HomeMy WebLinkAboutRESPONSE - RFP - P812 SECOND SHEET OF ICET H E N E E N A N C O M P A N Y
CITY OF FORT COLLIRS
CITY OF FORT COLLINS
SECOND SHEET OF ICE AT EPIC
REQUEST FOR PROPOSAL P-812
11-29-01
N E E N A N
5.2.4.3 PROJECT TEAM ROLES AND RESPONSIBILITIES
Overview The project team assembled for this project has worked together under a design/build
delivery model on over a dozen past projects. The familiarity of the team members
with each other and with the Neenan Archistruction® process will be of great value to
the City and help ensure the seamless delivery of the project requirements. The
primary roles and responsibilities of each team member follow; however every team
member will assist in insuring that the collective responsibilities described here are
successfully carried out. Resumes on each team member follow at the end of this
section.
Neenan Team Bob Meserve, Senior Project Manager, Project leader
Bob has primary oversight responsibility on the project and will coordinate and direct
all activities of the project team. Bob will be directly responsible for successful delivery
of the project, addressing Owner requests and delivering on Owner Conditions of
Satisfaction.
Steve Burns, Pre -Construction Manager
Steve has primary responsibility for all aspects of pre -construction estimating on the
project. Responsibilities will include determining parameter costs for development and
construction, coordination and oversight of major subcontractor's and their project
budgets during the pre -construction phase, alignment of project costs with design
owner needs. Steve will also provide value engineering studies, develop and present
design and pricing options for Owner review, and life costing analysis. He will develop
project outline specifications and assist in preparing the initial project schedule.
Tim Stern, Project Manager
Tim will provide both pre -construction and project management services. Pre -
construction responsibilities include estimating assistance, budget control, design
input, schedule and constructability review, product selections and day-to-day owner
coordination. Construction project management responsibilities include interface with
Owner's representative, purchasing and contract administration, cost control,
subcontractor negotiations, project buyout, management of project schedule and
project closeout.
Mike Mesa, Superintendent
As project superintendent, Mike will be responsible for all aspects of on -site
construction activities. Such activities include planning and executing the field work,
including scheduling and directing subcontractors on the jobsite; maintaining all on -site
records required by city, county or utility authorities; responsible for the layout and
dimensional control of the structure, monitoring the completed work for compliance
with the contract drawings and specifications; coordinating the quality control program
for the project, working with the Project Manager and General Superintendent during
the pre -construction phase of the project. Will additionally provide design and pre -
construction assistance regarding constructability issues.
Chris Wesche, Project Architect.
Chris is responsible for developing from the Owner's conditions of satisfaction, building
department and code requirements, the highest value design solution within the
budget. He is responsible for completion of construction documents and securing of
required permits for the construction, as well as construction administration to insure
compliance with the contract documents and quality standards.
Proposal to City of Fort Collins 5.2.4.3 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
City of Fort Collins
Mayor
David Neenan
The Neenan Company
2620 East Prospect Road
Fort Collins, CO 80525
October 11, 1999
Dear David:
I wanted to take a minute to tell you what a
great job you have done with the addition to
St. Joseph School. The architecture blends so
nicely with the original construction. It has
been a much needed addition to the school.
Thank you for the good work you do. Your
projects are changing the face of Fort Collins.
Sincerely,
Ray Martinez
Mayor
N E E N A N
The Group, Inc.
Fort Collins, Colorado
Architect:
The Noonan
Conse.0aa .is
December 1.
THE GROUP
Fort Collins, Colorado
The 27,000 square foot, wood -framed building
expresses a Colorado lodge theme, with extensive
use of rough timbers and native stone. The wood
framed structure has a two-story entry lobby
incoryoreting lam' wood beam construction
and tongue and ceilings, wi h a
massive 40 foci high place and second
floor balcony overlook. � Is theme carrle outside
to a rough m ports
QUANTUM CORPORATION SSPG
Colorado Springs, Colorado
Quantum Corporation engaged The Neenan Company for a three building 403,000
r AQW,was "ouec. An
)dates of Coorado sprir
1e �{� � S` Xmp 54. ➢Y
i i1W are '''3 g'µ • • w`
iz Architects. e-
All
each as a Iknee, hmovadm urvolvement, and du:
amNde ujgoing -'above and beymd." Pow
c is b Teamwork hat led 0 a etn"wftl
p jwt and a very eodsied awhmer."
-Wayne M. Tfmwa
Quantum RedFm e
andDk Agpment
January 7, 2000
Mr. David Neenan
The Neenan Company
2620 East Prospect Road, Suite 100
Fort Collins, Colorado 80525
Subject: New Office at 2803 Harmony Road
Dear David, THEGROUPINC.
We are "happy campers" as customers of The Neenan Company! The new Real Estate
office building "Team Neenan" created for us on Harmony Road is spectacular.
We continue to receive compliments on a daily basis from customers and guests. The
most enthusiastic comments have come from other builders, architects, interior designers,
and appraisers — people who really appreciate what you have created for us. We have
received numerous calls and letters from people in the community complimenting us on
the design statement the building makes as an entrance to Fort Collins. We have had
unsolicited job applications from people wanting to "work in such a beautiful building."
Most of all, our partners at The Group love it. The building puts them in a good mood
every time they enter. You have exceeded our expectations!
Our compliments go out to the team, especially architects, Bob Hosanna and Bob
Mooney, who have created a landmark building in Fort Collins. We believe interior
designer, Michelle Phenix Goodwin, is on the cutting edge of design. She captured
exactly what we wanted in a "Colorado lodge" look and feel. (Custom homebuyers and
builders have been "all over" her design, wanting to recreate the same "feel' in their
homes.) For great design to be appreciated, it has to have perfect execution, and Rick
Campbell is definitely the master. As project superintendent, the final product was his
responsibility and it came out as a masterpiece. Rick is a real pro and a class act!
We cannot say enough good things about The Neenan Company and the great people we
have had the opportunity to work with. This was our tenth office building. It is our best
one — best design, best quality, best budget, best schedule, best builder, and most fun.
The Group, Inc. wants to give a big thanks to you and your team. Archistruction works!
Sincerer,
6rc�a/
Larry K/p idall, Chairman
r
cc. Bob Hosanna, Bob Mooney, Michelle Goodwin, Rick Campbell, Ray Piggsoum oft,
375 East Horsetooth Road
Fort Collins, Colorado 80525
970/223-0700
113
®,
Quantum°
CAPACITY FOR THE EXTRAORDINARY TM
June 22, 1999
Dear Future Neenan Company Customer
The Neenan Company was an integral part of the team that was on time and on target in
the successful completion of Quantum's new three building campus in Colorado Springs,
CO. The team worked to develop win -win relationships and embraced values such as
excellence, innovation, flexibility, and the attitude of going "above and beyond". The
result achieved is a 403,000 square foot well -planned and flexible campus that was built
in record time. Quantum is using the campus for manufacturing, engineering labs, and
offices and we are a very satisfied customer.
As the construction manager, the Neenan Company played a significant role in the
project and led the effort to take the idea of a new campus and build it into a reality.
They did an excellent job of coordinating with the design team and leading the
construction team from initial cost estimates to design concepts, through construction and
occupancy.
They were instrumental in keeping the project construction on track - a major
accomplishment considering the speed of the project and the numerous bid packages. We
appreciated their flexibility and responsiveness to our many changes during the project.
Their attention to delivering quality workmanship, construction sequencing, and job site
organization was excellent.
Neenan is committed to safety and developed a quality safety program for the project.
A surprise visit by an OSHA inspector yielded only positive comments, plus a statement
from the inspector that he had not seen such a clean job site or a quality safety program
like the one developed for the Quantum project in the last seventeen years.
Quantum has teamed with the Neenan Company on two major projects in Colorado.
Both projects were extremely successful. We are a very satisfied customer and it is with
pleasure that I highly recommend them.
Sincerely,
Wayne M. Timura, P.E.
Director
Corporate Real Estate & Development
Quantum Coipoiation, 10125 Federal Drive, Colorado Springs'. Colorado 80908-4508, (719) 536-5000, hilp://www.quantum.com
F
it 141
i
6 May 1997
Mr. Ray Pigg
2290 East Prospect Road
Fort Collins, CO 80525
Dear Ray,
Of course I want to write a letter of recommendation for The Neenan Company.
After spending 16 months with the staff from Neenan's in the planning, site
development and construction of our new facility, your company is like family to
us at New Belgium Brewing Company. I am unqualified in my respect and
admiration for all that you've done and continue to do to provide value-added
service.
Perhaps we could have picked a more difficult piece of property to develop in
Fort Collins. If so, I'm unaware of its location! The Neenan team's expertise in
navigating the city process, working with attorneys, engineers, adjacent property
owners and irrigation ditch owners was crucial to our initial momentum. In
retrospect, I feel that the hurdles we had to overcome to begin construction might
have stopped me in my tracks had it not been for the "possibility thinking" of all of
the folks at Neenan. Your well of creative ideas seemed to be unending. Just as
important, attention to detail and follow through were unflagging.
As if this wasn't enough to do, The Neenan Company and New Belgium Brewing
Company were simultaneously working on design and financing options. Randy
Meyer's help in developing Pro Formas and understanding the financing options
was the springboard I needed to begirr the long and someTimes scary process of
researching and securing the financing for this 28,000 square foot building. I am
very pleased with the option I eventually chose, and feel that Randy's advice
helped me to explore the myriad of possibilities.
500 LINDEN • FORT COLLINS, COLORADO 80524.97Q 221-0524
N E E N A N
MCWHINNEY OFFICE PARK
Loveland, Colorado
This is a planned four -building office park located in the Rocky
Mountain Village in Loveland. The four buildings, when
completed, will create a distinctive office campus and share a
tastefully landscaped courtyard plaza area common to the
building lobbies. Architecture and construction were provided
by The Neenan Company.
The initial two structures are two-story steel framed, multi -
tenant office facilities consisting of 34,000 square feet each.
The stone, brick and wood exterior of the facilities set the
standard for the Rode Mountain Village Office Park. The natural
design of the gable entry and the lobby's exposed wood
structure surround a free-standing sitecast concrete elevator
shaft. Natural sandstone boulders set in stained concrete
flooring set off the rustic motif.
"...Your lean thinking strategy
really works..Yhe Neenan
Company provided excellent
value and we definitely received
'morefor less'.... "
- Chad McWhbiney s ...
Preridr,u of `i"•'k
McWhinney Enterprises
Client:
FDC Office I, LLC
Loveland, Colorado
Tenant:
Factual Data
Construction Start:
September 1997
Project Completion:
March 1998
6.
Car-raBeefComlaw'
September 6, 2001
To Whom It May Concern:
P.O. Box G / 80632.0350
1978 AA Street
Greeley, CO 80637.9663
Tel 970.395.8723
Fax 970.395.8890
Email dnerronocrfc.com
Danny Marron
vice President
se�ror rinencaf Off,=
The Neenan Company was selected in October 1999 to be the design/build firm for the new
ConAgra Beef Company World Headquarters. This project was originally' designed to fit multiple
sites as we decided where to build our new headquarters. I would like to offer the following
comments on the Neenan Team.
Overall Design:
The design team led by Bob Hosanna and Dawn McGilvray did an excellent job in transforming
our concepts and ideas into an office space that will allow us to offer our employees a world class
environment Their process included facilitating many group meeting that were focused on
drawing out our thoughts and ideas. What was most impressive was their attention to our needs
and the constant focus they had on making the space work for us.
Project Management:
Bob Meserve and his team managed this project very well from the beginning. They were well
organized and kept me abreast of all developing issues during weekly status meetings. They
insured that all changes to scope and budget were approved by me prior to work orders being
authorized, In addition, I thought they differentiated their firm from others by working with me to
accommodate system furniture installation while the building was still under construction.
Installing the furniture during construction is not a normal occurrence and they were flexible
enough to work out a solution that satisfied everyone involved and allowed our team to move into
the new building at least a month early.
In summary, I feel that the Neenan Team has delivered on the conditions of satisfaction that we
agreed to at the beginning of the project. They completed the project on time and if 1 started the
project over tomorrow I would still choose Neenan to be our partner,
Since ly,
Danny�n
N E E N A N
LONGMONT UNITED HOSPITAL
Longmont, Colorado
This new bedtower facility Is an addition to the ebstingloingle-story Longmont
United Hospital. The five -story type 1 steel structure betltevrar consists of
approximately 157,000 square feet that opens into a�ipppppolve four-story atrium.
The patient room floors are designed to provide a lrftrtqple residential
environment. r
The exterior skin of the building is adete9ep,mixture of architectural precast
concrete v@r1Cpr panels, modular lay-lo,brid,, and GFRC veneer panels. The high -
quality interierfimish uses archoctural prepaiIS concrete, modular brick, hardwoods,
and architectural! metals. The "Lent"rmomg ear{y a residential motif with vinyl wall
coverings, residential fumishingt;.and [a sebinelry:
Project delivery was a CWGC process that. included HLM Design for the
architecture ait9 structural engineering, and The Noonan Company for
preconstructlon•and construction management services.
WINDSOR MEDICAL CENTER
Wndsor, Colorado
Colorado decided to move
beating the competing
ROCKY Mold[ 614CANCER TER a
Denver, Colorado y"
A group of pedlato pI�VAIl It fo .r. Hematology On
Associates to pravW S1aaRe nd acquire the afi
The Neenah c°rnp�ayraadlhl'. design and constru .a
project. The facilitjvwasidesioned] y architects from The Neepull
". ry7"4 ;l sgo8re foot steel frann- cture was develoWd that
vi for
tad a covered drop off patient con' once. A comprehempiaa
#FMlaw
I incorporates the use of many trees, shrubs and eaten walls
Oajtcer Center
ct of the building to Its neighbors. 'Dgaver brick" was
��tver, Colo
;
Ilding's veneer to compligno tlla a. lroUriding architecture.
e Noon
TheN�eeyna,-h
ihe;Rr@II waseoordinated by The Neenan Company, who
Ce ructio
mated Liabillt Company to raise the equity, negotiated the land
`. 'b
I
NNov
November t
Purchase and.land lease from the hospital, arranged the construction loan,
PQ JVemect
will -secure permanent financing and created and finalized all the tenant
may z000,
leases.
atess:
Longmont United Hospital
Longmont,Coloredo
Archness:
!+W n
aemmr,.
comlir"gW on:
.)Pr,* 11on,
erell %aniiiiliMbtn,
Depent ar sags
Client:
h System
Colorado
Architect:
iCompany
Ion Start:
mbar 1999
N
E E N A N
of low n
which a
lisal3
steel OR
the park
SYr
f'
BUSINESS CENTER
i Rench, Colorado
siaess Center is a master planned 20 acre office
will ultimately contain half a million square feet
O; s A' space In four buildings and a setting
m tits this unique environment. Shea Center
�,C ysae foot, four-story, Type 11- one -hour
)a otthe northeast corridor of
is trough a double F N qse
gjJWing Identity to tho3fiseserby,
Via,
Y L }
T ¢+�i
come.Ft
0
w
,C S g
FJ r iX!
Client:
Sheaf
H �,
Client:
HUNTER DOUGLAS Hunter Douglas, Inc.
Broomfield, Colorado Broomfield, Colorado
Hunter Douglas is an intemational manufacturer and marketer
of window shades, ceiling products and architectural metals. Architect:
This campus began in 1988 with construction of the signature' Pouw a Associates
j9 _ Viand the first _ n rat W. facilities. The Neenen Company
iU - �,�1,1 ifi" 1qIA ; , .°'Cori tnucaon start:
architect %Nelln r> Cbm- -filch cts. Tbls J0114ty z; January 1990
t ..,Hen ri eslgq,I#latlpnstIWW1thi4oef.pIl,RowDfHbmgh
,. "III- rchit® eonNrlued oVer4 - It3. 'WiLoomp� _ ProJse�1 Completion:
S 5 compl itiidklps and one addition, t0 111 Map 2g0a
9 rd.5 W li^ec+r wMhafuture150 S.F. building/p InW.
o'
E � • "'i t al6hnes throughout
Th ,tiiree�aW llar i uildlh qs fOWNI
r this�t tTheNeenan
IQabeaniiga & fee story gl§pt# Vic'
i'^w.sf .. i'ompa{hevelexhibited the
durfalnvall It Ispitpped mid revfff• TJnla ofAee
build ed a Deli n rl k et4leve(s of integrity,
Institute Th �A"ceof eA S.F. c rtogler service and
9prod do ,f 2il , S.F. wsS `- technical ex ertise. The
expaa d tor�tyy 0 9.E .The produdbn fadl are kted% � p
'V"' quality of workmanship
bearing Be�aall with a s�teLb>1Y 'st roof sy The and materials was
building y�s t?e'lnpleted In,. 001. Mch of the ucbon !
g Product , this
fpolitipa sae connected b rnelosedlinks al ''' n.
silent. Additionally
end persoaanski rrygVe`t _ UghQutfaolll0l, tll�s _ PtQ/ectwas completed on
and within budget.
` ' bottom line is that this
d
"projectW a tremendous
;Wccej&,4ndI100kjbrwani
�,,, j# working with The
Neenah Company on our
fthoeyconstruction
.w .,
ElW* Mucheit
xunterpoug(as
N E E N A N
Bob Hosanna, Design Architect.
Bob's competency and greatest strength is in listening to the Owner's needs and
desires and converting them into a responsible design solution. Bob is responsible for
creating and maintaining the architectural character and integrity of the project,
including design compatibility with the existing facility, and internal functional
effectiveness. He is specifically responsible for planning, schematic design, and
programming project design components of the project, job -site observation.
Jon VanBenthem, Job Captain
Jon's experience with ice arenas will be a valuable addition to the project team. Jon
will be primarily responsible for the development of contract documents, and will work
directly with the other team members to generate documents that convey in detail the
design intent. He is specifically responsible for consultant coordination, construction
documentation, job -site observation, field coordination, and coordination with
regulatory agencies.
Consultants Merit Electric, Electrical Engineer/Design-Build Electrical Sub -Contractor
Responsible for establishing preliminary electrical budgets, assisting the team,
including the Owner, in analyzing alternates and options, evaluating these options as
they may impact other building systems, preparing complete plans for permit and
construction, and installation of electrical systems.
Design Mechanical, Mechanical Engineer/Design-Build Mechanical Sub -Contractor.
Responsible for establishing preliminary HVAC and plumbing budgets, and working
with the team, including the Owner, in analyzing alternates and options, evaluating
these options as they may impact other building systems, preparing complete plans for
permit and construction, and installation of HVAC and plumbing systems.
Gilfillan/Callahan Architects, Inc., Pat Callahan, Consulting Architect.
Responsible for consultant review of ice arena systems including dasher board design,
locker room size and location, Zamboni room size and location, ice plant type, ice
arena finishes, and building system compatibility with rink requirements.
Commercial Refrigeration, Ice consultant/Ice Package Design -Build Sub -Contractor.
Responsible for the ice system design and installation, including ice surface system
and piping, snow melt pit and piping, dasher boards and glass, and low E ceiling
options. They will also provide input on the design of other building systems to verify
compatibility with the ice package system and maximize building systems efficiency.
Proposal to City of Fort Collins 5.2.4.3 — Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
f
Nf3Rp��"`q " x -a^y'$�� �'-, .,:�4ty`^ .�a"b ^^o .F�§
�3�IP4'�F)P.� tp iYx SAP �riy Iq:�
j the development of a now campus. Xilinxp
n�@►
g- ad The Neenan Company to provide site and
4 Sci development services for this exciting new
jact and Neenan retained the services of the
and firm Downing
iloctural planning of Thorpe &
rB8•
naive measures were taken to create an
nment that will aid the company In attracting
retaining these creative designers. The first
a of development included all of the needed
Improvements for the 59 acres and
ielopment of the first building of 130,000 square
t. Additionally, a retreat building of 5,000 square
was constructed to serve as a "get away" area
fQf employees during their workday. The design of
uilding is reflective of many "Colorado" design
t,Itras derived from our mountain and agricultural
:Grand public spaces feature soaring ceilings
sd with timber with generous use of native
s ties and other materials, utilizing steel frame
stivction.
t 3N
. Clio 1,
Xilinx,
AmMoct:
Construction Start:
Phase Ua Melch 3000
� fR,rgl�5b¢smpNgon:
.FNq e'1 �August2001
N E E N A N
1899 WYNKOOP ("Ice House Office")
Denier, Colorado
The nine -story building at the Comer of 1 9th sph({
Wynkoop streets, offers 175,000 s Ieet of prime
offices space. A blending, �{,� elsNa�d lase
Pa I l NCI 9 ",
in s architectural rt apnbh l .
Western past, prod $�t19Fh.p loalfq tulre vlCal
to business in the n 1'
The structure is TvDe I Steel and oos'hfinsionsd
Mquare
bility
uOts 3 {
i�gcpp�suisr�g^
:v. ..
,
k �
y
i
T
t:
Ilen.M
C
s Develepr"nb3 I is
rtho
gy
k
Appendix
Proposal to City of Fort Collins 5.2.15.2 - Appendix November 28, 2001
Second Sheet of Ice at EPIC (P-812)
mdEl{ I�IA� j�iiIl M�'N'p q.111!11111711,
{�
Oak lawn Ice Arena Oak lawn, IIhn015
t
i
,1
<i)
�'a�nnnrmmgiu*onnuawonr
� � � 1 ., Iilli illill
alp
■fir . ��rrr rrr r av+rrir�wwn M��f �lil •� it t
I�
,Illi i�
IIYF.
Xg
Oak' Lawn Ice Arena Oak Lawn, Illinois
A;,
COMM'ERCI,A I
REIRIqERATION INC
Appendix
Proposal to City of Fort Collins 5.2.15.3 - Appendix November 28, 2001
Second Sheet of Ice at EPIC (P-812)
%
�\
m
I
li
Appendix
Proposal to City of Fort Collins 5.2.15.5 - Appendix November 28, 2001
Second Sheet of Ice at EPIC (P-812)
grit
mmmm
Integrity Skill I.mzgina Limi
Conagra
Owner:
Architect:
General Contractor:
Engineer:
Contract Amount:
% Completed:
Scheduled Completion:
. McWhinney
The Neenan Company
The Neenan Company
Merit Electric, Inc.
$1,581,124.50
100%
9/21/01
Cvtomation Bid
Owner:
Architect:
Greg Fisher
General Contractor:
Delta Construction
Engineer:
Merit Electric, Inc.
Contract Amount:
$235,796.00
% Completed:
100%
Scheduled Completion:
8/31/01
Oakridee Dental Office
Owner:
Delta Construction
Architect:
Vaught Frye
General Contractor:
Delta Construction
Engineer:
Merit Electric, Inc.
Contract Amount:
$7411.37
% Completed:
5%
Scheduled Completion:
2002
New Belgium
Brewery
Owner:
New Belgium Brewery
Architect:
The Neenan Company
General Contractor:
New Belgium Brewery
Engineer:
Merit Electric, Inc.
Contract Amount:
$600,000
% Completed:
5%
Scheduled Completion:
2002
Swallow Hill Condominiums
Owner:
FMC Corporation
Architect:
David Owen Tyrba
Architects
General Contractor:
J.E. Dunn Construction
Engineer:
Merit Electric
Contract Amount:
$1,600,000
% Completed:
40%
Scheduled Completion:
7/19/02
16 Suuare Market
Owner:
Continuum Partners, LLC
Architect:
Quinlivan Pierik Krause
Architects
General Contractor:
Turner Construction
Engineer:
Merit Electric
Contract Amount:
$1,970,745
% Completed:
100%
Scheduled Completion:
8/31/01
Greenwood II
Owner:
Greenwood Plaza Partners
Architect:
Klipp Colussey Jenks
DuBois
General Contractor:
Saunders Construction
Engineer:
Merit Electric
Contract Amount:
$2,600,000
% Completed:
100%
Scheduled Completion:
3/31/01
Bassett 12 Story High Rise Buildin
Owner:
Greystar Development
Architect:
Josh Comfort Lawrence
Group Associates
General Contractor:
Greystar Construction West
Engineer:
Merit Electric
Contract Amount:
$4,800,000
% Completed:
10%
Scheduled Completion:
1/29/03
N E E N A N
5.2.4.4 MANAGEMENT PLAN
Neenan Team The leadership and experience of the key construction team members will be critical to
the success of the Second Sheet of Ice at EPIC. For it's in-house team, The Neenan
Company has selected the strong experience and management skills of key leaders
Bob Meserve as Senior Project Manager, Steve Burns as Preconstruction Manager,
Chris Wesche as Project Architect, and Mike Mesa as Project Superintendent, with
Bob Meserve as the overall project leader of our project team.
The team supporting the key leaders is equally important. Consequently, The Neenan
Company has carefully drawn on individuals who, collectively, have accumulated a
vast array of construction experience on a wide range of projects within both the public
and private sectors. Each member brings unique talents and skills that will be
instrumental in the successful delivery of this project.
This team has worked closely and effectively together on previous projects, which will
help insure project success. The team of Bob Meserve, Tim Stern and Mike Mesa,
recently completed a new 175,000 square foot production facility for Hunter Douglas
Window Fashions in Broomfield, Colorado. Their on -time, on -budget delivery of this
project to the high satisfaction of our client evidences the effectiveness of this team.
Each member supporting the key leaders has worked with them on numerous past
projects in varying capacities, and understands the individual and team dynamics.
Maintaining the continuity of these project teams on the EPIC project will enable us to
leverage existing synergies and focus immediately on customer value. Each team
member is aware of the competencies and expertise of the other members, and
responsibilities are clearly defined and understood before the project begins. This will
create a win -win situation for both The Neenan Company and The City of Fort Collins.
