waiver of all claims by CONTRACTOR against OWNER other than those previously made in writing and still unsettled. ARTICLE 15—SUSPENSION OF WORK AND TERMINATION OWNER May Suspend Work: 15.1. At any time and without cause, OWNER may suspend the Work or any portion thereof for a period of not more than ninety days by notice in writing to CONTRACTOR and ENGINEER which will fix the date on which Work will be resumed. CONTRACTOR shall resume the Work on the date so fixed CONTRACTOR shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if CONTRACTOR makes an approved claim therefor as provided in Articles 11 and 12. OWNER May Terminate: 15.2. Upon the occurrence of any one or more of the following events: 15.2.1. if CONTRACTOR persistently fails to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment or failure to adhere to the progress schedule established under paragraph 2.9 as adjusted from time to time pursuant to paragraph 6.6); 15.2.2. if CONTRACTOR disregards Laws or Regulations of any public body having jurisdiction; 15.2.3. if CONTRACTOR disregards the authority of ENGINEER; or 15.2.4. if CONTRACTOR otherwise violates in any substantial way any provisions of the Contract Documents; OWNER may, after giving CONTRACTOR (and the surety, if any) seven days' written notice and to the extent permitted by Laws and Regulations, terminate the services of CONTRACTOR, exclude CONTRACTOR from the site and take possession of the Work and of all CONTRACTOR's tools, appliances, construction equipment and machinery at the site and use the same to the full extent they could be used by CONTRACTOR (without liability to CONTRACTOR for trespass or conversion), incorporate in the Work all materials and equipment stored at the site or for which OWNER has paid CONTRACTOR but which are stored elsewhere, and finish the Work as OWNER may deem expedient. In such case CONTRACTOR shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by OWNER arising out of or resulting from completing the Work such excess will be paid to CONTRACTOR. If such claims, costs, losses and damages exceed such unpaid balance, CONTRACTOR shall pay the difference to OWNER. Such claims, costs, losses and damages incurred by OWNER will be reviewed by ENGINEER as to their reasonableness and when so approved by ENGINEER incorporated in a Change Order, provided that when exercising any rights or remedies under this paragraph OWNER shall not be required to obtain the lowest price for the Work performed. 15.3. Where CONTRACTOR's services have been so terminated by OWNER, the termination will not affect any rights or remedies of OWNER against CONTRACTOR then existing or which may thereafter accrue. Any retention or payment of moneys due CONTRACTOR by OWNER will not release CONTRACTOR from liability. 15.4. Upon seven days' written notice to CONTRACTOR and ENGINEER, OWNER may, without cause and without prejudice to any other right or remedy of OWNER, elect to terminate the Agreement, In such case, CONTRACTOR shall be paid (without duplication of any items): 15.4.1. for completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work; 15.4.2. for expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses; 15.4.3. for all claims, costs, losses and damages incurred in settlement of terminated contracts with Subcontractors, Suppliers and others; and 15.4.4. for reasonable expenses directly attributable to termination. CONTRACTOR shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination. CONTRACTOR May Stop Work or Terminate: 15.5. If, through no act or fault of CONTRACTOR, the Work is suspended for a period of more than ninety days by OWNER or under an order of court or other public authority, or ENGINEER fails to act on any Application for Payment within thirty days after it is submitted or OWNER fails for thirty days to pay CONTRACTOR any 32 EJCDC GENERAL CONDITIONS 1910.8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) sum finally determined to be due, then CONTRACTOR may, upon seven days' written notice to OWNER and ENGINEER, and provided OWNER or ENGINEER do not remedy such suspension or failure within that time, terminate the Agreement and recover from OWNER payment on the same terms as provided in paragraph 15.4. In lieu of terminating the Agreement and without prejudice to any other right or remedy, if ENGINEER has failed to act on an Application for Payment within thirty days after it is submitted, or OWNER has failed for thirty days to pay CONTRACTOR any sum finally determined to be due, CONTRACTOR may upon seven days' written notice to OWNER and ENGINEER stop the Work until payment of all such amounts due CONTRACTOR, including interest thereon. The provisions of this paragraph 15.5 are not intended to preclude CONTRACTOR from making claim under Articles 11 and 12 for an increase