Design/Build
The primary sub -contractor team members selected for this project were chosen based
Sub-
on their competency with the type of construction proposed, and their ability to work
contractors
together as a team under a design/build delivery model. These sub -contractors have
worked on numerous projects with the Neenan team and proven their knowledge of
design/build, effectiveness working in a collaborative "team" environment, and most of
all client focus, all of which are unwavering requirements of any members of a Neenan
team. With their assistance, we can absolutely guarantee to deliver a project that
meets all of your requirements and exceeds your expectations.
Consulting
Integral to our design team and the verification of, our ice rink design solution is Pat
Architect
Callahan and the Architectural firm of Gilfillan/Callahan Architects, Inc.. This firm has
extensive experience in the design of ice rink facilities, and will act as the technical
consultant to the team for the overall rink design.
Pat has worked in the past with members of our design team and has demonstrated
his competency with ice rink design, and his design/build bias. Pat and his firm will be
integrally involved with the project team through the early stages of design to insure
that this is a state-of-the-art rink, and that all factors involved with contemporary ice
rink design have been identified and addressed.
Summary We are confident that our entire team possesses the traits necessary to work
collaboratively with The City of Fort Collins, Twice The Ice, project consultants, and all
other service providers to complete a high quality project on budget and on time.
Proposal to City of Fort Collins 5.2.4.4 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
Windsor Medical
Owner:
Lawton, Lembetz, & Mason
Architect:
The Neenan Company
General Contractor:
The Neenan Company
Engineer:
Merit Electric
Contract Amount:
$281,709
% Completed:
100%
Scheduled Completion:
12/31/00
Associates in Family Medicine
Owner:
Poudre Valley Hospital
Architect:
Vaught Frye Architects
General Contractor:
Drahota Construction
Engineer:
Merit Electric
Contract Amount:
$181,415
% Completed:
100%
Scheduled Completion:
3/31/99
Orthopedic of the Rockies
Owner:
Orthopedic of the Rockies
Architect:
The Neenan Company
General Contractor:
The Neenan Company
Engineer:
Merit Electric
Contract Amount:
$170,000
% Completed:
100%
Scheduled Completion:
11/12/99
Avista MOB
Owner:
Avista MOB
Architect:
The Neenan Company
General Contractor:
The Neenan Company
Engineer:
Merit Electric, Inc.
Contract Amount:
$11,491
% Completed:
100%
Scheduled Completion:
12/03/99
design
Appendix
Proposal to City of Fort Collins 5.2.15.6 - Appendix November 28, 2001
Second Sheet of Ice at EPIC (P-812)
BHA Desien, Inc. (I C S I 11
experience
The following list depicts representative planning and landscape architecture experience over the last 3-5 years.
Fossil Creek Park, 100 acre park, Fort Collins, Colorado
Southwest Community/Youth Sports Complex Master Plan, 100 acre park, Fort Collins, Colorado
Westfield Neighborhood Park, 14 acre park, Fort Collins, Colorado
Riverside Park, 60 acre park, Evans, Colorado
Sand Creek Park, Aurora, Colorado
Freemont County Trails and Open Space Master Plan, Canon City, Colorado
Mount Sopris Tree Farm Active Recreation Area, Basalt, Colorado
Latimer County Fairgrounds, Loveland, Colorado
Cache La Poudre Trail Master Plan and Guidelines, 23 mile trail, Weld County, Colorado
Greeley Northridge High School Number 3, Klipp Colusy Jenks, and DuBois Architects, Greeley, Colorado
Poudre School District- New high school for 2004, RB+B Architects, Fort Collins, Colorado
Downtown Transit Center, Fort Collins, Colorado
Fort Collins Civic Center Office Building, Fort Collins, Colorado
Fort Collins Downtown Streetscapes - City of Fort Collins, Fort Collins, Colorado
Lincoln Center for the Performing Arts - City of Fort Collins, Fort Collins, Colorado
Home State Bank, RB + B Architects, Downtown Fort Collins, Colorado
Salem Hospital Renovation, Salem, Oregon
McKee Medical Center, Loveland, CO
Poudre Valley Hospital, Lemay Campus, Fort Collins, Colorado
Poudre Valley Hospital, Harmony Campus
FE Warren Air Force Base, Courtyard remodels, Cheyenne, Wyoming
Agilent Technologies, Loveland, Colorado
Con Agra Beef Company World Headquarters, Greeley, Colorado
LSI Logic, Fort Collins, Colorado
Cements. Marketplace, SEM Architects, Loveland, Colorado
Centerra Business Park, Bob Hosanna, architect, Loveland, Colorado
Hewlett Packard/ West Campus Master Plan- HP, Fort Collins, Colorado
Hewlett Packard Loveland Master plan - HP, Loveland, Colorado
Hewlett Packard Greeley, Surplus Land Study - Hewlett Packard, Greeley
Harmony Technology Park -160 acre high-tech industrial park master plan- HP, Fort Collins
U S West Advanced Technologies Corporate Research Facility - MBT Associates, Boulder, Colorado
Neenan Company Headquarters, Fort Collins, Colorado
New Belgium Brewing Company Headquarters and Brewery - Neenan Company, Fort Collins, Colorado Eastern
Oakridge Business Park, Vaught Frye, Architects, Fort Collins, Colorado
Oakridge Design Center - RB+B Architects, Fort Collins, Colorado
Highlands Ranch Business Park Master Plan -Mission Viejo Company, Englewood, CO.
National Center for Atmospheric Research - Anderson DeBartolo Pan Architects, Boulder, Colorado
Finalist, Latimer County Civic Center Complex - Durrant Architects, Larimer County, Colorado
Eagle Ridge Apartments - Prowswood Management, Loveland, Colorado
Beth Israel at Shalom Park - KKE Architects, Aurora, Colorado
Windsor Downtown Urban Design - KBN Engineers, Windsor, Colorado
Rock Creek Planned Community - Richmond Homes, Superior, Colorado
Berthoud Cemetery, Berthoud, Colorado
Dodge City Gateway Signs, Dodge City, Kansas
Walden Downtown Urban Design Master Plan and implementation - Walden, Colorado
epresentaave EVerience
6Fa design, inc.
Experience
Inc.
C�CtiI�II
We enjoy the Design -Build process, and we believe that the process is a valuable tool for the owner, the
design team and for the contractor. It is a dynamic process with free flowing information that offers checks
and balances throughout. Best of all, the Design -Build process takes advantage of the combined knowledge
and expertise of the entire team to develop practical and constructable design solutions for unique situations.
Below are selected projects representing BHA Design's previous Design -Build experience:
• City of Fort Collins Office Building, Fort Collins, Colorado
• LSI Logic, Fort Collins, Colorado
• Terra View Office Building, Loveland, Colorado
• Poudre Valley Hospital — Harmony Campus, Fort Collins, Colorado
• Hewlett Packard — Genesis 4, Fort Collins, Colorado
• Harmony Technology Park, Fort Collins, Colorado
• Con Agra Beef Company World Headquarters, Greeley, Colorado
• Hunter Douglas Business Campus, Thornton, Colorado
• Home State Bank, Downtown Fort Collins, Colorado
• Home State Bank, South Fort Collins, Colorado
• The Neenan Company Headquarters, Fort Collins, Colorado
• Superior Pointe Office Park, Superior, Colorado
• Factual Data Corporation — Buildings I & 2, Loveland, Colorado
Design Build Experience
Bruce A. Hendee, ASLA { i g n
Principal
BHA Design, Inc.
Bruce is the President of BHA Design and a member of the American Society of Landscape Architects. He
will lead the BHA team in overall project coordination for landscape architecture. He has over 20 years of
experience in a wide variety of project types including trail design, park planning, and urban design.
Relevant Experience:
• Fossil Creek Community Park - 99 acre community park in Fort Collins, Colorado
• Westfield Park - 14 acre neighborhood park, in Fort Collins, Colorado
• Southwest Youth Sports Park - 103 acre community park in Fort Collins, Colorado
• Northridge High School — New high School in Greeley, Colorado
• Horsetooth Mountain Park Management Plan - Latimer County, Colorado
• Pondre River Trail Master Plan - 20 mile trail plan and design guidelines in Weld County,
Colorado
• Harmony Technology Park- Hewlett-Packard — 160 new office park, Ft. Collins, Colorado
• Riverside Park - 38 acre sports park in Evans, Colorado
• Eastern Fremont County Trail and Open Space Master Plan - 30 mile trail and open space plan
near Canon City, Colorado
• Mt. Sopris Tree Farm Community Park - 135 acre active park in Basalt, Colorado
• Poudre Valley Hospital — Harmony Campus- 100 acre new campus planning and landscape
architecture in Fort Collins, Colorado
Years of Professional Experience
Twenty one
Education and Professional Affiliations:
Masters Degree in Landscape Architecture (MLA), University of Colorado, 1980
Registered Landscape Architect
Member, American Society of Landscape Architects
Member, Lincoln Center Board of Directors, Ft. Collins, Colorado
Bruce A. Hendee - Resume
Roger B. Sherman, ASLA ci C S i g n
Principal
BHA Design, Inc.
Roger Sherman is a Landscape Architect and a Principal at BHA Design. Roger brings experience in
conceptual and detailed landscape design and implementation to each project as well as extensive
construction background. He enjoys refining design ideas, coordinating with clients spontaneously, and
working on site during the construction phase.
The projects listed below are selected relevant projects with which Roger has been involved:
• Westfield Neighborhood Park— 14 acre neighborhood park in Fort Collins, CO
• Fort Collins Soccer Complex — Fort Collins, CO
• Fossil Creek Community Park - 99 acre community park in Fort Collins, CO
• Southwest Youth Sports Complex -103 acre community park in Fort Collins, CO
• Mount Sopris Tree Farm Active Recreation Area - 129 acre active park in Basalt, CO
• Sand Creek Park — 62 acre open space park in Aurora, CO
• Cache La Poudre River Trail Master Plan in Weld County, CO
• African Watering Hole Exhibit at the Baltimore Zoo, Baltimore, MD
• Riverside Park - 38 acre sports park in Evans, CO
• Lakewood Country Club, Clubhouse Master Plan — Lakewood, CO
• Westminster City Park Master Plan Update - 130 acre community park in Westminster, CO
• Westwood Park - 11 acre neighborhood park in Denver, CO
• Northridge High School and Sports Complex - Weld County School District No. 6 Greeley, CO
Years of Professional Experience
Eleven
Education, Professional Affiliations and Community Service
BSLA, Landscape Architecture, Colorado State University, 1990
Member, American Society of Landscape Architects, 1993
Art in Public Places Board Member, Fort Collins, Colorado, 1997 to present
Chairperson of the Art in Public Places Board, Fort Collins, June 1999 to December 2000
Habitat for Humanity, Somoto, Nicaragua and Fort Collins
Westfield Park
detiin
BHA was commissioned by the City of Fort
Collins to develop a plan for a proposed
new 14 acre park located adjacent to
Johnson Elementary School. BHA's service
included a public charette process in which
adjacent residents were actively
incorporated into the design process. The
park plan concept that evolved created a
swirling, spherical motion that invited play
and encouraged imagination on the part of
adults and children alike. A fanciful
pavilion design was created that anchors a
visual swirl created in sculpted earthwork.
All of the energy of the site focuses on the
central pavilion and picnic area. In addition,
a number of specially designed curving
walls, orbs, and special paving patterns
were developed to unite the project in a
cohesive image that works both visually and
functionally.
Client: City ojFortCollins
Fossil Creek Community Park
dCsig11
Fossil Creek Community Park is a 100 acre park site located in a newly developing area of southeast Fort Collins, Colorado.
The park will fulfill the needs of the community and also protect and enhance the wetlands of Fossil Creek as it passes
through the site. BHA is currently developing thematic plans for the park utilizing Colorado's rich geologic history.
Coordinated within the interpretative theme will be many amenities including ballfields, a recreation center, an amphitheater,
basketball and tennis courts, a skateboard course, themed adventure playgrounds, group picnic areas, and interactive water
features. Projected to be completed in 2003, Fossil Creek Park is destined to become the gem of the Fort Collins city park
system.
Client: CltyofFort Collins
Fort Collins Civic Center Office Building
BHA Design teamed with OZ Architects and The Neenan
Company won a design competition for the City of Fort
Collins new office building. The City program was a new
70,000SF office building to be constructed in the Down Town
Fort Collins. The project was significant because it was to
occur in an area called "The Civic Center", designated by the
City as the future heart of government administration for both
the City and Larimer County. In addition, the project was to be
designed as a demonstration project resulting in significant
savings through use of "green" technologies. The proposed
building and site design will result in 35% energy savings
over traditional designs.
BHA's concept continues the themes established within the
Civic Center District. Wide tree lined sidewalks inset with
ornamental paving, ornamental lights and custom seat walls
provide a distinct urban character and pedestrian friendly
environment. Several "Best Management Practices" were
utilized within this project including water quality treatment
using special underground water filtration techniques, use of
indigenous plant materials where possible, and use of locally
available sandstone.
Client: City of Fort Collins
d C: S 1 ti Il
life Cycle Information
Appendix
Proposal to City of Fort Collins 5.2.15.7 - Appendix November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N
N A N
5.2.5.1 DESIGN/BUILD PROJECTS OF SIMILAR SCOPE
Following are examples of representative projects for your review. The information
provided on each project responds as nearly as possible to the information requested
in the RFP. Where not available, the requested information has been omitted or
indicated as "n/a". Additional project profiles are provided in the Appendix, Section
5.2.15.1.
Proposal to City of Fort Collins 5.2.5.1 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
EPIC "Twice The Ice" — Mechanical Systems Description — General
State-of-the-art arena design today incorporates high efficiency refrigeration compressors
for the ice sheet, low emissivity ceilings to prevent condensation and reduce the roof load
imparted on the rink, and desiccant based dehumidifying systems for energy efficient
moisture control.
The base system shall utilize a gas fired, roof mounted make-up air unit that has a
desiccant wheel designed for dehumidification only. The system will maintain a dew
point of 45 °F or less by ventilating the space with 15,000 cfm of conditioned air.
Regeneration of the desiccant wheel shall be by a warm air furnace that is separately
packaged within the roof top unit. The same RTU-1 shall also serve the new locker
rooms, showers, and referees room with hot water reheat coils on a branch duct. The
main arena shall be covered by two 24" round supply air ducts that discharge collinear
with each of the long sides of the rink. Return air will be drawn from above the middle
of the rink and exhaust air will be drawn from two opposite comers. A low emissivity
ceiling shall be installed above the rink.
The multi -purpose room will be served by a 7-1/2 ton, gas -electric roof top unit (RTU-2).
The spectator seating area will be heated by two, 60' long indirect fired gas radiant
heaters suspended from the ceiling.
Other new spaces that will require heating include storage rooms, zambom room, lobby
areas and an entrance corridor. These spaces will be served by hot water unit heaters and
convectors. A new pump set will be installed in the existing mechanical room to tap off
of the existing heating plant.
Option Two
The life cycle cost of two additional options is being analyzed. Option two includes a
7,500 cfm heat recovery ventilator to pre -warm the outside air during cold weather. The
extensive use of fresh air and the many occupied hours of this type of facility make this
an option that must be assessed. In this scenario, one of the two exhaust fans on the high
roof would be eliminated.
Option Three
This option is the same as option two except that the heat recovery ventilator would be
fitted with a pre -heat furnace to eliminate the need for a defrost cycle. In this scenario
the heat recovery ventilator would come without fans and the exhaust fan elinated for
option two would be restored.
Other Options To Be Analyzed in Design Phase
a) Consideration will be given to integrating RTU-2 with the rinks' brine system and
eliminating the DX compressors.
b) The base plan includes the use of heat recovery from the refrigeration condensers
to heat zamboni water and to prevent the ground from freezing under the rink. An
analysis will be performed to asses the economic value of using a low temperature
solar hot water system to prevent permafrost. This would free up some of the heat
recovery water for heating domestic hot water or preheating the new hydronic
heating loop serving the locker areas.
c) The use of variable speed supply and exhaust fans will be analyzed. These would
allow for the locker areas to be conditioned to a tight temperature span when
occupied and to "float" within a larger temperature swing when nobody is in
them. This would be accomplished by inatlling zone dampers in the supply ducts
to each zone. Modest reductions of the air flow over the rink would be possible
as well.
d) The ability of the new desiccant system to share it's capacity with the existing
rink and reduce or eliminate the periods of high moisture in that space.
Advantases of Fluorescent over HID's (Metal Halide)
The existing ice arena is presently illuminated through the use of Twin Head 40OW Metal
Halide fixtures. We are under the impression that this was done to limit labor costs, and
more importantly serve as a multi -function sheet of ice that can handle everything from a
hockey game to a figure skating event.
In a visit to EPIC, we took the current values of Illuminance over the ice and found very
low light levels. Not only that, but we found very high contrast in light levels on the ice.
These factors go against the recommendations set by the IES (Illuminating Engineering
Society). This society not only sets light levels for specific areas such as Hockey/Figure
Skating arenas, but also specifies areas of lighting that are important to a specific
function. According to these guidelines the "very important" areas of lighting a sheet of
ice are: Direct Glare, Light Distribution or Uniformity, Reflected Glare, and Horizontal
Illuminance. They also set light levels to meet on the task plane, in this case the ice.
Here is a summary of what they are recommending: 200 Footcandles at the professional
level, 150 footcandles for club sports and amateur leagues, 100 footcandles for High
Schools and Training facilities, and 50 footcandles for elementary and social events.
Although the existing layout provides some value, it is not doing an efficient and quality
job according to the data that we took from the ice. According to our measurements,
there was about 57.6 footcandles over the center of the ice, and levels ranging from 25.5
up to 56 footcandles, depending on where one took the readings. This is not a lot of light
according to the uses that are taking place on this ice, and it also does meet the "very
important" criteria set aside by the IES according to uniformity.
We are suggesting that we use an energy efficient option to HID (High Intensity
Discharge) Luminaries. HID lighting, and especially Metal Halide, which is currently
installed, have some serious downfalls such as not being able to come to full brightness at
the flip of a switch. Metal Halides also lose about 50% of initial output throughout the
life of the lamp. The fixture we are suggesting will save costs in energy consumption,
come to full brightness at the flick of a switch, and will maintain 95% of the initial lamp
output. The lamp hours for these fixtures are the same and the fluorescent alternative will
actually provide a better quality and color of light. It will also help in the areas of glare
as the Metal Halide fixtures are coming from a point source, where the light emitted from
a linear fluorescent is coming from a four foot tube. We are looking at a payback period
of less than one year for the new arena. We can retrofit the existing arena for a payback
of less than 10 years. It will also give greater flexibility in certain lighting applications
where the full brightness is not necessary, as it can be controlled in four light levels
through tandem wired fixtures, and multiple ballasts.
Advantages of Energy Efficient Transformers
There is a new standard in transformers that is referred to as the NEMA TP-1 Standard.
This standard was established in 1996, and sets criteria for the efficiency of low to
medium distribution transformers. The transformers that meet the 1996 standard have
been manufactured in a way to eliminate inefficiencies in the operation of these units.
There are losses referred to as "core losses" which have been nearly eliminated through
better internal construction of these highly efficient transformers. This simple action has
extremely fast paybacks. This is due to the fact that these transformers are in operation
24 hours a day and 365 days a year. The losses internal to the unit may only be 1-5% of
the total transformer rating, but when one realizes that this might be a 15-750KVA
transformer, it adds up quickly. Even when the facility is not operating, there is always
electricity moving through this transformer, and a percentage of that power is being lost
in the core of this transformer.
Payback studies have been included to reflect these values. A standard transformer will
operate anywhere from 95-96.7%, and the new standard sets this operating efficiency at
97.7-99%. This results in a fast payback, and considering that the average life of a
transformer is 25 years, the savings continue for far beyond the 1.5-3 year payback.
PAYBACK COMPARISON STUDY OF: Twin Head HID vs T5HO
Initial Construction Cost Comparison
Ouanti Cost Eaeh
Extension
Delete from Base Bid:
40OW Twin Head MH HID
50 x $1,458.78 =
$72,939.00
Add to Base Bid:
Williams 4' GL2000 Linear Flourescent
60 x $1,252.50 =
$75,150.00
Initial Cost Increase:
$2,211.00
Projected Utility Co. Rebate: -
$0.00
Net Projected Initial cost increase: _
$2,211.00
is per each
930
432
it Watts
46500
25920
at Kilowatts (Demand)
46.5
25.92
uating Hours per Year
4200
4200
watt-hours (KWH) per Year
195300
108864
nand charges per month (Cost per KW) "
: $15.37
$714.71
$398.39
nand charges per annum (Cost per KW) "'
: $15.37
$8,576.46
$4,780.68
Annum KWH charges (Cost per KWH) "
: $0.01550
$3,027.15
$1,687.39
Total per Annum base charges
$11,603.61
$6,468.08
Riders' deduct ***
: 0.00 %
$0.00
$0.00
'Due to Franchise' fee'*
: 0.00 %
$0.00
$0.00
State, local, RTD and culture taxes**
: 6.00 %
$696.22
$388.08
Total per Annum Electricity Costs
$12,299.83
$6,856.16
ire Quantity
50
60
Lamps per Fixture
2
8
if Quantity of Lamps
100
480
fd Average Lamp Life ( in hours)
20000
20000
Annum Hours of Operation'
4200
4200
ip Replacement Frequency ( in years)
4.76
4.76
lacement Cost per Lamp "'
$65.00
$15.00
t to Replace all Lamps
$6,500.00
$7,200.00
rage per Annum Lamp Replacement Cost
$1,365.00
$1,512.00
Total per Annum Lamp Replacement Cost Savings:
($147.00)
Total Estimated per Annum Savings: $5,296.67
Projected 10-year savings ***** : $52,966.65
Number of Years required to pay back Projected Initial Cost Increase ***' 0.42
Note: Numbers in parentheses indicate negative values
` Note: Our estimate of total operating hours per year is based upon an average of 14 hours per day,
300 days per year.
" Note: Based upon current Utility Company rates.
Note: Lamp replacement costs are based upon expected customer purchasing power and include installation
costs based upon an average of $15.00 per hour, 0.03 hours per lamp.
Note: This expected payback time does NOT factor in account interest expenses or savings from reducing air
conditioning loads corresponding to reduced lighting loads.
Note: This assumes no change in electric rates during the ten-year period.
Page 1
PAYBACK COMPARISON STUDY OF: 30KVA Xfmrs vs High Eff.30KVA
Delete from Base Bid:
Standard 30KVA Transformers
Add to Base Bid:
High Efficiency 30KVA Transformers
Quantit Cost Each
2 x $825.49 = $1,650.97
2 X $1,100.64 =
Initial Cost Increase:
Projected Utility Co. Rebate: -
Net Projected initial cost Increase: _
$2,201.29
$550.31
$0.00
$550.31
entity
2
2
9losses (wafts per each)
495
150
it Watts
990
300
it Kilowatts (Demand) -
0.99
0.3
:rating Hours per Year
8760
8760
watt-hours (KWH) per Year
8672.4
2628
Land charges per month (Cost per KW) "
: $15.37
$15.22
$4.61
nand charges per annum (Cost per KW) "
: $15.37
$182.60
$55.33
Annum KWH charges (Cost per KWH)'"
: $0.01550
$134.42
$40.73
Total per Annum base charges
$317.02
$96.07
Riders' deduct ***
: 0.00%
$0.00
$0.00
'Due to Franchise' fee"
: 0.00%
$0.00
$0.00
State, local, RTD and culture taxes**
: 6.00%
$19.02
$5.76
Total per Annum Electricity Costs
$336.04
$101.83
Total per Annum
Total Estimated per Annum Savings: $234.21
Projected 10-year savings ***** : $2,342.09
Number of Years required to pay back Projected Initial Cost increase **** • 2.35
Note: Numbers in parantheses indicate negative values
Note: Our estimate of total operating hours per year is based upon an average of 24 hours per day,
365 days per year.
Note: Based upon current Utility Company rates.
Note: This expected payback time does NOT factor in account interest expenses or savings from reducing air
conditioning loads corresponding to reduced electrical loads.
*`*`* Note: This assumes no change in electric rates during the ten-year period.
Page 1
Electric Usage Summary of Low Eff 30KVA
Total KWh Used per month (avg.)
990
Total KWh Used per day av
33.0
Pollution Responsible from Low Eff Transformer
Pounds of Coal used/KW h
1
Pounds of CO2 emitted into atmosphere/KWh(using coal
2.09
Pounds of coal used ear month
990.00
Pounds of CO2 emitted each month
2,069.10
Pounds of coal used per year
11,880.00
Pounds of CO2 emitted each year
24,829.20
Electric Usage SummarV of Hi
n Eff 30KVA
Total KWh Used per month(avg.)
300
Total KWh Used per day av
10.0
Pollution Responsible from High Eff Transformer
Pounds of Coal used/KWh
1 1
Pounds of CO2 emitted into atmosphere/KWh
usin coal
2.09
Pounds of coal used per month
300.00
Pounds of CO2 emitted each month
627.00
Pounds of coal used per year
3,600.00
Pounds of CO2 emitted each ear
7,524.00
Net Difference Per Year
CO2 emitted Ibs
8,280.00
Coal Reduction (Ibs
17,305.20
N E E N A
N
Project Name: Fort Collins City Building
Design Build Team: AEC, BHA,
Swanson Rink, Sear Brown
Occupancy type (UBC): B
Construction type (UBC): II-1 hour
Gross SF: 72,000
Structural system: Structural steel
HVAC system: VAV system
Original Schedule Duration: 12
months
Actual Duration: 10 months
Initial GMP: $8,203,011
Final Cost: $8,787,907
# Of Owner Change Orders: 11
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
City of Fort Collins
Jack Gianola
Owner Address:
215 N. Mason Street,
Fort Collins, CO
Owner Phone #:
970-221-6272:
The Neenan Design/Build team delivered this project, with virtually no changes from their original RFP
response. Late in the project, with the funds originally allocated for anticipated cost overruns and change
orders that never materialized, the City was actually able to add an additional $600,000 in much -needed
scope. The team still completed this additional scope within the original construction schedule.
Project Name: Latimer County Sheriff
Administration Building
Design Build Team: TNC/Oz
Architecture; Simpson, Piper, Allen
Plumbing; Nothhaft, Front Range Steel
Occupancy type (UBC): B
Construction type (UBC): II-1 hour
Gross SF: 36,500
Structural system: Steel & Structural
Masonry
HVAC system: VVT
Original Schedule Duration: 7 months
Actual Duration: 7 months
Initial GMP: $4,328,243
Final Cost: $4,176,733
# Of Owner Change Orders: 4
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
Latimer County
David Spencer
Steve Bebell
Owner Address:
2501 MidPoint
Fort Collins, CO 80526
Owner Phone #:
970-498-5914
970-690-5102
Used a hybrid steel and masonry bearing system to accommodate architectural reveals on facade (brick
veneer) while using more economical bearing block on read of building (save owner $65,000).
Proposal to City of Fort Collins 5.2.5.1 - Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A
0
Project Name: St. Joseph's School
Phase I
Design Build Team: Simpson,
H&H Electric
Occupancy type (UBC): E-1
Construction type (UBC): Type II & V
Gross SF: 21,000
Structural system: Steel/Masonry
HVAC system: VAV/Hydronic
Original Schedule Duration: 5 months
Actual Duration: 4 /2 months
Initial GMP: $2,400,000
Final Cost: $2,446,000
# Of Owner Change Orders: 2
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
Archdiocese of Denver
Owner Address:
1300 South Steel Street
Denver, CO 80210
Owner Phone #:
303-894-8994
School is listed on the National Registry of Historic Buildings and was awarded the City of Fort Collins "Friend
of Preservation" award in 2000 for the efforts made for a sensitive addition to a historical structure. Majority of
construction had to be completed during school summer recess in time for fall semester. This phase finished
two weeks ahead of schedule.
Project Name: Value Plastics
Design Build Team: The Neenan Co.
Occupancy type (UBC): B-2
Office/Production
Construction type (UBC): II-N Fully
sprinkled
Gross SF: 40,000
Structural system: Steele frame/spread
footings
HVAC system: RA44, Boiler VAV
Original Schedule Duration: 254 days
Actual Duration: 249 days
Initial GMP: STIP Sum $3,390,463
Final Cost: $3,596,591
# Of Owner Change Orders: 4
$206,128(all owner requested)
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
The Sampson Partnership
Value Plastics, Inc.
Kent Sampson
Owner Address:
3325 Timberline Road
Fort Collins, CO 80525
Owner Phone #:
970-223-8306
The facility houses administrative offices, a total of six self-contained molding cells, engineering offices and
related support facilities. Integral in the design of the facility is extensive use of daylighting and other energy
saving concepts to maximize energy efficiency, providing an outstanding example of sustainable architecture.
Other special construction features include:
❑ A fully automated pneumatic raw material distribution system to feed molding machines.
❑ Extensive process water and compressed air piping systems throughout.
❑ A chiller/boiler system for cooling of process water and heating and cooling of the building.
❑ Extensive use of a natural linoleum flooring products as a "sustainable architecture" application.
Proposal to City of Fort Collins 5.2.5.1 - Page 3 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A
Project Name: The Group
Design Build Team: The Neenan Co.
Occupancy type (UBC): A-3
Assembly/B Office
Construction type (UBC): Type V - one
hour
Gross SF: 27,000
Structural system: Hood
Frame/Spread footings
HVAC system: RTU VVT
Original Schedule Duration: 256 days
Actual Duration: 263 days
Initial GMP:
Final Cost: $3,730,000
# Of Owner Change Orders:
Special Characteristics /Methodology for cost and schedule control:
Owner Name:
The Group
Larry Kendall
Owner Address:
2803 Harmony Road
Fort Collins, CO 80528
Owner Phone #:
970-223-0700
The building expresses a Colorado lodge theme, with extensive use of rough timbers and native stone. The
wood -framed structure has a two-story entry lobby incorporating laminated wood beam construction and
tongue and groove wood ceilings, with a massive 40 foot high stone fireplace and a second floor balcony
overlook. This theme carries outside to a rough sawn laminated beam porte cochere, which covers the drop
off and main entry area. A 55 foot tall clock tower with two 8 foot diameter clocks ordains the roof of the
facility. The exterior of the building is a combination of wood siding, red brick and native stone in keeping with
the Architectural theme.
Project Name: New Belgium Brewing
Owner Name:
Company
Kim Jordan
Design Build Team: Water- Waste &
Jeff Lebesch
Land; Civil - HGH; Structural
Engineering - Merit Electric, Simpson
Owner Address:
Mechanical
500 Linden St.
Occupancy type (UBC): B-2
Fort Collins, CO
Office/Warehouse
Construction type (UBC): V N
Owner Phone #:
Gross SF: 27,800
970-221-0524
Structural system: Precast concrete,
steel, laminated wood
HVAC system: VAV & Hydronic
Original Schedule Duration: 7 months
Actual Duration: 7 months
Initial GMP: $2,581,163
Final Cost: $2,794,508
# Of Owner Change Orders: 2
Special Characteristics / Methodology for cost and schedule control:
The Neenan design/build team worked closely with New Belgium Brewing on the technical aspects of brewing
design and sustainable architecture to value engineer the project. This achieved the quality, budget and
schedule promised. New Belgium's goal to brew and distribute beer for the 1995 holiday season was a huge
success.
Proposal to City of Fort Collins 5.2.5.1 - Page 4 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A
N
Project Name: ConAgra Foods
Design Build Team: Design
Mechanical; Merit; Corporate Plumbing;
Nothhaft; BHA
Occupancy type (UBC): B
Construction type (UBC): II-1 hour
Gross SF: 103,000
Structural system: Steel and bar joist
HVAC system: VAV
Original Schedule Duration: 9 1/2
months
Actual Duration: 9 1/2 months
Initial GMP: $11,844,326
Final Cost: $12,437,530
# Of Owner Change Orders: 7
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
McWhinney Management Co.
LLC
Chris LaPlante
Owner Address:
5200 Hahns Peak Drive
Suite 130
Loveland, CO 80538
Owner Phone #:
970-935-3003
The location for this new corporate facility offers spectacular panoramic mountain views, water features in
park -like settings, and outdoor recreational opportunities for both ConAgra's employees and visitors. A state of
the art audiovisual and training room facility includes extensive video conferencing capabilities. Other features
include a full service kitchen, many exterior decks, and an outdoor amphitheater.
Project Name: Quantum Manufacturing
Phase 1 and 2
Design Build Team: Nakai; Oz;
Swanson Rink; Berwick Electric, Heating
and Plumbing Engineers; Nothhaft
Occupancy type (UBC): B,F2,S2,A3
Construction type (UBC): II-N
Gross SF: 403,000
Structural system: Steel bar joist and
deck
HVAC system:
Original Schedule Duration: 15 months
Actual Duration: 15 months
Initial GMP: $40,751,498
Final Cost: $50,586,242
# Of Owner Change Orders: 9
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
Lease Plan North America,
Inc. (Quantum Corporation)
Owner Address:
10125 Federal Drive
Colorado Springs, CO
80901
Owner Phone #:
719-886-6535
The new facility's major goal was to create the right kind of environment, to bring everyone together and to
create economies of scale. Because of the new layout and having everyone on the same site "the cycle time
has been reduced greatly.
Proposal to City of Fort Collins 5.2.5.1 — Page 5 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A
N
Project Name: Windsor Medical Clinic
Design Build Team: Corporate;
Simpson; Merit; Nothhaft
Occupancy type (UBC): B
Construction type (UBC): II-N
Gross SF: 20,400
Structural system: Steel
HVAC system: VAV
Original Schedule Duration: 30 weeks
Actual Duration: 30 weeks
Initial GMP: $2,081,602
Final Cost: $3,226,827
# Of Owner Change Orders: 19(tenant
finishes)
Special Characteristics / Methodology for cost and schedule control:
Owner Name:
Poudre Valley Hospital
Rulon Stacey
Owner Address:
1024 S. LeMay Ave.
Fort Collins, CO 80524
Owner Phone #:
970-495-7460
The Health System's objective was to establish its presence prior to that of a competing health system in the
market area. Neenan managed to expedite the land entitlements and municipality approvals through a
planning department overwhelmed by significant real estate development in the area. The design and
construction team at Neenan held to their budgets without sacrifice to the buildings aesthetic features and
functional performance. This enabled the Health System to follow through on their promise of an
architecturally attractive facility with the features to accommodate the diverse needs of imaging, urgent care,
primary and specialty care physicians.
Project Name: Hunter Douglas
Phases 1-5
Design Build Team: Humphries Poli;
Piper; Design Mechanical; Nothhaft
Occupancy type (UBC): B, F2, S2, A3
Construction type (UBC): II-N
Gross SF: 175,000
Structural system: Structural brick skin
with steel bar joist roof
HVAC system: Single zone packaged
roof top units
Original Schedule Duration: 11
months
Actual Duration: 11 months
Initial GMP: $7,752,731
Final Cost: $8,556,902
# Of Owner Change Orders: 7
Owner Name:
Hunter Douglas
Owner Address:
#1 Duette Way
Broomfield, CO 80020
Owner Phone #:
303-466-1848
Special Characteristics / Methodology for cost and schedule contror.
Phase 5 was originally designed as flexible space with no tenant finish or production area finishes included.
Five months into the project Hunter Douglas decided to build out 25,000 SF of office and 50,000 SF of
production area. The design build team responded to these requests and completed the project within the
original scheduled time. The additions to the budget were owner requested scope items needed to complete
the office and production fit up.
Proposal to City of Fort Collins 5.2.5.1 - Page 6 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
w
E E N A N
Project Name: Xilinx Colorado
Owner Name:
Campus, Phase I.
Forrest James
Design Build Team: TNC; DTJ Soulder
Director of Facilities
Occupancy type (UBC): B office
Construction type (UBC): V-N fully
Owner Address:
sprinklered
2100 Logic Dr.
Gross SF: 136,000
San Jose, CA 95124
Structural system: Steel frame
HVAC system: Under floor air
Owner Phone #:
Original Schedule Duration: 10
408-879-5335
months
Actual Duration: 12 months
Initial GMP: $32,222,326
Final Cost: $31,512,844
# Of Owner Change Orders: 16
Special Characteristics / Methodology for cost and schedule control:
Employees at this site design chips and create programming tools for the company's product line of
programmable logic devices. As such, the employees' intellectual capabilities are the most valuable asset of
the corporation. Extensive measures are being taken to create an environment that will aid the company in
attracting and retaining these creative designers. There is a retreat building of 5,000 square feet is being
constructed to serve as a "get away' area for employees during their workday. The design of the building is
reflective of many "Colorado" design themes derived from our mountain and agricultural past. Grand public
spaces will feature soaring ceilings framed with timber with generous use of native stones and other materials.
Project Name: Ice House
Design Build Team:
Occupancy type (UBC): 13,S3, A-2.1
Construction type (UBC): 1-FR Fully
sprinklered
Gross SF: 170,000
Structural system: Structural steel
HVAC system: Hydronic
Original Schedule Duration:
14 months
Actual Duration: 14 months
Initial GMP: $17,110,310
Final Cost: $17,692,169
# Of Owner Change Orders: 1
Special Characteristics / Methodology for cost and schedule control:
Owner Name: Loftus
Developments Nichols
Partnership - Randy Nichols
Owner Address:
1899 Wynkoop Street
Denver, CO 80202
Owner Phone #:
303-436-9191
The design reflects both the internal forces of the building program comprised of office and first floor retail and
from the external forces of the lower downtown historic context. Neenan delivered this project with minimal
change orders to the owner on a project that allowed no on site storage in a severely restricted Downtown
Denver location.
Proposal to City of Fort Collins 5.2.5.1 - Page 7 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
5.2.1 COVER PAGE
PROPOSAL IN RESPONSE TO
CITY OF FORT COLLINS
SECOND SHEET OF ICE AT EPIC
REQUEST FOR PROPOSAL P-812
• Name Of Team and Address
The Neenan Company
P. O. Box 2127
2620 East Prospect Road, Suite 100
Fort Collins, Colorado 80522
• Telephone Number
970-493-8747
• Fax Number
970-493-5869
• Name and Title of Individual Signing For the Team
James J. Neenan, President
• Signature
• Date
November 29, 2001
• The Guaranteed Maximum Price to the City
As Per Neenan Prouosal design and c., r .•
Three Million, Two Hundred Ninety -Six Thousand,
Eight Hundred Twenty -Two Dollars ($ 3,296,822.00)
With uossible noted deduct ontinnc
Two Million, Nine Hundred Fifty -Six Thousand, Seven Hundred
Seventy -Seven Dollars ($ 2,956,777.00)
Receipt of Addendums 1 and 2 Acknowledged
N E E N A N
5.2.5.2 PROJECT EXPERIENCE AND QUALIFICATIONS
Financial The Neenan Company has significant financial capability for this project, as is
Capability evidenced by Lockton Companies November 12, 2001, letter regarding our bonding
capability, as well as the November 27, 2001, letter from Jim Trupp regarding our
banking relationship with First National Bank. Both letters follow at the end of this
section. We will be happy to provide specific information regarding our current
financial position upon request.
Management The management experience and capability of the key leaders of our team is
Experience described in detail in Section 5.2.4, "Project Team Roles and Responsibilities" and in
and their individual resumes. The overall project leader, Bob Meserve, has over 20 years
Capability experience in construction, having managed highly complex projects with extremely
aggressive schedules, while adhering to tight budget constraints. Bob's recent
success with the completion of the City of Fort Collins Office Building is one very
recent and specific example of his ability to manage.
The team we have assembled to assist Bob, as will become apparent from a review of
their individual resumes, is more than qualified to deliver a project that will delight the
City and Twice The Ice. In fact, we will guarantee it! The management skills of these
individuals shows through in the quality of work on their past projects and the satisfied
customers they leave behind. Please refer to the client letters in the Appendix for an
indication of the level of satisfaction our teams routinely deliver.
Sustainable The Neenan Company has successfully completed and are in process of
Design design/construction on many building projects which incorporate green building design
Experience— practices. We view green building design as a key component in most buildings we
"Green deliver. We focus on the six general areas used by L.E.E.D.(Leadership in Energy and
Building Environmental Design), developed by the U.S. Green Building Council. Those areas
Design" are:
• Sustainable sites
. Water efficiency
' Energy and atmosphere
' Material and resources
• Indoor environmental quality
• Innovation and design process
The Neenan Company has knowledgeable staff as well as several ongoing
partnerships with green building consultants and design -build subcontractors.
Proposal to City of Fort Collins 5.2.5.2 - Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
The following TNC projects demonstrate our green building design and refer to
L.E.E.D. areas incorporated into the design and construction of these projects.
Indoor
Material Environ- Innovation
Sustainable Water Energy and and mental and Design
Site Efficiency Atmosphere Resources Quality Process
City of Fort Collins X X X X X
Larimer County X X
Sheriff's
Administrative
Offices
Value Plastics X X X
New Belgium X X X X X
Brewing Office
Addition
New Belgium X X X X X X
Brewing Water
Treatment
New Belgium X X X X X X
Brewing Brewhaus
Expansion
Xilinx X X X
The City of Fort Collins offices was the only building surveyed by an accredited
L.E.E.D. professional. It was given 22 points. The New Belgium projects in Fort
Collins are undoubtly the most green commercial buildings in the area.
This Project
On the second sheet of Ice at EPIC, we have incorporated or given options for the
& Green
following green building components.
Building
Sustainable sites
Design
* Erosion and sedimentation control
* Site selection
* Alternative transportation
* Light pollution reduction
Water Efficiency
* Innovative waste water technologies
* Water use reduction
Energy and Atmosphere
* Fundamental building system commissioning
* Minimum energy performance
* CFC reduction in HVACDR equipment
• Ozone depletion
Materials and Resources
• Storage and collection of recyclables
* Construction waste management
* Local/regional materials
Proposal to City of Fort Collins 5.2.5.2 - Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Indoor Environmental Quality
• Minimum IAQ performance
* Environmental tobacco smoke control
' Carbon dioxide monitoring
' Increase ventilation effectiveness
• Low -emitting materials
• Thermal comfort
Partnering
Neenan operates in a true partnering style with our customers, our consultants and our
subcontractors. It is the ONLY way we do business. Partnering and Neenan have
become synonymous in the design -build world. Neenan, it's consultants (planning,
civil, landscape and structural) and major design -build subcontractors (mechanical,
electrical, plumbing, fire protection and structural) have worked together on dozens of
successful projects over many years. The TNC job captain — Jon Van Benthem
previously worked for Gilfillan/Callahan on two ice rinks before coming to TNC. We
have worked collaboratively, utilizing our Collaborative Design Process (CDP) with
Commercial Refrigeration and the balance of the core team to develop this RFP
response.
Unique
TNC has two unique processes that minimize waste for the entire project and help to
Capabilities
build stronger teams.
of Team
The first process is our Collaborative Design Process or CDP. Our team begins with
concurrent design and pre -construction (pricing, sequencing and constructablity
evaluation). This is the heart of our process --we believe the first 20% of the time
expended on a project determines 80% of the outcome. The team of Owners, users,
architects, consultants, key construction persons, key subcontractors and often key
City personnel (even when they are not the client), all participate in our CDP.
The CDP begins with establishing clear customer conditions of satisfaction for the
completed facility and the process to deliver on these conditions of satisfaction. The
team works concurrently in a single large space for 1 — 3 days to arrive at the early
design concept(s), the cost, a schedule and a clear understanding of the next actions.
The CDP shortens the duration to get to the design concept dramatically and aligns the
team around the project success factors. The CDP process is used at additional key
points where high degrees of interaction are required to maintain good project flow and
collaboration. See the insert in the Appendix of this proposal for more on the CDP.
The second process is our Neenan Reliability Planning System — NRPS. It
streamlines the delivery process through planning and commitments. The result is
increased team reliability. Neenan has increased it's reliability on projects to
approximately 75%, double the construction industry average. Please refer to the
insert in the Appendix of this proposal for more on NRPS.
Proposal to City of Fort Collins 5.2.5.2 — Page 3 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
Nk4 I: go I k4 W J ,
Archistruction®
Customer:
Address:
Mailing Address:
City:
Description of Business:
In Business Since:
Company Organization:
Name & Title of Officers:
Fort Collins
Denver
P.O. Box 2127 (80522)
Eighteenth Street Atrium
2620 E. Prospect Road, Suite 100
1621 181h Street, Suite 250
Fort Collins, CO 80525
Denver, CO 80202
(970)493-8747
(303)296-0383
(970) 493-5869 FAX
(303) 296-0382 FAX
CREDIT APPLICATION
The Neenan Company LLLP
2620 E ProsRect Rd (80525)
PO Box 2127
Fort Collins State: CO Zip: 80522
Design/ Build General Contractor
1966
Parmershio FID: 84-1590338
David G. Neenan, CEO
1606 Brentford, Fort Collins, CO 80525
James J. Neenan, President
6090 S. Nome, Englewood, CO 80111
Sharon L. Neenan, Secretary
1606 Brentford, Fort Collins, CO 80525
Randolph P. Myers, Treasurer
2019 Brookwood Dr, Fort Collins, CO 80525
At Present Address Since: January 1997
Person Responsible for Accounts Payable Bruce Hood
Anticipated Credit Requirements:
Bank Reference
First National Bank of Fort Collins
205 W Oak, Fort Collins, CO 80524
Checking Account Number: 18-1848-8
Officer's Name: Jim Truon
Phone Number: (970)482-4861
Trade References:
Corcoran Company
4700 Innovation Dr Ste B-1, Fort Collins, CO 80525
(970)204-4700
Design Mechanical
5637 Arapahoe, Boulder, CO 80303
(303)449-2092
Merit Electric
4700 Innovation Dr Ste D-1, Fort Collins, CO 80525
(970)266-8100
Colorado Springs
P.O. Box 1478
Colorado Springs, CO
80901-1478
(719) 633-4713
(719) 633-9508 FAX
5.2.5.3 — PAGE 1
A C CORD
CERTIFICATE OF LIABILITY INSURAN
DATE(MMIDDIYY)
11/15/01
Lockton Companies of Colorado
4500 Cherry Creek Dr. S., #400
Denver Co 80246-1532
Phr :303-753-20DO Fax:303-753-2099
INSU,,
The Neenan Company
4Archistrvction) M17
620 E. Prospect Rd. #100
Fort Collins CO 80526
COVERAGES
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
INSURER A:
ST. PAUL
FI
INSURER 8:
NATIONAL
UN
INSURER C:
Pinnacol
AS
INSURER D:
FIREMAN IS
F
INSURER E:
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POUCIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR
LTR
TYPE OFINSURANCE
POLICY NUMBER
FOLICY EFFECTIVE
DATE MIDD
POLICY
DATE MMRI
LIMITS
A
GENERAL LIABILITY
X COMMERGALGENERAL LIABILITY
CLAIMS MADE F7xOCCUR
KK08301471
0l/01/O1
01/01/02
EACH OCCURRENCE
$1 , 000 , 0 0 0
FIRE DAMAGE (Anyone fln)
$100,000
NED EXP(Any one person)
$5 000
PERSONAL S ADV INJURY
$1 , 000 , 000
GENERAL AGGREGATE
$2,000,000
GEML AGGREGATE LIMIT APPLIES PER:
17 POLICY X jECO7 LOC
PRODUCTS -COMPIOP AGO
$2,000,000
A
AUTOMOBILE
LIABILITY
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
HIRED AUTOS
NON -OWNED AUTOS.
KKOB301471
01/01/01
01/01/02
COMBINED SINGLE LIMIT
(Ea eeeldent)
$ 1,000,000
X
BODILY INJURY
(Per Peron)
S
X
BODILY INJURY
(PerexMent)
$
X
PROPERTY DAMAGE
(Perecddent)
$
4E LIABILITY
ANY AUTO
AUTO ONLY - EA ACCIDENT
$
OTHER THAN EA ACC
AUTO ONLY: AGO
$
$
B
EXCESS LIABILITY
X OCCUR 7CLAIMSMADE
DEDUCTIBLE
RETENTION S
BE7409416
-
01/01/01
01/01/02
EACH OCCURRENCE
$25 , 000 , 000
AGGREGATE
$25,000,000
S
$
S
C
WORKERS COMPENSATION AND
EMPLOYERS' LIABILITY
4025258
COLORADO ONLY
01/01/01
01/01/02
X TORY LIMBS ER
E.LEACHACCIDENT
$100,000
E.L DISEASE - EA EMPLOYEE
S10D, 000
EL DISEASE - POLICY LIMIT
$500,000
D
OTHER
Workers Comp
All Other States
WC80871837
-
01/01/01
O1/O1/02
Limit $100,000/
$500,000/ $100,000
DESCRIPTION OF OPERATIONSR.00ATIONSIYEHICLESIEXCLUSKINS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS
RE: Second Sheet of Ice at EPIC.
r=n I rrra.w I c nvwcn d I ADDITIONAL INSURED; INSURER LETTER: CANCELLATION
CITF016 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN
City of Fort Collins NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
Attn: James B. lII
Dir. of Purchasinging & Risk Mgmt IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
215 N. Mason, 2nd Floor REPRESENTATIVES.
Fort Collins, CO 80522-0580 ALIT HORL&D REPRESENTATIVE
5.2.5.4- PAGE 1
November 12, 2001
Mr. James B. O'Neill II
The City of Fort Collins
215 N. Mason
Fort Collins, CO 80522
RE: THE NEENAN COMPANY
SECOND SHEET OF ICE AT EPIC
PROPOSAL P-812
Dear Mr. O'Neill:
Lockton Companies of Colorado, Inc. handles the insurance and surety bond requirements on behalf of
The Neenan Company. Their bonds are have been underwritten by Travelers Casualty and Surety
Company of America since 1994, and are issued through our office. Travelers Casualty and Surety
Company of America has a 2001 A.M. Best rating of A++, XV, and is authorized to do business in the
State of Colorado.
Travelers Casualty and Surety Company of America has approved bonds for The Neenan Company for
single projects in excess of $40,000,000 with an aggregate program in excess of $125,000,000 available
to them. The total cost to complete for all bonded work at this time is approximately $3,500,000. Based
upon their current and anticipated workload, The Neenan Company has the bonding capacity available,
should the referenced project be awarded to them.
Since inception, The Neenan Company has developed an excellent reputation with owners, architects,
subcontractors and suppliers, and is recognized as a highly competent and professional contractor. We
are very pleased to recommend this fine contractor to you. If you should need additional information,
please do not hesitate to call.
Sincerely,
LOCKTON COMPANIES OF COLORADO, INC.
Shelley Czajkdwski
Assistant Vice President
cc: The Neenan Company
Travelers Casualty and Surety Company
kaf
_.'..1 9 art•. ,_-, 1.! 1 .l�,Ju;:. n
5.2.5.5 — PAGE 1
00 First
National
Bank
November 27, 2001
James B O'Neill, II, CPPO, FNIGP
Director of Purchasing and Risk Management
City of Fort Collins Purchasing Division
215 N. Mason St.
P O Box 580
Fort Collins, Colorado 80522-0580
Re: The Neenan Company
Dear Mr. O'Neill:
Boardwalk Office
R/E Department
RO. Box 272500
Fort Collins, CO 80527-2500
970.29t.9690
The Neenan Company(TNC) has been a customer of First National Bank, since it was organized
in the early 1970's. TNC is a valued customer of First National Bank. First National Bank has
provided a variety of banking services including checking, loans, trust and cash management.