in Contract Price or Contract Times or otherwise for expenses or damage directly attributable to CONTRACTOR's stopping Work as permitted by this paragraph. ARTICLE 16—DISPUTE RESOLUTION If and to the extent that OWNER and CONTRACTOR have agreed on the method and procedure for resolving disputes between them that may arise under this Agreement, such dispute resolution method and procedure, if any, shall be as set forth in Exhibit GC -A, "Dispute Resolution Agreement", to be attached hereto and made a part hereof. If no such agreement on the method and procedure for resolving such disputes has been reached, and subject to the provisions of paragraphs 9.10, 9.11 and 9.12, OWNER and CONTRACTOR may exercise such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect of any dispute. ARTICLE 17--MISCELLANEOUS Giving Notice. 17.1. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if delivered in person to the individual or to a member of the firm, or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. 17.2. Computation of Time: .' 17.2.1. When any period of time is referred to in the Contract Documents by days, it will be computed to ` exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation. / E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) 17.2.2, A calendar day of twenty-four hours measured from midnight to the next midnight will constitute a day. Notice of Claim: 17.3. Should OWNER or CONTRACTOR suffer injury or damage to person or property because of any error, omission or act of the other party or of any of the other party's employees or agents or others for whose acts the other party is legally liable, claim will be made in writing to the other party within a reasonable time of the first observance of such injury or damage. The provisions of this paragraph 17.3 shall not be construed as a substitute for or a waiver of the provisions of any applicable statute of limitations or repose.Cumulative Remedies: 17.4. The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto, and, in particular but without limitation, the warranties, guarantees and obligations imposed upon CONTRACTOR by paragraphs 6.12, 6,16, 6.30, 6.31, 6.32, 13.1, 13.12, 13.14, 14.3 and 15.2 and all of the rights and remedies available to OWNER and ENGINEER thereunder, are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations by special warranty or guarantee or by other provisions of the Contract Documents, and the provisions of this paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right and remedy to which they apply. Professional Fees and Court Costs Included. 17.5. Whenever reference is made to "claims, costs, losses and damages", it shall include in each case, but not be limited to, all fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs. 17.6. The laws of the State of Colorado apply to this Agreement. Reference to two pertinent Colorado statutes are as follows: 17.6.2. If a claim is filed OWNER is required by law (CRS 38-26-107) to withhold from all payments to CONTRACTOR sufficient funds to insure the payment of all claims for labor, materials team hire sustenance provisions provender or other supplies used or consumed by CONTRACTOR or his 33 34 EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) I u 8 (This page left blank intentionally.) EJCDC GENERAL CONDITIONS 1910-8 (1990 Edition) 35 W/ CITY OF FORT COLLINS MODIFICATIONS (REV 412000) 36 EICDC GENERAL CONDITIONS 1910-8(1990 Edison) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 4/2000) EXHIBIT, GC -A to General Conditions of the Construction Contract Between OWNER and CONTRACTOR DISPUTE RESOLUTION AGREEMENT k OWNER and CONTRACTOR hereby agree that r Article 16 of the General Conditions of the Construction Contract between OWNER and CONTRACTOR is amended to include the following agreement of the parties: t 16.1. All claims, disputes and other matters in question between OWNER and CONTRACTOR arising out of or relating to the Contract Documents or the breach thereof (except for claims which have been waived by the 1 making or acceptance of final payment as provided by paragraph 14.15) will be decided by arbitration in i accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then - 1 obtaining, subject to the limitations of the Article 16. This agreement so to arbitrate and any other agreement or consent to arbitrate entered into in accordance herewith as provided in this Article 16 will be specifically enforceable under the prevailing law of any court having jurisdiction. 