First National Bank has extended credit to TNC in the form of lines of credit, equipment, interim
and term real estate loans, and letters of credit. Recently, the combined credit extensions have
totaled in the low 8 figure range. All dealings have been as agreed or better.
TNC has maintained deposits at First National Bank in the low to moderate 7 figure range.
First National Bank has contracted TNC on several occasions to do new construction and remodel
work. They have been excellent to deal with. The projects have been completed on time or
sooner and the final product has been of the highest quality.
First National Bank looks forward to providing banking services to TNC in the future.
Sincerely,
James H. Trupp
Vice President
5.2.5.6 — PAGE 1
5.2.6
N E E N A N
KEY PERSONNEL
Overview The project team assembled for this project has worked together under a design/build
delivery model on over a dozen past projects. The familiarity of the team members
with each other and with the Neenan Archistruction® process will be of great value to
the City and help ensure the seamless delivery of the project requirements. The
primary roles and responsibilities of each team member follow; however every team
member will assist in insuring that the collective responsibilities described here are
successfully carried out. Resumes on each team member follow at the end of this
section.
Resumes or company profiles of below team follow this page:
Neenan Team Bob Meserve, Senior Project Manager, Project leader
Tim Stern, Project Manager
Steve Burns, Pre -Construction Manager
Mike Mesa, Superintendent
Chris Wesche, Project Architect
Bob Hosanna, Design Architect
Jon VanBenthem, Job Captain
Consulting Gilfillan Callahan Architects, Inc.
Architect Patrick J. Callahan, Principal Architect
Subcontractor/ Commercial Refrigeration
Consultants Design Mechanical
Merit Electric
BHA Design
Proposal to City of Fort Collins 5.2.4.6 -Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
5.2.6.1 BOB MESERVE
Senior Project Manager
Responsibilities Pre -construction responsibilities include estimating, budget control, design
input, schedule and constructability review, product selections and owner
coordination. Construction responsibilities include contract administration, cost
control, subcontractor negotiations, project buyout, project scheduling and
project closeout.
Experience Bob has provided comprehensive project delivery services for 20 consecutive
years for projects ranging from $100,000 to over $50 million. His experience
includes both large and small projects and a thorough knowledge of building
codes, permitting and other regulatory processes and worked extensively in
pre -construction and construction phases of the projects. Pre -construction
experience involvement has included design input, schedule and
constructability review, product selections, procurement, estimating, and budget
control.
Representative Fort Collins City Building A 72,000 sf, three-story administration building for
Projects Fort Collins, CO the City of Fort Collins.
ConAgra Foods A 102,000 sf, three-story Corporate Headquarters
Greeley, CO office building located in the Promontory
Subdivision.
McWhinney Office, #2 A 35,000 sf multi -tenant office building.
Loveland, CO
New Belgium Brewhaus 18,000 sf micro-brewhaus addition
Addition
Green/sustainability building concepts used
Fort Collins, CO
throughout design and construction of project.
Woodmen Office Campus
Phased campus project consisting of three site
Colorado Springs, CO
cast office buildings. I — a 79,000 square foot two-
story building featuring fiber optics, a flexible
zoned heat pump system and 7 watts of power
per square foot. II— a 75,000 square foot two-
story building designed for flexible tenant
configurations and technology requirements. III —
a 46,000 square foot three-story office building.
Proposal to City of Fort Collins 5.2.6.1 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
N A N
TimSTERN
Project Manager
Responsibilities Pre -construction responsibilities include estimating, budget control, design
input, schedule and constructability review, product selections and owner
coordination. Construction responsibilities include contract administration, cost
control, subcontractor negotiations, project buyout, project scheduling and
project closeout.
Experience Three years as an Assistant Project Manager and three years as a Project
Manager.
Representative Hunter Douglas #5
Projects Broomfield, CO
DPC Genesee Point Office
Genesee, CO
Quantum SSPG
Colorado Springs, CO
New Belgium Brewhaus
Addition
Fort Collins, CO
Union Medical Campus
Phase II
Colorado Springs, CO
Quantum PSG
Colorado Springs, CO
New office and manufacturing building for window
shade manufacturer (170,000 sf).
New office building in Genesee Office Park
including finished office space (52,000 sf).
New research and production fab for the tape
drive business unit (440,000 sf).
18,000 sf micro-brewhaus addition.
Green/Sustainability building concepts used
throughout design and construction of project.
Multi -tenant surgical and diagnostic facility
housing MRI and related equipment (55,000 sf).
Computer tape storage manufacturing facility
(50,000 sf).
Proposal to City of Fort Collins 5.2.6.1 —Page 3 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
N A N
5.2.2 TABLE OF CONTENTS
5.2.3 Statement of Understanding
5.2.4 Team Organization and Management Plan
5.2.4.1 Organizational Chart
5.2.4.2 Team Member List
5.2.4.3 Project Team Roles and Responsibilities
5.2.4.4 Management Plan
5.2.5 Project Experience and Qualifications
5.2.5.1
Design/Build Projects Of Similar Scope
5.2.5.2
Project Experience and Qualifications
5.2.5.3
Legal Evidence of Form of Business/Credit Application
5.2.5.4
Certificate of Insurance
5.2.5.5
Bond Verification Letter
5.2.5.6
Banking Relationship Letter
5.2.6 Key Personnel
5.2.6.1 Resumes of Neenan Personnel
5.2.6.2 Resume for Consulting Architect
5.2.6.3 Resumes For Sub -Contractors and Consultants
5.2.7 Design Process
5.2.7.1 Narrative
5.2.8 Project Cost, Schedule, and Quality Control
5.2.9 Guaranteed Maximum Price
5.2.9.1 Detailed General Conditions Cost Breakdown
Project Construction Cost Breakdown, With Design, and Pre -Construction
5.2.9.2 Project Cost/Design Options Listing
5.2.9.3 Outline Specifications
5.2.10 Schedule
5.2.10.1 Schedule Narrative
5.2.10.2 Project Schedule
5.2.11 Proposal Security
5.2.12 Required Schematic Drawings
5.2.12.1
Design Statement
5.2.12.2
Site Plan
5.2.12.3
Floor Plan
5.2.12.4
Elevations
5.2.12.5
Building Sections
5.2.12.6
3-D Computer Images
5.2.12.7
Building Code Study
Proposal to City of Fort Collins 5.2.2 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
N A N
STEPHEN BURNS
Pre -construction Project Manager
Responsibilities Pre -construction responsibilities include estimating, budget control, design
input, schedule and constructability review, product selections and owner
coordination. Construction responsibilities include contract administration, cost
control, subcontractor negotiations, project buyout, project scheduling and
project closeout.
Experience Steve has been working in the construction industry for over 13 years, 8 of
which have been in the municipal sector. His involvement in these municipal
projects has been from both the Owner and Contractor perspectives. Project
sizes have ranged from $100,000 to $205 million. His experience includes
several fire stations and public safety facilities. During his career he has held
the following positions: Project Manager, Chief Estimator, Scheduler, Cost
Analyst, Field Engineer, Surveyor, and Assistant Civil Engineer. His wide range
of experiences allows him to be involved from the conceptual stage through
project closeout, ensuring both continuity and customer value.
Representative Providence Ice Center
Projects Windsor, CO
ConAgra
Corporate Headquarters
Greeley, CO
Design -Build pre-engineered metal building
including sheet of ice, locker rooms, retail, multi-
purpose room and mezzanine seating area.
A 102,000 sf three-story office building with full
service cafeteria, backup generator, UPS, training
center, and exercise room on a 22 acre site.
Latimer County Sheriff A 36,500 sf two-story office building with 911-
Administration Building dispatch center, emergency operations center,
Fort Collins, CO
bioenvironmental drying rooms, crime lab, and
open office areas. Building features also included
access control security system, microwave
communication tower, fiber optic link to adjacent
detention center, and daylighting system.
City of Ft. Collins Office
A 72,000 sf, three-story administration building for
Building, Fort Collins, CO
the City of Fort Collins.
Colorado State University
12,000 sf Level 3 infectious disease research
Bioenvironmental Hazard
laboratory. Including sealed containment areas,
Research Facility
redundant HVAC systems, and laboratory
Fort Collins, CO
equipment.
Windsor Joint Use
Pre-engineered metal building co -owned by the
Maintenance Facility
City of Windsor and Weld County RE-6 School
Windsor, CO
District. Building housed maintenance vehicles
and miscellaneous workshops.
Proposal to City of Fort Collins 5.2.6.1 — Page 5 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
E N A N
MIKE MESA
Superintendent
Responsibilities Planning and executing the field work, including scheduling and directing
subcontractors on the jobsite; maintaining all on -site records required by city,
county or utility authorities; responsible for the layout and dimensional control of
the structure, monitoring the completed work for compliance with the contract
drawings and specifications; coordinating the quality control program for the
project, working with the Project Manager and General Superintendent during
the pre -construction phase of the project.
Experience Mike has provided construction supervisory services for the past 17 years. His
experience includes office campus construction, speculative office, multi -tenant
office building, research and development, warehouse, and other projects.
Representative Hunter Douglas A 170,000 sf warehouse, production and two-story
Projects Office office building.
Fort Collins, CO
McWhinney Office #2 A 35,000 sf multi -tenant office building.
Complex
Loveland, CO
McWhinney Bank A 22,000 sf bank and office space.
Office
Loveland, CO
JP Lamborn A 30,000 sf warehouse addition.
Warehouse Addition
Denver, CO
Diagonal Technology A 122,000 sf research and development campus.
Center
Longmont, CO
ST Microelectronics A 60,000 sf tenant finish for an engineering firm.
R & D Tenant
Longmont, CO
Proposal to City of Fort Collins 5.2.6.1 -Page 7 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
CHRIS WESCHE
Project Architect
Responsibilities Responsible for planning, programming project design, construction documents,
job -site observation, and coordination with regulatory agencies.
Experience Over 10 years experience with projects ranging from $100,000 to $10 million.
He has coordinated and developed the design and construction documents for
a variety of projects, including advanced technology projects, retrofitting and
upgrading cleanrooms, large redevelopment projects, and design and
construction for new industrial and office facilities.
Representative Xilinx A 130,000 sf, two-story office building. Phase 1 of
Projects Longmont, CO a planned six building office campus totaling
550,000 sf.
Flextronics Building 2 A 130,000 sf electronics assembly facility that is
Longmont, CO part of a 5 building campus.
Flextronics Building 1 A 20,011 sf addition to an operating electronics
Longmont, CO assembly facility design/build in less than 10
weeks.
New Belgium Brewhaus 18,000 sf micro-brewhaus addition
Addition
Green/sustainability building concepts used
Fort Collins, CO
throughout design and construction of project.
HP Realiabilty Lab
Clean environment to support wafer production
Fort Collins, CO
including silicon test, vibration, process test with
utilities.
Balzer's Thin Films
A 20,000 sf Class 1000 cleanroom facility for the
Golden, Co
thin film coatings industry.
Graphic Packaging
A 290,000 sf corporate headquarters and
Golden, Co
manufacturing facility.
Diagonal Tech Center
A 120,000 sf speculative industrial, R & D and
Longmont, Co
office space.
Baker Instruments
A 40,750 sf R & D and production facility for
Fort Collins, Cc
electrical testing equipment.
DIBC
70,000 sf 1-story office.
Denver, CO
Proposal to City of Fort Collins 5.2.6.1 — Page 9 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
N A N
H. ROBERT HOSANNA
Project Architect
Responsibilities Responsible for planning,_ programming, schematic project design, construction
documents, job -site observation, and coordination with regulatory agencies.
Experience H. Robert Hosanna has provided 20 years of design services to the Neenan Co.
His experience includes medical facilities, food service facilities, micro -brewing
facility, banking facilities, retail centers, industrial/manufacturing facilities, but
his primary emphasis has been office facilities ranging in size from 12,000 S. F.
to 120,000 S.F. Robert's experience with an international interior design firm
before coming to Neenan rounds out his ability as both registered architect and
interior designer.
Representative The Group 27,500 sf two-story office building.
Projects Fort Collins, CO
St. Joseph's School Design -build for an addition and renovation
Fort Collins, CO project. This project included a classroom and
cafeteria addition, and the remodel of the existing
gymnasium. This project was partially performed
with the school in operation and allowed for
minimal disruption to existing activities.
New Belgium Brewhaus 18,000 sf micro-brewhaus addition.
and Addition Green/sustainability concepts used throughout
Fort Collins, CO design and construction of project.
ConAgra 102,000 sf, three-story corporate office.
Greeley, CO
First National Bank Banking Headquarters for First National Bank in
Loveland, CO Loveland (12,000 sf)
J-1-T Institute of Corporate Headquarters (50,400 sf)
Technology
Englewood, CO
Neenan Company Corporate Headquarters, seminar facility
Fort Collins, CO (40,000 sf)
Proposal to City of Fort Collins 5.2.6.1 -Page 11 November 28, 2001
Second Sheet of Ice at EPIC (P-S 12)
N E
N A N
aJON VINCENT VAN BENTHEM
Project Architect
Responsibilities Responsible for planning, programming, project design, consultant coordination,
construction documentation, job -site observation, field coordination, and
coordination with regulatory agencies.
Experience Jon is a Licensed Architect in the State of Colorado. His experience includes a
few years in Chicago working with Gilfillan & Callahan, Architects primarily in
the recreational, medical, & educational arenas. Since moving to Colorado in
1996, he has worked in office, light industrial, and R&D product types as well.
He has recently completed work on 1899 Wynkoop, a 9-story high-rise in
downtown Denver and assisted on the New Belgium Brewery Brewhaus
Addition in Ft. Collins.
Representative Oak Lawn Ice Arena
Projects Oak Lawn, Illinois
Rockford Ice Arena
Rockford, Illinois
Elk Grove Cancer Care Center
Elk Grove, Illinois
Berkeley School District 87
Berkeley, Illinois
Pacifica Inverness Office
Building
Denver, CO
Park district ice arena w/ pro shop, fitness
facilities and some leased retail. 68,000sf
Park district ice arena/Family entertainment
plaza. 74,000sf
Linear accelerator addition to an existing
cancer care facility. 60,000sf
General Life Safety upgrades as well as
facilities expansion and re -development.
5-story leased office building. 100,000sf
Quantum 3-building campus
Colorado Springs, CO Office/ Assembly/ Warehouse facility
1899 Wynkoop Office Tower 9-story leased high-rise office building
Denver, CO 170,000sf
Canyon Point 2 2-story office building. 28,000sf
Golden, CO
Proposal to City of Fort Collins 5.2.6.1 —Page 13 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
PRINCIPAL
REGISTRATION Illinois Architect
Michigan Architect
PROFESSIONAL American Institute of
ASSOCIATIONS Architects
EDUCATION University of Illinois,
Urbana -Champaign, IL
Master of Architecture
Bachelor of Science
PROJECT Berkeley SO 87
EXPERIENCE Palatine CCSD 15
Arbor Park SO 145
Rondout SO 72
McHenry CHSD 156
Harrison SO 36
Hillside SO 93
Palos Heights SO 128
Saratoga SD 60c
Blue Island SO 130
West Aurora SO 129
Keeneyville SD 20
North Shore SD 112
PAEC Special Education
Chicago Public Schools
Oak Lawn Library
Bridgestone/Firestone
Six Flags Great America
Edward Hospital
PCS PrimeCo
Mitsubishi
Patrick J. Callahan
In his eleven years of experience as a design
professional, Mr. Callahan has developed a
comprehensive understanding of all facets of the
practice of Architecture, and has been recognized by
clients and peers as a skilled project manager. His
background and experience in managing complex
school remodeling and life -safety projects gives him
the insight necessary to tackle the toughest of
architectural assignments.
Patrick understands the complexities of
construction projects. He believes that architects need
peripheral vision to understand and plan for the impact
that new construction and remodeling has on the
client's daily activities. Looking beyond the edge of the
AutoCAD image is essential for successful project
implementation.
Patience, understanding, and tenacity are
required to ensure timely project delivery and effective
cost control. Mr. Callahan has demonstrated these
attributes in efficiently managing public and private
building projects both under previous employment and
as a principal project architect at Gilfillan Callahan
Architects.
Mr. Callahan, who serve as a Commissioner of
the Batavia Park District, is dedicated to quality in the
built environment. He realizes the important role that
buildings play in our community. Not only in providing
places for programmed activities, but also as settings
for essential human interaction. His personal
commitment to excellence in the design and
construction of these very essential facilities is
evidenced by a long list of satisfied clients and users.
G9frgan=aDahan Architects, Inc.
itOfi or,,,oraTq -rr. ht? iC i0 3 fm VEF do, _ 50c :JS'S
5.2.6.2 — PAGE 1
COMMERCIAL
'1P I I REfRlqERATION Inc
Commercial Refrigeration Inc., an Edmonton (Alberta, Canada) based
Commercial Refrigeration Inc. is able to provide any
contractor, has been involved in the design, manufacture, installation and
of the following on a DESIGN/CONSTRUCT basis:
service of artificial ice plants for ice arena and curling rinks for the past 35
Advisory and Consulting Services
years.
During this time we have had involvement in the installation of some 300
• Conceptual Planning of new facilities to meet the
specific requirements of the market, while
different rinks - from small facilities to large 10,000 seat arenas. We have
maintaining the highest standards of ice quality,
accumulated a broad base of experience that is second to none in our field.
energy efficiency and project budgets
Commercial Refrigeration Inc. specializes in the Sport and Recreational Ice
Artificial Ice Refrigeration Systems
industry. Our expertise is in the design, manufacture, construction,
installation, and service of artificial ice refrigeration plants and rink floors.
Indusfial duty refrigeration plant of any type or size
complete with:
Our focus is to provide energy efficient, durable, and serviceable systems
that will produce the absolute best quality ice available! We not only
♦ Environmentally friendly products
design for it ... we insist on it!
• Industry leading components and design
To ensure high quality workmanship, our staff consists of specialists in the
* Electrical System and Controls
refrigeration, electrical, and welding trades.
♦ Operating and Maintenance instmctions
With 35 years in the business and some 350 projects completed, we have
• Detection and Safety Equipment
grown from a basic refrigeration service company to aleader in the
♦
artificial ice industry.
Computerized Control System
Advisoryand Services are
g part of the package we offer. Each
Ice Rink Floor Systems
project receives individual. design consideration to best suit its specific
♦ Patented high efficiency under floor rink piping.
purpose.
♦ Concrete or Sand Ice Rink Floor System and
Our projects have ranged from small two sheet curling rinks, to large
Accessories
commercial three rink arenas, both indoor and outdoor. Other projects
include ice plants powered by natural gas engines, ground freezing units
• Cooling and Under floor Heating Systems
for construction in unstable soil conditions, and numerous other specialty
♦ Sand Bedding and Floor Insulation
.projects. After -sales service is important, and at present we service many
♦ Installation supervision and support
rinks throughout North America.
♦ Design and Drawings for the Construction by the
We have extensive involvement in the U.S. Market, having completed rink
Owner of Rink Periphery Accessories, such as:
projects in Illinois, West Virginia, Georgia, North Carolina, Pennsylvania,
Header Pipe Trenches
New York, Indiana, Texas, New Mexico, California, Ohio, Colorado, and
Nevada. Commercial also has completed projects in Canada, New Zealand
Dashboard Base and Supports
and Russia.
Shaved Ice Melting Pit
Commercial's parent is Vector Industries Inc. of Edmonton, a 35 yew old
Heat Recovery & Energy Systems
company which is one of the largest refrigeration companies in Canada.
Companies in the Vector group are engaged in other aspects of the
• Waste Heat Recovery for:
refrigeration business including HVAC, Supermarket Refrigeration,
♦ Under floor Heating
Industrial Refrigeration, and Refrigeration for Natural Gas Processing.
♦ Shaved Ice Melting Coil
Commercial's affiliation provides access to technical expertise and
capabilities in these other aspects when required, while allowing
♦ potable Water Preheat
Commercial to maintain it's focus on Recreational Ice Refrigeration. The
• Dehumidification
Vector affiliation also brings increased stability and financial strength.
• Water Recovery and Reuse of:
HEAD OFFICE and SALES California Office
Melted Shaved Ice
Commercial Refrigeration Inc.
g Commercial Refrigeration (USA) Inc.
Dehumidifier's Water
421-116 Ave. N.W. 22748 Boxwood Lane
Rain Collection
Edmonton, Alberta Saugus, CA
Canada 176S 1G3 USA 91350
• Low Emissivity Ceiling for Ice Rink
Toll Free: 1-800-414-0990 Toll Free: 1-800-414-0990
♦ Infrared Ice Temperature Monitoring and Control
Phone: (780) 449-0990 Phone: (661) 263-8593
• Demineralized Ice Flooding Water System
Fax: (780) 464.4077
• Ice Banks for Building Air Conditioning
Email: info(@.ig?,arena.com
Proposal to City of Fort Collins 5.2.6.3 Page I
November 28, 2001
Second Sheet of Ice at EPIC (P-812)
ICE ARENA FACILITY EXPERIENCE
Design Mechanical, Inc. will be performing mechanical engineering services for the facility HVAC and
plumbing, including integration of the ice plant and related components. In addition, Design Mechanical,
Inc. will install the HVAC systems.
Project Description
Customer Completed
Construction
Performed by Design Mechanical or Key Employees
East Boulder YMCA
New +/- 60,000 SF
Wyatt Construction
12/98
Arapahoe & US 287
Athletic Club & Ice Rink
Design Build
Denver Country Club
Replace Ammonia Refrigeration
Denver Country Club
10/83
System for Ice Rink
University of Colorado
Replace Student Rec Center
University of Colorado
10/82
Ice Rink, Rink Piping
Design
Performed by Design Mechanical or key employees
Mesa Verde Sports Club
HVAC/Plumbing Design
City of Mesa, AZ
2004
For 3-Sheet Ice Arena
Indoor Water Park & 12-Story Hotel/Condo
Northeastern University
HVAC Energy Upgrades
Northeastern University
1993
Student Rec Ctr Ice Rink
Boston, MA
World Arena
New Ice Arena
HOK Sports
1994
Univ. Southern Maine
HVAC Energy Upgrades
Univ. Southern Maine
1995
Student Rec Ctr Ice Rink
PreConstruction
Performed by Design Mechanical or Key Employees
Pepsi Center New Hockey/Basketball/Events M.A. Mortenson
Budgeting
Center & Practice Rink
1994-1998
City of Westminster New Ice Arena Tamminga Construction
Budgeting
(Sun Arena)
1996,1997
Lowry Ice Arena
Ritchie Center
2 Ice Rinks
Existing Hanger Building
Hockey/Basketball/Events
Center & Practice Rink
Etkin Construction Budgeting
1996
Calcon Construction Budgeting
1996
5.2.6.3 — PAGE 2
.A.erit
Integrity Skill tn.gination
Established in 1984, Merit Electric is a full service electrical contractor specializing in design -build
electrical construction and electrical maintenance services.
A major factor in our success has been our exceptional ability to perform as part of a design -build
team. We've completed numerous major design -build projects with contracts ranging from
$50,000 to over $6,500,000, totaling more than $25,000,000 annually in sales. In the process,
we've developed a powerful system that allows us to establish preliminary budgets, assist the
architect and owner in analyzing alternates and options, prepare complete plans for permit and
construction, and install the systems at a pace that's unequaled in our market, all while
consistently providing superior overall value to the building owner.
Our design -build project list includes such high -profile projects as the following:
• Hunter Douglas in Broomfield (entire complex, including one office building and three
production buildings totaling over 300,000 square feet)
• Xllinx Building I in Longmont is a 130,000 square foot administrative building for a high tech
manufacturing facility
• Bren Shrelber in Inverness Park is a 6 story office building at 180,000 square feet, with a 4
story parking structure.
• Mack Cali/Woodward Clyde is the tenant for the above Bren Scheiber building. This tenant
build -out encompassed the entire building, and our design/build efforts were pretty much
ongoing at the same time.
• RSA Building was a 70,000 square foot office building.
• Shea Building I is a 118,000 square foot core and shell building for future tenants
• Shea Building II is a 134,000 square foot building, also for future tenants.
• 16 Market Square is a 256,000 square foot multi -use building. There are 3 floors of
subterranean parking, with an 8-story building above; 1 floor of retail, 5 floors of Class A
commercial and 2 floor of high -end multi -family units.
• Maxtor is a 490,000 square foot mid tech facility in Longmont, Co.
• Flextronics is a 120,000 square foot low -tech facility in Longmont, Co.
• Conagra is a 102,000 square foot office facility in Greeley, Co.
• Graphic Packaging is a 300,00 square ft. Coors packaging facility.
• New Belgium Brewery assorted projects.
Our customer satisfaction level is so high that more than 80% of our design -build
projects completed have been done for repeat customers. We take great pride in that
Fact!
5.2.6.3 — PAGE 3
L1CSl R
BHA Design
Company Profile
BHA Design Inc. is a landscape architecture and planning firm established in January of 1993. The
fine size is currently 9 full-time landscape architects and one administrative assistant. BHA
provides landscape architecture, planning, urban design, and graphic design services to both public
and private clients in a variety of settings. Our capabilities include expertise in landscape
architecture, urban design, land use planning, graphic design, and public participation.
Our company is driven by two philosophies: Innovation and Customer Service. Innovation to us
means striving to provide our clients with environmentally responsive designs that are unique,
attractive, and contextually sensitive. We find that each project setting provides its own unique
attributes that provide clues to the new and interesting design solutions. By understanding the site
parameters, combined with the program elements of the client, we are able to develop solutions that
are site sensitive, responsive, and have a unique sense of place.
Our second major philosophy, customer service, means more than just meeting deadlines and
budgets, although those certainly are significant. It also means providing our clients with
constructive recommendations and constantly searching for ways in which to provide better
solutions. Friendliness and courtesy are essential ingredients of our means of communication.
BHA is highly capable with electronic technologies including AutoCAD 2000i for drafting, 3D
Studio Vis for real time visual flythrough and still life simulations, Adobe and Corel for graphic
design and, Microsoft Project for scheduling. We have capabilities to interface with different word
processing formats including both MS Word and Corel WordPerfect. BHA maintains a DSL line to
all computers and is able to rapidly transfer data and drawings electronically.
omp¢ny ro e e
bha design, ine.
5.2.6.3 — PAGE 4
N E E N A N
5.2.13 Proposed Commissioning Plan
5.2.14 Proprietary Information
Not Applicable
5.2.15 Appendix
5.2.15.1
The Neenan Company
Neenan Reliability Planning System (NRPS)
Neenan Collaborative Design Process (CDP)
STAR Safety Program
Project Profiles
Letters of Recommendation
5.2.15.2
Gilfillan Callahan Architects, Inc.
5.2.15.3
Commercial Refrigeration
5.2.15.4
Design Mechanical
5.2.15.5
Merit Electric
5.2.15.6
BHA Design
5.2.15.7
Life Cycle Information
Proposal to City of Fort Collins 5.2.2 — Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
N A N
5.2.7.1 DESIGN PROCESS
Design Unique to The Neenan Company is our Archistruction® process. This outgrowth of the
Overview more traditional design/build approach is a process of concurrent design and
construction developed by Neenan, which is continuous and collaborative. Through
this process, Neenan has been able to achieve a performance history of 1 Y2%
average change orders with extremely happy clients, and has never been in court with
any of those clients in our 30 year history.
Our Archistruction® process brings the Owner, project team, and all major
stakeholders together earlyto establish Conditions Of Satisfaction for the project, and
often (typically weekly) to insure that those conditions are being met on an on -going
basis. The budget evolves continuously as the design is developed and refined, so
pricing feed -back is immediate as options are considered and allows for informed
decision making by all stakeholders.
Value engineering is a continuous process with ArchistructionO and is in sharp
contrast to the traditional use of the term "value engineering", which typically occurs
only when there is a budget problem, and typically degenerates into "value
elimination".
Design For The Second Sheet of Ice at EPIC, The Neenan Company will follow the design
Process and process steps of Schematic Design (SD), Design Development (DID), Construction
Sequence Drawings (CD) and Building Permitting. Schematic Design represents the first 15% of
our effort; it is completed when the major building systems are selected, all major
building components have determined, and the City of Fort Collins has accepted the
design. Design Development is the next 25% of our effort, where the team studies the
mid -level details and systems interfaces in the building and coordinates the site
information to 90%. Construction Drawings is the next 45% of our effort; it is the final
detailing, dimensioning and coordination of the project.
One of the first requirements in our design process is to perform a comprehensive
building code review to verify the occupancy, construction type, and resultant
construction requirements for the facility. To verify that our design assumptions are
valid, Neenan has performed a Code Review Study, which is included at the end of
this section. Based on this study, it was determined that a two-hour separation will be
required between the new and existing facilities, and our plan reflects this requirement.
At this time, we have not undertaken to verify if the existing facility meets current code
requirements.
Team/Owner The following matrix indicates the level of involvement in each phase by the primary
Involvement team personnel. The number in the box represents the average days per week of
involvement.
Proposal to City of Fort Collins 5.2.7.1 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
SD
DID
CD
PERMIT
City of Fort Collins Owners Representative
Twice The Ice Representatives
EPIC User Representatives
Chris Wesche —TNC project architect
5
5
5
5
Tim Stern — TNC project manager
21
3
51
5
Pat Callahan -Consulting Architect
1-2
0-1
0-1
0
Bob Hosanna - TNC design architect
2-3
1-2
2-3
1-2
Brennan Schumacher — Merit engineer
2-3
2-3
5
1
Bob Roth — Merit estimator
2-3
2.3
1
0
Dory Ross — Design Mech engineer
2-3
2-3
5
- 1
Steve Larson — Design Mech estimator
2-3
2-3
1
0
Nick Nothhaft — Nothhaft Fire designer/estimator
1-2
11
3-41
1
Gary Howell - HGH structural engineer
1-2
5
51
1
Mike Stajduhar — TNC general superintendent
1-2
1
2
0
Steve Burns — TNC pre -construction manager
5
5
1
0
Mike Mesa - TNC superintendent
0
0
21
5
Owner We propose that the City's designated Owner Representative participate in
Involvement regularly scheduled 2-hour working meetings each week with the project team
through completion of CD's (Construction Documents). Design working meetings
would then be held on a less frequent basis from permitting through construction
and Owner involvement would be only as needed for key decisions.
EPIC users/Twice The Ice meetings would be as needed beginning in SD
(Schematic Design) to determine end user needs. It is desirable to work with
users at least once a month to avoid changes late in construction, which can result
in unnecessary cost and schedule delay to the Owner. In addition to these
meetings, additional time must be allowed for the City Representatives, EPIC User
groups, and Twice The Ice to make decisions, perform internal coordination,
contract management, and related Owner requirements.
Proposal to City of Fort Collins 5.2.7.1 —Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
5.2.8 PROJECT COST, SCHEDULE & QUALITY CONTROL
Cost Controls Experience has proven that controlling budgets and costs is directly related to the
ability of the client and design team to work together and communicate frequently.
Working closely together promotes clear communication and allows client program
wishes to control and justify construction cost estimates. The Neenan Company
process promotes early and frequent meetings with the Owner to insure that this
happens.
The assembled Neenan Team will work closely with the City of Fort Collins, meeting
weekly to establish and monitor project schedules and budgets, and to resolve issues,
discuss options, and convey design progress. Our precise cost estimating and
effective communication will help keep budgets accurate and under control.
Cost Control Our process is unique to the construction industry. The key distinctions that follow,
Process truly differentiate TNC from other firms, and will significantly impact the outcome of
your project. We ask you to carefully consider these key distinctions as you evaluate
your options.
Preconstruction Services - Neenan's preconstruction services are the heart of our
process and the key to our ability to be responsive to our customers' needs. Over the
past 25 years, we have evolved our preconstruction capabilities to the point where we
are quickly and accurately able to establish project budgets with limited information.
This allows our customers to make cost decisions and consider options without
expending time, dollars or human resources for rework after designs have already
progressed well beyond the schematic stage.
We are very accustomed to early conceptual pricing, given limited information, with a
high degree of accuracy. We do this by utilizing an extensive historical cost database
combined with deep inquiry as to customer needs and expectations, which are not
typically apparent from preliminary plans or superficial program discussions.
Additionally, we commit adequate time to extrapolating detail that may not be available
from existing information. Our preconstruction personnel maintain close
communication with the project team as the design evolves to provide immediate
feedback on options and alternate cost considerations. This allows us to guarantee
budgets much earlier in the process, and provides the Owner with a much higher level
of predictability.
Value Engineering - Many firms profess that they practice value engineering when in
reality, they simply reduce costs by reducing scope or quality ("Value Elimination").
True value engineering requires that a project's components and systems are
evaluated and challenged to determine which alternative solutions may provide a
higher overall value to the client. When value engineering occurs after the design
direction is set, it generally becomes a cost cutting exercise. By working with the
design team during the design development process, true value alternatives can be
explored and incorporated into the project.
Proposal to City of Fort Collins 5.2.8 - Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
City of Fort Project costs and construction quality will greatly affect the overall performance of the
Collins EPIC facility as well as it's long-term occupancy costs. Our partnering process
Involvement ensures that costs and quality are effectively controlled and monitored throughout the
project and provides you with many benefits and protection not generally available with
a traditional design -bid -build approach to construction.
❑ Construction budgets are established jointly with you and are verified at the
conclusion of each step.
❑ City of Fort Collins is involved in all decisions related to design, cost, quality and
schedule, including the selection of building systems and materials and all aspects
of value engineering.
❑ Depending on the project delivery model, the selection of subcontractors and
suppliers, which typically represent approximately 90% of the construction cost,
can be done jointly with our client and is based on competitive pricing as well as
demonstrated past performance and integrity of each subcontractor.
❑ Regularly scheduled meetings are held with you or your representative, the
architect, consultants, project manager, site superintendent and major
subcontractors to ensure adherence to cost, quality, safety and schedule
requirements.
Methods of Construction activities are monitored and controlled by experienced project managers
Cost Control and site superintendents of The Neenan Company who have been involved in the
and project since the design development phase. In the last three years we have
Scheduling implemented three methods of tracking the critical aspects of projects from drawings,
scheduling to cost control.
The first method is the CDN Log, which allows the team to clearly follow the sequence
of drawings. Any time new information is distributed, the entire team is made aware of
changes or modifications. The CDN Log is a useful tool for managing the distribution
of information and since we began using it three years ago it has proved to be a great
asset for eliminating waste.
The second method we use is the Open Items List, which is our tool for monitoring
potential costs and value assessments of items being considered to be added to or
deleted from the scope of the project. The Open Items List is reviewed weekly with the
Owner and the team. This tool is extremely effective in keeping the team aware of the
base estimate/contract price, and charts questions that, until answered, may require
additional information or time.
The third method is the Neenan Reliability Planning System (NRPS). NRPS is the
foundation of Lean Construction and TNC's continuing effort to improve. Imbedded in
NRPS are some extremely effective management tools we utilize to deliver more value
to our clients at less cost.
Proposal to City of Fort Collins 5.2.8 - Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
In NRPS, planning is done at three levels - master schedule, eight -week look -ahead
schedule and weekly work plan. The master schedule is the overall strategy and
breaks work into smaller activity sequences without scheduling at this smaller activity
level. It does schedule key milestones, which release large portions of work to other
trades - long lead items and "big piece" activities; i.e., structural erection.
The eight week look -ahead is the mid level schedule. Here the superintendent pulls
detailed activities onto the eight -week look -ahead that "should" happen in eight weeks.
Over the next six weeks, the project management team makes that work ready. They
do this by removing the potential constraints like manpower, materials, safety,
information, tools and prerequisite work.
At the final and most detailed level is the weekly work plan. Once the work is made
ready through the eight -week look -ahead schedule, the final two -week planning is
done at the field foreman level. Work is broken down into work packages (one trade's
work of five days or less duration), sequenced at a day by day level, measured at each
week's end as to the percentage completed, reasons for non -completion of work noted
and how to improve so that it doesn't occur again.
We began implementation of NRPS in October 1998. The early findings demonstrate
projects completed on time (without major stacking of trades near completion) to 25%
early. This results in a higher quality project and a decline in subcontractor prices.
Quality At weekly construction phase meetings, The Neenan Company and City of Fort Collins
Control will walk the site and review quality, schedule, budget and cost control concerns. This
process has led to strong teamwork relationships between the Neenan Team and the
Owners. Communication, cooperation and understanding of the construction process
are actively encouraged by Neenan in order to foster an atmosphere of total teamwork
in delivering a successful facility.
Our Quality Control Management Team (QCM Team), created in 1998, has a goal of
continuous improvement of our projects through education, inspection and certification.
We expect quality to be built into our projects, not repaired into our projects. Our
Superintendents are tasked with providing a quality project and performing inspections
during the course of construction with the help of the Project Manager to assure that
we are meeting our quality commitments. If it is our client's desire, we will provide
inspection reports to assure that quality is being built into the project.
Proposal to City of Fort Collins 5.2.8 - Page 3 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
The Neenan Companv Second Sheet of Ice at EPIC 11/29/2001
rision Description
Takeoff Quantity
Total Cost/Unit
Total Amount
010',General Conditions
Project Manager ..
_ Salaried - PM
, 19.50 wk _-
3,140.00 /wk
.,_ _. 61,230
'.Superintendent
Salaried - Super
26.00 wk _ ,
3,540.00 /wk
92,040
Copier
Off Supply_ Copier
, -__ 5.50 mnth
100.00 /moth
550
Water Cooler
Supply_- Water Cooler
5.50 ninth
50.00 /mnth
„. 275
'Jobsite Trailer
Office - Jobsite Trailer
6.00 mnth
500.00 /mnth
- ,. 31000
,Temp Toilet
Office - Temp Toilet ..-.,,.,,., __ ---
_„_ 5.50 mnth
120.00 /ninth
660
,Temp Storage Trailer
_.
Stor- Temp Storage Trailer
5.50 ninth
300.00/mnth___
_. Trailer Set-Up/Tear Down
_
':-Office -Trlr_Set-uprrear Down
1,1.00 Is _._.
500.00/Is .,_
__. 500
.Job Site ID Sign
Sign Job ID Sign
;- , _ 1.00 pc
Electric Bill
(Temp Bec -_ MonthlyCharge
5.50 ninth
500.00 /ninth
Water Bill
Water-MonthlyCharge -
_ 5.50 ninth
100.00 /mnth
550
':;Storm Drainage Bill
!Temp Storm - Monthly Charge ...,,
5.50 mnth .,,.
150.00 /mnth
825
LTemp Water Service Install
_._ ....
Temp Water Sent Install
....- 1.00 pc _.
100A0 /pc
Professional Services - Survey_
_Prof Sere..-_Survey/Layout
1.00 hr -
75.00 /hr
,. _.,,. 75_
020 Sitework
Temporary Protection
32 302.00 sgft
0.02 /sgft
484
Temporary Fence
32 302.00 sgft
0.15 /sgft
4,900
Selective Structural Demo
32,302.00 sgft
0.16 /sgft
5,000
_.
Site Demo
32,302 00 sgft -_
0.62 /sgft
19,961
Site Demo Sawcut Cone
_32,302.00 sgft
0.01 /sgft
200
_ Site Demo Sawcut Asphalt _ _
32,302.00 sgft
'- --
0.01 !sgft_
_ 1 _ 400
Clear/Grub - Site
32,302.00 sgft
0.06 !sgft
-
1,826
-
Strip/Stock - Topsoil_
32,302.00 sgft
0.00 /sgft-.-
94
Site CuVFill
32,302.00 sgft
0.95 /sgft
30,606
Site Overexcavation
-- -
32 302.00 sgft -
-
0.40 !sgft -
12,906
-
Rlp/Recompact Paving
32,302.00 sgft
0.03 /sgft
889
Replace Topsoil __-
- - --
32,302.00sgft -:_
- -
0.03/sgft
- 896
Building Grading
32,302.00 sgft
0.07 /sgft
- 2,393
Curb/Gutter/Pavement Grading_
32,302.00 sqft
0.03 /sgft_
- 1,051
Earthwork Mobilization
,, 32,302.00 sgft
0.03 /sgft ._
1,000
IExcav/Trenchmg- Structural
i 32,302.00sgft
0.02/sgft _
_. 730
Haul off Caisson Spoils
32 302.00 sgft
0.04 /sgft
_ 1,116
Machine Backfill/Compaction __-
32,302.00 sgft
0.25 /sgft
8,202
_
_ Import Fill and Compact
32,302.00 sgft
0.72 /sgft
23,149
Subbase Material
- 32,302.00 s ft
0.09 /s ft
2,907
Section 5.2.9.1-Page 1
The Neenan Company Second Sheet of Ice at EPIC 11/29/2001
,ision Description
Erosion Control
:.Caisson Dulling/Casing __
(Place Caisson Concrete
Site Storm Draina4e
Asphalt Pvmnt Patch
!Asphalt Pvmnt Place_
iC&G Form/Place
C&G Cone Matl
'Cone Sidewalk - Form/Place
!Cone Sidewalk - Cone Matl
Allowance Landscaping
030' Concrete
Form/Place -_Wall Footing
j Form/Place - Trench
Form/Place - Int Curb/Pad/Pit
Form/Place - Ice Pit
Concrete Accessories
Conc Access SOG Exp Joint
Rebar - Foundation
Reber - Caisson
Reber - Trench
Reber - Site Cast Panel
Takeoff Quantity
Total Cost/Unit
Total Amount
32 302.00 sqft
0.91 /sgft
� 29,300
32,302.00 sgft_ _
0.54 /sgft
17 354
32,302.00 sqft
0.16 /sgft
5,032
32 302.00 sgft _
0.19 /sgft_,
6,200
32 302.00 sgft
0.22 /sgft
7,000
32,302.00 sqft
0.18 /sgft_ _
5,833
32,302.00 sqft
0.02 /sgft
469
32,302.00 sqft_
0.01 /sgft
- _255
32,302.00 sqft
0.07 /sgft
2,162
32,302.00 sqft __- _
0.02 /sgft
733
--
qo qn� nn enfi
1 qR /enft
ca onn
0.27
0.02
1
_160
1.250
763
Cone Matl Wall Footing
32 302.00 sgft
0.02 /sgft _
.._.
4
. 475
(Conc Matl _- Caisson _ _
32,302.00 sqft -------- _
0.40 /sgft'_-
13,020
- -
Cone Matl - Deck/Topping
32 302.00 sqft
0.04 /sgft
1,200
.Cone Matl - SOG
32,302.00 sgft
0.75 /sgft
24,085
Cone Matl Trench --
_
32,302.00 sqft
_
0.04 /sgft
j
1,200
Cone Matl - Int Curb/Pad/Pit
_ 32,302.00 sgft
0.02 !sgft
_ 639
]Cone Matl - Ice Pit
32,302.00sqft_
0.04 /sgft
1,151
Finish - Misc.32,302.00
sgft__-
0.03 /sgft
82-8
Place/Finish Deck
32 302.00 sgft
0.17 /sgft
0.
5,609
Place/Finish SOG_
32,302.00 sgft
0.25 /sgft _
8,189
.Concrete Sawcuttina
32,302.00 sqft
0.05 /sgft
1,592
SOG
Cone Pump - Ice Pit _
Cone Cure
Precast- Dynaspan
Precast Pni- Insulated
Precast- Bracing
Masonry
Ext CMU - Ext Wall
Int CMU Partition
Brick Veneer - Exterior
Steel
Steel Bar Joists
sgft
O.Otlsqf
0.05 /sqf
0.01 /sqf
0,02 /sqf
0.03 /sqf
0.76 /sqf
9.13 /sqf
0.25 /sqf
0.51 /sqf
2AO /sqf
3.86 /sqf
6.30 /sqf
318
531
819
Section 5.2.9.1-Page 2
The Neenan Companv Second Sheet of Ice at EPIC 11/29/2001
ision Description
Takeoff Quantity
Total Cost/Unit
Total Amount
'Int Stair - Steel
32,302.00 sgft
0.23 /sqft i
7,500
Int Handrail - Steel Tubular
32,302.00 sgft
1.57 /sgft
50,600
Header Trench Cover
32,302.00 sgft
0.21 /sqft
6,720
060;Wood Carpentry
Ext Door Frame Install
32,302.00 sqft
0.04 /sqft _
1,180
Ext Door Install
32 302.00 sqft
0.06 /sqft
1,854
'Int Door Frame Install
32,302.00 sqft _
0.04 /sqft
1,116
;Int Door Install _.._
-- 32,302.00 sqft
1.11 /sqft
35 949
Carp Lahor Wd Sheathing -_
- -
32 302.00 sgft_
0.06 /sqft -_
2,058
- -
Wd Framing - Roof
32,302.00 sgft
0.12 /sqft
4,000
070Thermal & Moisture
Dampproof - Foundation
- 32,302.00s9ft _
0.03 /sgft.__
1,095
Waterproof- Trench
32,302.00 sqft
0.04 /sgft
-._ 1,174
'Waterproof - Pit
32,302.00 sqft
0.02 /sqft_
648
Insulation - Foundation
32 302.00 sgft
0.05 /sqft
....
1,643
'Insulation -Under Ice
02.00
32,302.00 sqft
0.56 /sqft
-- -- 4
18,203
EDPM Roof Ballasted
32,302.00 sqft
2.11 /sgtt
67,984
,- ...
Sheet Metal Roofing_
32,302.00 sqft
0.28 /sqft _ _�
9,000
Flashings - Sheet Metal
32 302.00 sqft
0.26 /sqft
8,484
Rf Accessory Roof Hatch -
32 302.00 sgft __
-
0.04 /sqft __
Fireproof - Bar Joist/Deck
32 302.00 sqft
0.03 /sgft
1,050
Firesafe - Ext Fire Wall
32,302.00 sqft -
0.03 /
875
'Caulking.- Exterior _.
32,302.00, sqft
0.46 /sqft
� 14,750
080IDoors & Windows
iExt Door Frame - Hollow Mtl
32,302.00 sqft
0.03 /sqft
-1,050
_
Ext Door - Hollow Mtl
32 302.00 sgft
0.08 /sgft
2,475
Int Door Frame - Hollow Mtl
32 302.00 sqft_
0.13 /sgft
4,050
Int Door - Hollow Mtl
., 32,302.00 sqft
0.13 /sqft _._ _
4,200
Cotlin4Doors/Grilles
32,302.00 sqft _
0.40 sqft
13,000
Storefront Ext Wndw
32 302.00 sqft
0.10 /sqft
.-
3,300
'. Hollow Mtl Wndw Frame - Int
32,302.00 s ft
4
0.03 /sqft
g
1,056
- -- -
Door Hardware - Ext
- - --
32 302.00 sqft
0.18 /sgft, _,
5,775
!Door Hardware -Int
32,302.00 sqft
_0.16/sgft
5,025
Door Weatherstrip/Seals - Ext
32,3021.00 sgft
0.03 /sqft
945
Door Weatherstrip/Seals - Int
-- - ---
32 302.00 sg
-- --
q_8_ft 0.01 /s
-
308
-- --
:Glazing -Interior
32,302.00 sqft
0.09 /sgft
i 2,800
091 Framing & Drywall
Gyp Board Ceiling_
32,302.00_sgS
0.56/sgft_
18,000
'Gyp Board - Soffit
32,302.00 sqft
0.67 /sqft
21,545
095'Ceiling Finishes
Acoustical Clg - 2x4
32,302.00 sqft
0.05 /sqft
1,680
Paint - Interior
32,302.00 sqft
0.87 /sqft
28,200
096Floor Finishes
Flooring--. Rubber
32,302.00 _sqft - _
-1.59 /sqft _ _
_ 51,300
_
Base - Rubber
321302.00 sqft
0.05 /sgtt
11760
;Epoxy Flooring
32,302.00 sgft
0.10 /sqft
3,100
097 Wall Finishes
Section 5.2.9.1-Page 3
The Neenan Company Second Sheet of Ice at EPIC 11/29/2001
•ision Description
Paint - Interior
Paint - Door/Window
100
Interior SignaQe_-
Lockers - Metal
_:Fire Protection Sof
.Toilet Accessories
110, Equipment
'[Athletic Eqwpmenl
131:Fire Protection
Fire Sprinkler Syst,
150'Mechanical
HVAC System
Takeoff Quantity Total Cost/Unit Total Amount
32,302.00 sgft 0.24 /sgft 7,79D
32,302.00 1.24 40,000
32.302.00 soft 0.04 /saft 1,248
0.10
_-_-..._-...._.
0.02
0.06
0.01
0.97
13.25
6.36
3.59
6.16
11
Section 5.2.9.1-Page 4
The Neenan Company Second Sheet of Ice at EPIC 11/29/2001
2,724,262
2,724,262
Sub Plan Check
2,394
22.000 %
Plan Check Fee
7,072
65.000 %
Building Permit
10,880
0.330 %
20,346
2,744,608
Performance Bond
26,043
26,043
2,770,651
Gen Liab Ins
23,078
0.700 %
Bldrs Risk Ins
1,319
0.040 %
24,397
2,795,048
Constr Cont.
98,905
3.000 %
Preconstruction Fee
19,956
0.605 %
118,861
2,913,909
Systems Commissioning
24,000
Reimbursables allowance
13,000
Interior design
9,150
Civil engineering
20,000
TNC Planning/Landscape Design
13,000
Traffic Study
5,000
Structural engineering
16,500
Architectural Design
132,765
4.027 %
233,415
3,147,324
OH&P
149,498
4.750 %
Total
3,296, 822
102.062
Section 5.2.9.1-Page 5
N E E N A N
5.2.3 STATEMENT OF UNDERSTANDING
Oveview The Neenan Company Design/Build Team appreciates this opportunity to offer our
services for design and construction of the SECOND SHEET OF ICE AT EPIC. Our
highly qualified team has extensive experience working together under a design/build
delivery model in a team environment. We are committed to deliver a project for the
City of Fort Collins and Twice the Ice that meets your needs and exceeds your
expectations.
Our approach on responding to this RFP has been to attempt to discover and
understand the concerns and requirements that drive this unique facility regarding
functionality, maintenance, and operations, in addition to the financial parameters of
the project. Our proposal represents one possible solution that we feel addresses
those concerns, as we currently understand them. The solution we are proposing here
will serve as a baseline from which you and we can work as a team to design and
construct the best ultimate solution.
The project scope as we understand it consists of adding a second sheet of ice and all
ancillary requirements for a fully functional, regulation size ice rink at the EPIC Center,
including all site work and related requirements. The project budget is $3,600,000 for
the design/builder's portion of the work, and the City desires to receive as much value
and functionality as possible while remaining within this budget.
At the heart of our Archistruction process is the testing of our proposed solution and
other possibilities with the direct input of the City, the facility operators, and the various
user groups, to insure that the facility represents the best collaborative solution for all
stakeholders. The project really begins with our selection as your design/builder. At
that point, our job will be to work with all parties to effectively facilitate this discovery of
the best solution, and then convert this solution into it's physical representation --on
time, on budget, and to a level of quality exceeding your requirements.
Based on our current understanding of the project requirements, we believe that the
conceptual design submitted with the RFP does not adequately address the functional
and operational needs of the facility. Our basic premise in the solution we are
proposing is that the City has established a budget for the facility, and wants to receive
the maximum value for that budget.