16.2. No demand for arbitration of any claim, dispute or other matter that is required to be referred to ENGINEER initially for decision in accordance with paragraph 9.11 will be made until the earlier of (a) the date on which ENGINEER has rendered a written decision or (b) the thirty-first day after the parties have presented their evidence to ENGINEER if a written decision has not been rendered by ENGINEER before that date. No demand for arbitration of any such claim, dispute or other matter will be made later than thirty days after the date on which ENGINEER has rendered a written decision in respect thereof in accordance with paragraph 9.11; and the failure to demand arbitration within said thirty days' period will result in ENGINEER's decision being final and binding upon OWNER and CONTRACTOR. If ENGINEER renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but will not supersede the arbitration proceedings, except where the decision is acceptable to the parties concerned. No demand for arbitration of any written decision of ENGINEER rendered in accordance with paragraph 9.10 will be made later than ten days after the party making such demand has delivered written notice of intention to appeal as provided in paragraph 9.10. 16.3. Notice of the demand for arbitration will be filed in writing with the other party to the Agreement and with the American Arbitration Association, and a copy will s be sent to ENGINEER for information. The demand for arbitration will be made within the thirty -day or ten-day period specified in paragraph 16.2 as applicable, and in all other cases within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall any such demand be made after the date when institution of legal or equitable proceedings based on such claim, dispute or other matter in question would be barred by the applicable statute of limitations. 16.4. Except as provided in paragraph 16.5 below, no arbitration arising out of or relating to the Contract Documents shall include by consolidation, joinder or in any other manner any other person or entity (including ENGINEER, ENGINEER's Consultant and the officers, directors, agents, employees or consultants of any of them) who is not a party to this contract unless: 16.4.1. the inclusion of such other person or entity is necessary if complete relief is to be afforded among those who are already parties to the arbitration, and 16.4.2. such other person or entity is substantially involved in a question of law or fact which is common to those who arealready parties to the arbitration and which will arise in such proceedings, and 16.4.3. the written consent of the other person or entity sought to be included and of OWNER and CONTRACTOR has been obtained for such inclusion, which consent shall make specific reference to this paragraph; but no such consent shall constitute consent to arbitration of any dispute not specifically described in such consent or to arbitration with any party not specifically identified in such consent. 16.5. Notwithstanding paragraph 16.4, if a claim, dispute or other matter in question between OWNER and CONTRACTOR involves the Work of a Subcontractor, either OWNER or CONTRACTOR may join such Subcontractor as a party to the arbitration between OWNER and CONTRACTOR hereunder. CONTRACTOR shall include in all subcontracts required by paragraph 6.11 a specific provision whereby the Subcontractor consents to being joined in an arbitration between OWNER and CONTRACTOR involving the Work of such Subcontractor. Nothing in this paragraph 16.5 nor in the provision of such subcontract consenting to joinder shall create any claim, right or cause of action in favor of Subcontractor and against OWNER, ENGINEER or ENGINEER's Consultants that does not otherwise exist. 16.6. The award rendered by the arbitrators will be final, judgment may be entered upon it in any court having jurisdiction thereof, and it will not be subject to modification or appeal. 16.7. OWNER and CONTRACTOR agree that they shall first submit any and all unsettled claims, counterclaims, disputes and other matters in question between them arising out of or relating to the Contract Documents or the breach thereof ("disputes"), to mediation by the American Arbitration Association under the Construction Industry Mediation Rules of the American Arbitration Association prior to either of them initiating against the other a demand for arbitration pursuant to paragraphs 16.1 through 16.6, unless delay in initiating arbitration would irrevocably prejudice one of the parties. The respective thirty and ten day time limits within which to file a demand for arbitration as provided in paragraphs 16.2 and 16.3 above shall be suspended with respect to a dispute submitted to mediation within those same applicable time limits and shall remain suspended until ten days after the termination of the mediation. The mediator of any dispute submitted to mediation under this Agreement shall not serve as arbitrator of such dispute unless otherwise agreed. E1CDC GENERAL CONDITIONS 1910-8 (1990 Edition) w/ CITY OF FORT COLLINS MODIFICATIONS (REV 9/99) GC -Al