It is definitely possible to design and build a cheaper facility than we have proposed
here. However, our current understanding is that the City's desire is to receive as
much value as your defined project will allow, and our approach reflects this
assumption. In the "Guaranteed Maximum Price" section, we have attempted to
identify some of these "value added" features for your consideration. We can modify
the proposed design to eliminate some of these features as necessary if a lower
project budget is required.
Even with these "value added" features, our proposed GMP is well below the City's
stated budget. This will allow the City and Twice The Ice, at your option, to create a
separate Owner Contingency to provide for additional or up -graded Owner -supplied
equipment, and possible added scope in either the existing or new facility.
Proposal to City of Fort Collins 5.2.3 - Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
N A N
5.2.9.2 PROJECT COST/DESIGN OPTIONS
Overview Below you will find a listing of several project cost options we have identified for you to
consider as you evaluate the budget, your requirements and desires for the facility.
Most of these are what we consider to be "value added" options, which are above and
beyond the minimum requested in the RFP. This is not represented as a complete
listing of potential savings or value added features, but is offered only as an
introductory listing of budget reduction possibilities.
With the involvement of the City and Twice The Ice, we can explore these and other
options to arrive at the optimum solution for you. Depending on final budget
requirements, any or all of these options could be taken to reduce the final GMP.
Deductive 100% painted pre -cast exterior walls (delete brick veneer) $ 121,007
Cost options
Remove north storage room, adjacent to Zamboni room $ 59,478
Remove south storage room, adjacent to service area $ 84,077
Delete multi -purpose room $ 47,483
Reduce locker rooms to 4 vs. 5, and reduce size to match $ 8,000
existing (approximate)
Remove articulation of walls from north and east elevations (if $ 20,000
allowed by City/approximate)
Total Of Noted Deduct Options $ 340,045
Additive Cost Add low E ceiling $ 31,000
Options
Add elevator to mezzanine seating area $ 42,000
"Rated ceiling in rink area, if required (approximate) $ 88,000
"Fuelmaker" system for fueling of Zambonis w/ natural gas $ Undetermined
System to utilize ice melt water to flush water closets $ 21,000
'Note: The City Building Department has initially indicated that
a one -hour rated ceiling may be required for the entire rink area.
We believe that optional approaches or interpretations may
remove this requirement, but more research is required. This
cost is currently not included in our GMP.
Proposal to City of Fort Collins 5.2.9.2 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
OUTLINE SPECIFICATIONS
EPIC ICE ARENA ADDITION
November 29, 2001
These outline specifications relate to the detailed GMP Construction Project Cost
Breakdown and Preliminary Project Plans included in this proposal.
The building is constructed of load bearing, insulated, concrete pre -cast panels with an
exterior skin consisting of a brick veneer wainscot, vertical brick veneer architectural
elements, painted pre -cast panels, and standing seam metal siding to complement the
existing facility. The roof will be an EPDM ballasted, structurally sloped, flat system
composed of long span joist members with steel decking bearing on the existing west
wall and exterior concrete pre -cast panels. The floor system will be a combination of
concrete slab on grade and a single sheet of ice placed on an insulated sand floor
system. The foundation system is to be drilled concrete caissons. The foundation
system design is based on the soils report performed for the existing facility and has not
been confirmed with a building specific soils report.
The proposed building addition area is approximately 29,806 SF with second floor
mezzanine (spectator seating) area of approximately 2,496 SF.
Division 01 -- General Requirements
Inclusions:
01105 Administrative Requirements
1. Management services, including but not limited to, project
superintendent, project management and other management as
required on the project and at the Contractor's office to perform the
work.
2. Administrative Procedures: Coordinate scheduling and timing of
required administrative procedures with other construction activities,
the activities of other contractors and the operations of Edora Pool
and Ice Center to avoid conflicts and to ensure orderly progress of
the Work. Such administrative activities include, but are not limited
to the following:
A. Coordination and distribution of construction drawings.
B. Preparation of Contractor's Construction Schedule.
C. Installation and removal of temporary facilities and controls.
D. Coordination and distribution of submittals and shop drawings.
E. Design meetings to involve the facility staff and facility users in
design, functionality, and maintainability of proposed project.
Meeting minutes will be taken and distributed all attendees.
F. Pre -construction meetings with subcontractors and EPIC.
N E E N A N
G. Project closeout activities including:
1. 3 copies of the Operations & Maintenance manual with
equipment operating procedures.
2. 1 copy of the commissioning report.
3. 1 Mylar hard copy of complete and accurate record
drawings.
4. 1 compact disc of complete and accurate record drawings.
H. Purchase Order Tracking.
I. Daily Construction Reports.
J. Proposed schedule for design process milestones including
dates for all required meetings.
K. Perform life cycle costing for critical building systems during
project design.
L. Regular project meetings to discuss open items list and look -a-
head schedule using the Neenan Reliability Planning System.
M. Coordination of all inspections and tests, to ensure conformance
with the Contract Documents and for the purpose of obtaining a
Certificate of Occupancy. Contract and payment for testing and
inspections is to be by owner.
N. Coordinate with reasonable notice any potential disruptions of
EPIC operations through out the construction process.
0. Provide EPIC with site logistics plan.
P. Provide EPIC with a schedule of values prior to first payment
request.
3. Jobsite safety provisions, including OSHA required signage,
temporary railings, fencing, MSDS information, toolbox talks
and weekly safety meetings.
01111 Temporary Office Equipment
1. Office equipment required for daily operations such as:
A. Copier.
B. Water Cooler.
01121 Temporary Construction Facilities
Temporary enclosures, sanitary facilities, and construction office as
necessary for storage and use during daily construction operations
and as necessary to perform the work such as:
A. (1) Job site trailer.
B. Temporary toilets.
C. Temporary storage trailer for construction equipment.
01125 Temporary Construction
1. Temporary construction necessary to perform daily construction
activities such as:
A. (1) Trailer set-up and removal.
B. Project identification and temporary signs to inform public and
persons seeking entrance to Project.
Proposal to City of Fort Collins 5.2.9.3 — Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E
01131 Temporary Utilities
N A N
1. Temporary utilities are assumed to be available within construction
boundary.
2. Temporary site utilities necessary to perform daily construction
activities such as:
A. Temporary electric bill.
B. Temporary water bill.
C. Temporary water service install.
D. Temporary Storm drainage bill.
01175 Professional Survey
Exclusions:
1. Before construction, verify the location and points of connection of
utility services.
2. Verification: Before proceeding to lay out the Work, verify layout
information shown on Drawings, in relation to existing benchmarks.
3. Engineering services required establish lines, grades, site survey /
layout, building survey / layout, and interior layout involved with
construction.
1. Building specific soils report.
2. Water or sewer development fees.
3. Storm drainage fee.
4. Public improvements (such as street widening, sidewalks,
vegetation)
5. Storage for owner supplied materials and equipment.
6. All testing will be contracted and paid for directly by owner. Owner
will engage a qualified independent testing and inspecting agency to
sample materials, perform tests, and submit test reports.
Division 02 -- Sitework
Inclusions:
02220 Temporary Protection & Site Demolition
1. Supply and install temporary fencing to separate construction
activities from public access for safety and security. Temporary
barricades and fencing will designate hazardous areas, direct traffic
and protect existing site and landscaping features to remain.
2. Supply and install temporary plywood enclosures at selective
demolition areas to separate construction activities from public
access for safety and security.
3. Equipment required for demolition Qack-hammers, back -hoe, slid
loader etc.)
4. Loading of demolition debris, hauling of debris and land fill dump
charges.
Proposal to City of Fort Collins 5.2.9.3 — Page 3 November 28, 2001
Second Sheet of lee at EPIC (P-812)
N E E N A N
5. Selective structural demolition — removal of structural masonry for
proposed penetrations and structural connection to existing building.
6. Saw cutting of concrete and asphalt including labor and equipment to
remove debris and clean up demolition areas.
02230 Clear, Grub, Strip & Stockpile Topsoil
1. Clear & grub site removing ground vegetation in preparation for earth
work, grading operations and installation of new construction.
2. Strip topsoil in order to separate / isolate bio-mass materials from
usable fill materials. The bio-mass materials contained in topsoil
possess unsuitable characteristics for proper re -compaction in fill
areas.
3. Topsoil will be stockpiled on site and later placed on compacted fill
areas designated for installation of landscaping and the re -growth of
vegetation.
02310 &
02315 Earthwork
1. Excavate / cut material for structures, pavements, and walks to
elevations and dimensions indicated on drawings. Extend
excavations for placing and removing concrete form -work.
2. Backfill or place fill material in layers to required elevations and
compact to specifications stated in soils report.
3. Remove and replace material under pavements and compact to
specifications stated in soils report.
4. Fine grading of material under slabs and foundations to required
elevations and compact to specifications stated in soils report.
5. Grading of material under curbs, gutter, and pavement to required
elevations and compact to specifications stated in soils report.
6. Grade lawns, walks, unpaved sub -grades and pavements to a
smooth surface, free from irregular surface changes. Comply with
compaction requirements and grade to cross sections, lines, and
elevations indicated.
7. Mobilization and set up of earthwork equipment.
8. Structural excavating, trenching, backfill, and compaction as required
for foundation connection to concrete panels.
9. Removal of caisson spoils.
10. Gravel / sub base material under slab on grade.
02370 Erosion Control
1. Provide erosion -control measures to prevent erosion or displacement
of soils and discharge of soil -bearing water runoff or airborne dust to
adjacent properties and walkways.
2. Prevent surface water and ground water from entering excavations,
from ponding on prepared subgrades, and from flooding Project site
and surrounding area.
Proposal to City of Fort Collins 5.2.9.3 — Page 4 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
02465 Caissons
1. Mobilization and set up for drilling caissons.
2. Drilling, casing, and placement of all caissons.
02510 &
02530 Site Utilities
1. Provide piping, connections, layout, excavation, bedding and backfill
for proposed site storm drainage line to handle additional flows from
new construction to include the following:
A. 18" RCP line to connect to existing manhole.
02740 Asphalt Paving & Patch
1. Provide and install 6" full depth asphalt for proposed modification to
existing asphalt area at south end of building. Base course to be 4"
of HBP, grade C and finish course to be 2" HBP, grade CK To be
confirmed with the building specific soils report.
02770 Concrete Curb and Gutter
1. Provide, labor, and concrete material to form and place 18" site
concrete curb and gutter for proposed modification to existing
asphalt area at south end of building.
02775 Exterior Concrete Sidewalks & Slabs
1. Provide labor, material, and equipment to install proposed sidewalks
and propane tank slab at west elevetion.
02905 Landscape Allowance
Exclusions:
1. Landscape and landscape irrigation system allowance of $44,000.
Proposed landscape will match existing landscape conditions.
1. All vehicle parking, bicycle and pedestrian traffic will use the existing
accommodations with the exception of the proposed modifications to
the south drive and two new sidewalks at the west elevation.
2. Gas and electrical service charges are assumed to be construction
credits and are therefore excluded from this scope.
3. Rock excavation requiring ripping or blasting, if encountered during
excavation. Including removal and disposal of unanticipated
obstructions :boulders, concrete, masonry, or other unforeseen
obstructions that cannot be removed by conventional earth moving
equipment.
4. Hazardous materials surveys or abatement.
Proposal to City of Fort Collins 5.2.9.3 — Page 5 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
5. Over excavation and replacement of unsuitable material or man
made fills.
6. Permanent fencing, retaining or decorative walls.
7. Soil stabilization with lime.
B. Tree re -location
9. Irrigation system re -location.
10. Storm drainage.
11. Re -location of Storage sheds.
12. Additional trash dumpsters and trash dumpster screening.
13. Owner will engage a qualified independent testing and inspecting
agency to sample materials, perform tests, and submit test reports
during excavation and concrete placement all site work.
Division 03 -- Concrete
Inclusions:
03110 Form & Place
1. Provide labor and materials to place all form -work, reinforcing steel,
and concrete materials for the following cast in place components:
A. Caissons.
B. Concrete wall panels.
C. Cast in place wall footings.
D. Cast in place walls for ice pit.
E. Slab on grade.
F. Cast in place header trench for ice sheet piping.
2. All concrete work shall have the appropriate control joints, expansion
joint material, and reinforcing steel required to complete these
elements of the project.
03150 Concrete Accessories
1. Provide required concrete accessories including anchor bolts, imbed
plates, water stop, void form, and expansion joint material as
required.
03210 &
03220 Reinforcing Steel
Provide required reinforcing rebar or welded wire mesh for the
following:
A. Caissons.
B. Concrete wall panels.
C. Cast in place wall footings.
D. Cast in place walls for ice pit.
E. Slab on grade.
F. Cast in place header trench for ice sheet piping.
Proposal to City of Fort Collins 5.2.9.3 — Page 6 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
03310 Concrete Material
1. Concrete materials in slabs, walls, foundations, including exterior
concrete shall be a minimum of 3000psi. and will conform to
specifications provided by structural engineer. Structural engineer
shall approve all final design mixes prior to concrete placement.
2. Provide required concrete material for the following:
A. Caissons.
B. Concrete wall panels.
C. Cast in place wall footings.
D. Cast in place walls for ice pit.
E. Slab on grade.
F. Cast in place header trench for ice sheet piping.
G. Curb and gutter.
H. Concrete pans (at mezzanine stair)
03350 Place and Finish
Provide labor, materials and equipment to place and finish the
following:
A. Caissons.
B. Concrete wall panels.
C. Cast in place wall footings.
D. Cast in place walls for ice pit.
E. Slab on grade.
E. Cast in place header trench for ice sheet piping.
F. Concrete pans (at mezzanine stair)
Saw cutting - All concrete work shall have the appropriate control
joints.
03370 Concrete Pumping
1. Provide mobilization, set-up, labor, and equipment to pump material
for concrete elements as required.
03390 Concrete Cure
1. Provide and apply concrete cure to all horizontal concrete surfaces
to control the rate at which concrete cures and provide optimum
strength. (slabs on grade & slabs on deck).
03410 Pre -cast Dynaspan Plank
1. Provide material, labor, and equipment to install pre -cast Dynaspan
plank system at mezzanine floor.
Proposal to City of Fort Collins 5.2.9.3 — Page 7 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
03430 Pre -cast Concrete Panels
Exclusions:
1. Provide mobilization, set-up, labor, and equipment to place and erect
exterior pre -cast concrete wall panels.
2. Provide material, labor, and equipment to install concrete dead -men
caissons for bracing at exterior concrete wall panels.
3. Subcontractor will be certified by the pre-cast/pre-stressed concrete
institute or possess equivalent credentials.
1. Special concrete mixes other than those specified by the structural
engineer for the concrete work shown on the drawings.
2. Owner will engage a qualified independent testing and inspecting
agency to sample materials, perform tests, and submit test reports to
inspect form -work and during concrete placement.
3. Special rebar coatings such as galvanized or epoxy coatings.
4. Floor surface hardeners.
5. Power steel trowels with non -slip swirls.
6. Floating isolation floors under mechanical equipment.
Division 04 — Masonry
Inclusions:
04220 Interior CMU Walls, Partitions & Infill
1. Provide labor, material and equipment to install concrete masonry
units (block) at interior walls, partitions and infill. Chamfered, radius
corners will be used at locations where chipping may occur due to
heavy athletic traffic and daily use.
2. Provide labor, material and equipment to inf ill masonry wall at
proposed locations where existing wall penetrations are to be
removed.
04810 Exterior Masonry Brick Veneer
Exclusions:
1. Provide labor, material and equipment to install masonry brick
veneer for wainscot and architectural features to complement the
existing facility.
1. Exact color match with existing brick veneer.
Proposal to City of Fort Collins 5.2.9.3 — Page 8 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N
Division 05 -- Metals
Inclusions:
E E N A N
05120 &
05210 Structural Steel Joists and Framing
1. Provide and install structural metal elements, framing, permanent
bracing and bridge members including the following:
A. Structural metal roof trusses.
B. Connections to existing and proposed load bearing walls.
C. Steel deck and bar joists.
2. Cut openings in metal roof deck for HVAC curbs, mechanical and
plumbing vents.
3. Provide, fabricate, and install steel framework in metal roof openings
for HVAC curbs, mechanical and plumbing vents.
4. Provide material and installation of permanent roof access ladder
and safety posts at structural metal roof.
05510 &
05520 Interior Steel Stair & Handrail
Provide and install steel stairs and handrails in the following
locations:
A. Concrete pan stairs with closed risers and associated steel
handrail for access to mezzanine.
B. Steel handrail system at mezzanine level and at handicap
viewing area.
05530 Metal Trench Cover
Exclusions:
1. Provide labor, material and equipment to fabricate and install steel
trench cover at header trench (ice piping trench).
1. Interior permanent stair to access roof (Roof equipment will be
accessed by fixed steel ladder and roof hatch).
2. Galvanized or stainless steel finishes not specifically mentioned.
3. Owner will engage a qualified independent testing and inspecting
agency to inspect steel members, fastener connections, weld
connections, and submit test reports during structural steel erection.
Division 06 — Carpentry
Inclusions:
06100 Rough Carpentry
Proposal to City of Fort Collins 5.2.9.3 — Page 9 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Proposed Our team will provide complete design services, including mechanical, electrical and
Team Scope of plumbing engineering, fire protection engineering, structural engineering, traffic
Services engineering, planning and landscape design services, and specialty consulting for the
ice rink and ice equipment package. The team will facilitate meetings with the Owner
and various user groups to understand and incorporate their requirements into a final,
functional design.
Our design personnel will facilitate all negotiations with the City for the development
review process, planning and building approvals, public presentations and
neighborhood meetings, and coordinate with Art In Public Places.
Our construction personnel will manage construction of the project to the stated
schedule, implement safety protocols for construction personnel and the public, and
insure timely completion to strict quality standards.
Image The proposed design consists of insulated painted pre -cast exterior concrete walls with
brick veneer wainscot and standing seam metal panel accents. Alternate materials
could be utilized, but we feel that the pre -cast concrete and brick will convey the sense
of permanence and timeless design desired, while complementing the existing facility.
The proposed floor plan creates more usable space in the existing facility, and
provides extensive storage space and additional locker room space in the expansion.
Practical public access and viewing space for handicapped users is also provided.
Flexibility/ The proposed design, consisting exclusively of concrete and/or brick masonry exterior
Durability and block masonry interior walls, provides an extremely durable facility and insures a
serviceable life exceeding 40 years. The floor plan provides maximum flexibility,
allowing for alternative room uses and multiple access control for users.
The building as proposed is approximately 30,000 square feet plus a mezzanine
seating area of 3,000 square feet, compared to the 27,144 square foot building
indicated in the RFP. The primary difference is in added storage areas and locker
rooms, as well as generous pedestrian circulation space. The five proposed locker
rooms are larger than those in the existing building, and are designed to allow
simultaneous use by both males and females. For additional convenience, the locker
room configuration allows for direct access to the player boxes in the existing facility.
The mezzanine seating area is currently designed for 200 people, and includes areas
for overflow spectator viewing, concessions and additional storage. The seating could
easily be increased by expanding into these areas, if desired. The handicapped
viewing area is currently shown in the southwest corner of the rink, to provide a full
unrestricted view of the rink area. If desired, this area could be located in the lobby, or
provided on the second level with the addition of an elevator. An option is included for
an elevator, should this be an option you wish to consider.
UsabiliryiSafe Primary access to the new facility will remain from the main lobby and behind the
Public access dasher boards on the south end of the existing rink. Other accesses are certainly
possible, but our preliminary estimates indicate them to be cost prohibitive or
impractical. To improve public access, mitigate safety issues, and maximize
operational efficiencies, we propose moving the Zamboni room to the north end of the
new facility and providing for both Zambonis in this location. This eliminates the
concern of pedestrian traffic across the Zamboni rink access, while combining
services.
Proposal to City of Fort Collins 5.2.3 — Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
1. Installation of all exterior and interior door frames and doors.
2. Provide rough carpentry labor, material and equipment for interior /
exterior blocking, backing and supports as required.
3. Provide rough carpentry labor, material and equipment to install
raised platforms at players benches and handicap viewing area.
06110 Wood Framing - Roof & Parapet
Exclusions:
1. Provide labor, material and equipment to install wood blocking for
metal parapet cap at exterior wall conditions and minor sheathing for
metal canopy at west elevation.
1. Wood railing, chair rail, base, casing or paneling.
2. Built in cabinetry or casework.
Division 07 -- Thermal and Moisture Protection
Inclusions:
07110 Dampproofing
1. Provide labor, material and equipment to apply bituminous
dampproofing at below grade foundation structures and concrete
wall panels.
07120 Water proofing
1. Provide labor, material and equipment to apply water proofing
membrane at header trench (ice piping trench).
07210 Insulation
1. Provide labor and material to install 2" rigid insulation to a minimum
depth of 36" at exterior foundation walls and concrete wall panels as
required.
2. Provide labor and material to install (2) layers of 1.5", 25psi.
polystyrene rigid insulation ice rink floor system.
07530 EPDM Roof
1. Provide labor, material and equipment to install 45 mil EPDM
ballasted single ply membrane roof system with 15 year warranty.
Roof insulation will consist of a one layer of R19, polyisocyanurate
insulation.
2. Roof drains will be located approximately 40' on center.
3. Roof system will use pavers to access roof top equipment.
Proposal to City of Fort Collins 5.2.9.3 —Page 10 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
07610 &
07620 Sheet Metal Roofing
1. Provide labor, material and equipment to install standing seam,
sheet metal roofing and associated flashing at sloped roof conditions
and architectural vertical elements. Pre -finished colors to match
existing facility.
07720 Roof Hatch
1. Provide labor, material and equipment to install roof hatche for
access to roof top units.
07810 Fire Proofing and Fire Safe
1. Provide labor, material and equipment to apply fire proofing and fire
safe materials required to meet code.
07920 Sealant - Exterior
Exclusions:
1. Provide labor, material and equipment to apply all exterior sealant
compounds at joints and connections to provide weather tight
construction as required.
1. Custom colors for pre -finished metal flashing or roofing.
2. Any membranes required to reach manufacturers specified vapor
emissions of concrete coatings.
3. Custom colors for sealant compounds.
4. Sound attenuating insulation or sound masking.
Division 08-- Doors, Windows, Glazing
Inclusions:
08110 Metal Doors & Frames
1. Hollow metal doors and frames will be provided and installed at all
interior and exterior door locations. Hollow metal doors and frames
will have painted finish.
2. Interior doors at locker rooms will be a minimum of 316" wide to
accommodate athlete traffic carrying oversized equipment bags.
3. Doors will be rated as required by code.
Proposal to City of Fort Collins 5.2.9.3 — Page 11 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
08360 Overhead Doors
1. Provide labor, material and equipment to install motor operated,
overhead, steel roll -up doors at the north zamboni room(1 @ 16' x
12', 2hr. rated) and the south storage room(2 @ 10' x 14'). Overhead
doors will have painted finish.
2. Provide labor, material and equipment to remove and reinstall
existing 16' x 18' overhead door on west wall to the proposed
location adjacent to new zamboni room.
08410
& 08510 Exterior Storefront & Interior Hollow Metal Windows
1. Exterior storefront window system shall be insulated glass installed
in aluminum storefront frames with standard pre -finished color to
match existing facility.
2. Interior window systems shall have wired glass installed in HIM
frames with finish to match doors and door frames.
08710 Exterior & Interior Door Hardware
1. Hardware will include commercial grade hinges, passage sets, lock -
sets and closures. Hardware shall meet A.D.A. requirements.
2. Exterior doors will have keyed locks.
08720 Weather Stripping / Seals
Exclusions:
1. All exterior doors will have weather stripping and seals as required to
provide weather tight construction.
1. Daylighting.
2. Folding partition doors.
3. Sound attenuating insulation.
4. Keyless entry devices.
5. Window coverings.
Proposal to City of Fort Collins 5.2.9.3 — Page 12 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Division 091 — Framing & Drywall
Inclusions:
09250 Gypsum Board Ceiling
Exclusions:
1. Provide labor, material and equipment to frame and install gypsum
board ceiling and soffit with metal studs over mezzanine. Gypsum
board ceilings will be constructed in accordance with UL Fire
Resistance listings as required. Drywall will be type "X" with a
minimum thickness of 5/8".
1. Special wall coverings or finishes.
2. Sound attenuating insulation or sound masking.
Division 095 — Ceiling Finishes
Inclusions:
09510 Acoustical Ceiling — 2x4
Provide labor, material and equipment to install 2' x4' lay -in
acoustical ceiling tile system at officials room and multi -purpose
room.
09910 Paint Interior
Exclusions:
1. Provide labor, material and equipment to apply paint to gypsum
board ceiling and soffit above mezzanine (spectator seating).
2. Provide labor, material and equipment to apply epoxy paint to interior
exposed structural steel ceiling conditions.
1. Sound attenuating insulation.
2. Special finishes other than noted above.
Proposal to City of Fort Collins 5.2.9.3 —Page 13 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Division 096 — Floor Finishes
Inclusions:
09650 Rubber Flooring
1. Provide labor, material and equipment to install Tuflex resilient
rubber flooring at slab surrounding ice rink and at locker rooms.
Tuflex is a recycled rubber flooring that is made from vulcanized
recycled rubber.
09650 Rubber Base
1. Provide labor, material and equipment to install standard 6" rubber
base at floor perimeter in public use areas.
09670 Floor Finishes
Exclusions:
Provide labor, material and equipment to apply seamless epoxy floor
finish at shower areas.
1. Special patterns, colors, or profiles associated rubber flooring and
epoxy finishes.
2. Recessed floor mats or frames.
Division 097 — Wall Finishes
Inclusions:
09910 Paint
1. Provide labor, material and equipment to apply Texcoat finish at
exposed exterior concrete panels.
2. Provide labor, material and equipment to clean, prepare and tape off
wall surfaces where finishes are to be applied.
3. Provide labor, material and equipment to apply block filler plus two
coats of epoxy finish at interior CMU wall surfaces.
4. Provide labor, material and equipment to apply one primer coat and
two coats epoxy paint at interior concrete wall surfaces.
5. Provide labor, material and equipment to sand and apply two coats
of oil based enamel paint to all hollow metal doors, door frames and
miscellaneous exterior metals.
Proposal to City of Fort Collins 5.2.9.3 — Page 14 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
Exclusions:
N E E N A N
1. Wall coverings.
2. Spray on vinyl.
3. Special wall finishes.
4. "Green" sustainable type paints or coatings.
5. Budget for Art in public places.
Division 10 — SDeciatlies
Inclusions:
10150 Restroom Compartments
1. Provide labor, material and equipment to install floor -supported,
standard color compartments / partitions for toilets including
hardware and accessories.
10440 Interior Signage
1. Provide labor and material to install interior identifying signs as
required for Certificate of Occupancy.
10500 Employee Lockers
1. Provide labor and material to install standard size metal lockers at
employee entrance (south storage room).
10520 Fire Protection Specialties
1. Provide and install (5) surface mounted fire extinguisher cabinets
and fire extinguishers.
10810 Toilet and Locker Room Accessories
Provide labor, material and equipment to install the following
toilettlocker room accessories:
A. Handicapped grab bars
B. Toilet tissue dispensers.
C. Trash receptacles.
D. Feminine napkin dispenser.
E. Feminine napkin receptacle.
F. Vanity mirrors.
G. Robe hooks.
H. Locker room bench system to match existing.
I. Athletic equipment hooks around the perimeter of locker rooms.
Proposal to City of Fort Collins 5.2.9.3 — Page 15 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
Exclusions:
N E E N A N
1. Interior signage except as required for Certificate of Occupancy.
Division 110 — Equipment
Inclusions:
11480 Athletic Equipment
1. Ice Package — Provide labor, material, and equipment to install the
following:
A. Artificial ice refrigeration system - for a year round ice plant that
will utilize ammonia as a primary refrigerant and calcium chloride
as the secondary refrigerant. This plant will be a 114 Ton
capacity system operating at 90F condensing temperature. The
major components of this system include two heavy-duty
industrial compressors, a flooded shell and tube chiller, and an
evaporative condenser.
B. Operating and maintenance instruction.
C. Electrical system and controls.
D. Detection and safety equipment.
E. Computerized control system.
2. Ice rink floor system (Sand) — Provide labor, material, and
equipment to install the following:
A. Start-up and installation of initial 1.5" sheet of ice.
B. Cold floor including cooling pipes, cooling pipe chairs and 3.5" of
sand.
C. 3" of 25psi polystyrene insulation.
D. 6 Mil vapor barrier.
E. Warm floor including warming pipes and 8" of sand.
F. 3" of compacted base material.
G. Concrete header trench including warm and cold header pipes,
header pipe supports, insulation, and flush cover. Proposed
header trench will extend to existing west wall to allow for future
retrofit connection to existing sheet of ice.
H. 1.5' deep turn down w/ rigid insulation barrier at ice rink
perimeter to provide structural base for dasher boards system
and retention of ice rink floor system.
3. Dasher Board System — Provide labor, material, and equipment to
install the following Becker dasher board system:
A. 1/4" hot dipped galvanized welded steel frame for lower dasher
board. 50 Mil poly plastic is slotted and fastened to the steel
frame with through bolts allowing expansion and contraction of
the poly to occur without shearing off the fasteners.
B. Clear acrylic panels will be used around the perimeter. Clear
acrylic panels will 6' at the ends and radius sections with 4' at the
sides.
C. Doors to be installed in the dasher board perimeter include 2 for
player benches, 2 for penalty boxes, 2 @ 5' for equipment, and 1
adjacent to entry for public access.
D. Side partitions between player benches and penalty boxes.
Proposal to City of Fort Collins 5.2.9.3 —Page 16 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
Exclusions:
N E E N A N
1. Furniture.
2. Ice resurfacer.
3. Scoreboard.
4. Clock.
5. Spectator seating.
Division 131 — Fire Protection
Inclusions:
13910 Fire Sprinkler System
Exclusions:
1. Wet pipe system throughout entire addition.
2. New zone valve assembly including flow and tamper switch located
in existing chiller room near existing fire service.
3. Design based on light hazard occupancy for arena, office locker and
first aid rooms.
4. Ordinary hazard occupancy in storage rooms.
5. Brass upright sprinklers in areas of exposed construction.
6. White semi recessed sprinklers in areas having suspended ceilings.
7. Head guards on all sprinklers in arena.
1. Electric wiring for new flow and tamper switches at wet system riser
and new air compressor at dry system.
2. Ceiling removal and replacement at existing building.
3. Stand pipe system,
4. High piled storage criteria.
5. Fire hydrants.
Division 15 — Mechanical
Inclusions:
15050 HVAC Systems
1. Arena HVAC
A. Furnish and install one 15,000 cfm packaged dessicant
ventilation dehumidification unit, mounted on the low roof above
the storage/staging area. The unit will include the following
features:
1. natural gas reactivation system in the dessicant rotor
2. Post heat natural gas furnace (facility heat)
3. Modulating outside and return air dampers to allow a full
range of mixed air, including economizer or "free cooling"
capability
4. Full microprocessor controls and DDC connection points
Proposal to City of Fort Collins 5.2.9.3 — Page 17
Second Sheet of Ice at EPIC (P-812)
November 28, 2001
N E E N A N
5. Communication capability for temperature and humidity
control
B. Extend supply air duct into upper level in the south end of the
arena. The duct will split, with a branch routed to either side of
the ice rink. The supply air will discharge at the south end of the
arena.
C. Route return air from the unit into the upper level of the arena.
The return air will be taken in above the center of the ice rink.
D. Furnish and install a 7500 CFM exhaust fan at the north end of
the arena. Placement of this fan will also assist in drawing the
supply air through the facility.
E. Route an additional supply air branch duct from the air handler
into the locker room areas. These areas will be 100% make-up
and exhaust.
F. Furnish and install an exhaust fan and duct for the locker
room/office areas.
G. Connect a new heating hot water loop to the existing in the
existing mechanical room. We will furnish and install a booster
pump and all necessary hydronic accessories and control
interlocks for a complete system.
H. Route heating hot water piping to reheat coils (6 each) in the
ductwork serving the locker rooms/offices indicated by item 5.
2. Viewing area HVAC
A. Furnish and install two each 60' long infrared radiant tube
heaters above the front of the elevated viewing area
B. Radiant heaters will be gas fired, with flues through the roof.
C. Reflectors will be directed toward the occupied viewing area,
away from any contact with the ice surface.
3. Multi -Purpose Room HVAC
A. Furnish and install a separate, stand alone gas fired packaged
DX cooling HVAC unit
B. Route supply and return ductwork to grilles and diffusers in the
lay -in ceiling
C. Furnish and install setback thermostat or tie into building
automation system as required.
4. Other Areas
A. Extend hot water heating loop to hydronic unit heaters in the
staging area and employee entrance; and the zamboni room and
storage room adjacent to the ice equipment room.
B. Furnish and install louvers and exhaust fans to ventilate the ice
equipment room.
5. Miscellaneous
A. Engineering and design for HVAC systems
B. DDC control tie in to the customers existing Johnson Control
system
C. Air and water balancing
Proposal to City of Fort Collins 5.2.9.3 —Page 18 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Exclusions:
15400 Plumbing System
Inclusions:
1. Provide labor, material and equipment to install the following:
A. 4-WC-1 Regular water closet floor mounted flush valve
type
B. 3-WC -1 Handicapped water closet floor mounted flush
valve type
C. 8-L-1 Ada lavatory with metering faucets
D. 11-SH-1 Shower drain and metering shower valve
E. 1-P-1 Domestic hot water re -circulation pump
F. 1-SC-1 Sillcock
G. 6-FD-1 Floor Drain
H. 1-IMP-1 Ice melt pit (hook up only)
I. 10-RD-1 6" roof drain
2. Tie into existing drain waste vent and water piping for complete and
operating plumbing system.
3. Engineered drawings.
4. Insulation of domestic water.
5. Gas piping from meter to equipment.
6. ADA required fixtures.
7. Insulation of horizontal roof drain piping.
8. Interior roof drainage system.
Exclusions:
1. Solar heating for hot water heating.
2. Drain at header trench.
Division 16 — Electrical
Inclusions:
16050 Electrical System
1. FIRST FLOOR LIGHTING
A. At the lobby entrance, we will install Six (6) recessed fluorescent light
fixtures. These fixtures will be controlled at the panel.
B. At the mechanical rooms, Zamboni Room and storage areas, we will
be installing 4' and 8' surface mounted fluorescent strip light fixtures.
The fixtures at the Mechanical Room will be controlled via local
single pole switching, while the ones if the Zamboni Room and the
Storage Rooms will be controlled with a motion sensor.
C. At each of the four locker rooms, we will install four (4) 1 x4 surface
mounted fluorescent light fixtures controlled by local motion sensors.
Proposal to City of Fort Collins 5.2.9.3 — Page 19 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Additionally, the new refrigeration equipment room, as well as the equipment and utility
services, is designed to be up -graded to service both rinks, at such time as the existing
ice package needs to be replaced. At this time, the existing ice plant could be
removed, which would allow for construction of a hallway from the existing lobby to the
second sheet of ice thru the current mechanical equipment room, and provide a better
permanent solution for access.
Energy
The Neenan Company is a leader in Energy Efficiency and Sustainable Design
Efficiency/
applications, as is evidenced in representative local projects such as New Belgium
sustainability
Brewery, City of Fort Collins Office Building, Latimer County Sheriff Administration
Building, and Value Plastics. We utilize sustainable design applications on nearly
every project we do. Our focus is on the six general areas used by L.E.E.D.
(Leadership in Energy and Environmental Design) developed by the U.S. Green
Building Council.
A more complete description of our utilization of Green Building Design is included in
Section 5.2.5, "Project Experience and Qualifications".
Building
The commissioning of the project is specifically addressed in Section 5.2.13. A
Performance/
complete commissioning report will be provided upon project completion. In addition,
Commissioning
Neenan provides to all it's clients an Ownership and Maintenance (O & M) Manual at
project completion, which defines all warranties, start-up and maintenance protocols,
materials and suppliers, and related information.
Life Cycle
With our Archistruction® process, life cycle cost analysis of various building systems
Costs
and components is continuous and on going throughout the development of design
and even into construction. Typically, in the weekly project meetings the team will
identify options to be evaluated, then present research and recommendations at the
subsequent meeting. Depending on the complexity of the project, literally hundreds of
options may be evaluated for short-term versus long-term benefit, responsible
sustainable design considerations, and performance.
This process will really begin with our initial meetings with you, where we can begin to
identify your specific concerns and desires, and suggest options to you to be further
investigated. The process is of little value without your input. However, we have
developed several mechanical and electrical studies on possible life cycle options for
EPIC, as samples, for your consideration. These samples are included in the
Appendix.
Proposal to City of Fort Collins 5.2.3 - Page 3 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
D. In the bathrooms, we will provide one (1) wall mounted fluorescent
light fixtures above each sink and stall. For additional illumination,
two (2) recessed fluorescent cans will be installed in the ceiling at
the walk-through area. The lighting in these areas will be controlled
by motion sensors.
E. Each of the shower areas will be lit with three (3) recessed
fluorescent cans that are rated for a damp location installation.
F. The Referee Room will be illuminated in the same fashion as the
locker rooms and bathrooms indicated above.
G. The First Aid Room and the Office will be lit with 2x4 recessed
fluorescent fixtures controlled locally with single pole switching.
H. Above each of the new building entries, we will install one (1) 100W
HID wall pack above the man -door. These will be controlled with a
photocell, timeclock and relay for operation after dark.
I. Universal LED exit signs will be installed in accordance with code
requirements. The selection of LED light source will conserve
energy.
J. Emergency egress lighting will be accomplished via battery powered
surface mounted frogeye fixtures.
2. SECOND FLOOR LIGHTING
A. At the bleacher area, we will install fourteen (14) 1 x4 recessed
fluorescent light fixtures for general public lighting. These will be
locally controlled via two (2) three-way keyed switches.
B. The storage area will be illuminated via three (3) 4' fluorescent strip
fixtures surface mounted on the ceiling. These will be locally
controlled with a motion sensor.
C. At the landing of each stairwell, there will be a 4' wall bracket
fluorescent light fixture.
D. Universal exit signs will be installed in accordance with code
requirements. The selection of LED light source will conserve
energy.
E. Emergency egress lighting will be accomplished via battery powered
surface mounted frogeye fixtures.
3. BASE ICE RINK LIGHTING
A. The base lighting system for the ice rink will be installed to match the
lighting in the existing facility. This system is twin head 400W metal
halide high bay light fixtures. These fixtures will be installed at 25'
above the ice surface, which will provide a light level of
approximately 100 fc average.
4. ELECTRICAL DISTRIBUTION EQUIPMENT
A. Upon our physical inspection of the existing switchgear, there is
adequate capacity to add devices to accommodate this expansion.
B. We will add two (2) circuit breakers to the existing switchboard. One
will be rated at 480V 3PH 400A and the other at 480V 3PH 600A.
These circuit breakers will feed the distribution equipment for this
expansion.
C. A 480/277V Panel rated at 400A will be installed in the existing Multi -
Purpose Room. This panel will feed a 30KVA transformer to a
Proposal to City of Fort Collins 5.2.9.3 — Page 20 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
120/208V 100A Panel. The feed for this equipment will be installed
underground.
D. A 480/277V Panel rated at 600A will be installed in the new Ice Plant
Room. This panel will feed a 30KVA transformer to a 120/208V 100A
Panel. The feed for this equipment will be installed underground
partially under the ice sheet.
5. FIRST FLOOR POWER
A. Standard commercial grade 20A flush mounted wall receptacles will
be installed as convenience power so any area can be reached with
a 50' extension cord.
B. In the Mechanical Rooms, Zamboni Room and Storage Rooms,
appropriate commercial grade receptacles will be installed for the
application. We have not anticipated any specialty receptacles will be
necessary.
C. In the bathrooms, one (1) GFI protected receptacle will be installed
above each countertop. At this time, we have not anticipated that
there will be any other power requirements (hand driers, etc.)
6. SECOND FLOOR POWER
A. At the bleacher area, we have included the installation of four (4)
double -duplex receptacles for convenience power. No other work is
anticipated in this area.
7. ICE RINK POWER
A. In accordance with the information provided, we have anticipated
that the Ice Equipment will be installed complete on a self-contained
skid. Our electrical connection will be rated at 480V and 400A. We
will install the appropriate electrical feed for this equipment, a 400A
HD disconnect switch and a single point connection rated for a
weatherproof situation.
B. In addition to the above Ice Equipment, we have included the
electrical connection to two (2) pumps, one rated at 5HP in the same
room as the skid and one rated at 15HP which will be installed on the
roof of this area.
8. MECHANICAL SYSTEMS
A. Two (2) Roof Top Units rated at 15HP each. These will be installed
over the Storage Rooms at either end of the ice sheet.
B. One (1) Roof Top Unit rated at 5 ton installed above the Multi -
Purpose Room
C. Four (4) local Exhaust Fans, one installed over the ice, one in the Ice
Equipment Room and two for the Locker Roomlroilet areas.
D. Two (2) 3HP Circulation Pumps located in the existing Mechanical
Room.
E. One (1) fractional horsepower pump for the Glycol System installed
in the Mechanical Room.
F. Six (6) Unit Heaters installed at various locations throughout the
building expansion.
G. Two (2) 120V Control Voltage connections.
Proposal to City of Fort Collins 5.2.9.3 — Page 21 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
9. SOUND SYSTEM ALLOWNCE
Exclusions:
A. A Sound System is a part of the design narrative for this project, but
is not clearly defined at this point. Sound system is being carried as
a $30,000 allowance.
1. PI lamps for incandescent fixtures.
Plan Check Fees and Buildinq Permit
1. All new construction, additions, alterations of existing buildings,
demolition of existing buildings, and awnings attached to commercial
buildings require the payment of a plan check fee and acquisition of
a building permit prior to the start of construction.
2. The City of Fort Collins cost of plan check fees and building permits
is based on the valuation of construction. Fees are determined by
using the plan check and building permit fee schedule provided by
the City of Fort Collins.
Performance Bond
1. Performance bond per RFP requirements.
General Liability & Builders Risk Insurance
1. General Liability Insurance.
2. Builders Risk Insurance.
Construction Contingencv
1. Construction Contingency value is based on 3% of the estimate
value.
Summary of Allowances
1. Landscape Allowance $44,000
2. PA system $30,000
3. Design Reimbursables $13,000
& Printing Allowance
Proposal to City of Fort Collins 5.2.9.3 — Page 22 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
5.2.10.1 SCHEDULE NARRATIVE
The preliminary schedule which follows represents our current estimate of design
duration, City of Fort Collins approval process, and construction activities and duration.
It is based on our knowledge and past experience with the described activities on
projects of similar scope. For this schedule, we have assumed that the City of Fort
Collins staff will follow a minor amendment approval process, with no special
consideration for this project.
The Planning/Engineering and Building Department process with the City of Fort
Collins is driving the start date of the project. Anything we can do to accelerate the
initial submittal will improve the planned construction start date. Obviously, the more
quickly an acceptable design is approved by the Owner, the sooner we can begin the
review process.
The schedule as presented exceeds your expectation to be complete by August 2003.
We have completed many similar projects over the years and this schedule is aligned
with what we would expect in working through the City process and design and
construction activities required on this project. Our current completion date is January
3, 2003.
This schedule represents our honest assessment of durations for the various project
activities, but we will focus on improving on the dates shown. One of our first actions
will be to meet with the City staff, lay out their specific requirements and timelines, and
coordinate our activities to facilitate their process. Concurrently, we will work
aggressively with you to finalize a building design with the goal of allowing us to submit
as early as possible for City review.
The Collaborative Design Process (CDP), which is described in the Appendix, Section
5.2.15, can save weeks in this process. This process will help our team to move the
project through the City process in the most expeditious manner and possibly
accelerate the schedule to achieve an earlier completion date.
Proposal to City of Fort Collins 5.2.10.1 -Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
Task Name
CITY MILESTONE SCHEDULE PER RFP # P-812
Submit Proposal
Finalist Interview
City Council Approval / Appropriation
City Council Approval / Appropriation
Notice to Proceed
Preliminary Design and Cost Estimate
City Planning Approval
Complete Final Design
Owner Occupancy
NEENAN PROPOSED DESIGN AND PERMITTING PHASE
General Design Criteria
Core and Shell Space Coordination
Foundation Coordination (elev 100)
Site Coordination
Structure Coordination
Skin Coordination
PLANNING/ENGINEERING APPROVAL PROCESS
BUILDING PERMIT PACKAGE
BUILDING DEPARTMENT PROCESS
NEENAN PROPOSED CONSTRUCTION PHASE
Pre -Construction Activities
Site / Exterior Building
Foundations
Structure
MOD 1 - Interior 1st Floor
MOD 3 - Ice Sheet and Ice Equipment Room
MOD 2 - Interior 2nd Floor
NEENAN PROPOSED C/O (Sharpen the Skateslll)
Duration I Start I Finish
428 days
11/29/01
8/5103
1 day
11/29/01
1129/01
1 day
12/17/01
12/17/01
1 day
1/15/02
1/15/02
1 day
2/5/02
2/5/02
1 day
2/15/02
2/15/02
1 day
524/02
524/02
1 day
7/3/02
7/3/02
1 day
7/31/02
7/31/02
1 day
8/5/03
8/5/03
101 days 2/18/02 7/11/02
25 days
2118102
3/22/02
37 days
2118102
4/9102
23 days
2118102
3/21/02
23 days
2119102
3/21/02
26 days
2/19102
3/26/02
31 days
3/4/02
4115/02
80 days
3/5/02
6/25/02
10 days
4/16102
4/29102
50 days
4/30102
7/11/02
127 days 6/28102 112103
11 days
6/28/02
7/16/02
72 days
7112/02
10/22/02
27 days
7/22/02
8127/02
36 days
8112/02
1011102
62 days
8/21/02
11/15/02
86 days
8/28/02
112/03
47 days
9/17/02
11/20/02
0 days 1/3103 1/3/03
Epic Ice Rink Addition
Fort Collins, Colorado
Jov Dec Jan Feb M
j 11129
♦ 12/17
♦ 1115
r 215
♦ 2/15
Dec
1/3
Feb
I Jul I Aug I
5.2.10.2-Page 1
N
E N A N
5.2.11 PROPOSAL SECURITY
The proposal security is provided in the form of a certified check, under separate
cover.
Proposal to City of Fort Collins 5.2.11 —Page I November 28, 2001
Second Sheet of Ice at EPIC (P-812)
No Text
N E E N A N
5.2.12.1 DESIGN STATEMENT
Architectural The proposed solution is intended to compliment the clean massing of the existing
Image facility and meet the new City of Ft. Collins design criteria. The addition uses existing
design components, new complimentary components and increased massing elements
to accomplish this.
Brick similar in color to that on the existing building (which is no longer available), and
metal panels to match the existing are blended with the new design materials of heavy
texture painted pre -cast panels.
Additional massing steps, screening and architectural metal roofing are added to the
north elevation to reduce the scale and break up this elevation per the new code.
Functionally, the internal functions in this "bumped out" area eliminates cross traffic
between pedestrians and Zambonis, and facilitates replacing the existing ice slab
when required in the future.
The east elevation uses new design canopy elements to create the pedestrian scale
along Riverside Avenue and vertical column elements to break up this elevation per
the new city code. Functionally these plan offsets create a deeper coach's box. The
south elevation continues the architecture of the existing building's massing steps.
Function The proposed solution addresses several issues that are concerns on the existing RFP
floor plan. Most importantly is the separation of the Zamboni equipment from the
pedestrian access to both the existing and new slabs of ice. This makes for a much
safer rink. The refrigeration room has been located at the north end of the rink, which
separates the trench cover from the primary pedestrian access.
The locker areas have been increased approximately 8' in the east west dimension.
This provides for adequate sized locker rooms for adults, individual showers in lieu of
gang showers, four showers in lieu of two showers for each pair of locker rooms, and
fifth locker room specifically for women's use. The elimination of a mezzanine
overhang of the walkway adjacent to the ice allows for improved mezzanine viewing of
the ice slab.
Additional storage spaces have been added, including freeing the existing Zamboni
room for storage as well as providing two new storage rooms in the addition. We are
providing a total of 3,456 S.F. of new storage space.
A raised handicap accessible viewing platform has been included at the southeast
corner of the rink. Given the possible concern regarding segregation of handicapped
spectators, this area could easily be located adjacent to the lobyy if preferred. An
option has also been provided for the addition of an elevator if handicapped access to
the mezzanine is preferred. This would be our recommendation, if budget allows.
We have added a single fixture water closet in the multi -purpose room to make it self-
contained for the birthday or team parties.
We have added a restroom for the officials adjacent to their office/changing room.
Proposal to City of Fort Collins 5.2.12.1— Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Future The refrigeration room is sized for the future equipment, so when the existing slab is
planning converted to a sand bed the trench cover will also be located away form the primary
pedestrian route. We have extended the trench in the expansion to the existing east
wall of the existing ice slab for ease of extension. By locating the refrigeration room at
the north end of the building future pedestrian access during the replacement of the
existing ice slab will permit continued internal pedestrian access to the new ice slab.
Once the existing ice slab is replaced and the existing refrigeration equipment is
removed, we recommend creating an enclosed hall through the old equipment room,
connecting the existing lobby to the east end of the existing Zamboni room. This
would help the current situation, which provides access to the new facility through a
relatively narrow aisle behind the boards by creating a wider enclosed walkway behind
the existing masonry wall.
Proposal to City of Fort Collins 5.2.12.1 — Page 2
Second Sheet of Ice at EPIC (P-812) November 28, 2001
T H E.
FUTURE
PARKING AREA
N E E N A N C O
SECOND SHEET OF ICE A
.. TNC -h
Nov. 29, 2001
in association with GllttCallahan Architects. Inc.
N E E N A N
1
PmjeGNM80p
Ica
In
Daelan
Wgn I
I
I
Chan
Oscan AmM
Pogacl Cmplsin
Callahan
Robert Hoeanne
Banthe
Jon Van BenMe
Proposal to The City of Fort Collins
Second Sheet of Ice at EPIC
DONE
EPIC
Ice Rink
Team Organization
Construction
Q"
Sedw Project Mon@W
Bob Me m
"Bums
"Mika
Pmleot Msnsax
A'emietructlon
Superirnenoem
Tim Stem
Steve
Mesa
nESe�N "R` '•i ��`F•
eJe¢ ., (AlIe1B19E
IieIE0e
MxhOngal Eletlrle 41mCnnwftaM
5.2.4.1 - Page 1 November 28, 2001
T H E N E E N A N
Edging
jce nk
MEZZANINE PLAN
SULE: 146'=t'-0'
3.496 SQUARE FT
')POSED SECOND ICE PLAN
�6'=1'-0" 33J025Q. FE TOTAL
10
10 ]0
SECOND SHEET OF ICE A
TNC -Nov. 29th- 2001
In ass. c latlon with Gil(illanallahan Architects, Inc.
O.H. � Trans area
FM
TNG - Nov. 29th, 2001
in assodatton with Giltillan-Callahan Architects. Inc.
T H E N E E N A N
fth
PROPOSED ELEVATIONS
NOT TO RACE
-
SECOND SHEET OF ICE A
6'd"
Brick vent o—
Mad,enioll riem
,vond —
pt,sl conuEe
panel
TNC -Nov . 29tha 2001
In association with Gilfillan -Calla Xan Architect'. Inc.
B lwadl si 81 PH
invnerane.mf
PROPOSED
E%ISTING
EXPANSION
BUILDING
New bean and
mlumnline
EA,dnB wall
}
l�l b enparlid
ea
bearin8 contlltim
to renan---
by
/
�otnan
,Yrface
@ BUILDING SECTION_
NOT TO SCALF
Rod aloe
A
ailing steel roof i ' C
`Painted cont.
® panels
Players
PR POSED HE_ET2
Iw/ nsula=d bed
(2� BUILDING SECTION_
NOT TO SChIF
g1Nall Panels
000
SECOND SHEET OF ICE AT
T H E N E E N A N
SECOND
TNC - Nov. 29th, 2001
in association with Gilfillan-
Callahan Architects, Inc.
t l� NORTH PERSPECTVE
QSOUTH PERSPECTIVE
C O M
P A N
Y
r
. nNO�HEAST PERSPECTIVE
SHEET OF ICE AT
5.2.12.7
Existing
N E E N
A N
BUILDING CODE STUDY
Total SF 71,292 SF (first floor) + 12,570 SF (mezzanine) = 83,862 SF approx.
Uses Assembly (pool, ice rink and seating) A 2.1 67,089 approx
Offices, storage, lockers, lobby, equipment rooms B 16,773 approx
Actual stories I
Construction type II — 1 hour
Allowable area per 1997 UBC
increase for separation*
total
increase for sprinkler**
total
A 2.1
B
13,500
18,000
x 2
x 2
27,000
36,000
x 3
x 3
81,000
108,000
Mixed use calculation 67,089 + 1LM = .828 + .155 = .983 < 1 (existing building is ok,
81,000 108,000 but no expansion SF capacity)
Based on the above information, the new expansion must be separated from the existing building by a
2 hour separation wall, per UBC section 504.6.
* per 505.1.2
** per 506.3
New Total SF
Uses
Actual stories
Construction type
29,806 SF (first floor) + 2,496 SF (mezzanine) = 32,302 SF approx.
Assembly (ice rink and seating) A 2.1 28542 approx
Offices, storage, lockers, multipurpose, equip rooms B 3,760 approx
Allowable area per 1997 UBC
increase for separation*
total
increase for sprinkler**
total
A 2.1
B
13,500
18,000
x 2
x 2
27,000
36,000
x 3
x 3
81,000
108,000
1
II — 1 hour
Mixed use calculation 24.000 + 3.760 = .296 + .035 = ..331 < 1 (building is ok)
81,000 108,000
Based on the above information, the new expansion must be separated from the existing building by a
2 hour separation wall, per UBC section 504.6.
* per 505.1.2
** per 506.3
Proposal to City of Fort Collins 5.2.12.7 — Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
5.2.13 PROPOSED COMMISSIONING PLAN
Background The Neenan Company as leader of the design/build team will contract with a
Commissioning Agent to perform a commissioning process in order to ensure that
the building complies with all of the Owner's requirements.
Commissioning Commissioning is a systematic process of ensuring that the building systems
Goats and perform according to the design intent and the owner's operational requirements. All
Objectives equipment and systems should be installed according to manufacturer's
recommendations and the best practices and standards of the industry.
Commissioning will include documenting the design intent, followed by activities in
the construction, acceptance, and warranty phases of the project. The three main
goals of the commissioning process are:
• Facilitate the final acceptance of the project at the earliest possible date.
• Facilitate the transfer of the project to the City maintenance staff through
improved operations and maintenance documentation and training.
• Ensure that the comfort, lighting, and safety systems meet the requirements of
the occupants.
Commissioning is also intended to achieve the following specific objectives:
• Document that equipment is installed and started per manufacturer's
recommendations.
• Document that equipment and systems receive complete operational
checkout by installing contractors.
• Document system performance with thorough functional performance
testing and monitoring.
• Ensure that operations and maintenance documentation left on site is
complete.
• Ensure that the building operating personnel are adequately trained on
the operation and maintenance of building equipment.
Verify the documentation of as -built description of system operation and
performance.
Commissioned The following systems will be commissioned in this project.
Systems
• HVAC components:
• Roof Top Units
• Exhaust Fans
• Cabinet Heaters
• HVAC system: interaction of cooling, heating, and comfort delivery systems
• Building Automation System (BAS): control hardware and software, sequence of
operations, integration of factory controls with BAS
• Interior lighting controls
• Fire alarm and detection system
Proposal to City of Fort Collins 5.2.13 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
General General descriptions of the commissioning roles are as follows:
Descriptions of
Roles • Commissioning Agent: Coordinates, directs, and documents the commissioning
process.
• General Contractor: Facilitates and supports the commissioning process, ensures
that subcontractors perform their responsibilities and integrates commissioning
into the construction process.
• Subcontractors: Demonstrate correct system performance.
• Operations Staff: Participate in commissioning tasks and performance testing,
review O&M documentation, attend training.
• Architect, Mechanical/Electrical Engineer: Assist in resolving issues identified
through commissioning activities.
■ Manufacturers and Vendors: Provide documentation to facilitate commissioning
activities, perform contracted startup and participate with functional testing.
Commissioning This section sequentially details the commissioning process by commissioning task
Process or activity.
Commissioning The scoping meeting brings together all members of the design/build and owner
Scoping Meeting team that will be involved in the commissioning process. Each building energy
system to be commissioned is addressed, including commissioning requirements,
and completion and start-up schedules. During the scoping meeting, all parties
agree on the scope of work, tasks, schedules, deliverables, and responsibilities for
implementation of the Commissioning Plan.
Final The commissioning agent finalizes the draft Commissioning Plan using the
Commissioning information gathered from the scoping meeting. The initial commissioning schedule
Plan is also developed along with a detailed timeline. The timeline is fine-tuned as
construction progresses.
Design Intent The design requirements, relative to the building systems selected for
Documentation commissioning, must be explicitly documented in order to establish a baseline of
performance expectations to which the actual installed performance is compared.
AEC will prepare, with the assistance of the building owner and design team, a
Design Intent Summary which documents the design intent for those building energy
systems selected for commissioning. The Design Intent Summary reflects the
underlying assumptions and requirements that become represented in the
construction documents.
The commissioning scope does not directly address the energy performance of the
building and sub -systems. However, the results of the commissioning process will
aid the utility in evaluating the energy performance.
Submittals The general contractor will provide the commissioning agent with a set of equipment
and system submittals. This equipment data includes installation and start-up
procedures, O&M data, performance data and temperature control drawings. The
subcontractors, general contractor or A/E notify the commissioning agent of any new
design intent or operating parameter changes, added control strategies and
sequences of operation, or other change orders that may affect commissioned
systems.
Proposal to City of Fort Collins 5.2.13 — Page 2 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Site Observation
The commissioning agent makes periodic site visits to witness equipment and
system installations. Each site visit will have a specific agenda and will be
coordinated with the general contractor site supervisor. The commissioning agent
attends selected planning and job -site meetings in order to remain informed on
construction progress and to update parties involved in commissioning. The general
contractor provides the commissioning agent with information regarding substitutions
or change orders that may affect commissioned equipment, systems or the
commissioning schedule.
Pre functional
A Pre -Functional Inspection Checklist will be developed and completed for all
Checklists and
mechanical equipment being commissioned (RTU's, VAV boxes, computer room AC
Startup
units, exhaust fans, cabinet heaters). The checklist captures equipment nameplate
Procedures
and characteristics data, and confirms the as -built status of the equipment or system.
The checklists ensure that the systems are complete and operational and document
the installation of components and completion of systems.
The checklists will be prepared by the commissioning agent from manufacturer's
data, drawings and specifications to include the required installation, checkout, and
start up procedures. The installing subcontractors date and initial the checklists as
the construction and start-up is completed. The commissioning agent will review and
verify the completed checklists before scheduling the functional performance testing.
Development of
Functional performance testing verifies the intended operation of individual
Functional Test
components and system interactions under various conditions and modes of
and verification
operation. The systems are run through all of the sequences of operation and the
Procedures
response of components is verified. Testing proceeds from components to
subsystems to systems, and finally to interlocks and connections between systems.
The commissioning agent will prepare functional performance test plans so that the
complete sequence of operations is included. The commissioning agent obtains all
documentation, including an updated points list, control sequences, and setpoints. If
necessary, the commissioning agent may request clarifications from contractors and
the design team regarding sequences and operation. Prior to execution, the
commissioning agent provides a copy of the primary equipment tests to the installing
subcontractor and general contractor who can review the tests for feasibility, safety,
warranty and equipment protection.
Component testing executed in the test and balance process will be incorporated
into the functional testing documentation. Descriptions of the functional testing
procedures and participants, by equipment and system type, are included in Section
8 of this commissioning plan.
Execution of The commissioning agent schedules functional tests through the general contractor
Functional and subcontractors. Under the supervision of the commissioning agent, the
Testing installing subcontractor performs the hardware and/or software manipulations
Procedures required for the testing. Owner maintenance staff may also be present in order to
assist in system observations. The commissioning agent witnesses and records the
results of functional performance testing.
Proposal to City of Fort Collins 5.2.13 - Page 3 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Any deficiencies found from functional performance testing will be documented in a
Deficiency Report. The report will include all details of the components or systems
found to be non -compliant with the parameters of the functional performance test
plans and design documents. The deficiency report will become part of the punch
list. The report will detail the adjustments or alterations required to correct the
system operation, and identify the responsible party. The deficiency report will be
continuously updated. The commissioning agent schedules any required retesting
through the general contractor. Decisions regarding deficiencies and corrections are
made at as low a level as possible, preferably between commissioning agent, sub-
contractor and general contractor.
Short -Term Short-term diagnostic testing, using data acquisition equipment to record system
Diagnostic operation over a two to three week period, will be used to investigate the dynamic
Monitoring interactions between components in the building system.
The short term diagnostic testing will concentrate on the roof top unit air handling
systems, terminal reheat, and lighting control systems. The monitoring will occur
after occupancy, and may be scheduled in the winter to test the reheat system
demand limiting. The objectives of the monitoring are to evaluate the scheduling, the
interaction between heating and cooling, and the effectiveness of the lighting
controls.
Operations and The operation and maintenance manuals prepared by the contractors for the owner's
Maintenance
maintenance personnel will be reviewed for completeness. The contractors are
Manuals
encouraged to submit 0&M manuals at the earliest possible date. Materials may be
added, or requested from the contractors, to stress and enhance the importance of
system interactions, troubleshooting, and long-term preventative maintenance and
operation. A database of preventative maintenance information is created from the
materials in the O&M manuals.
Training and
Effective maintenance personnel training is critical to the long term performance of
Orientation of
the new building. The commissioning agent will assist the owner and general
Owner
contractor in organizing the training sessions by identifying the appropriate staff for
Personnel and
each session and creating an overall training plan.
Occupants
For each training session, the contractors provide a detailed agenda for each piece
of equipment or system for which training is required. The agenda describes the
training scope, duration, and methods, along with the name and qualifications of the
trainers. The commissioning agent develops a plan for including in the training
session contractors / trainers from different disciplines, when appropriate. The
trainer documents each training session (duration, general subjects covered, and
attendees). The commissioning agent may witness any of the training sessions.
The commissioning team will prepare an occupant manual that describes the unique
aspects of the building systems from an occupant's perspective. The occupant
manual will help the occupants understand the intended operation, comfort ranges,
and lighting levels of the building.
Proposal to City of Fort Collins 5.2.13 — Page 4 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A N
Warranty The building systems will be initially tested during the summer season with building
Period occupancy planned for fall 2003. Seasonal variation in operations or control
strategies may require additional testing during peak cooling and heating seasons to
verify system performance. During the warranty period, seasonal testing and other
deferred testing is completed as required to fully test all sequences of operation.
The commissioning agent coordinates this activity. Tests are executed and
deficiencies corrected by the appropriate subcontractors, witnessed by facilities staff
and the commissioning agent. Any final adjustments to the O&M manuals and as-
builts due to the testing are made.
The commissioning agent will request input from the owner's operations staff and
occupants about the performance of the building systems. The commissioning agent
also supports the general contractor's troubleshooting process during the warranty
period. The general contractor's warranty team will first try and resolve the issues
before requesting assistance from the commissioning agent.
Commissionin A final Commissioning Report will be compiled which summarizes all of the tasks,
g Report findings, and documentation of the commissioning process. The report will address
the actual performance of the building systems in reference to the design
documents. All test reports by various sub -contractors, manufacturers and
controlling authorities will be incorporated into the final report.
The commissioning report includes:
• An evaluation of the operating condition of the systems at the time of functional
test completion,
• Deficiencies that were discovered and the measures taken to correct them,
• Functional test procedures and results,
• Reports that document all commissioning field activities as they progressed, and
• A description and estimated schedule of required deferred testing.
Proposal to City of Fort Collins 5.2.13 — Page 5 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A
NO
5.2.4.2 TEAM MEMBER LIST
Design The Neenan Company
Builder Bob Meserve, Senior Project Manager, Project Leader
2620 E. Prospect Road Suite 100
Fort Collins, CO 80525
Telephone: 970-495-6319
Fax: 970-495-5869
Consultants Gilfillan/Callahan Architects, Inc.
(Pat Callahan, Consulting Architect0
1600 Golf Road Suite 1000
Rolling Meadows, IL 60008
Telephone: 847-9 52-0545
Fax: 847-952.0575
Commercial Refrigeration
(Ice Consultants/Ice Package Design -Build Sub -Contractor)
Ron Jackson
421-116 Ave. N.W.
Edmonton, Alberta, Canada T6S-1 G3
Telephone: 1.800-414-0990
Fax: 403-464-4077
Merit Electric
(Electrical Engineer/Design-Build Electrical Sub -Contractor)
Brennan Schumacher
4700 Innovation Drive
Suite D-1
Fort Collins, CO 80525
Telephone: 970-266-8100
Fax: 970-266-1640
Design Mechanical
(Mechanical Engineer/Design-Build Mechanical Sub -Contractor)
Steve Larson
5637 Arapahoe Road
Boulder, CO 80303
Telephone: 303-449 -2092
Fax: 303-449-8739
Proposal to City of Fort Collins 5.2.4.2 —Page 1 November 28, 2001
Second Sheet of Ice at EPIC (P-812)
I
F
I
Archistructioe
Appendix
Proposal to City of Fort Collins 5.2.15.1 - Appendix November 28, 2001
Second Sheet of Ice at EPIC (P-812)
N E E N A jss ,
R
r
3 $ryv l
�4� ,.
r1P2 2
An: Integrated Approach To Building New Envlronmerlts
a� W,j-S x ': .
00. n
l
(} ^x1M
al,'x= Yes
y
F ^:1
N E E N A N
Shattering the Myths approach
The buildings you see in this brochure are unique. Their singularity comes not necessarily from appearance or
physical attributes. They are diBerent because they are the result of a new, more efficient approach to the entire
building process.
A Digerent Historically, the traditional approach takes diverse disciplines with individual profit motives and places them in an
App'°O h adversarial relationship. This approach embraces the myth that competition yields the best price. However, this
Tb Building
industry tradition yields problems, such as high change orders, litigation and unfinancable projects that never
come to fruition. If this process works so well, why are there so many problems?
Our process takes diverse disciplines and places them in a cooperative relationship, where the service motive of
meeting your objectives is the highest priority. Together, with you, we are partners in the construction of your
building environment. As such, we help you identify the target of your project and get the entire development
process initiated properly, right from the start. We take responsibility for all aspects of the project, including
design, construction and financing. Our process will save you time and money, avoiding delays, liens, lawsuits
and many of the other unpleasant realities of conventional construction.
11s Ne AWk6aky M-nba srWm
Our Services
o Development Ownership
o Development Management
o Asset Management
o Site Selection & Land Acquisition
o Financing
o Design
o Pm -construction
o Construction
a Project Review
a Safety Program
o Post Construction Warranty
4nbFla,YI,W
Mission Statement
To significantly improve
the economic vitality
of our clients,
and to improve the lives of
all that we touch
to such a degree that it
transforms the industry
of the built environment
(one project at a time)
Scheduling
At the heart of our scheduling success is
tr The Neenan Reliability Planning System
(NRPS). We developed this system after
worldng with other industry professionals to
streamline our delivery process and
increase our reliabll{ty. We have Increased
our rellabigty on pRifects to approximately
75%, double the q #w,gUan Industry
��— average., This system is unique to•our,
companyRnd all of our project managers
and supetintendents use it consistently.
Pro- onittructlonServices-estimatingandcostmanagement
In a construction project 80% of the cost is determined in the first 20% of the design. Because of , we know how important it Is for pre-
rbnstructionstaftoworkwiththedesignstafffromthebeginning. Asneany100%ofourworkisde ' uild,ourpre-consfntctlonpersonnel
ve excellent skills to conceptually estimate a projectproviding alternate solutions while the design being created. Through ourprocess,
.slue is added at the startofthe projectso scope doesnothave to be cutatthe and.
Collaborative Design Process
MNhere has this process been for
30 rears?"
According te Jerry Mear,'Nothing has
charged in design -wild In the last 30
years, What Is dtifaram Is your
Ccllabomtiva Design Process.'
Jerry Is a Colorado developer, an
eutperienoad purcheser of daagNbuild
services.
(CDP) Is o aof Design
our design and pecomhudlon
delivery process. In a short period of
one or two days, m bring together the
m
city
The CDP is unque In the Industry and
Is dnferad ham a'dasign chsrta .'
We deliver innovative design solutions
In conjunction with accurate pricing M
much less time Man the traditional
design -build process The CDP is
on used on an going"to design
and coordinate she project as it
WON".
lypical CDP Deliverables:
Building Design Direction
Conditions of Satisfaction
Outline Specifications
Project Schedule
Project Budget
open Items List
,•Y.a'c
=^._
The Results: ✓fi Faster Delivery
Alignment of Stakeholders - _
Harty Reliability and Accountability
=
of Project Schedule and Cost
_--
Ffeldlgafety Management
The Neenan STAR Safety Process
Safety In each project is vary
wee deelpned from a beheviorbeW a
Important to TNC. Our full time Safely
safety concept and all of Ole
Director takes aide In working wIM
components of the program are
all of our Superintendents, Project
STAR
" intermleted and designed to function
Managers and Subcontradars to
00v7buMaeanvemo
together in support of the overall
assure that they exceed our
SAFETY PROCESS
_ goal. A Tbfal Safety Culture Is our
standards. We lave an E.M.R. rating
eeerm
ultimate goal and achieving it
of 0.54. which Is considered excellent
requires that attention be given to
in our Industry. We bike great pride In
three basic domain: the environment
"no together a spedac safety plan ev,.ww
none
Including rods, equipment, and
for every project that wit bulk) and
dimete of the work setting; the
am very diligent about meeting or
parson Including attitudes, bellefs,
exceeding OSHA requirements on
personalities and sickle of the
each projea
amp"; the behavior Including
safe and at dek work practices and
intervening for a oD•worWs safety.
9eMyMtwim
ibawpra SrdaryGL/mrinAmli46uNm•whoeProJat]imvfxuanFSrMmrrwm4NMbWa, and
ra.m eaW®mr Paronfacpnabauweamdu+�wrlwN!lwrpnnvmWmmgf'nrawa✓xr
5•Year Safety history
1996 1997 1998 1999 2000
y Incident Rate 10.80 2.56 5.75 5.31 8.06
EMR 0.70 0.70 0.63 0.56 0.54
N
FORT COLLIIJS CITY BUILDING
Fort Collins, Colorpdp
The design solution for this project demonstra
civic image for the City of Fort Collins. The bu
frame construction with brick and native sand;
skin. The rmeterials and building systems were
specifically to address overall building perfom
regards to life cycle costing, sustainable desig
daylighting and flexibility of layout. The desigr
upon the precedent established by the Larime
Justice Center by providing visual linkage acn
that unifies the city master plan while still mair
unique identity.
This 72,000 square,foot, three-story building v
completed in the spring of 2001. The Neenan
provided design/tiulld services partnering with
Architecture owdssign services.
ructlon ahrt:
N E
E
N A N
,;,,q:,
LARIMER COUNTY SHERIFF
ADMINISTRATIVE BUILDING
Fort Collins, Colorado
This facility, completed in 2000, was built to
accommodate the expanded requirements for the
Larimer County Sheriff's administrative offices and all
support functions. The project was awarded utilizing a
design/build delivery model, with Neenan Company as
the design/builder„grid CZArchiledty, PrgvIdIng�desililp
services tluougkl enan Thg two-story, 36,5001square
foot bulldjp'g w �Yflrelgt�6f schedule anSj , Cot
YJtdiiation.®fpartlsllp1oasIg bearing afrdhit<iii i blo
laack
exterior walnd conventional steel framing, helped the
County achieve an extremely tight project'budget, which
allowed for the extensive technical requirements within
the building. Included in this fully secured facility are a
forensic evidence processing laboratory with biohazard
evidence processing capabilities, 911 dispatch center,
and an emergency operations center with microwave
radio communications.
client:
Larimer County
Fort Collins, Colorado
Archhod:
OZ Architecture
Construction Star:
grpject completion:
October 2*-
r r
COMMITTED TO EXCELLENCE
November 8, 2001
To Whom It May Concern:
FACILITIES DEPARTMENT
David J. Spencer, CFM, Director
2555 Midpoint Drive Suite D
Fort Collins, Colorado 80525
PHONE (970) 498-5914
FAX (970) 498-5901
E-MAIL spencedj@co.larimer.co.us
I have had the opportunity to interact with the Neenan Company in a variety of capacities
over the last four years and find them to be an excellent organization to work with. They
have assisted Larimer County in a number of ways including project estimation, feasibility
study, peer review of concepts and designs and the full Design Build function of the
Sheriff's administrative facility. In every way they have been the consummate
professionals and have kept customer satisfaction as their primary goal. Their attention
to detail and strict adherence to schedules contributed to the complete success of the
project. Additionally they have not forgotten us after the last check was cut, our requests
for service under warranty have had prompt attention and are completed to our
satisfaction.
In light of these positive experiences I have no reservation in recommending the
Neenan Company to be a part of your team in any capacity. Should you have any
questions please feel free to contact me.
Respectfully Submitted,
avid ]. Spencer
N E E N A N
ST. JOSEPH'S SCHOOL
Fort Collins, Colorado
The Neenan Company provided design -build services for an
addition and renovation project, partnering with Hartman
Associates to provide architectural services. This project included y ,'
a classroom and cafeteria addition, and the remodel of the
existing gymnasium. This project was partially performed with the
*ssc�ht1ool in operation and allowed for minimal disruption to existing
ac�iviges.
Client
Pt. Joseph's School
Fort -Collins, Colorado
Architect:
Hgttmon gaepcjateq
ArGiheelu 8 Plannlnp
& the Noonan Company
"if hen they werefirst recommended to me, it was with the fact that they have a
track record of coming in on budget and on time with their projects. This was true
of the Saint Jbssph School project. Phase One was completed a month ahead of
schedule and on budget. Phase Tivo also was completed on time, and this is saying
something because this phase included major renovation of the 1925 building. "
Philip S. Meredith, Pastor
,...
ConstruatlonStart:
May 1999
project Completion:
October 1999
1
ARCHDIOCESE OF DENVER
MANAGEMENT CORPORATION
1300 South Steele Street
Denver, CO 80210,2599
Phone: 303.722.4687
March 10, 2000
Mr. David Neenan
The Neenan Company
2620 E. Prospect Road
Ft. Collins, CO 80524
Dear David:
On behalf of the Archdiocese of Denver and St. Joseph Parish of Ft. Collins, I would like to thank
you and all of your staff for a job well done. We are very proud of the addition to the school, and
the children, teachers and parents are delighted with their new building.
I would like to especially thank the Neenan team, Ron Kechter, Jarrod Daddis, Dean Barber, Jim
Deitchler, Roger Wedderburn, April Sultan, and Pat Marchetti. These people all were responsive
to our request and delivered the building on time and on budget. Out of the $55 million worth of
construction projects that the Archdiocese was responsible for last year, this project has been one
of the smoothest running I was involved with from the initial collaborative design meeting through
building completion.
We look forward to Phase II and to working on future projects with The Neenan Company.
Very truly yours,
�" V
Walter E. Wostenberg
Director of Construction
c: Rev. Phillip S. Meredith, Pastor
CATHOLIC CHURCH
600 West Mountain Avenue
Post Office Box 502
1 Collins, Colorado 80522
aphone (9701 482-4148
' r9701 221-0635
February 8, 2001
Reverend Timothy J. Evans
Pastor - Saint Elizabeth Ann Seton Parish
5450 South Lemay Avenue
Fort Collins, CO 80525
Dear Tim,
ELEMENTARY SCHOOL
127 North HOWBS Sheet
Fort Collins, Colorado 80521
Telephone (9701 484-1 171
FAX (9701 221-0635
I know that you and your Parish are in the midst of planning for a major construction project. As
you know, we finished our project this past September.
As you look to choosing an architect, contractor, etc., I would like to recommend to you the
Neenan Company.
Neenan was with us from the very beginning with the design phase to the completion of the
project. We already had an architect, Ric Hartman, who they worked with throughout the project.
Because of the style of business that they offer, called "archistruction," I can honestly say that our
project went better than I ever hoped or imagined it would. When I heard horror stories from
other pastors as to what they endured in their construction projects, I really dreaded having to
"build a building." But with Neenan it was a wonderful experience.
When they were first recommended to me, it was with the fact that they have a track record of
coming in on budget and on time with their projects. This was true of the Saint Joseph School
project. Phase One was completed a month ahead of schedule and on budget. Phase Two also
was completed on time, and this is saying something because this phase included major
renovation of the 1925 building.
l am enclosing copies of correspondence between Walt Wostenberg and David Neenan which 1
think tells pretty much the whole story.
Yours in Christ.
Philip S. Meredith
Pastor